Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work...

48
, Phone: 713.640.3000 Fax: William P. Hobby Airport Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property Filter: [Shop] = 'HVAC Contractor' Airfield - General 50429 A/C UNIT NOT WORKING DOG HOUSE C15 7/10/2009 Building NR-07 23150 COLD CALL AT BADGING OFFICE NR-7 BLDG HVAC System, Building NR 7, Level 1 1/21/2010 49208 MAKE AIR COOLER HVAC System, Building NR 7, Level 1 6/12/2009 49216 HOT CALL IN NR07 BLDG, ROOM 1.Y10.1 HVAC System, Building NR 7, Level 1 6/12/2009 49310 HOT CALL IN HPD SERGENTS OFFICE HVAC System, Building NR 7, Level 1 6/12/2009 49893 HOT CALL IN NR7 BUILDING (NORTH END). HVAC System, Building NR 7, Level 1 7/10/2009 49904 HOT CALL IN NR7 BUILDING (PUBLIC SAFETY SIDE) HVAC System, Building NR 7, Level 1 7/10/2009 50034 HOT CALL IN NR7 BUILDING (PUB. SAFETY SIDE) HVAC System, Building NR 7, Level 1 7/10/2009 50063 HOT CALL FOR NR-7 BUILDING HVAC System, Building NR 7, Level 1 7/10/2009 50099 A/C NOT WORKING IN BLDG NR-07 HVAC System, Building NR 7, Level 1 7/10/2009 50637 HOT CALL AT NR-7 (HPD) AREA HVAC System, Building NR 7, Level 1 7/10/2009 50680 FRONT A/C UNIT AT NR-7 NOT WORKING HVAC System, Building NR 7, Level 1 7/10/2009 50759 HOT CALL @ NR-7 (HPD AREA) HVAC System, Building NR 7, Level 1 7/23/2009 50772 AC NOT COOLING HVAC System, Building NR 7, Level 1 7/23/2009 53018 HOT CALL IDF 502 IN NR-7 HVAC System, Building NR 7, Level 2 11/5/2009 Page 1 of 48 Printed 7/6/2012 11:00:30 AM

Transcript of Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work...

Page 1: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

,

Phone: 713.640.3000 Fax:

