Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard ....

39
Competency Standard - Signalling T HR CY 03000 ST Standard Version 1.0 Issued date: 15 June 2016 Important Warning This document is one of a set of standards developed solely and specifically for use on Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose. You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval. This document is uncontrolled when printed or downloaded. Users should exercise their own skill and care in the use of the document. This document may not be current. Current standards may be accessed from the Asset Standards Authority website at www.asa.transport.nsw.gov.au. © State of NSW through Transport for NSW

Transcript of Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard ....

Page 1: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

Competency Standard - Signalling

T HR CY 03000 ST

Standard

Version 1.0

Issued date: 15 June 2016

Important Warning This document is one of a set of standards developed solely and specifically for use on Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose. You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval. This document is uncontrolled when printed or downloaded. Users should exercise their own skill and care in the use of the document. This document may not be current. Current standards may be accessed from the Asset Standards Authority website at www.asa.transport.nsw.gov.au. © State of NSW through Transport for NSW

Page 2: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Standard governance

Owner: Manager Competency Systems, Asset Standards Authority

Authoriser: Principal Manager Industry and Technical Development, Asset Standards Authority

Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control Board

Document history

Version Summary of Changes

1.0 First issue.

For queries regarding this document, please email the ASA at [email protected] or visit www.asa.transport.nsw.gov.au

© State of NSW through Transport for NSW

Page 3: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Preface The Asset Standards Authority (ASA) is an independent unit within Transport for NSW (TfNSW)

and is the network design and standards authority for defined NSW transport assets.

The ASA is responsible for developing engineering governance frameworks to support industry

delivery in the assurance of design, safety, integrity, construction, and commissioning of

transport assets for the whole asset life cycle. In order to achieve this, the ASA effectively

discharges obligations as the authority for various technical, process, and planning matters

across the asset life cycle.

The ASA collaborates with industry using stakeholder engagement activities to assist in

achieving its mission. These activities help align the ASA to broader government expectations

of making it clearer, simpler, and more attractive to do business within the NSW transport

industry, allowing the supply chain to deliver safe, efficient, and competent transport services.

The ASA develops, maintains, controls, and publishes a suite of standards and other

documentation for transport assets of TfNSW. Further, the ASA ensures that these standards

are performance-based to create opportunities for innovation and improve access to a broader

competitive supply chain.

TfNSW has identified an absence of nationally recognised qualifications or competency

standards for certain specialised functions within the railway signalling discipline. It has also

identified the need to assist the Authorised Engineering Organisations (AEOs) in articulating

and assessing the competency of their personnel on certain signalling systems and functions

that are carried out on the TfNSW Transport Network.

This standard has been developed in response to this identified need and sets the generic

competency requirements for personnel to be recognised as competent to perform functions

within the signalling discipline on the TfNSW heavy rail network.

This document has been approved by the ASA Configuration Control Board and is a first issue.

© State of NSW through Transport for NSW Page 3 of 39

Page 4: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table of contents 1. Introduction .............................................................................................................................................. 5

2. Purpose .................................................................................................................................................... 5 2.1. Scope ..................................................................................................................................................... 5 2.2. Application ............................................................................................................................................. 6

3. Reference documents ............................................................................................................................. 6

4. Terms and definitions ............................................................................................................................. 7

5. Overview of competency standard ........................................................................................................ 8 5.1. TfNSW competence, compliance and licensing .................................................................................... 9 5.2. Domain and product specific requirements ........................................................................................... 9 5.3. Role and functions ............................................................................................................................... 10 5.4. Signalling functions and asset life cycle .............................................................................................. 11 5.5. Defining prerequisite competence requirements ................................................................................. 12 5.6. Proficiency levels ................................................................................................................................. 13 5.7. Competency requirements ................................................................................................................... 14

6. Signalling concept design generic competencies ............................................................................. 15

7. Signalling detailed design generic competencies ............................................................................. 19 7.1. Generic competency requirements for check, review and approve .................................................... 23 7.2. Signalling design evidence requirements guidelines ........................................................................... 28

8. Signalling commissioning generic competencies ............................................................................. 30 8.1. Signalling commissioning - evidence requirement guidelines ............................................................. 35

Appendix A Process flow for claiming competence ........................................................................... 37

© State of NSW through Transport for NSW Page 4 of 39

Page 5: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

1. Introduction Every Authorised Engineering Organisation (AEO) has a responsibility to ensure that

engineering activities carried out by an AEO on behalf of TfNSW are performed by suitably

trained and experienced personnel, that is, personnel designated as being 'competent' persons.

This is important to meet the legislative and regulatory obligations of the Rail Safety National

Law 2012, AS 4292.1 Railway Safety Management - General Requirements, Work Health and

Safety Act 2011 and the requirements stated in T MU MD 00009 ST AEO Authorisation

Requirements.

