Competitive Entry Exemption: New Proposal - NYISO … · · 2013-12-13Competitive Entry...
Transcript of Competitive Entry Exemption: New Proposal - NYISO … · · 2013-12-13Competitive Entry...
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved.
Competitive
Entry Exemption:
New Proposal Dr. Nicole Bouchez Principal Economist, Market Design
New York Independent System Operator
Installed Capacity Working Group December 10, 2013
KCC
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 2 DRAFT – FOR DISCUSSION PURPOSES ONLY
Background
Extensive ICAP WG discussions on a Competitive Entry Exemption
(CEE) proposal have not resulted in broad support.
In an effort to provide what the NYISO believes is a tariff
enhancement, the NYISO has further revised the CEE proposal:
Exemptions based on PJM CEE rules, or
ICAP market clearing rules based on Hogan’s Alternative Pricing Rule
(“APR”) proposal, or
Rules based on both PJM’s CEE rules and Hogan’s APR proposal.
The NYISO is also considering an exemption for units needed for
reliability.
The NYISO is seeking stakeholder feedback on these proposals.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 3 DRAFT – FOR DISCUSSION PURPOSES ONLY
PJM Based CEE Proposal:
This proposal would not change the current buyer-side
mitigation (“BSM”) exemption tests and Offer Floor
rules. It adds to the ways a proposed new Installed
Capacity project in a Mitigated Capacity Zone
(presently Load Zones, G, H, I and J) can be exempt.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 4 DRAFT – FOR DISCUSSION PURPOSES ONLY
PJM Based CEE Proposal:
Additional opportunities for an exemption from BSM:
Create the rule based on the PJM Competitive Entry
Exemption rules and a reliability exemption:
A. Installed Capacity projects that receive no “out-of-market
funding” are exempt from the Offer Floor.
B. Exempts Installed Capacity projects that do receive “out-of-
market funding” only if the funding is received as a part of
competitive, non-discriminatory RFP open to all available
resources, both new and existing.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 5 DRAFT – FOR DISCUSSION PURPOSES ONLY
PJM Based CEE Proposal:
Criteria for A
Proposing to use the PJM criteria for no “out of market
funding”:
No costs are recovered from customers either directly or
indirectly through a non-bypassable charge linked to the
construction, or clearing in any ICAP auction, of the Installed
Capacity project;
No costs of the Installed Capacity project are supported
through any contract with a term of at least one year obtained
in any state-sponsored or state-mandated procurement
processes that are not Competitive and Non-Discriminatory;
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 6 DRAFT – FOR DISCUSSION PURPOSES ONLY
PJM Based CEE Proposal:
Criteria for A (Continued)
The Installed Capacity project does not have any
arrangements to seek or receive, and it does not receive, any
material payments from any government entity connected with
the construction, or the resource clearing in an ICAP auction
(industrial siting incentives and federal production tax credits
are permitted), or other material support though contracts,
with a term of at least one year, obtained in any state-
sponsored or state-mandated procurement processes
connected to the construction, or clearing in any ICAP
auction, or the resource; and
The Installed Capacity project submits a sworn, notarized
officer certification similar to the certification required for the
PJM self-supply exemption.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 7 DRAFT – FOR DISCUSSION PURPOSES ONLY
PJM Based CEE Proposal:
Criteria for B
Proposing to use the PJM criteria to determine if a
state procurement process is eligible for an exemption.
An RFP is competitive and non-discriminatory if:
a) both new and existing Installed Capacity Resources can
satisfy the requirements of the procurement process;
b) the selection criteria do not give a preference to new
Installed Capacity Resources;
c) the procurement process does not use indirect means to
discriminate against existing Installed Capacity Resources;
d) the requirements are fully objective and transparent; and
e) the procurement terms do not restrict the type of Installed
Capacity Resource that may participate in and satisfy the
requirements of the procurement.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 8 DRAFT – FOR DISCUSSION PURPOSES ONLY
APR Proposal
This proposal is included in the Evaluation of the New
York Capacity Market by FTI Consulting
http://www.nyiso.com/public/webdocs/markets_operations/doc
uments/Studies_and_Reports/Studies/Market_Studies/Final_
New_York_Capacity_Report_3-13-2013.pdf , see pages 83-
90.
The proposal is a design similar to the proposed (and
subsequently rejected ) ISO-NE “Alternative Capacity
Price Rule.”
The NYISO does not believe FERC’s decision for ISO-NE
means that a NYISO proposal would necessarily be rejected
given that ISO-NE has a significantly different design
including both a vertical demand curve and a forward
procurement.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 9 DRAFT – FOR DISCUSSION PURPOSES ONLY
APR Proposal
Allows BSM mitigated capacity offered below the buyer side mitigation
offer floor to clear, and meet capacity obligation(s). (This means that
more capacity would be purchased)
Allows resources supported by out of market contracts to meet capacity
market obligations (and receive capacity revenue) without impacting the
capacity price paid to existing capacity suppliers and allows state policy
objectives to be met without impacting existing generation.
Addresses the potential in the current design of the price sending a
signal for the construction of new capacity that is not actually needed
because capacity subject to an offer floor is not clearing the spot auction.
This is done by clearing all new capacity at the Initial Capacity Price.
As is the case today, capacity subject to an Offer Floor can only offer its
capacity in the ICAP Spot Market Auction (it cannot be certified
bilaterally, or be sold in the Capability Period or Monthly Auctions). This
is done so the mitigation measures can not be evaded.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 10 DRAFT – FOR DISCUSSION PURPOSES ONLY
APR Proposal: the details
How this is done:
Two spot capacity auction clearings are run each month.
In the first auction clearing, all offers of existing and new
generators are accepted without applying any offer floors.
• The price determined by this auction is referred to as the Initial
Auction Price.
• All the capacity that clears the first auction clearing will receive a
capacity award.
The second auction clearing uses the same offers but
replaces the offer of any unit subject to an offer floor with the
higher of the offer floor and the offer of the unit.
• The price determined by this auction is the Alternative Capacity
Price.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 11 DRAFT – FOR DISCUSSION PURPOSES ONLY
APR Proposal: the details
Pricing:
The Initial Auction Price will be paid to all new resources that
cleared in this initial clearing of the auction, whether or not
subject to an offer floor.
All existing capacity that clears the second clearing is paid the
Alternative Capacity Price.
• Existing capacity that does not clear the second clearing but cleared the
first clearing is paid the Initial Auction Price.
Capacity (including new capacity) that did not clear either
auction would not be selected to provide capacity.
Open questions:
How long does a new resource remain new?
Is it appropriate to revise the “Clearing Rule” on how long a
resource is subject to an offer floor when applying this
proposal?
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 12 DRAFT – FOR DISCUSSION PURPOSES ONLY
Reliability Exemption
Proposal
The NYISO is also considering an exemption for
incremental Installed Capacity projects that do receive
“out-of-market funding” if that project is needed for a
NYISO determined or NYISO recognized reliability
need (up to the MW needed for reliability.)
The NYISO intends for this requirement to cover both Bulk
and Non-Bulk Power Transmission Facility Reliability Issues.
The NYISO is considering if this exemption should be limited
to only the RNA base case identified reliability needs or if this
should apply to other scenarios as well.
© 2013 New York Independent System Operator, Inc. All Rights Reserved. 13 DRAFT – FOR DISCUSSION PURPOSES ONLY
Next Steps
The NYISO welcomes all comments on these
proposed CEE exemptions and how we can achieve
broad stakeholder support.
Written comments can be sent to
The NYISO plans on returning to the ICAP WG in
January.
Targeting BIC and MC February/March