William P. Hobby Airport

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

Airfield - General

50429 A/C UNIT NOT WORKING

DOG HOUSE C15

7/10/2009

Building NR-07

23150 COLD CALL AT BADGING OFFICE NR-7 BLDG

HVAC System, Building NR 7, Level 1

1/21/2010

49208 MAKE AIR COOLER

HVAC System, Building NR 7, Level 1

6/12/2009

49216 HOT CALL IN NR07 BLDG, ROOM 1.Y10.1

HVAC System, Building NR 7, Level 1

6/12/2009

49310 HOT CALL IN HPD SERGENTS OFFICE

HVAC System, Building NR 7, Level 1

6/12/2009

49893 HOT CALL IN NR7 BUILDING (NORTH END).

HVAC System, Building NR 7, Level 1

7/10/2009

49904 HOT CALL IN NR7 BUILDING (PUBLIC SAFETY SIDE)

HVAC System, Building NR 7, Level 1

7/10/2009

50034 HOT CALL IN NR7 BUILDING (PUB. SAFETY SIDE)

HVAC System, Building NR 7, Level 1

7/10/2009

50063 HOT CALL FOR NR-7 BUILDING

HVAC System, Building NR 7, Level 1

7/10/2009

50099 A/C NOT WORKING IN BLDG NR-07

HVAC System, Building NR 7, Level 1

7/10/2009

50637 HOT CALL AT NR-7 (HPD) AREA

HVAC System, Building NR 7, Level 1

7/10/2009

50680 FRONT A/C UNIT AT NR-7 NOT WORKING

HVAC System, Building NR 7, Level 1

7/10/2009

50759 HOT CALL @ NR-7 (HPD AREA)

HVAC System, Building NR 7, Level 1

7/23/2009

50772 AC NOT COOLING

HVAC System, Building NR 7, Level 1

7/23/2009

53018 HOT CALL IDF 502 IN NR-7

HVAC System, Building NR 7, Level 2

11/5/2009

Page 1 of 48Printed 7/6/2012 11:00:30 AM

Page 2: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

53355 CHANGE AIR FILTERS IN AC UNITS AT HPD OFFICE

HVAC System, Building NR 7, Level 1

10/29/2009

53728 A.C MAKING EXCESSIVE NOISE, RUNNING CONSTANTLY

HVAC System, Building NR 7, Level 1

10/29/2009

54418 HOT CALL PUBLIC SAFETY OFFICES BLDG NR-7

OFFICES - BADGING/PUBLIC SAFETY

12/30/2009

55312 HOT CALL NR-07 BUILDING LEVEL 2

HVAC System, Building NR 7, Level 2

12/30/2009

56296 HOT CALL IN THE WEATHER OFFICE.

HVAC System, Building NR 7, Level 1

1/20/2010

56756 A/C IN NR-7 BUILDING NOT WORKING C-3 SIDE

HVAC System, Building NR 7, Level 1

2/9/2010

59330 HOT CALL IN THE BADGING OFFICE.

HVAC System, Building NR 7, Level 1

4/28/2010

59605 REPAIR AC PANEL IN THE NR7 BUILDING.

HVAC System, Building NR 7, Level 1

6/30/2010

60355 HOT CALL FOR NR-07 BUILDING

OFFICES - BADGING/PUBLIC SAFETY

7/1/2010

60488 A/C NOT WORKING IN THE NR-07 BUILDING.

HVAC System, Building NR 7, Level 1

7/1/2010

60567 HOT CALL @ PUBLIC SAFETY AREA NR7 BUILDING

HVAC System, Building NR 7, Level 1

7/1/2010

60774 THERMOSTAT IN P/S NR-07 NOT WORKING.

HVAC System, Building NR 7, Level 1

7/9/2010

61079 HOT CALL

HVAC System, Building NR 7, Level 1

7/1/2010

61110 HOT CALL

HVAC System, Building NR 7, Level 1

7/1/2010

62044 HOT CALL FOR NR-07 BLDG

HVAC System, Building NR 7, Level 1

7/9/2010

62328 HOT CALL IN THE NR7 BUILDING.

HVAC System, Building NR 7, Level 1

8/6/2010

62507 HOT CALL IN ROOM NR-411

HVAC System, Building NR 7, Level 1

8/6/2010

62724 HOT CALL

HVAC System, Building NR 7, Level 1

7/29/2010

62765 AC UNIT IN OFFICE MAKING SQUEAL NOISE

HVAC System, Building NR 7, Level 1

7/29/2010

65341 AC UNIT NOT WORKING AT NR-7 BUILDING.

HVAC System, Building NR 7, Level 1

9/21/2010

65595 AC NOT WORKING

HVAC System, Building NR 7, Level 1

9/30/2010

66320 HOT CALL IN NR7.304 IDF ROOM

HVAC System, Building NR 7, Level 1

10/29/2010

Page 2 of 48Printed 7/6/2012 11:00:30 AM

Page 3: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

Central Concourse

1012 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

1070 DIRTY FILTER

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

3872 CHANGE FILTER

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

4186 FAN FAILED

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

4233 FAN FAIL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

4599 DIRTY FILTER T 303

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

4930 DIRTY FILTER AHU T301

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

8291 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

8296 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

9184 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

9804 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

10225 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

10368 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

11125 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

11172 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

11364 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

11592 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

14673 HOT CALL WN TRAINING ROOM 3RD LVL

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

16537 COLD CALL WN SUPER OFFICE

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

18287 NO AC AT WN OFFICE 3RD LVL

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

19974 COLD CALL WN 3RD LVL OFFICE

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

Page 3 of 48Printed 7/6/2012 11:00:30 AM

Page 4: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

20577 HOT CALL TRAINING ROOM CENTRALCONCOURSE.

HVAC System, Atrium, Level 3 - WN Offices

1/21/2010

21263 FIX AIR CONDITIONING

HVAC System, Atrium, Level 3 - WN Offices

1/22/2010

23249 OPS (WN) LVL 3 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

10/29/2009

25640 HOT CALL AT TSA CENTRAL CHECKPOINT

CHECKPOINT CENTRAL CONC

10/29/2009

32291 HOT CALL IN CENTRAL ATRIUM

HVAC System, Connector Bridge, Level 2

10/29/2009

38780 HOT CALL CENTRAL CONCOURSE LVL-1.

HVAC System, Atrium, Level 1

10/29/2009

49203 A/C UNIT NOT WORKING AT GATE #28

Jetbridge # 28

6/12/2009

49224 COLD CALL CENTRAL EAST BY GRAB N GO #1.

HVAC System, East End, Level 2

6/12/2009

49409 A/C NOT WORKING AT JETBRIDGE #29

Jetbridge # 29

6/12/2009

49417 CHECK HVAC AT JETBRIDGE 28

Jetbridge # 28

6/12/2009

49429 HOT CALL IN (AA) OPS OFFICE

HVAC System, East End, Level 1

6/12/2009

49436 HOT CALL IN ROOM 1.Y.10.4

HVAC System, Atrium, Level 1

6/12/2009

49479 ROLLER DOOR NOT WORKING AT JETBRIDGE #29

Jetbridge # 29

6/12/2009

49620 AC ON JETBRIDGE NOT WORKING.

Jetbridge # 30

6/12/2009

49796 HOT CALL IN RR 35,36 AND ASSIST

RESTROOM #35 - MEN'S

6/12/2009

49801 HOT CALL

HVAC System, West End, Level 2

6/12/2009

49863 HOT CALL FOR JET BRIDGE GATE 30

Jetbridge # 30

6/17/2009

49896 HOT CALL IN RR #1.Y29.10

RESTROOM - SWAL LINE MAINT OFFICE MEN'S

7/10/2009

49920 HOT CALL HUDSON NEWS EAST

HVAC System, East End, Level 2

7/10/2009

49936 HOT CALL IN CENTRAL CONCOURSE

HVAC System, Connector Bridge, Level 2

7/10/2009

50053 HOT CALL IN RR 31&32

HVAC System, East End, Level 2

7/10/2009

50076 CHECK AC WN INFLIGHT ROOM (3Y18.10)

HVAC System, Atrium, Level 3 - WN Offices

7/10/2009

Page 4 of 48Printed 7/6/2012 11:00:30 AM

Page 5: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

50136 CHECK AC UNIT ROOM 1Y29.10

HVAC System, West End, Level 1

7/10/2009

50267 HOT CALL @ THE ATRIUM.

HVAC System, Atrium, Level 2

7/10/2009

50277 AC ON JETBRIDGE @ G-30 NOT WORKING

Jetbridge # 30

7/10/2009

50300 COLD CALL BETWEEN GATES 47-49

HVAC System, West End, Level 2

7/10/2009

50303 G-30 THE AC ON JETBRIDGE NOT WORKING.

Jetbridge # 30

7/10/2009

50512 A/C HOSE ON JETBRIDGE 30 INOP

Jetbridge # 30

7/10/2009

50568 A/C HOSE NOT WORKING AT GATE #29

Jetbridge # 29

7/10/2009

50661 CHECK CONDESATION PUMP IN ROOM 1Y10.3

HVAC System, West End, Level 1

7/10/2009

50699 HOT CALL @ THE 3RD FLOOR CONFERENCE ROOM

HVAC System, Atrium, Level 3 - WN Offices

7/23/2009

50935 AC HOSE LOSE JETBRIDGE #29

Jetbridge # 29

7/23/2009

50970 WATER LEAK W/CHILL WATER SUPPLY LINE.

HVAC System, Atrium, Level 1

7/23/2009

51070 CHECK AIR CONDITION UNIT IN COMMUNICATION ROOM

HVAC System, East End, Level 1

8/5/2009

51082 COLD CALL @ G-44.

HVAC System, West End, Level 2

7/24/2009

51220 WATER LEAK FROM HVAC UNIT

HVAC System, Atrium, Level 1

11/5/2009

51250 HOT CALL

SWAL LINE MAINT OFFICE

8/6/2009

51280 VENTS NOT BLOWING OUT AIR

HVAC System, West End, Level 1

8/6/2009

51439 HOT CALL FOR CENTRAL CHECKPOINT

CHECKPOINT CENTRAL CONC

11/5/2009

51612 AC NOT WORKING WN OFFICE (1Y29.37)

HVAC System, West End, Level 1

11/5/2009

51613 HOT CALL WN TICKET COUNTER

HVAC System, West End, Level 1

10/23/2009

51639 A/C AT JETBRIDGE 29 IS INOP

Jetbridge # 29

10/16/2009

51642 REPAIR AC LEAK @ LOADING DOCK.

APRON AREA - CENTRAL CONCOURSE

10/21/2009

51755 TSA REPORTED DIRTY A/C FILTERS AT WN BAGGAGE CHECK

HVAC System, Ticket Lobby, Level 1

10/21/2009

Page 5 of 48Printed 7/6/2012 11:00:30 AM

Page 6: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

51845 HOT CALL IN ATRIUM

HVAC System, Atrium, Level 2

10/16/2009

51932 HOT CALL FOR CENTRAL CONCOURSE

HVAC System, East End, Level 2

11/5/2009

51997 HOT CALL AT WN TICKET COUNTER

HVAC System, Ticket Lobby, Level 2

10/16/2009

52112 HOT CALL TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

10/16/2009

52127 CLEAN VENT DUCTS IN PAPPADEAUX.

HVAC System, Atrium, Level 2

12/30/2009

52653 A/C HOSE DISCONNECTED FROM A/C UNIT

Jetbridge # 25

11/13/2009

52770 HVAC LEAKING IN T-POINT

HVAC System, Atrium, Level 1

10/29/2009

52864 A/C UNIT NOT WORKING

Jetbridge # 29

10/28/2009

52865 HOT CALL CENTRAL CONCOURSE

HVAC System, Atrium, Level 2

11/5/2009

53301 CLEAN AC VENT IN RR 36.

HVAC System, West End, Level 2

10/29/2009

53433 COLD CALL @ GATE-42 & GATE-44

HVAC System, West End, Level 2

10/29/2009

53478 COLD CALL BETWEEN G-41-43 & 47-49

HVAC System, West End, Level 2

10/29/2009

53608 COLD CALL PILOT LOUNGE

HVAC System, Atrium, Level 3 - WN Offices

10/29/2009

53682 HOT CALL IN WN BAG SCREEN

HVAC System, East End, Level 1

10/29/2009

53718 HOT CALL

HVAC System, East End, Level 1

10/29/2009

53866 A/C NOT WORKING ON THE THE JET BRIDGE.

Jetbridge # 29

10/23/2009

53941 LEAK FROM AIR HANDLER AT T-POINT

HVAC System, East End, Level 2

10/28/2009

53942 FIX REMAINING ELECTRICAL REPAIRS ON AHU

HVAC System, East End, Level 1

12/30/2009

53955 LOUD NOISE COMING FROM A/C.

HVAC System, Atrium, Level 3 - WN Offices

10/28/2009

54179 HOT CALL IN THE TSA CHECK BAGGAGE AREA.

HVAC System, West End, Level 1

11/5/2009

54388 COLD CALL FOR PILOT LOUNGE

HVAC System, Atrium, Level 3 - WN Offices

12/30/2009

54511 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

12/30/2009

Page 6 of 48Printed 7/6/2012 11:00:30 AM

Page 7: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

54554 COLD CALL

HVAC System, Atrium, Level 2

12/30/2009

54585 COLD CALL BETWEEN G-42-44.

HVAC System, West End, Level 2

12/30/2009

54592 HOT CALL AT TSA SWA SCREENING

HVAC System, Atrium, Level 1

12/30/2009

54599 TURN ON A/C

HVAC System, Ticket Lobby, Level 2

12/30/2009

54666 CLEAN AC SUPPLY VENTS

HVAC System, West End, Level 1

12/30/2009

54810 COLD CALL IN SWA FLIGHT OPS AREA

HVAC System, Atrium, Level 3 - WN Offices

12/30/2009

54978 HOT CALL TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

12/30/2009

54985 CHECK AIR CONDITION HOSE

Jetbridge # 41

12/2/2009

54992 CHECK AIR CONDITION IN SWA COMPUTER ROOM #1.Y19.10

HVAC System, West End, Level 1

12/30/2009

55020 HOT CALL AT GATES 40 - 49

HVAC System, West End, Level 2

12/30/2009

55081 HOT CALL WN OFFICE

HVAC System, West End, Level 2

12/30/2009

55186 COLD CALL IN THE CENTRAL CONCOURSE.

HVAC System, West End, Level 2

12/31/2009

55233 HOT CALL SOUTHWEST TICKET COUNTER.

HVAC System, Ticket Lobby, Level 2

8/4/2010

55306 HOT CALL CENTRAL CONCOURSE WEST LVL-1

HVAC System, West End, Level 1

12/31/2009

55332 HEATING UNIT HOSE HAS COME LOOSE.

HVAC System, West End, Level 2

12/10/2009

55340 TIGHTEN THE SCREWS ON THE AC VENT.

HVAC System, East End, Level 2

12/31/2009

55365 HVAC UNIT NOT WORKING

HVAC System, East End, Level 1

12/31/2009

55390 PIPE LEAKING IN SW STORAGE AREA

Piping System, East End, Level 2

12/16/2009

