Competive Power

download Competive Power

of 47

Transcript of Competive Power

  • 7/27/2019 Competive Power

    1/47

    COMPARATIVE OVERVIEW OF ENERGY COST IN SHORT

    TERM OPEN ACCESS MARKET AMONG ADVANCE, FIRST-CUM-FIRST-SERVE, DAY AHEAD AND CONTINGENCIES

    TRANSACTIONS AND COLLECTIVE TRANSACTION

  • 7/27/2019 Competive Power

    2/47

    ORGANIZATION

    Power System Operation Corporation Limited

    Eastern Regional Load Despatch Centre

    Kolkata

  • 7/27/2019 Competive Power

    3/47

    Presentation Outline

    Open Access Concept

    Power Trading Concepts

    Short Term Open Access

    Bilateral Transaction

    Collective Transaction

    Project

    http://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppthttp://localhost/var/www/apps/conversion/tmp/scratch_6/STOA_SIP.ppt
  • 7/27/2019 Competive Power

    4/47

    DEFINITION OF OPEN ACCESS IN THEELECTRICITY ACT, 2003

    . Open Access means the non-discriminatoryprovision for the use of transmission lines ordistribution system or associated facilities withsuch lines or system by any licensee, orconsumer, or a person engaged in generation in

    accordance with the regulations specified by theAppropriate Commission.

    Section 2(47) of Electricity Act 2003

  • 7/27/2019 Competive Power

    5/47

    INTRODUCTION

    Open Access is necessary for utilization of short timesurpluses.

    Efficient Market Mechanism to address supply / demandmismatches

    Encourage investment in Transmission

  • 7/27/2019 Competive Power

    6/47

    Agencies involved in Short-Term Open Access

    Transaction

    RLDC (s)

    SLDC (s)

    CTU STU (s)

    Buyer

    Seller

    Trader

  • 7/27/2019 Competive Power

    7/47

    Categorization of

    Open Access customers The transmission customers divided into three categories:

    (a) Long-term Access customers (LTA)- Thecustomers availing or intending to avail access to theinter-state transmission system for a period of 12 years to25 years shall be the long-term customers.

    (b) Medium-term Open Access customers (MTOA)-The persons availing or intending to avail open access tothe inter-state transmission system for a period of 3months to 3 years shall be the medium-term customers.

    (c) Short-term Open Access customers (STOA) -The persons availing or intending to avail open access tothe inter-state transmission system upto a period of 3months but 1 month at a time.

    STOA are categorized into two different ways: Bilateral Transaction

    Collective Transaction

  • 7/27/2019 Competive Power

    8/47

    Criteria for - Transmission Access

    Long Term Open access: In accordance with the Transmission Planning criteria as per

    IEGC

    Short Term Open access

    Inherent design margins Margins available due to variation in power flow schedule

    Margins available due to in-built spare transmission capacitycreated to cater future load growth

  • 7/27/2019 Competive Power

    9/47

    NODAL AGENCY

    For Long-Term and Medium Term Customers Central Transmission Utility (CTU), if its system is used

    For Short-Term Customers RLDC of the Region in which the drawal point is located.

  • 7/27/2019 Competive Power

    10/47

    SHORT TERM OPEN ACCESS

    CERC REGULATIONS, 2008

    Regulation, 2008 w.e.f 01.04.08

  • 7/27/2019 Competive Power

    11/47

    CERC/Regulations on Open Access

    Final Order issued : 30.01.2004

    Final Regulations issued : 30.01.2004

    Gazette Notification : 06.02.2004

    CERCs Order effective from 06.02.2004

    Amendments on 21-02-2005

    Revised Regulations for Open Access in ISTS issued on 25.1.2008.

    These revisions effective from 1.4.2008.

    Amendments on 20.05.2009

    Amendments on 28.10.2009

  • 7/27/2019 Competive Power

    12/47

    Highlights of CERC Regulations 2008 on Short-Term Open Accessand Amendment thereof

    S. No. Regulations, 2009 and Amendments thereof

    1. Transmission Charges: Bilateral:

    - Injection POC charges- Drawal POC charges

    Collective Transactions():

    - Injection POC charges

    - Drawal POC charges

    2. Retention by CTU- 25% to be retained by CTU

    - Balance adjusted with long term payment.