This standard sets the generic competency requirements for the designing and commissioning

functions within the signalling discipline. This standard provides additional information to an

AEO to develop a competency management system (CMS) that meets the minimum AEO

requirements, stated in T MU MD 00009 ST. It also provides guidance to the AEOs in the

assessment of personnel who are required to demonstrate competency within the signalling

discipline.

2. Purpose This standard aims at establishing the generic competency requirements of personnel who are

required to be recognised as competent to perform functions within the signalling discipline on

the TfNSW heavy rail network. This standard assists in the assessment and determination of

the competency of the signalling personnel in a consistent manner.

2.1. Scope This standard provides the competency requirements that can be incorporated into the AEO's

CMS and can be used for assessing the competency of the signalling personnel. It also

provides the context, drivers and definitions behind the standards that serve as a point of

reference for AEOs and other key stakeholders.

This standard is limited to generic competency requirements only and does not cover specific

domain or product knowledge elements which may be required by the AEO for network specific

licensing and authorisation; for example, domain and product requirements set out by the

relevant operator and maintainer or rail infrastructure manager (RIM).

This standard covers the requirements for the functions within the concept design phase,

detailed design phase and commissioning phase of the asset life cycle.

This standard does not cover other functions that exist in the asset life cycle.

© State of NSW through Transport for NSW Page 5 of 39

Page 6: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

2.2. Application This standard applies to AEOs who engage signalling personnel to perform work on the TfNSW

heavy rail network. This standard is intended to provide the AEOs with information on

function-specific minimum generic competency requirements.

3. Reference documents The following documents are cited in the text. For dated references, only the cited edition

applies. For undated references, the latest edition of the referenced document applies.

Australian standards

AS 4292.1 Railway Safety Management - General Requirements

Transport for NSW standards

ESG 001 Basic Principles and Configuration Standards

ESG 002 Signalling Practice Standards

ESG 003 Signalling Equipment Configuration Standard

ESG 004 Signalling Equipment Strategy

ESG 005 Signalling Operator Interface

ESG 007 Glossary of Signalling Terms

ESG 008 Management of Computer-Based Control Equipment for Signalling Systems

ESG 100 Signal Design Principles

SPG 0710 Type Approval Requirements for Signalling Systems and Equipment

T MU AM 04001 PL TfNSW Configuration Management Plan

T MU MD 00009 ST AEO Authorisation Requirements

Legislation

Rail Safety National Law (NSW) pursuant to the Rail Safety (Adoption of National Law) Act

2012 (NSW)

Work Health and Safety Act 2011 (NSW)

Other references

Network Rules and Network Procedures

Institution of Railway Signal Engineers

© State of NSW through Transport for NSW Page 6 of 39

Page 7: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

4. Terms and definitions The following terms and definitions apply in this document:

AEO Authorised Engineering Organisation; a legal entity (which may include a Transport

Agency as applicable) to whom the ASA has issued an ASA Authorisation

ASA Asset Standards Authority

AST Advanced-Signalling Technology

CMS competency management system

competent person a person identified or certified within an organisation to have required skills

and knowledge to perform specified tasks

domain knowledge specific to an application or industry, as opposed to generic knowledge

that is independent of the details of any particular application or industry

HARA hazard analysis and risk assessment

IDR interdisciplinary review; a specific term applied to a peer review process and interaction

with other disciplines focusing outside of the area of the author's subject of expertise

IST Intermediate Signalling Technology

railway signalling a series of electrical, electronic, and electro-mechanical units brought

together to form a system which controls the safe movement of trains, is a system used to direct

railway traffic and keep trains clear of each other at all times and safe movement of users at

level crossings

RAMS reliability, availability, maintainability and safety; a form of analytical techniques and

engineering safety management methods to examine the factors that may influence RAMS

aspects of systems. Working across several sectors providing pragmatic solutions to ensure

that designed products satisfy specific requirements throughout the system lifecycle

RIM rail infrastructure manager; as described in Rail Safety National Law (NSW) pursuant to the

Rail Safety (Adoption of National Law) Act 2012 (NSW)

SFS signalling functional specification

SME subject matter expert; person assessed or recognised as having the highest level of

competence (including knowledge, skills and practical experience) in a particular field or

discipline

SRS system requirements specification; a description of what the system should do in terms of

the system’s functions, interactions and interfaces with its operational environment. It

communicates the stakeholder requirements to the technical community who will specify and

build the system; alternatively, referred to as system requirements document.

© State of NSW through Transport for NSW Page 7 of 39

Page 8: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Sydney metropolitan area area including the Sydney CBD and suburbs of Sydney and

bounded by the Blue Mountains, Central Coast, Hunter, Illawarra / South Coast and Southern

Highlands regions of NSW

TfNSW Transport for New South Wales

TfNSW OD Transport for New South Wales Organisational Development

Transport Network the transport system owned and operated by TfNSW or its operating

agencies upon which TfNSW has power to exercise its functions as conferred by the Transport

Administration Act 1988 or any other Act

5. Overview of competency standard This standard provides the competency requirements for personnel to develop and demonstrate

the competencies and proficiency levels required to undertake the specified signalling functions.