55408 COLD CALL TSA CENTRAL CHECKPOINT

HVAC System, Ticket Lobby, Level 2

12/31/2009

55414 COLD CALL FOR THE CENTRAL CHECKPOINT

HVAC System, Atrium, Level 2

12/31/2009

55431 HOT CALL

HVAC System, West End, Level 1

12/31/2009

55458 HOT CALL @ THE CENTRAL CHECKPOINT AREA

HVAC System, West End, Level 2

12/31/2009

Page 7 of 48Printed 7/6/2012 11:00:30 AM

Page 8: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

55508 HOT CALL CENTRAL CONCOURSE GATE #28

HVAC System, East End, Level 2

12/31/2009

55641 NO HOT WATER IN SW BREAKROOM

HVAC System, East End, Level 1

12/31/2009

55702 TURN UP HEAT

TSA SCREENING AREA

12/31/2009

55824 HOT CALL TSA CHECKPOINT AREA

HVAC System, West End, Level 2

12/31/2009

55851 HOT CALL IN USO

HVAC System, West End, Level 1

12/31/2009

55868 CHECK ALL SYSTEMS

HVAC System, Atrium, Level 1

12/29/2009

55886 COLD CALL @ THE CENTRAL INFO BOOTH

HVAC System, Atrium, Level 2

12/31/2009

55890 COLD CALL @ SW TICKET COUNTER

HVAC System, West End, Level 2

12/31/2009

55899 HOT CALL IN THE SWA INFLIGHT AREA

HVAC System, Atrium, Level 3 - WN Offices

1/20/2010

55909 HOT CALL WN INFLIGHT OFFICE

HVAC System, Atrium, Level 3 - WN Offices

1/20/2010

55917 HOT CALL CHECKPOINT

HVAC System, West End, Level 2

1/20/2010

55918 HOT CALL AT SOUTHWEST TICKET COUNTER

HVAC System, Ticket Lobby, Level 2

12/31/2009

55920 HOT CALL SWAL BAGGAGE ROOM 1-Y10-4

TSA SCREENING AREA

12/31/2009

55972 HOT CALL WN INFLIGHT OFFICE

HVAC System, Atrium, Level 3 - WN Offices

1/20/2010

55975 HOT CALL WN MAINTENANCE (1Y29.35)

HVAC System, West End, Level 1

1/20/2010

55984 CLEAN CEILING VENTS

HVAC System, West End, Level 2

1/20/2010

56005 COLD CALL IN TSA BAG SCREEN

HVAC System, Atrium, Level 1

1/20/2010

56040 HOT CALL AT THE SOUTHWEST TICKET COUNTER.

HVAC System, Ticket Lobby, Level 2

1/20/2010

56041 HOT CALL @ THE CENTRAL CHECKPOINT.

HVAC System, West End, Level 2

1/20/2010

56096 HOT CALL WN TICKET COUNTER.

HVAC System, Ticket Lobby, Level 2

1/20/2010

56152 HOT CALL WN COUNTER

HVAC System, West End, Level 2

1/20/2010

56183 HOT CALL IN THE T-POINT (TSA SCREENING AREA)

HVAC System, Atrium, Level 1

1/20/2010

Page 8 of 48Printed 7/6/2012 11:00:30 AM

Page 9: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

56214 HOT CALL IN THE FLIGHT OPS OFFICE

HVAC System, Atrium, Level 3 - WN Offices

2/3/2010

56217 COLD CALL

HVAC System, West End, Level 2

1/20/2010

56219 COLD CALL

HVAC System, Atrium, Level 2

1/20/2010

56228 COLD CALL CENTRAL CONCOURSE .

HVAC System, Atrium, Level 2

1/20/2010

56283 COLD CALL

HVAC System, Atrium, Level 2

1/20/2010

56284 HOT CALL IN THE JETBLUE OFFICE.

HVAC System, East End, Level 1

1/20/2010

56287 COLD CALL @ THE CHECKPOINT.

HVAC System, Atrium, Level 2

1/20/2010

56291 HOT CALL SW INFLIGHT OFFICES.

HVAC System, Atrium, Level 3 - WN Offices

2/3/2010

56312 HOT CALL IN SW EQUITMENT ROOM.

HVAC System, West End, Level 1

1/20/2010

56322 HOT CALL IN SW OFFICES

HVAC System, West End, Level 1

2/3/2010

56334 COLD CALL

HVAC System, West End, Level 2

1/20/2010

56348 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

1/20/2010

56476 CLEAN VENTS IN THE SW INFLIGHT OFFICE.

HVAC System, Atrium, Level 3 - WN Offices

1/20/2010

56509 HOT CALL IN THE SW OFFICES ON LVL 1.

HVAC System, West End, Level 1

1/21/2010

56520 HOT CALL

HVAC System, Atrium, Level 2

1/20/2010

56655 A/C MAKING LOUD NOISE IN WN OFFICE AREA.

HVAC System, Atrium, Level 3 - WN Offices

2/9/2010

56677 HOT CALL FOR CENTRAL CONCOURSE

INFORMATION BOOTH - CENTRAL CONC

2/9/2010

56706 HOT CALL

HVAC System, Atrium, Level 2

2/9/2010

56828 HOT CALL AT T-POINT

HVAC System, Atrium, Level 1

2/9/2010

56900 CHECK WATER LEAK IN BUFFULO WILD WINGS.

Ceiling, East End, Level 2

2/9/2010

56924 COLD CALL SOUTHWEST BAGGAGE

TSA SCREENING AREA

2/9/2010

56946 READJUST AIR

HVAC System, West End, Level 2

2/9/2010

Page 9 of 48Printed 7/6/2012 11:00:30 AM

Page 10: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

56947 COLD CALL

HVAC System, West End, Level 2

2/9/2010

57005 COLD CALL CENTRAL CHECKPOINT

HVAC System, Ticket Lobby, Level 2

2/9/2010

57033 COLD CALL

HVAC System, Atrium, Level 1

3/4/2010

57048 HOT CALL IN CENTRALCONCOURSE (EAST AND WEST)

HVAC System, West End, Level 2

2/10/2010

57062 COLD CALL AT CENTRAL INFO BOOTH

HVAC System, Atrium, Level 2

2/10/2010

57071 COLD CALL IN THE CENTRAL CONCOURSE

HVAC System, East End, Level 2

2/10/2010

57107 CLEAN AC VENT OVER GATES 21 & 41.

HVAC System, East End, Level 2

3/4/2010

57114 HOT CALL WN TICKET COUNTER

HVAC System, Ticket Lobby, Level 2

2/10/2010

57138 COLD CALL AT CHECKPOINT

TSA SCREENING AREA

2/10/2010

57260 HOT CALL

SWAL LINE MAINT OFFICE

4/28/2010

57282 HOT CALL IN SW ROOM UNDER G-49

HVAC System, West End, Level 2

3/4/2010

57323 COLD CALL

HVAC System, East End, Level 2

3/4/2010

57342 HOT CALL

HVAC System, Ticket Lobby, Level 2

3/4/2010

57344 CLEAN VENT

HVAC System, West End, Level 2

3/4/2010

57469 HOT CALL IN WN PILOT LOUNGE

HVAC System, West End, Level 3

3/4/2010

57555 TURN DOWN HEATER

OFFICES - TSA BREAKROOM

3/4/2010

57678 COLD CALL IN THE TSA SW CHECK BAGGAGE AREA

HVAC System, West End, Level 1

4/28/2010

57708 CLEAN AC VENTS OVER GATES 21,23,41,43 AND 45

HVAC System, East End, Level 2

4/22/2010

57749 HOT CALL

HVAC System, Ticket Lobby, Level 2

4/27/2010

57792 HOT CALL

HVAC System, Ticket Lobby, Level 2

4/27/2010

57860 COLD CALL AND CLEAN AC FILTERS.

HVAC System, Atrium, Level 1

4/27/2010

57887 HOT CALL CENTRAL CONCOURSE

HVAC System, Atrium, Level 2

4/28/2010

Page 10 of 48Printed 7/6/2012 11:00:30 AM

Page 11: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

57939 AC CRADLE ON JB 49 NOT OPERATING PROPERLY

Jetbridge # 49

4/22/2010

57953 CLEAN VENTS

HVAC System, Connector Bridge, Level 1

4/27/2010

57959 HOT CALL

HVAC System, West End, Level 2

4/27/2010

58038 HOT CALL CENTRAL TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

4/27/2010

58076 HOT CALL IN THE TSA CHECK BAGGAGE AREA.

HVAC System, West End, Level 1

4/28/2010

58092 HOT CALL IN THE CENTRAL CHECKPOINT AREA.

HVAC System, Atrium, Level 2

4/28/2010

58118 AC BLOWING HOT AIR

Jetbridge # 23

4/22/2010

58180 HOT CALL

HVAC System, West End, Level 2

4/28/2010

58354 HOT CALL AT CENTRAL INFO BOOTH

HVAC System, Atrium, Level 2

4/28/2010

58408 COLD CALL AT THE TSA / SWA SCREENING (T-POINT)

HVAC System, Atrium, Level 1

4/28/2010

58508 CHECK WATER FOUNTAINS TEMP.

Water Fountain - 27

4/28/2010

58518 AC NOT WORKING ON JETBRIDGE 28.

Jetbridge # 28

4/13/2010

58531 HOT CALL IN THE 3RD FLOOR SW INFLIGHT OFFICE.

HVAC System, East End, Level 3

4/28/2010

58635 COLD CALL IN THE BAGGAGE CLAIM AREA

HVAC System, West End, Level 1

4/28/2010

58636 CHECK AIR CONDITION IN JETBRIDGE-47

Jetbridge # 47

4/13/2010

58707 HOT CALL ON THE 3RD FLOOR

HVAC System, Atrium, Level 3 - WN Offices

4/28/2010

58761 TURN DOWN HEAT

HVAC System, West End, Level 2

4/28/2010

58812 AC ON THE JETBRIDGE @ G-50 IS NOT WORKING.

Jetbridge # 50

4/13/2010

58930 HVAC HOSE ON JB 47 TORN

Jetbridge # 47

4/13/2010

58965 HOT CALL AT T-POINT (TSA)

HVAC System, Atrium, Level 1

4/28/2010

59234 HOT CALL IN THE TSA SW CHECK BAGGAGE AREA.

HVAC System, West End, Level 1

4/28/2010

59248 AC CARRIAGE HOSE STUCK

Jetbridge # 47

4/28/2010

Page 11 of 48Printed 7/6/2012 11:00:30 AM

Page 12: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

59338 PC AIR HOSE NEEDS CLAMP

Jetbridge # 25

4/28/2010

59400 HOT CALL

HVAC System, Atrium, Level 2

4/28/2010

59454 AC NOT BLOWING

HVAC System, East End, Level 1

4/28/2010

59473 HOT CALL IN JETWAY #42 AIRCRAFT AREA.

Jetbridge # 42

4/28/2010

59568 HOT CALL IN THE SW INFLIGHT OFFICE.

HVAC System, Atrium, Level 3 - WN Offices

6/30/2010

59606 HOT CALL

HVAC System, Atrium, Level 2

6/30/2010

59733 HOT CALL

HVAC System, Ticket Lobby, Level 2

6/30/2010

59802 A/C THERMOSTAT NOT WORKING

HVAC System, Atrium, Level 3 - WN Offices

6/30/2010

59803 CONDENSATION LEAKING FROM A/C PIPE .

HVAC System, East End, Level 1

6/30/2010

59983 HOT CALL CENTRAL CHECKPOINT.

HVAC System, Ticket Lobby, Level 2

6/30/2010

59997 HOT CALL IN 1.W6.1

HVAC System, West End, Level 1

6/30/2010

60009 HOT CALL CENTRAL CHECKPOINT.

HVAC System, Ticket Lobby, Level 2

6/30/2010

60044 HOT CALL

HVAC System, Atrium, Level 2

6/30/2010

60225 HOT CALL AT CHECKPOINT

HVAC System, Ticket Lobby, Level 2

7/1/2010

60255 A/C NOT WORKING IN SW TRAINING ROOM

HVAC System, Atrium, Level 3 - WN Offices

7/1/2010

60262 A/C IS NOT WORKING

Jetbridge # 43

6/25/2010

60298 A/C NOT WORKING AT GATE 43

Jetbridge # 43

6/25/2010

60315 OPEN A/C CEILING VENTS

HVAC System, Atrium, Level 3 - WN Offices

7/1/2010

60370 HOT CALL IN BS SUPERVISOR OFFICE

HVAC System, East End, Level 1

7/1/2010

60445 HOT CALL

HVAC System, Ticket Lobby, Level 2

7/1/2010

60454 CHECK A/C UNIT AT EAST END

HVAC System, Atrium, Level 1

7/1/2010

60464 ADJUST AIR CONDITIONING

TSA SCREENING AREA

7/1/2010

Page 12 of 48Printed 7/6/2012 11:00:30 AM

Page 13: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

60481 HOT CALL IN TSA OSARP ROOM #OSR 1-Y10-4

HVAC System, Atrium, Level 1

7/1/2010

60498 HOT CALL FOR CENTRAL CONCOURSE

HVAC System, East End, Level 2

7/1/2010

60511 ADJUST AIR CONDITIONING

OFFICES - TSA BREAKROOM

7/1/2010

60523 CLEAN A/C VENTS IN RM# 3Y18.10

HVAC System, Atrium, Level 3 - WN Offices

7/1/2010

60532 A/C NOT WORKING IN TSA OSARP RM #1Y104.

HVAC System, Atrium, Level 1

7/1/2010

60534 HOT CALL

HVAC System, Atrium, Level 2

7/1/2010

60644 HOT CALL

HVAC System, Ticket Lobby, Level 2

7/9/2010

60703 REPAIR AC IN IDF ROOM # 1.W6.1 NOT WORKING

HVAC System, West End, Level 1

7/1/2010

60727 HOT CALL

HVAC System, Ticket Lobby, Level 2

7/1/2010

60728 HOT CALL

OFFICES - TSA BREAKROOM

7/1/2010

60729 HOT CALL IN WN MAINTENCE OFFICE UNDER 49.

HVAC System, Atrium, Level 1

7/1/2010

60730 HOT CALL WN OPS OFFICE

HVAC System, Atrium, Level 1

7/1/2010

60776 HOT CALL

HVAC System, West End, Level 1

7/1/2010

60778 HOT CALL

HVAC System, Atrium, Level 1

7/1/2010

60845 COLD CALL IN THE PILOT LOUNGE.

HVAC System, Atrium, Level 3 - WN Offices

7/1/2010

60848 HVAC HOSE TORN

Jetbridge # 50

6/25/2010

60872 HOT CALL

HVAC System, Ticket Lobby, Level 2

7/1/2010

60942 CHECK ROOF LEAK HUDSON NEWS

Roof, West End, Level 3

7/1/2010

61024 A/C BLOWING HOT AIR

Jetbridge # 28

6/25/2010

61069 CONDENSATION PUMP FAILED

HVAC System, West End, Level 1

7/9/2010

61126 HOT CALL @ THE TSA CHECKPOINT.

CHECKPOINT CENTRAL CONC

7/1/2010

61130 HVAC BLOWING HOT AIR

Jetbridge # 30

6/25/2010

Page 13 of 48Printed 7/6/2012 11:00:30 AM

Page 14: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

61141 REPLACE THE AIR CONDITION FILTERS

HVAC System, Atrium, Level 1

7/1/2010

61238 HOT CALL IN THE SW INFLIGHT OFFICE.

HVAC System, Atrium, Level 3 - WN Offices

7/9/2010

61254 CHECK WATER TEMPERATURE IN SWA BREAK ROOM

HVAC System, Atrium, Level 3 - WN Offices

7/1/2010

61266 A/C UNIT LEAKING

HVAC System, West End, Level 1

7/1/2010

61404 HOT CALL AT AMERICAN EAGLE OPERATIONS

HVAC System, East End, Level 1

7/1/2010

61457 CHECK WATER TEMP IN RR-28

HVAC System, West End, Level 2

7/1/2010

61488 HOT CALL @ THE SW TICKET COUNTER.

Floor, Ticket Lobby, Level 2

7/1/2010

61600 CHECK A/C LEAK BY FREIGHT ELEVATOR 13

HVAC System, Atrium, Level 1

7/9/2010

61754 HOT CALL WN TICKET COUNTER.

HVAC System, Ticket Lobby, Level 2

8/4/2010

61806 HOT FOR FOR GATES 29, 29, 32

Jetbridge # 28

7/2/2010

61969 CONDENSATION LEAK INSIDE HUDSON NEWS

HVAC System, East End, Level 2

7/29/2010

61997 CHECK THE AIR CONDITION COUPLER AT GATE-42

Jetbridge # 42

7/6/2010

62074 HOT CALL AT WN TICKETING

HVAC System, Ticket Lobby, Level 2

8/6/2010

62276 CLEAN AIR VENTS

HVAC System, East End, Level 2