  • 7/27/2019 Competive Power

    13/47

    3. RLDC Charges :

    Bilateral:

    a. Application feeRs. 5000/-

    b. Scheduling Charges

    Rs. 2000/day for each RLDC involved

    c. Regional/State Transmission Charges

    Collective Transactions:

    a. Application feeRs. 5000/-

    b. Scheduling ChargesRs. 5000/day to NLDC for each State involved

    - NLDC retains Rs. 2000 and to Share Rs. 500 with each RLDCs.

    c. Regional/State Transmission Charges

    4. Open Access Duration

    Bilateral

    Advance (upto 3 months separate application for each month)

    FCFS

    Day Ahead

    Contingency

    Collective:

    Only Day ahead

  • 7/27/2019 Competive Power

    14/47

  • 7/27/2019 Competive Power

    15/47

    Case Study

    Short-Term Open Access transaction

    by Captive Power Plants

    A typical example:

    From : SAIL Durgapur Steel Plant (DVC),To : SAIL Bhilai Steel Plant (CSEB)

    Quantum : 20 MW

    Source : SAIL

  • 7/27/2019 Competive Power

    16/47

    Network Involved

  • 7/27/2019 Competive Power

    17/47

    Transmission Losses

    Injection POC

    Loss 3.2 %

    Withdrawal POC

    Loss 5.5 %

  • 7/27/2019 Competive Power

    18/47

    PROCEDURE FOR SCHEDULING OF

    OPEN ACCESS (BILATERAL

    TRANSACTION)

    Advance, FCFS, Day-Ahead & Contingency

  • 7/27/2019 Competive Power

    19/47

    ADVANCE SCHEDULING

    Advance Scheduling 3 months in advance Separate Application

    Month wise - each transaction

    Time Line for submission Last date for submission ( -10 / -5 / 0 days prior to end of current

    month MO for transaction in M1, M2, M3) Cut-off time of application: 17:30 Hrs. of last day (Day 0)

    Request for concurrence (RLDC) by 12:00 Hr. next day (Day 1)

    Concurrence - by 20:00 Hrs (Day 1)

    Congestion Information to Applicant next day 12:00 Hrs (Day 2)

    Revised Request next day 11:00 HRs. (Day3)

    E-bidding in case of Congestion (next day) (Day 4)

    Acceptance/Refusal of Scheduling Request (Day 5)

  • 7/27/2019 Competive Power

    20/47

    Time Line for Advance Scheduling

    M0 M1 M2 M3

    510 5

    Last Day for

    submission of

    Applications for

    transactions in

    M1, M2, M3

    Processing timefor RLDCs

  • 7/27/2019 Competive Power

    21/47

    e-Bidding Procedure Invitation of Bids from the concerned applicant

    period of congestion

    RTS/IR corridor expected to get over stressed

    Only Registered Users User ID & Password

    Electronic submission website of CTU

    Bid Closing time as specified

    Single Price Bid No Modification/withdrawal once submitted

    Bid Price - in addition to Open Access Transmission Charges

    Multiples of Rs. 10/ MWh . ( Min. Rs. 10/MWh)

    Mandatory - Non-participation Rejection of Application

    Acceptance - Decreasing order of Price Quoted

    Equal Price Bids Pro-rata

    Applicants getting less quantum than applied shall pay the charges quoted byhim.

    Applicant getting equal quantum of what sought by him shall pay the chargesquoted by the last Applicant getting approval of its full scheduling request.

  • 7/27/2019 Competive Power

    22/47

    e-Bidding ProcedureCase Study:

    Margin available in a corridor = 200 MW

    Bid Submitted by the applicants are as followed:

    Sl.

    No.

    Applicant

    NameBid Amount (MW)

    Bid Amount

    (Rs.)

    1 A 100 200

    2 B 50 1503 C 100 100

    4 D 50 100

    Sl.

    No.

    Applicant

    Name Bid cleared (MW)

    Bid cleared price

    (Rs.)

    1 A 100 150

    2 B 50 150

    3 C 33.33 100

    4 D 16.67 100

  • 7/27/2019 Competive Power

    23/47

    FIRST-COME-FIRST-SERVED BASIS Scope

    FCFS shall be considered only when transactions arecommencing & terminating in the same calendar month.

    Separate Application for each month To be submitted 4 days prior to date ofScheduling

    Processing time 3 days Processed on FCFS basisApplication Received upto 17:30 Hrs in a day tobe processed together same priority

    Application Received after 17:30 Hrs. - consideras received on next day Congestion Management pro-rata (proportional)

  • 7/27/2019 Competive Power

    24/47

    DAY-AHEAD BILATERAL TRANSACTION

    Applications received within 3 days prior to the day ofScheduling and up to 15:00 Hrs. of the day immediatelypreceding the day of scheduling shall be treated as samepriority.

    Processing will be done only after processing of theCollective Transactions of the Power Exchange (s).