It also specifies the minimum generic competency tasks and evidence criteria, relevant to these

functions.

The functions that are selected and addressed within this standard primarily exist across the

infrastructure designing, and testing and commissioning areas of signalling systems.

The competency tasks and associated evidence criteria presented within this standard

encompass the competency requirements of functions within a role. The AEOs should

determine the applicability of each competency task, based on the scope of work being carried

out in the project and tailor the criteria accordingly. AEOs may choose to specify on a

commercial basis more than is documented within this standard.

The competency standards are provided for those functions where there is limited information

available to enable AEOs to develop reasonable assessment criteria. They are not intended to

cover the exhaustive list of functions that exist over the full asset life cycle.

Note: Reference has been made to the competency requirements of the Institution of

Railway Signal Engineers as an internationally recognised framework and extracted

the relevant elements, while adding specific local requirements.

The competency standard is subject to review at regular intervals as the industry needs

changes.

Section 5.1 through to Section 5.7 explains the different elements of the competency standard

such as the roles and functions, proficiency levels, and competency requirements.

Appendix A explains the process flow and guides the AEOs in applying this standard.

© State of NSW through Transport for NSW Page 8 of 39

Page 9: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

5.1. TfNSW competence, compliance and licensing The ASA has presented the competency standards which are generic and considered the

minimum requirements to work on the TfNSW heavy rail network.

The standards are independent of network specific domain or product knowledge requirements

that are required to perform the services or operate the network.

This is illustrated in Figure 1.

© State of NSW through Transport for NSW Page 9 of 39

Figure 1 - Competency laws and regulations

5.2. Domain and product specific requirements The domain knowledge and product knowledge are specific to an application or industry area

and are gained from a combination of organisational standards, safety practices, locality, local

systems, infrastructure arrangements and principles, and local arrangements for work. This can

be independent or supplementary to generic knowledge.

Each RIM has developed processes and procedures for the management of the engineering

activities in their respective discipline area or area of operation (that is, domain). In many

instances, the processes were developed independently and over many years, often being

bespoke to the specific domain or discipline area. This has resulted in similar, but different,

approaches being used for the same area of activity from one domain or discipline to another.

To deliver particular engineering tasks, the AEO shall demonstrate competence to domain

specific requirements when undertaking an engineering task that affects any Transport asset.

Page 10: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

The AEO shall ensure that the person undertaking the designing, testing and commissioning

engineer functions has demonstrated domain and product specific competence relating to the

specific RIM domain for which works are being carried out.

The AEO can demonstrate its capabilities in meeting the domain or product competence by

satisfying the following:

• evidence requirements specified in Section 6, Section 7, Section 8 and achieving the

identified domain knowledge and product knowledge; this can vary slightly within each

railway network

• licensed to the RIM specific authorisation standard (refer to the applicable RIM for

guidance)

5.3. Role and functions This standard covers a range of generic role functions, rather than referring to generic job titles;

that is, the functions that a jobholder is expected to perform. The function is a speciality area of

a role comprised of a collection of tasks.

Figure 2 illustrates how the functions are attached to a particular role.

© State of NSW through Transport for NSW Page 10 of 39

Figure 2 - Functions within a role

Table 1 provides a list of high level functions and their description within any signalling roles.

Table 1 – Signalling functions and description

Function Description

Design The process of defining requirements or creating a solution or modifying the existing solution based on the identified requirements of that phase.

Check (review) A document based process of examination of the design to determine the adequacy of the output items of a specific development phase fulfils the requirements of that phase.

Verify A process of examination of the design followed by a judgement based on evidence that output items of a specific development phase fulfils the requirements of that phase in relation to completeness, correctness and consistency.

Approve A process based examination of the design to make sure all required steps have been completed in that phase in accordance with the approved quality requirements.

Page 11: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Function Description

Construct (install) The process of realisation of the design by building one or more products or set up the product to be functional as specified within the design phase.

The application of these functions to a particular job or role is explained in the following

examples:

• Example 1

A design engineer responsible for designing a part of a subsystem in the signalling

infrastructure requires competency for signalling detailed design.

• Example 2

An experienced signalling engineer responsible for verifying the detailed signalling design

for a signalling system requires competencies in detailed design, checking / reviewing and

verification.

• Example 3

A commissioning engineer responsible for deploying a major system into service requires

competencies for the testing and commissioning functions.

5.4. Signalling functions and asset life cycle The functions within the signalling systems cover the following:

• requirements specification (includes subsystem requirements)

• concept design

• preliminary design

• detailed design

• construction (build)

• factory acceptance subsystem testing

• site acceptance testing

• certification

• commissioning

• preventative

• corrective maintenance

• investigations

© State of NSW through Transport for NSW Page 11 of 39

Page 12: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

• technical strategy

• type approval

This standard covers the functions and the generic competency requirements within the concept

phase, design phase, and testing and commissioning phase of the TfNSW asset life cycle

model.