7/29/2010

62314 HOT CALL

HVAC System, East End, Level 2

7/14/2010

62375 HOT CALL CENTRAL CHECKPOINT

HVAC System, Ticket Lobby, Level 2

8/6/2010

62442 COLD CALL IN 3 RD FLOOR PILOT LOUNGE.

HVAC System, Atrium, Level 3 - WN Offices

8/6/2010

62517 HOT CALL FOR SOUTHWEST TICKET COUNTER

HVAC System, Ticket Lobby, Level 2

8/13/2010

62522 HOT CALL FOR TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

8/6/2010

62555 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

8/6/2010

62590 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

62592 AC NOT WORKING IN AA OPS

HVAC System, East End, Level 1

8/6/2010

Page 14 of 48Printed 7/6/2012 11:00:30 AM

Page 15: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

62638 HOT CALL IN THE AMECIAN EAGLE SERVER ROOM.

HVAC System, East End, Level 1

8/6/2010

62704 HVAC PAN LEAKING

HVAC System, Atrium, Level 1

8/13/2010

62746 CLEAN A/C VENTS

Wall, West End, Level 2

7/29/2010

62851 DUST A/C VENTS AT GATE #40

Ceiling, West End, Level 2

8/6/2010

62878 DUST ALL A/C VENTS

HVAC System, West End, Level 2

8/6/2010

62919 DUST A/C VENTS

HVAC System, West End, Level 2

8/6/2010

62976 DUST ALL A/C VENTS AT GATE 44

Ceiling, West End, Level 2

8/6/2010

63038 HOT CALL

HVAC System, West End, Level 2

7/29/2010

63046 DUST ALL A/C VENTS AT GATE 45

Ceiling, West End, Level 2

8/6/2010

63075 AC BLOWING HOT AIR

Jetbridge # 46

8/5/2010

63109 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

8/13/2010

63138 CLEAN ALL A/C VENTS AT GATE 46

HVAC System, West End, Level 2

8/6/2010

63191 HOT AT TSA CHECK POINT AREA

HVAC System, Ticket Lobby, Level 2

8/6/2010

63192 PILOT'S LOUNGE LEVEL 3 IS FREEZING

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

63221 CLEAN ALL A/C DUCTS

HVAC System, West End, Level 2

8/6/2010

63292 HOT CALL AT THE SW TICKETING COUNTER

HVAC System, Ticket Lobby, Level 2

8/6/2010

63299 COLD CALL AT GATES 41-44

HVAC System, West End, Level 2

8/6/2010

63335 CLEAN ALL A/C DUCTS AT GATE 48

HVAC System, West End, Level 2

8/13/2010

63344 CLEAN ALL A/C DUCTS AT GATE 48

HVAC System, West End, Level 2

8/6/2010

63368 HOT CALL FOR SOUTHWEST TICKET COUNTER

HVAC System, Ticket Lobby, Level 2

8/6/2010

63375 CLEAN A/C DUCTS AT GATE 49

HVAC System, West End, Level 2

8/13/2010

63389 CLEAN VENT ABOVE DOOR WITH CIPHER LOCK…

Wall, West End, Level 1

8/6/2010

Page 15 of 48Printed 7/6/2012 11:00:30 AM

Page 16: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

63424 CHECK GATE-46, A/C BLOWING HOT AIR

Jetbridge # 46

8/6/2010

63450 DUST ALL A/C VENTS

HVAC System, West End, Level 2

8/13/2010

63455 CLEAN A/C VENTS

HVAC System, West End, Level 2

8/13/2010

63474 DUST ALL A/C VENTS AT GATE 51

HVAC System, West End, Level 2

8/25/2010

63544 DUST ALL A/C VENTS AT GATE 20

HVAC System, East End, Level 2

9/8/2010

63589 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

8/13/2010

63607 AIRCONDITION AT GATE 43 KEEPS SHUTTING ITSELF OFF

Jetbridge # 43

8/6/2010

63609 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

8/13/2010

63634 CLEAN A/C DUCTS AT GATE 21

HVAC System, East End, Level 2

8/18/2010

63684 DUST A/C VENTS

HVAC System, East End, Level 2

8/18/2010

63796 DUST ALL A/C VENTS AT GATE 23

HVAC System, East End, Level 2

8/18/2010

63833 DUST ALL VENTS

HVAC System, East End, Level 2

8/18/2010

63842 CLEAN A/C VENTS

HVAC System, East End, Level 2

8/13/2010

63859 HOT CALL AC JETBRIDGE 46

Jetbridge # 46

8/13/2010

63877 A/C UNIT NOR WORKING

Jetbridge # 43

8/13/2010

63878 A/C NOT WORKING

Jetbridge # 46

8/13/2010

63886 RESTORE A/C IN TSA OSEC ROOM

HVAC System, East End, Level 1

8/13/2010

63892 HOT CALL IN SW TRANING ROOM #3.Y9.33

HVAC System, Atrium, Level 3 - WN Offices

8/18/2010

63901 A/C NOT COOLING AT GATE 46

Jetbridge # 46

8/13/2010

63907 DUST ALL A/C VENTS

HVAC System, East End, Level 2

8/13/2010

63922 DUST A/C VENTS

HVAC System, East End, Level 2

8/13/2010

63946 HOT CALL TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

8/13/2010

Page 16 of 48Printed 7/6/2012 11:00:30 AM

Page 17: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

63952 HOT CALL IN THE SW TRAINING OFFICE .

HVAC System, Atrium, Level 3 - WN Offices

8/13/2010

64032 DUST ALL A/C VENTS AT GATE 27

HVAC System, East End, Level 2

8/18/2010

64045 DUST ALL A/C VENTS AT GATE 28

Wall, West End, Level 2

8/18/2010

64069 HOT CALL IN ROCKETS ROOM

HVAC System, West End, Level 3

8/18/2010

64105 CLEAN A/C VENTS

HVAC System, East End, Level 2

9/8/2010

64230 DUST ALL A/C VENTS AT GATE 30

HVAC System, East End, Level 2

9/8/2010

64274 COLD CALL IN SWA PILOT LOUNGE

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

64283 HOT CALL IN ROOM 3.Y9.33

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

64339 WATER LEAK REPORTS IN TSA SCREENING AREA

TSA SCREENING AREA

9/8/2010

64445 HOT CALL 3RD FLOOR, RM 3.Y9.33

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

64530 TEMPERTURE PROBE AT GATE 44

Jetbridge # 44

9/8/2010

64533 A/C VENT RESTING ON FIRE SPRINKLER

HVAC System, Atrium, Level 2

9/8/2010

64555 DUST AROUND THE A/C VENTS ABOVE THE TILED…

HVAC System, West End, Level 2

9/21/2010

64577 REPAIR BENT A/C VENT

HVAC System, Atrium, Level 2

9/21/2010

64578 CLEAN A/C VENTS

HVAC System, Atrium, Level 2

9/8/2010

64597 HOT CALL

HVAC System, West End, Level 1

10/27/2010

64662 ADJUST AC VENT

HVAC System, Atrium, Level 3 - WN Offices

9/8/2010

64687 DUST THE AC VENTS IN THE CONNECTOR BRIDGE AREA

HVAC System, Connector Bridge, Level 2

9/8/2010

64728 A/C NOT WORKING AT HUDSON NEWS

HVAC System, East End, Level 2

9/8/2010

64732 HOT AIR CALL @ JETWAY 51

Jetbridge # 51

9/30/2010

64755 HOT CALL IN WN BAG SCREEN

HVAC System, West End, Level 1

9/8/2010

64978 A/C HOSE HAS A HOLE

Jetbridge # 23

10/27/2010

Page 17 of 48Printed 7/6/2012 11:00:30 AM

Page 18: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

65064 CHECK ACU #C104

HVAC System, Connector Bridge, Level 1

9/21/2010

65074 HOT CALL IN RR-32

HVAC System, East End, Level 2

9/21/2010

65123 HOT CALL IN THE SW INFLIGHT OFFICES

HVAC System, Atrium, Level 3 - WN Offices

9/21/2010

65197 AC HOSE HAS A TEAR

Jetbridge # 41

9/21/2010

65331 HOT CALL

HVAC System, Ticket Lobby, Level 2

9/21/2010

65332 HOT CALL

HVAC System, West End, Level 2

9/21/2010

65339 HOT CALL WN CHECK BAGGAGE AREA.

HVAC System, Atrium, Level 1

9/21/2010

65437 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

9/30/2010

65548 COLD CALL IN THE FLIGHT OPS OFFICE.

HVAC System, Atrium, Level 3 - WN Offices

9/30/2010

65554 AC UNIT SHUT OFF

Jetbridge # 23

9/30/2010

65561 LEAK IN A/C HOSE

Jetbridge # 46

9/30/2010

65590 HOT CALL IN THE SW OPS OFFICE.

HVAC System, Atrium, Level 3 - WN Offices

9/30/2010

65592 CHECK WATER FOUNTIAN BY TSA SW CHECK BAGGAGE

HVAC System, Atrium, Level 1

9/30/2010

65632 HOT CALL WN OFFICES 3RD LEVEL

HVAC System, Atrium, Level 3 - WN Offices

10/27/2010

65673 HOT CALL IN WN MAINT OFFICE

HVAC System, West End, Level 1

9/30/2010

65759 AC SHUTS OFF

Jetbridge # 49

9/30/2010

65902 AC KEEPS SHUTTING OFF

Jetbridge # 49

10/28/2010

66008 COLD CALL

HVAC System, Atrium, Level 3 - WN Offices

10/29/2010

66031 COLD CALL IN RM 1.Y.104

HVAC System, Atrium, Level 1

10/29/2010

66055 COLD CALL IN RM # 3Y11.10

HVAC System, Atrium, Level 3 - WN Offices

10/29/2010

66082 HOT CALL TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

10/29/2010

66135 COLD CALL GATE 42

HVAC System, West End, Level 2

10/29/2010

Page 18 of 48Printed 7/6/2012 11:00:30 AM

Page 19: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

66272 A.C. SHUTS OFF

Jetbridge # 28

10/28/2010

66297 HOT CALL IN SWA INFLIGHT RM 3Y933

HVAC System, Atrium, Level 3 - WN Offices

10/29/2010

66321 HOT CALL IN THE SW ROCKETS ROOM

HVAC System, Atrium, Level 3 - WN Offices

10/29/2010

66361 HOT CALL IN THE ROCKET ROOM LEVEL 3.

HVAC System, Atrium, Level 3 - WN Offices

10/29/2010

66644 HOT CALL

HVAC System, Ticket Lobby, Level 2

10/29/2010

66865 HOT CALL

HVAC System, Atrium, Level 3 - WN Offices

11/9/2010

66898 A/C LEAKING WATER IN SW T-POINT AREA

HVAC System, West End, Level 1

11/9/2010

66906 HOT CALL AT THE TSA CHECKPOINT

HVAC System, Ticket Lobby, Level 2

11/9/2010

66917 HOT CALL

HVAC System, Ticket Lobby, Level 2

11/9/2010

Concourse C

4425 A/C NOT WORKING AT ALL IN KBR OFFFICE - RAMP LEVEL-CON. C

HVAC System, Concourse C, Level 1

1/22/2010

23251 JET BLUE OFFICES COLD CALL

OFFICES - JET BLUE

10/29/2009

24274 CONC C HOT CALL

CHECKPOINT C

10/29/2009

Main Terminal

3463 A/C LEAKING

OFFICES - VERIZON, PEGASUS

1/21/2010

3731 HOT CALL

HVAC System, Main Terminal West, Level 1

1/21/2010

23577 HOT CALL WN TICKET COUNTER

TICKET COUNTER - SWAL

10/29/2009

48325 COLD CALL IN BS BREAKROOM

HVAC System, Main Terminal East, Level 1

7/23/2009

48996 HOT CALL IN BS SUP'S OFFICE

HVAC System, Main Terminal East, Level 1

7/23/2009

49100 COLD CALL IN BAGGAGE CLAIM AREA

HVAC System, Main Terminal West, Level 1

6/12/2009

49287 REPAIR AC UNIT

HVAC System, Main Terminal West, Level 1

6/12/2009

49297 HOT CALL

HVAC System, Main Terminal, Baggage Claim

6/12/2009

Page 19 of 48Printed 7/6/2012 11:00:30 AM

Page 20: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

49312 HOT CALL @ LOWER INFO BOOTH.

HVAC System, Main Terminal, Baggage Claim

6/12/2009

49328 HOT CALL IN BS OFFICE

HVAC System, Main Terminal East, Level 1

6/12/2009

49334 HOT CALL FOR AOC(RACOM)

OFFICES - RACOM

6/12/2009

49338 HOT CALL FOR BUILDING SERVICES

OFFICES - AMIS, SAFETY, BUILDING SVC

6/12/2009

49525 HOT CALL BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

6/12/2009

49579 HOT CALL IN BS OFFICES

HVAC System, Main Terminal East, Level 1

11/5/2009

49580 HOT CALL WEST END OF BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

6/12/2009

49590 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

6/12/2009

49621 HOT CALL IN ROOM BEHIND TICKETCOUNTER

HVAC System, Main Terminal West, Level 2

6/10/2009

49674 CHECK THE AC IN THE OPERATION AREA

HVAC System, Main Terminal East, Level 1

6/10/2009

49792 HOT CALL IN THE PPM SHOP

HVAC System, Main Terminal West, Level 1

6/12/2009

49812 HOT CALL SW BAGGAGE CLAIM.

HVAC System, Main Terminal West, Level 1

6/12/2009

49819 HOT CALL DELTA BAGGAGE CLAIM

HVAC System, Main Terminal West, Level 1

7/10/2009

49841 HOT CALL MGMT CONFERENCE ROOM

HVAC System, Main Terminal West, Level 2

7/10/2009

49868 HOT CALL FOR DUTY OPS OFFICE IN AOC

OFFICES - RACOM

7/10/2009

49894 HOT CALL @ WN BAGGAGE CLAIM PODUIM

HVAC System, Main Terminal West, Level 1

7/10/2009

49913 HOT CALL WN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

7/10/2009

49935 HOT CALL IN BS OFFICE AREA

HVAC System, Main Terminal East, Level 1

7/23/2009

50025 HOT CALL IN OLD MDF ROOM

HVAC System, Main Terminal West, Level 1

7/10/2009

50057 HOT CALL FOR DELTA AIRLINES BREAKROOM

OFFICES - DELTA BAGGAGE

7/10/2009

50072 HOT CALL IN BAGGAGE CLAIM AT T-POINT

HVAC System, Main Terminal, Baggage Claim

7/10/2009

50077 HOT CALL BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

7/10/2009

Page 20 of 48Printed 7/6/2012 11:00:30 AM

Page 21: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

50078 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

7/10/2009

50097 HOT CALL @ THE AIRTRAN CHECK BAGGAGE AREA

HVAC System, Main Terminal, Tug Tunnel

7/10/2009

50110 HOT CALL IN BS AREA

HVAC System, Main Terminal East, Level 1

7/10/2009

50112 HOT CALL AT SWA TICKET COUNTER

HVAC System, Main Terminal West, Level 2

7/10/2009

50125 HOT CALL BS OFFICE AREA

HVAC System, Main Terminal East, Level 1

7/10/2009

50212 HOT CALL BY LOWER INFORMATION BOTH

HVAC System, Main Terminal, Level 1

7/23/2009

50213 HOT CALL IN DELTA BREAKROOM.

HVAC System, Main Terminal East, Level 1

7/10/2009