    Congestion Management Pro-rata (proportional)

  • 7/27/2019 Competive Power

    25/47

    SCHEDULING OF BILATERAL

    TRANSACTION IN A CONTINGENCY

    Applications received within 15:00 Hrs. to 18:00

    Hrs. of the immediately preceding the day of

    scheduling shall be treated as same priority.

    Congestion ManagementPro-rata (proportional)

    Applications received after 18:00 Hrs. of the

    immediately preceding the day of scheduling to 6th

    time block prior to scheduling shall be considered.

    Congestion ManagementFirst Cum First Serve basis

  • 7/27/2019 Competive Power

    26/47

    DOWNWARD REVISON OF SCHEDULE In case of Advance Scheduling or First-Cum-First Served

    basis

    Minimum two (2) clear days notice.

    Transmission Charges and Operating Charges for 2 days.

    In case of all the accepted bilateral subject to the following

    condition as per I.E.G.C. clause 6.5.19 The injecting utility is a generator of unit capacity of 100 MW and

    above.

    At the time of applying for STOA the said unit of the generating

    station was mentioned in the application.

    The expected time of synchronization is mentioned in the

    application of revision.

    Margin Available could be utilized for scheduling of other

    Open Access Transactions

  • 7/27/2019 Competive Power

    27/47

    Example: For example: Say an Applicant has been scheduled for 10 days from

    21st day of a month to 30th day of a month for 100 MW on round theclock basis (i.e. for 2400 MWh per day). If this Applicant, on or before

    18th day of that month, submits request for revision of schedule to

    50MW on round the clock basis (i.e. 1200 MWh per day), the revised

    schedule will get implemented from the beginning of the transactions

    (i.e. 21st day of the month). The Applicant shall pay the TransmissionCharges for 2400 MWh per day for the period from 21st to 22nd day

    of the month. Whereas for the period from 23rd day to 30th day of

    the month, Transmission Charges shall be payable for 1200MWh per

    day.

    However, if the Applicant requests for such revision on 20th day ofthe month, his request will be implemented from 23rd day of the

    month. He shall pay Transmission charges for 2400 MWh per day for

    2 days i.e. from 23rd to 24th day of the month and for the

    remaining period he shall pay the Transmission Charges based

    on 1200MWh per day.

  • 7/27/2019 Competive Power

    28/47

    CURTAILMENT IN CASE OF

    TRANSMISSION CONSTRAINTS

    Transmission constraint or to maintain gridsecurity

    Curtailed in the manner, which in the opinion ofRLDC, would relieve transmission constraints/enhance grid security

    Open Access Bilateral Transactions wouldgenerally be curtailed first followed by the

    Collective Transactions Pro-rata refund of Transmission Charges

  • 7/27/2019 Competive Power

    29/47

    DEFAULT IN PAYMENT OF OPEN ACCESS

    CHARGES

    Nodal RLDC, at its discretion May not schedule the transaction

    or

    May cancel the scheduling of already scheduled

    transaction or

    May not entertain any Application of such Applicantin future until such time the default is cured.

    Simple interest at the rate of 0.04 % for each day ofdefault from the Due Date of Payment

    If cheque has been dishonored No cheque payment - next three (3) months

  • 7/27/2019 Competive Power

    30/47

    DISBURSAL OF PAYMENT

    Reconcile the Open Access Charges Nodal RLDC will reconcile the Open Access Charges collected during the previous

    month and disburse the Transmission Charges and Operating Charges by 7 working

    days from the issuance of monthly Regional Energy Accounting by the respective

    Regional Power Committees.

    Transmission Charges and Operating Charges for StateSystem Concerned STUs/SLDCs

    For ISTS To be disbursed to CTU

    Refund due to curtailment Within 15th day of the next month

  • 7/27/2019 Competive Power

    31/47

    PROCEDURE FOR SCHEDULING OFOPEN ACCESS (COLLECTIVETRANSACTION)

  • 7/27/2019 Competive Power

    32/47

    Agencies involved in Short-Term Open Access

    Collective Transaction

    Power Exchanges (IEXL & PXIL)

    NLDC

    RLDC (s) SLDC (s)

    CTU

    STU (s)

    Buyer

    Seller

    Trader

  • 7/27/2019 Competive Power

    33/47

    Collective Transactions (through PX) Nodal Agency

    National Load Despatch Center

    Both Buyers and Sellers of Collective transactions to beartransmission charges.