Figure 3 shows the alignment of the signalling functions within the TfNSW asset life cycle

model. The asset life cycle includes the following stages:

• demand/need

• plan

• acquire

• operate/maintain

• dispose

© State of NSW through Transport for NSW Page 12 of 39

Figure 3 – Signalling system life cycle model

5.5. Defining prerequisite competence requirements The mandatory requirement for defining competence requirements is stated in

T MU MD 00009 ST AEO Authorisation Requirements.

The level and depth of the requirements depends on industry requirements or those required by

the standards.

An AEO's processes shall satisfy quality and safety requirements, as a minimum.

Page 13: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

As part of the AEO authorisation process, AEOs shall have their own competency assessment

process as described in T MU MD 00009 ST.

The AEO may tailor the competency standard requirements to meet the project or industry

needs in consultation with the relevant stakeholders to align with the project requirements. Any

modification to the competency requirements stated in Section 6, Section 7 and Section 8 shall

be justified and be subject to audit. The ASA shall establish and maintain consistency among

AEOs’ assessments using the surveillance audit mechanism.

5.6. Proficiency levels The AEO’s competency management system shall define the proficiency levels that are relevant

and current for any particular function in accordance with the requirements of

T MU MD 00009 ST. While the AEO is responsible for setting a proficiency level framework, the

proficiency levels provided in Table 2 are suggested as most appropriate to be used with this

standard.

Table 2 – Proficiency levels and description

Proficiency Description

Level 0 A person who has had no previous experience of a particular task or activity. Requires supervision while performing tasks.

Level 1 A person who has limited knowledge. Requires supervision in more complex tasks and activities to allow that person to gain relevant experience. May perform simple tasks unsupervised where previous experience can be demonstrated.

Level 2 A person who has sufficient knowledge allowing to work unsupervised in tasks and activities within the relevant experience. May perform more complex tasks unsupervised where previous experience can be demonstrated. Requires supervision to perform more complex activities and tasks where previous experience cannot be demonstrated.

Level 3 A person who has demonstrated knowledge and experience, who can work unsupervised in tasks and activities within their relevant experience. May perform more complex tasks unsupervised where previous experience can be demonstrated. Has the relevant experience to execute the duties in a senior position as a leader and has the ability to solve problems. Can interpret and apply applicable domain standards and principles. Is considered to be a subject matter expert (SME) and has the capability and experience to supervise.

© State of NSW through Transport for NSW Page 13 of 39

Page 14: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

5.7. Competency requirements This standard establishes the signalling competency requirements for the personnel carrying

out the key signalling functions during the concept phase, design phase, and testing and

commissioning phase of the asset life cycle.

The competency requirements apply to the key functions that are broken down into tasks and

evidence criteria. The signalling personnel are assessed based on these tasks and the

evidence criteria that help to support and demonstrate the competency of a person.

The generic evidence and domain and product evidence should be mapped against each

evidence criteria of a given task.

The generic tasks within the signalling discipline that are identified in this standard are as

follows:

• application of principles

• general technical skills and experience

• railway operations

• interdisciplinary review (IDR)

• safety assurance

• product safety

• commission system into service

Table 3 lists some examples that explain the evidence criteria and provides appropriate

examples of evidence for a task.

Table 3 – Examples of tasks and evidence criteria

© State of NSW through Transport for NSW Page 14 of 39

Task Evidence criteria Appropriate evidence examples

Application of signalling design principles

Understanding of general signalling principles including signal positioning, calculation of braking distances, headways requirements and signal sighting

• assessment of logbook and currency of entries; these will typically include work experience storyboards detailing particulars of work carried out, training records (academic or industry) and so on

• demonstrate academic record to include relevant industry training

• example deliverables, meeting minutes • design review comments registers • reports of corrective actions • reassessment engineer reports • approved signalling design

documentation

Page 15: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Task Evidence criteria Appropriate evidence examples

General technical skills and experience

• creates concept design deliverables

• reliability, availability, maintainability and safety (RAMS) analysis

• understanding of operators’ requirements

• evidence of meeting minutes • design review comments registers • reports of corrective actions • reassessment engineer reports

The order in which the tasks and the evidence criteria are presented is not intended to imply

relative importance to each other; however, it attempts to correspond to the logical sequence of

tasks performed across the asset life cycle model.

Different levels of responsibility and proficiency apply to each task, rising from designer up

through checker to verifier. While the evidence criteria described for each task can be the same,

the appropriate proficiency level for the role shall be considered.

AEOs shall seek scalable evidence that reflects the range and complexity of the work being

carried out to ensure that the signalling personnel has the required breadth of knowledge and

the experience and expertise to enable them to carry out the required function in a competent

manner.