50229 HOT CALL IN PPM KEY SHOP.

HVAC System, Main Terminal West, Level 1

7/10/2009

50230 HOT CALL BUILDING SERVICES OFFICE AREA.

HVAC System, Main Terminal East, Level 1

7/10/2009

50236 HOT CALL BAGGAGE CLAIM AREA

HVAC System, Main Terminal, Baggage Claim

7/10/2009

50259 HVAC ALARM 3.W71 IDF

HVAC System, Main Terminal, Level 3

7/10/2009

50278 HOT CALL FOR FRONT OF SOUTHWEST TICKET COUNTER

TICKET COUNTER - SWAL

7/10/2009

50316 HOT CALL IN BS SUPPLY ROOM

BUILDING SVC SUPPLY ROOM

7/10/2009

50332 CHECK AC UNIT IN T134M (MECHANICAL ROOM)

HVAC System, Main Terminal West, Level 1

7/10/2009

50343 HOT CALL IN PPM SHOP

HVAC System, Main Terminal West, Level 1

7/10/2009

50494 HOT CALL IN BS ASST SUPERINTENDENT OFFICE.

HVAC System, Main Terminal East, Level 1

7/10/2009

50505 CHECK ON REPORTED CONDENSATION LEAK TSA AREA

Ceiling, Main Terminal, Tug Tunnel, Level 1

7/10/2009

50570 HOT CALL IN SW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

7/10/2009

50639 HOT CALL AE TICKET OFFICE

TICKET COUNTER - AMERICAN EAGLE

7/10/2009

50664 HOT CALL

HVAC System, Main Terminal West, Level 1

7/10/2009

50760 HOT CALL IN BS AREA

HVAC System, Main Terminal East, Level 1

7/23/2009

50861 HOT CALL IN BS ASST SUPERINTENDENT'S OFFICE.

HVAC System, Main Terminal East, Level 1

7/23/2009

Page 21 of 48Printed 7/6/2012 11:00:30 AM

Page 22: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

50929 HOT CALL

OFFICES - PPM

7/23/2009

50975 HOT CALL WN BAGGAGE CLAIM AREA

HVAC System, Main Terminal West, Level 1

7/23/2009

51035 AC LEAKING/CONDENSATION IN B/S AREA.

HVAC System, Main Terminal East, Level 1

7/23/2009

51048 HOT CALL

HVAC System, Main Terminal, Baggage Claim

7/23/2009

51049 COLD CALL

HVAC System, Main Terminal West, Level 2

7/23/2009

51062 COLD CALL IN MANAGEMENT OFFICE

HVAC System, Main Terminal West, Level 2

8/5/2009

51074 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal West, Level 1

7/24/2009

51102 CHECK ALL HVAC UNITS

HVAC System, Main Terminal East, Level 1

7/24/2009

51112 HOT CALL IN BS ASST SUPERINTENDENT OFFICE.

HVAC System, Main Terminal East, Level 1

8/5/2009

51121 COLD CALL FOR MANAGEMENT OFFICE

OFFICES - MANAGEMENT

8/6/2009

51143 HOT CALL AT WN TICKET COUNTER

TICKET COUNTER - SWAL

8/6/2009

51234 HOT CALL IN BS ASST SUPERINTENDENT OFFICE

HVAC System, Main Terminal East, Level 1

8/6/2009

51243 HOT CALL IN PPM SHOP

OFFICES - PPM

8/6/2009

51246 HOT CALL IN TSA BREAKROOM

HVAC System, Main Terminal, Baggage Claim

8/6/2009

51253 HOT CALL ALAMO RENTAL CAR

HVAC System, Main Terminal, Baggage Claim

8/6/2009

51254 HOT CALL IN BS ASST SUPERINTENDANT OFFICE

HVAC System, Main Terminal East, Level 1

11/5/2009

51277 COLD CALL FOR EOC

HVAC System, Main Terminal East, Level 1

8/6/2009

51279 FILTER CHANGE OUT IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

8/6/2009

51290 HOT CALL WN TICKET COUNTER

HVAC System, Main Terminal West, Level 2

8/6/2009

51294 HOT CALL @ BUDGET RENTAL CAR

HVAC System, Main Terminal West, Level 1

8/6/2009

51295 AC LEAKING IN THE TUG TUNNEL

HVAC System, Main Terminal, Tug Tunnel

8/6/2009

51308 CHECK VENT FAN

HVAC System, Main Terminal, Level 2

8/6/2009

Page 22 of 48Printed 7/6/2012 11:00:30 AM

Page 23: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

51375 HOT CALL BS OFFICE AREA

HVAC System, Main Terminal East, Level 1

11/5/2009

51378 AC LOUD IN CONFERENCE ROOM

HVAC System, Main Terminal West, Level 2

11/5/2009

51393 AC NOT WORKING IN BS AREA

HVAC System, Main Terminal East, Level 1

11/5/2009

51417 HOT CALL

HVAC System, Main Terminal, Level 2

11/5/2009

51509 HOT CALL IN THE OFFICE BEHIND DELTA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

11/5/2009

51526 HOT CALL FOR AMERICAN EAGLE/AIRTRAN OFFICE

HVAC System, Main Terminal East, Level 2

11/5/2009

51714 CHECK THERMASTAT IN CONSTRUCTION OFFICE.

HVAC System, Main Terminal East, Level 1

10/21/2009

51715 CHECK THERMASTAT IN CONSTRUCTION OFFICE.

HVAC System, Main Terminal East, Level 1

10/21/2009

51718 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

10/21/2009

51722 HOT CALL AMERICAN EAGLE OFFICE SPACE

TICKET COUNTER - AMERICAN EAGLE

11/5/2009

51753 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

10/21/2009

51868 HOT CALL IN MGMT OFFICES.

HVAC System, Main Terminal West, Level 2

10/21/2009

51877 HVAC LEAKING IN BS OFFICE

HVAC System, Main Terminal East, Level 1

10/16/2009

51893 COLD CALL IN MGMT OFFICE

HVAC System, Main Terminal West, Level 2

10/21/2009

51984 COLD CALL AT THE JETBLUE TICKET COUNTER

HVAC System, Main Terminal East, Level 2

12/30/2009

52087 CLEAN VENTS IN IN RR 11 AND 12

HVAC System, Main Terminal West, Level 1

10/16/2009

52092 CHECK CEILING WATER LEAK

HVAC System, Main Terminal East, Level 1

11/5/2009

52114 CEILING LEAKING IN BS OFFICE.

HVAC System, Main Terminal East, Level 1

2/10/2010

52235 COLD CALL RACOM

HVAC System, Main Terminal West, Level 1

11/5/2009

52383 COLD CALL BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

11/5/2009

52479 COLD CALL BAGGAGE CLAIM AREA

HVAC System, Main Terminal West, Level 1

11/5/2009

52569 A/C SHUTDOWN AFTER POWER FAILURE

HVAC System, Main Terminal, Level 2

2/10/2010

Page 23 of 48Printed 7/6/2012 11:00:30 AM

Page 24: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

52571 AC LEAKING IN BS CONFERENCE ROOM

HVAC System, Main Terminal East, Level 1

11/5/2009

52590 HOT CALL IN THE GT SUPERVISOR OFFICE

HVAC System, Main Terminal West, Level 1

11/5/2009

52603 COLD CALL OPS CONSTRUCTION'S OFFICE

HVAC System, Main Terminal East, Level 1

11/5/2009

52654 HOT CALL FOR IT ROOM OF JET BLUE

HVAC System, Main Terminal, Level 2

2/23/2010

52662 HOT CALL IN THE (DL) BAGGAGE CLAIM OFFICE

HVAC System, Main Terminal West, Level 1

11/5/2009

52682 HOT CALL AT THE SWA BAGGAGE CLAIM AREA

HVAC System, Main Terminal, Baggage Claim

11/5/2009

52691 HOT CALL IN TSA BREAKROOM

HVAC System, Main Terminal, Baggage Claim

11/5/2009

52749 HOT CALL BS OFFICE AREA

HVAC System, Main Terminal East, Level 1

10/29/2009

52775 HOT CALL IN BS SUPERVISOR OFFICE.

HVAC System, Main Terminal East, Level 1

11/5/2009

52860 AC LEAKING IN BS SUPERVISORS OFFICE

HVAC System, Main Terminal East, Level 1

11/5/2009

52866 HOT CALL

HVAC System, Main Terminal West, Level 2

11/5/2009

52940 REPAIR A/C LEAK

HVAC System, Main Terminal, Tug Tunnel

11/5/2009

53009 HVAC LEAKING ABOVE BAG #4

HVAC System, Main Terminal, Baggage Claim

10/29/2009

53025 REPAIR LEAK FROM A/C UNIT

HVAC System, Main Terminal East, Level 1

11/5/2009

53029 HOT CALL @ THE DELTA TICKET COUNTER.

HVAC System, Main Terminal East, Level 2

11/5/2009

53037 THERMSTAT NOT WORKING

HVAC System, Main Terminal East, Level 2

11/5/2009

53066 REMOVE LEAKING PAN FROM THE CEILING

HVAC System, Main Terminal East, Level 2

11/5/2009

53512 CONDENSATION COMING FROM THE ROOF

Ceiling, Main Terminal East, Level 2

10/29/2009

53535 AC NOT WORKING IN THE BS AREA.

HVAC System, Main Terminal East, Level 1

10/29/2009

53537 HOT CALL BEHIND DELTA TICKET COUNTER.

HVAC System, Main Terminal East, Level 2

10/29/2009

53548 CHANGE AC FILTER

HVAC System, Main Terminal, Tug Tunnel

10/29/2009

53591 HOT CALL SWAL SUPERVISOR OFFICE

TICKET COUNTER - SWAL

10/29/2009

Page 24 of 48Printed 7/6/2012 11:00:31 AM

Page 25: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

53607 HOT CALL WN CHECK BAGGAGE

HVAC System, Main Terminal, Tug Tunnel

10/29/2009

53692 REPAIR AC LEAK .

HVAC System, Main Terminal East, Level 2

10/29/2009

53732 HOT CALL IN RACOM

OFFICES - RACOM

10/29/2009

53749 HOT CALL BS OFFICES

HVAC System, Main Terminal East, Level 1

10/29/2009

53755 HOT CALL BAGGAGE CLAIM AREA

HVAC System, Main Terminal, Baggage Claim

11/4/2009

53860 HOT CALL IN PPM

HVAC System, Main Terminal West, Level 1

10/28/2009

53865 COLD CALL IN RACOM

OFFICES - RACOM

10/29/2009

53867 COLD CALL IN MANGEMENT OFFICE.

HVAC System, Main Terminal, Level 2

10/29/2009

53956 CONDENSATION LEAK BY BAGGAGE CLAIM #3.

HVAC System, Main Terminal West, Level 3

10/28/2009

53987 COLD CALL FOR BUILDING SERVICES OFFICES

OFFICES - AMIS, SAFETY, BUILDING SVC

10/28/2009

54003 HOT CALL FOR BAGGAGE CLAIM AREA

HVAC System, Main Terminal, Baggage Claim

10/28/2009

54008 HOT CALL AT INFORMATION @ LOWER LEVEL

HVAC System, Main Terminal East, Level 1

10/28/2009

54013 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

10/28/2009

54110 COLD CALL IN ALL OF THE IT OFFICES.

HVAC System, Main Terminal East, Level 1

12/30/2009

54176 A/C VENTS DIRTY IN B/S MEN RESTROOM.

HVAC System, Main Terminal East, Level 1

11/5/2009

54275 HOT CALL PPM OFFICES

OFFICES - PPM

11/5/2009

54282 LOST AND FOUND TOO COLD

OFFICES - LOST & FOUND ROOM

11/5/2009

54294 HOT CALL IN PPM OFFICE AREA

HVAC System, Main Terminal West, Level 2

11/5/2009

54330 HOT CALL PPM OFFICE AREA

HVAC System, Main Terminal West, Level 1

11/5/2009

54332 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

11/5/2009

54379 CLEAN VENT IN B/S AREA

HVAC System, Main Terminal East, Level 1

12/17/2009

54385 HOT CALL FOR SOUTHWEST BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

12/30/2009

Page 25 of 48Printed 7/6/2012 11:00:31 AM

Page 26: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

54386 HOT CALL

Fitness Center

12/30/2009

54400 COLD CALL IN THE MANAGEMENT OFFICE

HVAC System, Main Terminal West, Level 2

12/30/2009

54416 HOT CALL LOWER INFO BOOTH

HVAC System, Main Terminal, Level 1

12/30/2009

54473 COLD CALL IN MANAGEMENT AREA

HVAC System, Main Terminal West, Level 2

12/30/2009

54521 COLD CALL BY BAGGAGE CLAIM 1&2

HVAC System, Main Terminal West, Level 1

12/30/2009

54533 COLD CALL IN SW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

12/30/2009

54551 COLD CALL IN EXERCISE ROOM.

HVAC System, Main Terminal East, Level 1

12/30/2009

54564 HOT CALL EAST END BAGGAGE CLAIM

HVAC System, Main Terminal East, Level 1

12/30/2009

54594 HOT CALL AOC RACOM

HVAC System, Main Terminal West, Level 1

12/30/2009

54670 COLD CALL

HVAC System, Main Terminal, Baggage Claim

12/30/2009

54692 COLD CALL IN THE PPM OFFICES

HVAC System, Main Terminal West, Level 1

12/30/2009

54695 HOT CALL IN THE EXERCISE ROOM.

HVAC System, Main Terminal East, Level 1

12/30/2009

54706 HOT CALL

HVAC System, Main Terminal West, Level 1

12/30/2009

54743 HOT CALL IN THE SW CHECK BAGGAGE AREA.

HVAC System, Main Terminal, Tug Tunnel

12/30/2009

54746 HOT CALL IN THE TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

12/30/2009

54747 HOT CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal East, Level 1

12/30/2009

54754 HOT CALL IN THE TSA CHECKPOINT AREA

HVAC System, Main Terminal, Level 2

12/30/2009

54756 HOT CALL TSA BREAKROOM

HVAC System, Main Terminal West, Level 1

12/30/2009

54782 HOT CALL IN TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

12/30/2009

54924 HOT CALL @ THE TSA CHECKPOINT.

HVAC System, Main Terminal, Level 2

12/23/2009

54967 HOT CALL IN THE TUG TUNNEL

HVAC System, Main Terminal, Tug Tunnel

12/30/2009

54976 COLD CALL LOBBY AREA EAST END.

HVAC System, Main Terminal East, Level 2

12/30/2009

Page 26 of 48Printed 7/6/2012 11:00:31 AM

Page 27: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

54995 COLD CALL FOR BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55006 HOT CALL BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55008 COLD CALL BAGGAGE CLAIM #1 AREA

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55026 TURN DOWN HEAT

HVAC System, Main Terminal West, Level 2

12/30/2009

55127 COLD CALL

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55139 COLD CALL @ AMERCIAN EAGLE TICKET COUNTER.

HVAC System, Main Terminal West, Level 2

12/30/2009

55144 COLD CALL BAG 1 & 2

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55178 COLD CALL BY THE GRAB & GO.