  • 7/27/2019 Competive Power

    34/47

    Outline STOA- Collective

    CERC Regulations on Open Access in inter-State

    Transmission, 2008 and amendments thereof

    Applicable for Scheduling of Open Access (Collective

    Transactions) w.e.f. 01.07.2011

  • 7/27/2019 Competive Power

    35/47

    Bidding procedure Time Line for submission of bid

    10 a.m. to 12 a.m. of preceding day NLDC communicates the margin to PX at 11:00 hrs. During the bid hours the bid can be revised or cancelled. Volume and price of the bid submitted by market players are stored

    in central order book. Matching of bids for each 15 minute time block in carried out.

    Price Determination Process (Provisional)The aggregate supply and demand curves will be drawn on Price-Quantity axes. The intersection point of the two curves will give Market ClearingPrice (MCP) and Market Clearing Volume (MCV).

    Successful members will be provided with clearing price and volume. After working out of provisional obligation funds available in the

    settlement account of the Members shall be checked with the

    Clearing Banks. In case sufficient funds are not available in the settlement account ofthe Member then his bid (s) will be deleted from further evaluationprocedure.

    Requisition for capacity allocation will be sent to NLDC at 13:00 hrs.

  • 7/27/2019 Competive Power

    36/47

    Bidding procedure

    NLDC at 14:00 hrs. send the available margin to the PXs. Power Exchange at 14:30 hrs. will run the fresh iteration

    for final MCP and MCV.

    Obligations will be sent to the bank of buying members at

    14:30 hrs. for settlement.At 15:00 hrs. cleared volume will be send to NLDC for

    incorporation in schedules.

    At 16:00 hrs. NLDC sends the cleared volume to respective

    RLDCs.

    At 17:30 hrs. NLDC shall confirm the accepted schedule to PX.

    At 18:00 hrs. RLDC issues schedule Rev-0.

  • 7/27/2019 Competive Power

    37/47

    Time Line for PX transaction

    1210 14

    Bid submission

    by applicants

    13 15 1611

    NLDC

    sends

    the

    margin

    to PX

    PX sends the cleared

    volume of different

    control area to NLDC

    NLDC informs

    about thecongestion in

    any link

    PX submits

    applicationto NLDC

    NLDC communicates

    to all RLDC about the

    cleared volume

    17:30

    RLDCs communicates toNLDC and NLDC

    confirms the schedule to

    PX

    18

    RLDC

    issuesschedu

    le Rev

    0

  • 7/27/2019 Competive Power

    38/47

  • 7/27/2019 Competive Power

    39/47

    Congestion Management- Market Splitting

    In deficit area the already cleared (provisionally) buyersbid get rejected on following criteria:

    Lower price

    Less volume

    Time priority

    Surplus

    partDeficit part

    ATC < Margin Cleared

    Congest

    ed link

  • 7/27/2019 Competive Power

    40/47

    area 1

    price

    MWh

    area 2

    price

    MWh

    (exchange volume)area surplus

    atMCP

    (exchange volume)area deficit

    atMCP

    neededcapacity

    neededcapacity

    availablecapacity

    availablecapacity

    availablecapacity

    availablecapacity

    price forarea 1

    price forarea 2

    Systemprice

    Congestion Management : Market Splitting

    SCHEDULE OF PARTICULAR ENTITY (BUYER/SELLER)

  • 7/27/2019 Competive Power

    41/47

    SCHEDULE OF PARTICULAR ENTITY (BUYER/SELLER)

  • 7/27/2019 Competive Power

    42/47

    Project

    COMPARATIVE OVERVIEW OF ENERGY COST IN

    SHORT TERM OPEN ACCESS MARKET AMONG

    ADVANCE, FIRST-CUM-FIRST-SERVE, DAY

    AHEAD AND CONTINGENCIES TRANSACTIONS

    AND COLLECTIVE TRANSACTION FOR BUYER

  • 7/27/2019 Competive Power

    43/47

    What have we done ??

    Select all the major power purchase utility across the

    country (25 states).

    Take the power transaction of the power purchase utility in

    Open Access for both bilateral and collective transaction.

    Categorize the power purchase cost for both bilateral and

    collective transaction across all the states taken.

    Evaluate and analyse the data and plot the graph

    accordingly.

    Analyse the graph.

  • 7/27/2019 Competive Power

    44/47

    Purchase Price of various STOA Bilateral

    and Collective transaction for the state of

    Assam

  • 7/27/2019 Competive Power

    45/47

    Weighted Average Purchase Price of

    Various STOA Bilateral Transaction for the

    state ofAssam

  • 7/27/2019 Competive Power

    46/47

    Inferences

    From the above two charts it is clear that, state Assam

    should reduce power purchase from FCFS and Advance as

    the price is maximum in that category and should go for

    either DAM market or power exchange. So that their

    average cost of purchase reduces.

  • 7/27/2019 Competive Power

    47/47