6. Signalling concept design generic competencies The signalling concept design is the phase of project planning that includes producing ideas and

taking into account the pros and cons of implementing those ideas. This phase of a project is

done to minimise the likelihood of error, manage costs, assess options and risk, and evaluate

the potential success of the intended project.

The signalling personnel undertaking works on behalf of the AEO during the concept design

phase shall demonstrate sufficient competence and understanding of minimum requirements

detailed in T MU AM 04001 PL TfNSW Configuration Management Plan; however, the size and

complexity of the work being carried out should be considered.

Table 4 through to Table 9 describes the minimum generic competence requirements for the

signalling concept design phase. These tables also indicate when the applicable RIM is required

to seek further evidence of domain and product competency requirements and minimum

evidence requirements.

The information provided in Table 4 through to Table 9 can also be used as a guide or template

for the AEOs to gather evidence of assessment to satisfy the AEO's CMS and their claim for

competence to the applicable RIM for licensing.

The signalling personnel shall have the assessable ability to produce the following key

deliverables during the concept design phase:

• signalling arrangement plan or scheme plan © State of NSW through Transport for NSW Page 15 of 39

Page 16: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

• control tables

• signalling functional specification (SFS)

• input into the assurance process in accordance with applicable configuration management

process

Note: Depending on individual project requirements, these deliverables are not

necessarily required at the concept design phase.

Table 4 – Concept design - application of principles generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

1.1 Application and interpretation of systems requirements specification (SRS) in the production of concept design Knowledge of producing signalling functional specification

E1, E7, E8, No specific domain or product requirements

1.2 Understanding of general signalling principles including signal positioning, calculation of braking distances, headways requirements and signal sighting Knowledge of ASA standards that cover signal design principles

E1, E9 Examples: double light signals, fully braked overlaps

1.3 Application of signalling principles in the production of concept design

E1, E9 Application of domain signal design principles such as ESG 100 Signal Design Principles Knowledge of domain signalling practices, Network Rules and Network Procedures Use of domain train modelling systems

Table 5 – Concept design - general technical skills and experience generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

2.1 Creates concept designs including supporting evidence for design decisions

E1, E5, E8 Knowledge of domain signalling systems, for example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

© State of NSW through Transport for NSW Page 16 of 39

Page 17: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

2.2 Interpret and analyse project scope, relevant functional and interface specifications, other documents determining the impacts of the project interfaces

E2, E3, E6 Knowledge of design requirements

2.3 Understands maintenance requirements in relation to signalling infrastructure Can recognise where RAMS is required and have input to the relevant client strategies to define system performance requirement

E1, E2, E3, E4, E5, E8

Knowledge of domain signalling equipment practices, such as ESG 003 Signalling Equipment Configuration Standard and ESG 004 Signalling Equipment Strategy and RAMS requirements

2.4 Carried out three previous similar size designs without supervision

E1, E2, E3, E4, E7

No specific domain or product requirements

2.5 Performed signalling design and carried out three previous similar size designs without supervision

E1, E2, E3, E4, E8

No specific domain or product requirements

Table 6 - Concept design – railway operations generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

3.1 Application and interpretation of higher level requirements in relation to railway operations

E1, E2, E3, E4, E5, E7, E8

Knowledge of producing domain subsystem requirements specification and operational requirement documentation

3.2 Understand and apply the railway operating rules and regulations pertaining to the signalling infrastructure

E1, E7, E8, Knowledge of domain signalling practices, for example, signalling practices and configuration standards, Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

Table 7 - Concept design - IDR generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

4.1 Understand different discipline’s design requirement and applications, for example, track alignment, overhead alignment, civil structures and bridges

E1, E2, E3, E4, E5, E7, E8

Knowledge of domain design management process

4.2 Apply and interpret SRS in relation to production of the concept design

E1, E7, E8, No specific domain or product requirements

© State of NSW through Transport for NSW Page 17 of 39

Page 18: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

4.3 Involved in the interdisciplinary review process or meetings and applied the outcomes

E1, E4, E7, E8

No specific domain or product requirements

4.4 Able to communicate and discuss the signalling design requirement at IDR meetings

E4, E7, E8 No specific domain or product requirements

Table 8 - Concept design– safety assurance generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.1 Understand the operator’s safety requirements Interpret and apply these requirements in the concept design where required

E1, E2, E3, E5, E6, E8

Knowledge of domain signalling practices, for example, signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008), Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

5.2 Interpret and analyse project safety requirements, to determine the impacts on the project life cycle

E1, E3, E4, E5, E7, E8

No specific domain or product requirements

5.3 Understand the safety requirements in relation to signalling infrastructure maintenance through the asset life cycle

E1, E3, E4, E5, E7, E8

Knowledge of domain requirements for signalling safeworking procedures

5.4 Interpret, analyse and apply risk mitigation associated with the project hazard analysis and risk assessment (HARA) process, where hazards, threats and safety issues are identified

E1, E3, E4, E5, E7, E8

No specific domain or product requirements

Table 9 - Concept design – product safety generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

6.1 Consider and interpret products’ safety requirements in a railway environment

E1, E3, E4, E5, E8

Knowledge of domain type approval requirements for signalling systems and equipment such as SPG 0710 Type Approval Requirements for Signalling Systems and Equipment

© State of NSW through Transport for NSW Page 18 of 39

Page 19: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

7. Signalling detailed design generic competencies The signalling detailed design is the phase of the asset life cycle where deliverables produced,

such as plans, control tables, engineering details, functional specifications and data are

required to sufficiently define the signalling system in alignment with the system requirements

specification (SRS).