HVAC System, Main Terminal East, Level 2

12/30/2009

55180 COLD CALL IN THE BS OFFICE AREA.

HVAC System, Main Terminal East, Level 1

12/30/2009

55194 COLD CALL

HVAC System, Main Terminal East, Level 2

12/30/2009

55195 HOT CALL

OFFICES - VERIZON, PEGASUS

12/30/2009

55196 COLD CALL

HVAC System, Main Terminal, Baggage Claim

12/30/2009

55221 COLD CALL

HVAC System, Main Terminal West, Level 1

12/30/2009

55348 HOT CALL IN TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

12/31/2009

55366 HOT CALL

HVAC System, Main Terminal West, Level 1

12/31/2009

55373 TURN DOWN HEATING SYSTEM

OFFICES - C-3 DISPATCH

12/31/2009

55382 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

12/31/2009

55410 COLD CALL DELTA TICKET COUNTER.

HVAC System, Main Terminal East, Level 2

12/31/2009

55416 COLD CALL MAIN TERMINAL LVL2.

HVAC System, Main Terminal East, Level 2

12/31/2009

55417 COLD CALL IN THE MANGEMENT OFFICE

HVAC System, Main Terminal West, Level 2

12/31/2009

55420 COLD CALL IN THE OPS OFFICE.

HVAC System, Main Terminal West, Level 1

12/31/2009

55455 HOT CALL IN THE TSA BREAKROOM

HVAC System, Main Terminal West, Level 1

12/31/2009

Page 27 of 48Printed 7/6/2012 11:00:31 AM

Page 28: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

55460 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

12/31/2009

55473 COLD CALL AT THE UPPER INFORMATION BOOTH

HVAC System, Main Terminal West, Level 2

12/31/2009

55496 COLD CALL RACOM

HVAC System, Main Terminal West, Level 1

2/9/2010

55505 HOT CALL FOR BAGGAGE CLAIM SOUTHWEST SIDE

HVAC System, Main Terminal, Baggage Claim

12/31/2009

55635 HOT CALL AT WN TICKET COUNTER

HVAC System, Main Terminal, Level 2

12/31/2009

55637 HOT CALL IN TSA BREAKROOM

HVAC System, Main Terminal West, Level 1

12/31/2009

55804 COLD CALL ALL OF BAGGAGE CLAIM.

HVAC System, Main Terminal, Baggage Claim

12/31/2009

55809 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

12/31/2009

55833 HOT CALL

HVAC System, Main Terminal West, Level 1

12/31/2009

55842 HOT CALL @ DELTA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

12/31/2009

55869 CHECK ALL HVAC UNITS

HVAC System, Main Terminal, Baggage Claim

12/31/2009

55872 COLD CALL

HVAC System, Main Terminal West, Level 2

12/31/2009

55885 COLD CALL @ DELTA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

2/9/2010

55900 HOT CALL AT TSA CHECK POINT

HVAC System, Main Terminal, Level 2

12/31/2009

55901 HOT CALL IN SWA SUPERVISOR OFFICE

HVAC System, Main Terminal West, Level 2

12/31/2009

55977 COLD CALL WN CHECK BAGGAGE

HVAC System, Main Terminal, Tug Tunnel

1/20/2010

56064 HOT CALL IN THE BAGGAGE CLAIM OFFICE AREAS.

HVAC System, Main Terminal West, Level 1

1/20/2010

56167 HOT CALL AT THE SWA TICKET COUNTER

HVAC System, Main Terminal West, Level 2

1/20/2010

56175 COLD CALL

HVAC System, Main Terminal West, Level 1

1/20/2010

56179 COLD CALL

HVAC System, Main Terminal West, Level 2

1/20/2010

56180 COLD CALL

HVAC System, Main Terminal West, Level 1

1/20/2010

56207 COLD CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal East, Level 1

1/20/2010

Page 28 of 48Printed 7/6/2012 11:00:31 AM

Page 29: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

56227 COLD CALL IN RENTAL CAR AREA

HVAC System, Main Terminal East, Level 1

1/20/2010

56260 COLD CALL

OFFICES - RACOM

2/3/2010

56264 COLD CALL

HVAC System, Main Terminal, Baggage Claim

1/20/2010

56265 COLD CALL IN MANAGEMENT OFFICE .

HVAC System, Main Terminal West, Level 2

1/20/2010

56271 HOT CALL IN RACOM

OFFICES - RACOM

2/9/2010

56279 JETBLUE OFFICE TOO HOT

HVAC System, Main Terminal East, Level 2

1/20/2010

56288 COLD CALL @ SW TICKET COUNTER.

HVAC System, Main Terminal East, Level 2

1/20/2010

56289 COLD CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

2/3/2010

56297 HOT CALL

OFFICES - RACOM

2/3/2010

56301 COLD CALL

HVAC System, Main Terminal, Level 2

1/20/2010

56339 COLD CALL

HVAC System, Main Terminal, Level 1

2/9/2010

56347 COLD CALL ALL OF BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

1/20/2010

56360 HOT CALL IN RACOM

OFFICES - RACOM

1/20/2010

56477 HOT CALL IN THE SMARTE CARTE OFFICE.

HVAC System, Main Terminal West, Level 1

1/20/2010

56507 HOT CALL IN THE TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

1/20/2010

56508 HOT CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

6/25/2010

56548 COLD CALL BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

1/20/2010

56637 HOT CALL AT DELTA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

2/9/2010

56699 COLD CALL

HVAC System, Main Terminal West, Level 1

2/9/2010

56727 HOT CALL IN PPM OFFICES.

HVAC System, Main Terminal West, Level 1

2/9/2010

56755 HOT CALL FOR RACOM

OFFICES - RACOM

2/9/2010

56832 TURN DOWN AIR IN C3

OFFICES - C-3 DISPATCH

2/9/2010

Page 29 of 48Printed 7/6/2012 11:00:31 AM

Page 30: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

56850 TOO COLD IN C3 OFFICE!

OFFICES - C-3 DISPATCH

2/10/2010

56855 HOT CALL IN TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

2/9/2010

56881 HOT CALL IN THE C3 OFFICE.

HVAC System, Main Terminal West, Level 1

2/9/2010

56915 HOT CALL IN THE TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

2/9/2010

56916 COLD CALL @ THE SW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

2/9/2010

56935 COLD CALL IN THE MAIN LOBBY

HVAC System, Main Terminal West, Level 2

2/9/2010

57004 COLD CALL LOWER LEVEL INFO BOOTH.

HVAC System, Main Terminal, Level 1

2/9/2010

57007 COLD CALL MAIN TERMINAL LOBBY AREA LVL 2.

HVAC System, Main Terminal, Level 2

2/9/2010

57136 COLD CALL IN C-3

HVAC System, Main Terminal West, Level 1

2/10/2010

57203 HOT CALL AT SWA TICKET COUNTER

HVAC System, Main Terminal West, Level 2

3/4/2010

57218 HOT CALL IN THE AA BAGGAGE CLAIM OFFICE.

HVAC System, Main Terminal West, Level 1

3/4/2010

57219 HOT CALL IN SMARTE CART OFFICE.

HVAC System, Main Terminal West, Level 1

3/4/2010

57233 HOT CALL

HVAC System, Main Terminal West, Level 1

3/4/2010

57265 COLD CALL AT THE LOWER-LEVEL INFORMATION BOOTH

HVAC System, Main Terminal, Level 1

3/4/2010

57283 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

3/4/2010

57298 COLD CALL

HVAC System, Main Terminal West, Level 1

3/4/2010

57308 HOT CALL FOR RACOM

OFFICES - RACOM

3/4/2010

57320 HOT CALL

HVAC System, Main Terminal West, Level 1

3/4/2010

57413 COLD CALL IN THE AIRPORT LOBBY

HVAC System, Main Terminal, Level 2

3/4/2010

57416 COLD CALL AT BAGGAGE CLAIM #1

HVAC System, Main Terminal, Baggage Claim

3/4/2010

57450 HOT CALL IN THE SMARTECART OFFICE.

HVAC System, Main Terminal West, Level 1

3/4/2010

57468 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

3/4/2010

Page 30 of 48Printed 7/6/2012 11:00:31 AM

Page 31: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

57470 HOT CALL AT TSA CHECKPOINT

HVAC System, Main Terminal, Level 2

3/4/2010

57528 COLD CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

3/4/2010

57532 HOT CALL FOR RACOM

OFFICES - RACOM

3/4/2010

57538 HOT CALL FOR TSA BREAKROOM

BREAKROOM - TSA

3/4/2010

57552 HOT CALL IN TSA BREAKROOM.

HVAC System, Main Terminal West, Level 1

3/4/2010

57561 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

57569 HOT CALL AT CHECKPOINT

HVAC System, Main Terminal, Level 2

3/4/2010

57646 HOT CALL IN RACOM OFFICE.

HVAC System, Main Terminal West, Level 1

3/4/2010

57648 COLD CALL @ THE LOWER LEVEL INFO BOOTH.

HVAC System, Main Terminal, Level 1

3/4/2010

57675 COLD CALL BY BAGGAGE CLAIM 1 & 2

HVAC System, Main Terminal, Baggage Claim

4/27/2010

57681 COLD CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

3/4/2010

57683 COLD CALL IN SMART CART OFFICE AREA.

HVAC System, Main Terminal West, Level 1

4/28/2010

57690 HOT CALL FOR RACOM

OFFICES - RACOM

3/4/2010

57711 COLD CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

4/28/2010

57750 HOT CALL BY BAGGAGE CLAIM 1 & 2.

HVAC System, Main Terminal, Baggage Claim

4/27/2010

57853 HOT CALL AT CENTRAL CHECKPOINT

HVAC System, Main Terminal East, Level 2

4/27/2010

57886 HOT CALL

HVAC System, Main Terminal West, Level 1

4/27/2010

57926 COLD CALL IN BS BREAKROOM.

HVAC System, Main Terminal East, Level 1

4/27/2010

57938 HOT CALL IN RACOM

OFFICES - RACOM

4/27/2010

57948 HOT CALL IN RACOM

OFFICES - RACOM

4/27/2010

57952 HOT CALL AT THE SWA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

4/22/2010

58042 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

4/28/2010

Page 31 of 48Printed 7/6/2012 11:00:31 AM

Page 32: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

58057 HOT CALL IN SW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

4/28/2010

58103 HOT CALL AT THE TSA CHECKPOINT

HVAC System, Main Terminal, Level 2

4/28/2010

58156 HOT CALL RACOM

HVAC System, Main Terminal West, Level 1

4/28/2010

58177 HOT CALL IN THE MAIN LOBBY

HVAC System, Main Terminal, Level 2

4/28/2010

58182 HOT CALL IN RACOM/AOC

OFFICES - RACOM

4/28/2010

58242 HOT CALL AT THE TSA CHECK POINT

HVAC System, Main Terminal, Level 2

4/28/2010

58243 HOT CALL AT THE SWA TICKET COUNTER

HVAC System, Main Terminal East, Level 2

4/28/2010

58248 HOT CALL IN THE BS AREA

HVAC System, Main Terminal East, Level 1

4/28/2010

58250 HOT CALL

HVAC System, Main Terminal West, Level 1

6/25/2010

58257 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

4/28/2010

58264 HOT CALL AT THE TSA CHECKPOINT.

HVAC System, Main Terminal, Level 2

4/28/2010

58265 HOT CALL IN THE TSA BDO OFFICE.

HVAC System, Main Terminal West, Level 1

4/28/2010

58272 HOT CALL IN BS SUPERVISOR OFFICE.

HVAC System, Main Terminal East, Level 1

4/28/2010

58273 COLD CALL IN BS BREAKROOM.

HVAC System, Main Terminal East, Level 1

4/28/2010

58274 HOT CALL BEHIND DELTA TICKET COUNTER.

HVAC System, Main Terminal East, Level 1

4/28/2010

58285 COLD CALL

OFFICES - SWAL BAGGAGE

4/28/2010

58289 HOT CALL

HVAC System, Main Terminal West, Level 2

4/28/2010

58291 HOT CALL

HVAC System, Main Terminal East, Level 2

4/28/2010

58292 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

58329 HOT CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

4/28/2010

58388 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

58401 COLD CALL FOR BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

4/28/2010

Page 32 of 48Printed 7/6/2012 11:00:31 AM

Page 33: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

58411 COLD CALL AT THE SWA BAGGAGE PODUIM

HVAC System, Main Terminal, Baggage Claim

4/28/2010

58424 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

58502 HOT CALL IN TSA VIDEO ROOM

HVAC System, Main Terminal West, Level 1

4/28/2010

58529 HOT CALL IN THE BDO OFFICE.

HVAC System, Main Terminal West, Level 1

4/28/2010

58566 COLD CALL LOWER INFORMATION BOOTH.

HVAC System, Main Terminal West, Level 1

4/28/2010

58590 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

58624 COLD CALL SW BAGGAGE CLAIM.

HVAC System, Main Terminal West, Level 1

4/28/2010

58638 HOT CALL

HVAC System, Main Terminal West, Level 2

4/28/2010

58768 HOT CALL IN BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

4/28/2010

58769 HOT CALL CHECKPOINT AREA.

HVAC System, Main Terminal West, Level 2

6/25/2010

58952 HOT CALL BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

4/28/2010

58968 CHECK AIR CONDITION UNIT DRIP PANS

HVAC System, Main Terminal West, Level 1

4/28/2010

58989 TURN HEAT OFF IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

4/28/2010

59015 COLD CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

59127 HOT IN THE DELTA BAGGAGE CLAIM OFFICE.

HVAC System, Main Terminal West, Level 1

4/28/2010

59134 HOT CALL IN THE PPM OFFICES

HVAC System, Main Terminal West, Level 1

4/28/2010

59155 HOT CALL IN SW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

4/28/2010

59204 HOT CALL FOR TSA BREAKROOM

HVAC System, Main Terminal, Tug Tunnel

4/28/2010

59221 HOT CALL

HVAC System, Main Terminal, Baggage Claim

4/28/2010

59245 HOT CALL

HVAC System, Main Terminal, Tug Tunnel

4/28/2010

59337 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

4/28/2010

59481 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

4/28/2010

Page 33 of 48Printed 7/6/2012 11:00:31 AM

Page 34: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

59486 HOT CALL

HVAC System, Main Terminal West, Level 1

4/28/2010

59589 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal East, Level 1

6/30/2010

59607 HOT CALL

HVAC System, Main Terminal West, Level 1

6/30/2010

59620 HOT CALL MAINT TERMINAL LVL 1.

HVAC System, Main Terminal, Level 1

6/30/2010

59621 COLD CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

6/30/2010

59865 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

6/30/2010

59937 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

6/30/2010

59971 HOT CALL

HVAC System, Main Terminal West, Level 1

6/30/2010

59986 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

6/30/2010

59991 A/C LEAKING UNDER THE WALL IN OPS CONSTRUCTION

HVAC System, Main Terminal East, Level 1

6/30/2010

59996 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

6/30/2010

60064 COLD CALL IN RACOM.

HVAC System, Main Terminal West, Level 1

6/30/2010

60097 CHECK A/C LEAK IN CONSTRUCTION PROJ MGT OFFICE

HVAC System, Main Terminal East, Level 1

6/30/2010

60139 COLD CALL RACOM

HVAC System, Main Terminal West, Level 1

6/30/2010

60226 HOT CALL IN RACOM

HVAC System, Main Terminal West, Level 1

7/1/2010

60245 COLD CALL IN RACOM

HVAC System, Main Terminal West, Level 1

7/1/2010

60311 HOT CALL OPS CONFERENCE ROOM.

HVAC System, Main Terminal West, Level 1

7/1/2010

60335 AC NOT WORKING

HVAC System, Main Terminal West, Level 1

7/1/2010

60360 HOT CALL JBT AND MID-AMERICA OFFICES

HVAC System, Main Terminal, Tug Tunnel

7/1/2010

60373 HOT CALL

HVAC System, Main Terminal, Level 1

7/1/2010

60480 HOT CALL WN BAGGAGE OFFICE.

HVAC System, Main Terminal East, Level 1

7/1/2010

60483 HOT CALL IN THE NEW TSA BREAKROOM.

HVAC System, Main Terminal East, Level 2

7/1/2010

Page 34 of 48Printed 7/6/2012 11:00:31 AM

Page 35: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

60500 A/C REGISTERS NEED TO BE CLEANED

OFFICES - MANAGEMENT

7/1/2010

60589 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

7/1/2010

60723 ADJUST A/C THERMOSTAT

HVAC System, Main Terminal East, Level 2

7/1/2010

60724 HOT CALL

HVAC System, Main Terminal East, Level 2

7/1/2010

60725 HOT CALL

HVAC System, Main Terminal East, Level 2

7/1/2010

60726 HOT CALL

HVAC System, Main Terminal West, Level 2

7/1/2010

60759 HOT CALL IN ERMC OFFICE

HVAC System, Main Terminal, Tug Tunnel

7/9/2010

60825 COLD CALL

HVAC System, Main Terminal West, Level 1

7/1/2010

60870 AC NOT WORKING BS AREA

HVAC System, Main Terminal East, Level 1

7/1/2010

60948 COLD CALL

HVAC System, Main Terminal West, Level 2

7/1/2010

60965 LEAKING HVAC UNIT

HVAC System, Main Terminal East, Level 1

7/9/2010

61031 LEAKING HVAC UNIT

HVAC System, Main Terminal West, Level 1

7/1/2010

61050 HOT CALL @ WN TICKET COUNTER

HVAC System, Main Terminal, Level 2

7/7/2010

61148 HOT CALL

OFFICES - BADGING

7/1/2010

61290 REPAIR AC IN THE PPM HALLWAY.

HVAC System, Main Terminal West, Level 1

7/1/2010

61292 REPAIR A/C VENT

HVAC System, Main Terminal East, Level 1

7/1/2010

61475 HOT CALL SW TICKET COUNTER

HVAC System, Main Terminal West, Level 2

7/1/2010

61557 HOT CALL DELTA BAGGAGE CLAIM

HVAC System, Main Terminal East, Level 1

7/1/2010

61800 SMART CART WANT A/C TURN DOWN IN THERE OFFICE

HVAC System, Main Terminal East, Level 1

7/9/2010

61823 HOT CALL AT THE JETBLUE TICKET COUNTER.

HVAC System, Main Terminal East, Level 2

7/7/2010

61829 COLD CALL IN BAGGAGE CLAIM AREA

HVAC System, Main Terminal, Baggage Claim

7/2/2010

61838 HOT CALL IN PPM HALLWAY

HVAC System, Main Terminal West, Level 1

7/2/2010

Page 35 of 48Printed 7/6/2012 11:00:31 AM

Page 36: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

62045 COLD CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

7/9/2010

62108 HOT CALL IN THE SMARTE OFFICE

HVAC System, Main Terminal East, Level 1

7/29/2010

62144 HOT CALL BAGGAGE CLAIM EAST

HVAC System, Main Terminal East, Level 2

7/9/2010

62145 HOT CALL IN ROOM #102.49

HVAC System, Main Terminal East, Level 1

7/9/2010

62270 HOT CALL

HVAC System, Main Terminal East, Level 1

7/14/2010

62283 HOT CALL FOR SOUTHWEST TICKET COUNTER

HVAC System, Main Terminal West, Level 2

8/6/2010

62288 ACC REQUESTS TDI RESET SYSTEM

HVAC System, Main Terminal East, Level 1

8/13/2010

62303 A/C NOT WORKING

HVAC System, Main Terminal West, Level 1

7/14/2010

62347 HOT CALL

HVAC System, Main Terminal West, Level 2

8/6/2010

62376 HOT CALL OPERATIONS OFFICE

HVAC System, Main Terminal West, Level 1

8/6/2010

62408 AIR CURTAIN NOT WORKING

HVAC System, Main Terminal East, Level 1

8/5/2010

62422 HOT CALL

HVAC System, Main Terminal West, Level 2

8/13/2010

62508 HOT CALL IN NEW BAGGAGE CLAIM AREA.

HVAC System, Main Terminal East, Level 1

8/6/2010

62729 HOT CALL SOUTHWEST TICKET COUNTER

TICKET COUNTER - SWAL

7/29/2010

62733 HOT CALL SOUTHWEST BAGGAGE CLAIM COUNTER

HVAC System, Main Terminal, Baggage Claim

7/29/2010

62820 BAGGAGE CLAIM HOT & HUMID

HVAC System, Main Terminal East, Level 1

7/29/2010

62835 INVESTIGATE IF THERE IS STAGNANT AIR BY BAG CLAIM

HVAC System, Main Terminal East, Level 1

7/29/2010

62952 HOT CALL TERMINAL

AIRPORT

8/6/2010

62953 COLD CALL ADMIN MANAGEMENT OFFICE

OFFICES - ADMIN

7/29/2010

62972 HOT CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

7/29/2010

63023 HOT CALL AT THE SW TICKET COUNTER

HVAC System, Main Terminal West, Level 2

8/18/2010

63126 HOT CALL NEW SOUTH OFFICE 101.55

HVAC System, Main Terminal East, Level 1

8/6/2010

Page 36 of 48Printed 7/6/2012 11:00:31 AM

Page 37: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

63127 HOT CALL FOR DELTA BAGGAGE OFFICE

OFFICES - DELTA BAGGAGE

8/6/2010

63195 HOT CALL IN OPERATIONS OFFICE

HVAC System, Main Terminal West, Level 1

8/6/2010

63419 HOT CALL SOUTHWEST TICKETING COUNTER

TICKET COUNTER - SWAL

8/6/2010

63433 HOT CALL DELTA BAGGAGE

OFFICES - DELTA BAGGAGE

8/18/2010

63610 AC NOT WORKING

HVAC System, Main Terminal West, Level 1

8/13/2010

63651 HOT CALL IN THE GT ADMIN OFFICE.

Floor, Main Terminal West, Level 1

8/13/2010

63869 HOT CALL

HVAC System, Main Terminal, Baggage Claim

8/18/2010

64074 THERMOSTAT IS BROKEN IN OFFICE

HVAC System, Main Terminal East, Level 1

9/8/2010

64306 CLEAN AC VENTS

HVAC System, Main Terminal East, Level 2

9/8/2010

64358 HOT CALL IN BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

9/8/2010

64433 CLEAN A/C VENTS IN BAGGAGE CLAIM

Wall, Main Terminal, Baggage Claim

10/27/2010

64593 HOT CALL AT THE SWA TICKET COUNTER

HVAC System, Main Terminal West, Level 2

10/27/2010

64616 A/C NOT WORKING IN SW BREAKROOM

HVAC System, Main Terminal East, Level 2

10/27/2010

64618 A/C IN BUILDING SERVICES BREAKROOM

OFFICES - AMIS, SAFETY, BUILDING SVC

10/27/2010

64713 COLD CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

9/8/2010

64733 HOT CALL IDF ROOM IN PARKING GARAGE

HVAC System, Main Terminal, Level 1

9/8/2010

64825 HOT CALL IN THE LOBBY AREA BY SSR BOTH

HVAC System, Main Terminal East, Level 2

10/27/2010

64853 HOT CALL

HVAC System, Main Terminal, Baggage Claim

10/27/2010

65097 HOT CALL

HVAC System, Main Terminal, Baggage Claim

9/21/2010

65107 COLD CALL

HVAC System, Main Terminal West, Level 1

9/21/2010

65124 HOT CALL IN THE BAGGAGE CLAIM BAGGAGE.

HVAC System, Main Terminal, Baggage Claim

9/21/2010

65403 HOT CALL

HVAC System, Main Terminal West, Level 2

9/21/2010

Page 37 of 48Printed 7/6/2012 11:00:31 AM

Page 38: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

65557 COLD CALL IN BAGGAGE CLAIM

HVAC System, Main Terminal, Baggage Claim

9/30/2010

65591 CHECK FCU-108

HVAC System, Main Terminal, Level 1

9/30/2010

65807 HOT CALL IN THE PPM HALLWAY

HVAC System, Main Terminal West, Level 1

9/30/2010

65812 COLD CALL IN THE BAGGAGE CLAIM AREA.

HVAC System, Main Terminal West, Level 1

9/30/2010

65873 HOT CALL IN (DL) BAGGAGE OFFICE

HVAC System, Main Terminal East, Level 1

10/29/2010

65898 HOT CALL

HVAC System, Main Terminal West, Level 1

10/29/2010

66071 COLD CALL LOST AND FOUND OFFICE

HVAC System, Main Terminal East, Level 1

10/29/2010

66098 AIR CONDITIONER FILITER HANGING FROM CELLING

HVAC System, Main Terminal East, Level 1

10/29/2010

66274 ADJUST TEMPERATURE SW BAGGAGE-TOO WARM

HVAC System, Main Terminal, Baggage Claim

10/29/2010

66704 HOT CALL SW TICKET COUNTER

HVAC System, Main Terminal West, Level 2

11/4/2010

66802 HOT CALL IN BAGGAGE CLAIM AREA.

HVAC System, Main Terminal, Baggage Claim

11/9/2010

66808 HOT CALL

HVAC System, Main Terminal West, Level 1

11/4/2010

66860 HOT CALL AT THE SOUTHWEST TICKET COUNTER

HVAC System, Main Terminal West, Level 2

11/9/2010

66892 A/C DRIPPING WATER IN TSA BAG SCREENING AREA

HVAC System, Main Terminal East, Level 1

11/9/2010

66905 HOT CALL

HVAC System, Main Terminal East, Level 2

11/9/2010

66941 COLD IN BAGGAGE CLAIM AT SSR DESK

HVAC System, Main Terminal East, Level 1

11/9/2010

NORTH RAMP

49859 FAN BELT HAS COME OFF FAN.

FIRE STATION #36

7/10/2009

50058 HOT CALL FOR N-60 GUARD SHACK

GATE N-60

7/10/2009

50479 CHECK AC

TRAILERS - GROUND TRANSPORTATION

7/10/2009

53551 REPLACE DRIP PANS FROM A/C UNITS

Roadway, Upper U Ramp, Level 2

10/29/2009

62607 BURNING SMELL COMES FROM AC UNIT

GATE N-60

7/29/2010

Page 38 of 48Printed 7/6/2012 11:00:31 AM

Page 39: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

63182 AIR CONDITIONER NOT WORKING-HOT

GATE N-60

8/18/2010

65168 HOT CALL IN N-60'S SHACK.

GATE N-60

9/21/2010

65192 AC NOT WORKING

GATE N-60

9/21/2010

Parking Garage

49361 A/C UNIT NOT WORKING

GT BOOTH

6/12/2009

49732 AC IN CAB STAND NOT WORKING

CURB ZONE 3

6/12/2009

49800 HOT CALL

GT BOOTH

6/12/2009

49823 AC @ CABSTAND LEAKING WATER.

Door, Garage, Level 1

6/12/2009

50235 TOO MUCH WATER DRAINING FROM AC PIPE.

GT BOOTH

7/10/2009

50305 HOT CALL

GT BOOTH

7/10/2009

50969 STOPPED UP DRAIN PIT FROM AC

GT BOOTH

7/23/2009

51562 REPAIR AIR CONDITIONING

GT BOOTH

10/21/2009

51563 A/C IN GT INFORMATION BOOTH IS OUT OF SERVICE

GT BOOTH

11/5/2009

51625 AC NOT COOLING IN CAB STAND

GT BOOTH

10/21/2009

54719 HOT CALL GT BOOTH

GT BOOTH

12/30/2009

54829 FOUNTAIN NOT WORKING IN FRONT OF AIRPORT

FOUNTAIN

12/30/2009

55011 FOUNTAIN AT PARKING GARAGE NOT WORKING

FOUNTAIN

12/30/2009

55893 RESTART FOUNTAIN IN FRONT OF AIRPORT

FOUNTAIN

1/20/2010

56176 REPAIR PUMP ON FOUNTAIN

FOUNTAIN

1/20/2010

59022 A/C UNIT WONT TURN OFF

GT BOOTH

4/28/2010

59029 FOUNTAIN OVERFLOWING

FOUNTAIN

4/28/2010

59185 AC UNIT IN THE CABSTAND IS BLOWING HOT AIR.

GT CAB STAND

4/28/2010

Page 39 of 48Printed 7/6/2012 11:00:31 AM

Page 40: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

59939 A/C NOT WORKING AT THE CAB STAND.

GT CAB STAND

6/30/2010

61139 AC NOT WORKING

GT BOOTH

7/1/2010

61277 HOT CALL AT THE GT SUPV OFFICE

GT BOOTH

7/2/2010

61332 HOT CALL

GT BOOTH

7/1/2010

62050 HOT CALL

GT BOOTH

7/9/2010

62150 AIR CONDITIONER NOT WORKING IN STAIRWELL

STAIRWELLS - ALL PARKING GARAGE STAIRWELLS

8/6/2010

62637 HOT CALL IN IDF ROOM # G1 IN THE GARAGE.

Electrical/Lighting System, Garage, Level 1

8/6/2010

63681 AC UNIT LEAKING

GT BOOTH

8/13/2010

64017 HOT CALL AT THE STAGING CAB BOOTH

CURB ZONE 3

8/18/2010

64281 A/C NOT WORKING

GT CAB STAND

9/8/2010

64341 A/C NOT WORKING IN GT OFFICE

GT BOOTH

9/8/2010

64754 HOT CALL IN GT OFFICE

GT BOOTH

9/8/2010

64899 REPAIR LEAKING WATER FOUNTAIN

FOUNTAIN

9/21/2010

South Ramp

3710 HOT CALL

SR-18

1/21/2010

49225 HOT CALL AT STATION #81.

FIRE STATION #81

6/12/2009

49285 HOT CALL EAST SIDE OF STATION #81.

FIRE STATION #81

6/12/2009

49298 CHECK HVAC UNITS

FIRE STATION #81

6/12/2009

50874 HOT CALL IN THE A&G OFFICE.

SR-14 (FLEET SHOP - A&G OFFICES)

7/23/2009

51169 WATER OVERFLOW @ AC UNIT

SR-22 (ELECTRICAL SHOP)

8/6/2009

51275 AC PUMP NOT WORKING IN ELECTRICAL SHOP

SR-22 (ELECTRICAL SHOP)

8/6/2009

51939 A/C UNITS 3&4 AT STATION 81 NOT WORKING

FIRE STATION #81

10/16/2009

Page 40 of 48Printed 7/6/2012 11:00:31 AM

Page 41: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

52251 HOT CALL IN HFD BLDG

FIRE STATION #81

11/5/2009

52370 NO HOT WATER IN FS81.

FIRE STATION #81

11/5/2009

52424 HOT WATER NOT WORKING @ THE FS81

FIRE STATION #81

11/5/2009

52447 WATER HEATER IN FS81 NOT WORKING

FIRE STATION #81

11/5/2009

52449 AC NOT WORKING @ FS81

FIRE STATION #81

11/5/2009

52462 CHECK HOT WATER HEATER IN ARFF BLDG

FIRE STATION #81

11/5/2009

53264 CHECK THE DUCT WORK IN THE A&G OFFICE

SR-14 (FLEET SHOP - A&G OFFICES)

10/29/2009

53265 CHECK DUCT WORK IN THE ELECT BREAKROOM.

SR-22 (ELECTRICAL SHOP)

10/29/2009

53510 CONDENSATION COMING FROM CEILING

SR-22 (ELECTRICAL SHOP)

10/29/2009

54572 RECONNECT PIPE TO AC DRAIN

SR-22 (ELECTRICAL SHOP)

12/30/2009

55137 HEATER NOT WORKING IN A&G PAINTER'S BARN.

SR-20

2/9/2010

55418 HEAT FAN MAKING NOISE IN FLEET SHOP.

SR-14 (FLEET SHOP - A&G OFFICES)

12/31/2009

55612 COLD CALL IN THE PAINTERS BARN.

SR-17

1/20/2010

55649 HEATER NOT WORKING @ FS81

FIRE STATION #81

12/31/2009

55652 HEATER FAN MAKING LOUD NOISE

SR-14 (FLEET SHOP - A&G OFFICES)

2/9/2010

56042 PUT COVER OVER AC UNIT IN FS81.

FIRE STATION #81

3/4/2010

56043 AC UNIT IN A&G SUPERVISORS OFFICE NOT WORKING

SR-14 (FLEET SHOP - A&G OFFICES)