The signalling personnel undertaking works on behalf of the AEO during the detailed design

phase shall demonstrate sufficient competence and understanding of minimum requirements

detailed in T MU AM 04001 PL; however, the size and complexity of the work being carried out

should be considered.

Table 10 through to Table 16 describes the minimum generic competence requirements for

signalling detailed design phase. These tables also indicate when the applicable RIM is required

to seek further evidence of domain and product competency requirements and minimum

evidence requirements.

The signalling personnel shall have the ability to produce the following key deliverables:

• lineside circuits

• interlocking circuits

• interlocking data

• interlocking configuration / architecture

• automatic train protection (ATP) data

• input into the assurance process in accordance with applicable configuration management

process

The information provided in Table 10 to Table 16 can also be used as a guide or template for

the AEOs to gather evidence of assessment to satisfy the AEO's CMS and their claim for

competence to the applicable RIM for licensing.

Table 10 - Detailed design - application of principles generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

1.1 Interpretation and application of SRS in the production of detailed designs

E1, E6, E7, E8,

Knowledge of producing domain SFS

1.2 Understand the general signalling principles and apply the requirements and outcomes of signal arrangements, control tables and signal sighting

E1, E3, E6, E8

Application of domain signal design principles and signalling practices

© State of NSW through Transport for NSW Page 19 of 39

Page 20: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

1.3 Understand and apply signalling standards in detailed design process

E1, E9 Application of domain signalling documentation and drawings standards Knowledge of domain circuit design standards, standard CBI system architectures and data constructs, such as Microlok 2

1.4 Management and distribution of the detailed design documentation through the project life cycle

E4, E5, E7, E8, E9

Application of domain signalling documentation and drawings standards

1.5 Verify and validate the veracity of documentation: • approval of detailed design

documentation • checking of detailed design

documentation • verification and review of detailed

design documentation

E1, E3, E5, E6, E7, E8, E9

Application of domain signalling documentation and drawings standards

1.6 Understand the testing and commissioning process: • process and respond to test logs • process and provision of design

modification

E1, E2, E3, E4, E6, E7, E8, E9

Knowledge of domain inspection and testing of signalling process

1.7 Consider product requirements Interpret and apply manufacturer product requirements and functional interfaces

E1, E2, E3, E6

Knowledge of domain signalling systems, for example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

1.8 Understand product operation in the rail environment and integration with other products

E1, E2, E3, E8

Knowledge of domain signalling systems, for example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

© State of NSW through Transport for NSW Page 20 of 39

Page 21: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 11 - Detailed design – general technical skills and experience generic competency

requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

2.1 Creates detailed designs using project documentation: • understand and apply control

tables • understand and apply signal

arrangements plan • extract and implement SFS

requirements

E1, E2, E3, E5, E6, E8

Application of domain signal design principles and signalling practices Knowledge of domain circuit design standards, standard CBI system architectures and data constructs such as Microlok 2 Knowledge of producing domain SFS

2.2 Interpret and analyse project scope, relevant functional and interface specifications, other documents determining the impacts of the project interfaces

E1, E2, E3, E6, E7, E8

No specific domain or product requirements

2.3 Performed detailed signalling design and carried out three previous similar size designs without supervision

E1, E2, E3, E5, E6, E7

No specific domain or product requirements

2.4 Perform detailed signalling design under supervision of a suitably competent mentor

E1, E2, E3, E8

No specific domain or product requirements

Table 12 - Detailed design – railway operations generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

3.1 Plan and program all design activities in relation to the operating railway and occupation schedule requirements

E1, E2, E3, E5, E7, E8

Application of domain signalling documentation, drawings standards and domain signalling design process

3.2 Understand and apply railway operating rules and regulations pertaining to the signalling infrastructure

E1, E2, E3, E6, E8

Knowledge of domain signalling practices, Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

© State of NSW through Transport for NSW Page 21 of 39

Page 22: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 13 - Detailed design – IDR generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

4.1 Interact with other disciplines to coordinate design, particularly in relation to other disciplines, for example, track, overhead, civil structures and bridges

E3, E4, E5, E6

Knowledge of domain design management process

4.2 Apply and interpret SRS in relation to testing and commissioning requirements

E3, E4, E5, E6, E7, E8

No specific domain or product requirements

4.3 Involved in the IDR process or meetings and applied outcomes

E1, E2, E3, E5, E7

No specific domain or product requirements

Table 14 - Detailed design – safety assurance generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.1 Understand operator’s safety requirements Interpret and apply these requirements in relation to signalling system life cycle

E3, E5, E6, E7, E8

Knowledge of domain signalling practices, Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

5.2 Understand the safety requirements in relation to signalling infrastructure maintenance through the asset life cycle

E1, E2, E5, E6, E8

Knowledge of domain requirements for signalling safeworking procedures

5.3 Understand, interpret, analyse and apply risk mitigation associated with the HARA process Identify hazards, threats and safety issues during the design life cycle

E2, E5, E7, E8

No specific domain or product requirements

Table 15 - Detailed design – product safety generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.4 Consider and interpret products safety requirements in a railway environment

E1, E2, E3, E6, E8

Knowledge of domain type approval requirements for signalling systems and equipment, for example, SPG 0710

© State of NSW through Transport for NSW Page 22 of 39

Page 23: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 16 - Detailed design – commission systems into service generic competency

requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

6.1 Understanding of the testing and commissioning process: • process and respond to test logs • process and provision of design

modification

E1, E2, E3, E6, E8

Knowledge of domain inspection and testing of signalling process

7.1. Generic competency requirements for check, review and approve The minimum generic competence requirements for the functions of check, review, verify,

validate and approve in the detailed design phase are provided in Table 17 through to Table 23.

These tables also indicate when the applicable RIM is required to seek further evidence of

domain and product competency requirements and minimum evidence requirements.

The signalling personnel shall have the ability to produce, check, review, verify, validate and

approve the following key deliverables:

• lineside circuits

• interlocking circuits

• interlocking data

• input into the assurance process in accordance with applicable configuration management

process

The information provided in Table 17 to Table 23 can also be used as a guide or template for

the AEOs to gather evidence of assessment to satisfy the AEO's CMS and their claim for

competence to the applicable RIM licensing.

Table 17 - Detailed design – check/review/approve - application of principles generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

1.1 Interpret and apply SRS in the production of detailed designs

E1, E2, E5, E6, E7, E8,

Knowledge of producing domain SFS

© State of NSW through Transport for NSW Page 23 of 39

Page 24: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

1.2 Applies first principles and the requirements and outcomes of signal arrangements, control tables and signal sighting during the check and review process

E1, E2, E3, E7, E9

Application of domain signal design principles and signalling practices Knowledge of signalling practices such as signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008)

1.3 Understand and apply signalling standards in detailed design process

E1, E2, E3, E5, E6, E8

Application of domain signalling documentation and drawings standards Knowledge of domain circuit design standards, standard CBI system architectures and data constructs such as Microlok 2

1.4 Manage and distribute the detailed design documentation through the project life cycle

E1, E2, E3, E4, E5

Application of domain signalling documentation and drawings standards

1.5 Verify and validate the veracity of documentation: • approve detailed design

documentation • check detailed design

documentation • verify and review of detailed

design documentation

E1, E2, E5, E6, E7

Application of domain signalling documentation and drawings standards

1.6 Understand the testing and commissioning process: • process and respond to test logs • process and provision of design

modification

E1, E2, E3, E4, E6, E8

Knowledge of domain inspection and testing of signalling process

1.7 Consider product requirements Interpret and apply manufacturer product requirements and functional interfaces

E1, E2, E3, E6

Knowledge of domain signalling systems For example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

1.8 Understand product operation in the rail environment and integrate with other products

E1, E2, E3, E6, E8

Knowledge of domain signalling systems For example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

© State of NSW through Transport for NSW Page 24 of 39

Page 25: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 18 - Detailed design – check/review/approve – general technical skills and

experience generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

2.1 Checks, reviews and approves detailed designs using project documentation: • understand and apply control

tables • understand and apply signal

arrangements plan • extract implement SFS

requirements

E1, E2, E3, E5, E6, E8

Application of domain signal design principles and signalling practices Knowledge of domain circuit design standards, standard CBI system architectures and data constructs such as Microlok 2 Knowledge of producing domain SFS

2.2 Interpret and analyse project scope, relevant functional and interface specifications, other documents determining the impacts of the project interfaces

E1, E2, E3, E6, E7, E8

No specific domain or product requirements

2.3 Check, review and/or approve detailed signalling design and carried out three previous similar size designs without supervision

E1, E2, E3, E6, E7

No specific domain or product requirements

2.4 Check, review and approve design under supervision of a suitably competent mentor

E1, E2, E3, E8

No specific domain or product requirements

Table 19 - Detailed design – check/review/approve – railway operations generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

3.1 Apply and interpret SRS in relation to railway operations

E1, E2, E5, E6, E8

Knowledge of producing domain SFS

3.2 Apply the first principles and the requirements and outcomes of signal arrangements, control tables and signal sighting during the check/review process and their effects on railway operations