1/20/2010

56181 APPARATUS FLOOR HEATER BROKEN

FIRE STATION #81

3/4/2010

56280 HOT CALL IN THE ELECTRICAL SHOP.

SR-22 (ELECTRICAL SHOP)

1/20/2010

56562 GAS SMELL IN PAINT BARN

SR-20

1/20/2010

57409 CHECK THE HEATERS IN THE FLEET SHOP

SR-14 (FLEET SHOP - A&G OFFICES)

3/4/2010

57644 COLD CALL @ FS81.

FIRE STATION #81

3/4/2010

Page 41 of 48Printed 7/6/2012 11:00:31 AM

Page 42: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

57669 HOT CALL FOR STATION

FIRE STATION #81

3/4/2010

58041 HOT CALL IN SOUTH VAULT

SOUTH ELECTRICAL VAULT

4/28/2010

58094 A/C UNIT NOT WORKING AT FIRE STATION

FIRE STATION #81

4/28/2010

58330 A&G STORAGE ROOM HEATER HAS A GAS SMELL

SR-17

4/28/2010

58370 CHECK FOR GAS SMELL IN A&G PAINT BARN.

SR-17

4/28/2010

60056 HOT CALL IN A&G OFFICES.

SR-14 (FLEET SHOP - A&G OFFICES)

6/30/2010

60082 COMPRESSOR NOT WORKING (A/C NOT WORKING)

SOUTH ELECTRICAL VAULT

6/30/2010

60279 FSS WINDOW UNIT NOT BLOWING

SR-14 (FLEET SHOP - A&G OFFICES)

7/1/2010

61010 CHECK AIR CONDITION UNIT AT FUEL FARM

SR-23

7/1/2010

61014 HOT CALL AT ARFF

FIRE STATION #81

7/1/2010

61863 AC NOT WORKING PROPERLY IN FS81.

FIRE STATION #81

7/2/2010

62302 CHECK AIR CONDITION VENT

SR-22 (ELECTRICAL SHOP)

7/14/2010

62318 HOT CALL

SOUTH ELECTRICAL VAULT

8/18/2010

62391 A/C NOT WORKING IN ELECTRIC HANGER

SR-22 (ELECTRICAL SHOP)

7/16/2010

62710 AC UNIT LEAKING WATER ON HER DESK

SR-22 (ELECTRICAL SHOP)

7/29/2010

62829 AC AT FIRE STATION IS MAKING LOUD NOISE

FIRE STATION #81

7/29/2010

62866 HOT CALL SOUTH VAULT

SOUTH ELECTRICAL VAULT

7/29/2010

62918 REPAIR A/C

SR-22 (ELECTRICAL SHOP)

8/6/2010

63203 AIR CONDITIONER IS OUT ELECTRICAL HANGAR

SR-22 (ELECTRICAL SHOP)

9/8/2010

63987 AIR CONDITION NOT WORKING PROPERLY

FIRE STATION #81

8/13/2010

64075 AC AT MS81 IS NOT WORKING PROPERLY

FIRE STATION #81

8/18/2010

64251 HOT CALL IN FS81 FRONT OFFICE.

FIRE STATION #81

9/8/2010

Page 42 of 48Printed 7/6/2012 11:00:31 AM

Page 43: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

64977 HOT CALL

FIRE STATION #81

9/21/2010

65170 HOT CALL

SR-14 (FLEET SHOP - A&G OFFICES)

9/21/2010

65210 A/C NOT WORKING IN A&G OFFICE

SR-14 (FLEET SHOP - A&G OFFICES)

9/21/2010

65314 CHECK A/C UNIT AT FIRST AID STATION-MS81

FIRE STATION #81

9/21/2010

65473 REMOUNT A WALL THERMSTAT IN THE KITCHEN

FIRE STATION #81

9/30/2010

66610 STATION 81 NO A.C.

FIRE STATION #81

10/29/2010

66690 HOT CALL AT A&G SUPERVISOR OFFICE

SR-14 (FLEET SHOP - A&G OFFICES)

11/4/2010

66869 AC NOT WORKING

SR-14 (FLEET SHOP - A&G OFFICES)

11/9/2010

66916 HOT CALL

SR-14 (FLEET SHOP - A&G OFFICES)

11/9/2010

SR-02 (FAA BLDG)

50954 A/C NOT WORKING AT FAA BLDG WX OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/23/2009

53084 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

11/5/2009

53103 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

11/5/2009

53673 COLD CALL IN FACILITIES AREA

HVAC SYSTEM, FAA BLDG, LEVEL 2

10/29/2009

53864 TOO COLD IN THE OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 2

10/29/2009

53879 HOT CALL IN SR-02

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2009

53895 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

10/28/2009

53958 HOT CALL IN ROOM #212 AND #216.

HVAC SYSTEM, FAA BLDG, LEVEL 2

10/28/2009

53975 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

10/28/2009

54329 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

54397 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

54534 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

Page 43 of 48Printed 7/6/2012 11:00:31 AM

Page 44: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

54552 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

54653 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

54689 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

12/30/2009

55023 HOT CALL IN WX OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

12/30/2009

55423 COLD CALL

HVAC SYSTEM, FAA BLDG, LEVEL 2

12/31/2009

55688 HOT CALL IN FACILITY BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

12/31/2009

55828 TOO HOT IN THE ROOM, ROOM # 202

HVAC SYSTEM, FAA BLDG, LEVEL 2

2/10/2010

55889 HOT CALL IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

12/31/2009

56130 HOT CALL OLD FAA BLDG.

HVAC SYSTEM, FAA BLDG, LEVEL 1

6/25/2010

56350 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

1/20/2010

56469 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

1/20/2010

56670 HOT CALL IN PDC CONFERENCE ROOM.

HVAC SYSTEM, FAA BLDG, LEVEL 1

2/9/2010

56752 HOT CALL FOR OLD FAA BUILDING

HVAC SYSTEM, FAA BLDG, LEVEL 1

2/9/2010

56771 COLD CALL IN FAA BLDG, 2ND LVL

HVAC SYSTEM, FAA BLDG, LEVEL 2

2/9/2010

57304 CHECK FOR EXHAUST FUMES COMING FROM HEATER

OFFICES - FACILITIES ADMINISTRATION

3/4/2010

57447 COLD CALL IN PDC OFFICES 146-147.

HVAC SYSTEM, FAA BLDG, LEVEL 1

3/4/2010

57568 HOT CALL IN SR-02

HVAC SYSTEM, FAA BLDG, LEVEL 1

3/4/2010

57714 HOT CALL IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/27/2010

57754 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

4/27/2010

58012 WEATHER OFFICE REPORTED A HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

58075 HOT CALL OLD FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

58421 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

Page 44 of 48Printed 7/6/2012 11:00:31 AM

Page 45: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

58699 HOT CALL AT THE WEATHER STATION

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

58744 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

4/28/2010

58773 HOT CALL IN THE ADMIN TRAINING ROOM.

HVAC SYSTEM, FAA BLDG, LEVEL 2

8/18/2010

58774 HOT CALL IN THE FAA TRAINING ROOM.

HVAC SYSTEM, FAA BLDG, LEVEL 2

4/28/2010

58810 HOT CALL IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

58923 HOT CALL IN WX OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

59028 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

59124 HOT CALL IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

59327 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

4/28/2010

59462 HOT CALL IN SR-2 BLDG (U.S. CUSTOMS)

HVAC SYSTEM, FAA BLDG, LEVEL 1

4/28/2010

59652 HOT CALL AT WEATHER STATION

HVAC SYSTEM, FAA BLDG, LEVEL 1

6/30/2010

59660 HOT CALL

OFFICES - CUSTOMS

6/30/2010

59791 HOT CALL IN CUSTOMS OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/9/2010

60366 HOT CALL IN THE FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/1/2010

60704 HOT CALL - FACILITIES ADMIN

OFFICES - FACILITIES ADMINISTRATION

7/1/2010

60710 HOT CALL IN WX OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/1/2010

61215 CHECK MOTOR MOUNTS

HVAC SYSTEM, FAA BLDG, LEVEL 2

7/2/2010

61729 HOT CALL AT OLD FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/1/2010

61741 AC NOT WORKING IN WEATHER OFFICE/FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/1/2010

61784 A/C ON 2ND FLOOR OF THE FAA BULD NOT WORKING

HVAC SYSTEM, FAA BLDG, LEVEL 2

7/9/2010

61976 BUILDING IS HOT & HUMID

HVAC SYSTEM, FAA BLDG, LEVEL 2

8/4/2010

62066 AC NOT WORKING CONDENSATION LEAK

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/9/2010

Page 45 of 48Printed 7/6/2012 11:00:31 AM

Page 46: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

62070 HOT & HUMID FACILITIES ADMIN OFFICES

HVAC SYSTEM, FAA BLDG, LEVEL 2

8/4/2010

62123 HOT CALL IN TRAINING ROOM FAA BUILDING

HVAC SYSTEM, FAA BLDG, LEVEL 2

7/9/2010

62292 CHECK AIR CONDITION CONDENSER

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/14/2010

62299 A/C NOT BLOWING COLD

HVAC SYSTEM, FAA BLDG, LEVEL 2

8/4/2010

62677 HOT CALL IN WEATHER OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/6/2010

62870 HOT CALL AC FOR FAA LEVEL 1 WEATHER STATION

HVAC SYSTEM, FAA BLDG, LEVEL 1

7/29/2010

63025 HOT CALL AT THE OLD FAA BUILDING

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/18/2010

63041 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/6/2010

63074 HOT CALL IN THE WEATHER OFFICE; OLD FAA BLDING

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/13/2010

63420 HOT CALL OLD FAA BUILDING

OFFICES - WEATHER STATION

8/6/2010

63497 HOT CALL IN THE WEATHER OFFICE .

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/6/2010

63498 HOT CALL IN THE PDC OFFICES.

CEILING, FAA BLDG, LEVEL 1

8/13/2010

63511 BUILDING IS HUMID

HVAC SYSTEM, FAA BLDG, LEVEL 2

8/13/2010

63520 HOT CALL IN THE PDC OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/13/2010

63887 A/C OUT AT THE OLD FAA ON THE 1ST FLOOR

HVAC SYSTEM, FAA BLDG, LEVEL 1

8/13/2010

64440 HOT CALL AT THE WEATHER OFFICE

HVAC SYSTEM, FAA BLDG, LEVEL 1

9/8/2010

64442 A/C NOT BLOWING

OFFICES - FACILITIES ADMINISTRATION

9/8/2010

64822 HOT CALL FOR WEATHER STATION ROOM

HVAC SYSTEM, FAA BLDG, LEVEL 2

10/27/2010

64824 HOT CALL IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/27/2010

65090 HOT CALL AT FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

9/21/2010

65100 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

9/21/2010

65357 A/C NOT BLOWING COLD

HVAC SYSTEM, FAA BLDG, LEVEL 2

9/21/2010

Page 46 of 48Printed 7/6/2012 11:00:31 AM

Page 47: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

65358 HOT CALL IN ROOM 216 AT THE FAA BUILDING

HVAC SYSTEM, FAA BLDG, LEVEL 2

9/21/2010

65362 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

9/21/2010

65799 HOT CALL OLD FAA WEATHER OFC

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/27/2010

65896 HOT CALL IN ROOM #219 (FAA BLDG) 2ND FLOOR

HVAC SYSTEM, FAA BLDG, LEVEL 2

10/29/2010

66028 HOT CALL

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2010

66047 NO A/C IN THE WEATHER OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2010

66096 COLD CALL AT THE FAA BULD.

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2010

66152 COLD CALL

OFFICES - FACILITIES ADMINISTRATION

10/29/2010

66280 CHECK CHILLERS AT THE FAA BLDG

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2010

66307 HOT CALL AT THE OLD FAA BULD.

HVAC SYSTEM, FAA BLDG, LEVEL 1

10/29/2010

66436 COLD CALL REBECCA MEYER'S OFFICE

OFFICES - FACILITIES ADMINISTRATION

10/29/2010

66829 HOT CALL IN PDC (MIKE WAGONER'S) OFFICE.

HVAC SYSTEM, FAA BLDG, LEVEL 1

11/9/2010

66897 HOT CALL AT THE OLD FAA BULD.

HVAC SYSTEM, FAA BLDG, LEVEL 1

11/9/2010

Taxi Staging Lot

50735 CLEAN AC FILTER

STAGING BOOTH

7/23/2009

53798 CHANGE FILTERS

CAB LOUNGE

10/29/2009

54680 COLD CALL, STAGING LOUNGE

CAB LOUNGE

12/30/2009

55168 CALL COLD FOR TAXI LOUNGE

CAB LOUNGE

12/30/2009

55299 HOT CALL AT THE TAXI STAGING LOUNGE.

CAB LOUNGE

12/30/2009

58591 COLD CALL @ THE TAXI STAGING LOT.

STAGING BOOTH

4/28/2010

59854 HOT CALL FOR CAB STAND

STAGING BOOTH

6/30/2010

61474 HOT CALL

CAB LOUNGE

7/1/2010

Page 47 of 48Printed 7/6/2012 11:00:31 AM

Page 48: Completed Work Orders - Houstonpurchasing.houstontx.gov/bids/T24289/HOU - HVAC... · Completed Work Orders WO # Service/Asset Between 06/01/2009 and 11/17/2010 Completed Property

Completed Work Orders

WO # Service/Asset

Between 06/01/2009 and 11/17/2010

Completed

Property

Filter: [Shop] = 'HVAC Contractor'

61766 HOT CALL STAGING LOUNGE

CAB LOUNGE

7/2/2010

64001 CLEAN AC VENTS IN STAGING LOT.

Grounds, Taxi Staging Lot, Level 1

10/29/2010

64087 HOT CALL

CAB LOUNGE

8/18/2010

66510 HOT CALL AT STAGING LOT

CAB LOUNGE

10/29/2010

Page 48 of 48Printed 7/6/2012 11:00:31 AM