E1, E2, E5, E6, E7

Application of domain signal design principles and signalling practices

3.3 Plan and program all design activities related to operating railway and occupation schedule requirements

E1, E2, E5, E7

Application of domain signalling documentation and drawings standards and domain signalling design process

© State of NSW through Transport for NSW Page 25 of 39

Page 26: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

3.4 Understand and apply the railway operating rules and regulations pertaining to the signalling infrastructure

E1, E2, E8 Knowledge of domain signalling practices, for example, signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008), Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

Table 20 - Detailed design – check/review/approve – IDR generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

4.1 Able to communicate and discuss the signal design requirement at interdisciplinary review meetings

E1, E2, E3, E4, E5, E6

No specific domain or product requirements

4.2 Interact with other disciplines to coordinate design, particularly in relation to other disciplines, for example, track, overhead, civil structures and bridges

E3, E4, E5, E6

Knowledge of domain design management process.

4.3 Apply and interpret SRS in relation to testing and commissioning requirements

E3, E4, E5, E6, E7, E8

No specific domain or product requirements

4.4 Involved in the IDR process or meetings and applied outcomes

E2, E3, E5, E8

No specific domain or product requirements

Table 21 - Detailed design – check/review/approve – safety assurance generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.1 Verify and validate the veracity of documentation: • approve detailed design

documentation • check detailed design

documentation • verify and review detailed design

documentation

E1, E2, E3, E5, E7, E8, E9

No specific domain or product requirements

© State of NSW through Transport for NSW Page 26 of 39

Page 27: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.2 Understand the operator’s safety requirements Interpret and apply these requirements in relation to signalling system life cycle

E3, E4, E5, E6, E7, E8

Knowledge of domain signalling practices, for example, signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008), Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

5.3 Understand the safety requirements in relation to signalling infrastructure maintenance through the asset life cycle

E2, E5, E7, E8

Knowledge of domain requirements for signalling safeworking procedures

5.4 Understand, interpret, analyse and apply risk mitigation associated with the HARA process Identify hazards, threats and safety issues during the design life cycle

E2, E5, E7, E8, E9

No specific domain or product requirements

Table 22 - Detailed design – check/review/approve – product safety generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

5.5 Consider and interpret products' safety requirements in a railway environment

E1, E2, E3, E6, E9

Knowledge of domain type approval requirements for signalling systems and equipment, for example, SPG 0710

Table 23 - Detailed design – check/review/approve – commission systems into service generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 7.2)

Domain and product evidence

6.1 Understand testing and commissioning process: • process and respond to test logs • process and provision of design

modification

E2, E5, E6, E9,

Knowledge of domain inspection and testing of signalling process

6.2 Apply ‘as built’ designs in relation to production of final design records to the domain drawing management system requirement

E1, E2, E3, E5, E6, E8

Application of domain signalling documentation and drawings standards and domain signalling design process

© State of NSW through Transport for NSW Page 27 of 39

Page 28: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

7.2. Signalling design evidence requirements guidelines Table 24 provides the reference to evidence requirements, type of evidence and the

deliverables required for each type of evidence for signalling design competence, which

includes concept design and detailed design.

Table 24 – Design evidence requirements guidelines

Reference Type of evidence Typical evidence required for concept design (deliverables)

Typical evidence required for detailed design (deliverables)

E1 Assessment of logbook and currency of entries, these will typically include work experience storyboards detailing particulars of work carried out, training records (academic or industry) and so on

Authenticated logbook entries: • signalling scheme plans • control tables • system requirements • SFS • equipment nomination

Authenticated logbook entries: • system requirements • SFS • signalling bonding plans • traction bonding • cable route and services

design • cable schematic plans • control tables • equipment nomination • interlocking circuit design • interlocking data design • lineside circuit design • location layouts

E2 Continue self-assessment and maintenance of work experience logbook

Authenticated logbook entries - detailing specific requirements for E1

Authenticated logbook entries - detailing specific requirements for E1

E3 Competency assessment to be demonstrated through continuing professional development

Authenticated logbook entries: • design production under

supervision • training in applicable

industry requirements • keeping abreast of new

equipment and continuous development in self-instruction and standards updates

Authenticated logbook entries: • design production under

supervision • training in applicable

industry requirements • keeping abreast of new

equipment and continuous development in self-instruction and standards updates

© State of NSW through Transport for NSW Page 28 of 39

Page 29: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Reference Type of evidence Typical evidence required

for concept design (deliverables)

Typical evidence required for detailed design (deliverables)

E4 Manage client interface and communicate requirements relating to proposed signalling infrastructure detailed at the project concept stage

Provision of documented evidence together with authenticated logbook entries: • documented meeting

minutes • report and design

submissions for client approval and acceptance

• address client review comments

• provide client clarifications in relation to design decision using an agreed design log mechanism

Provision of documented evidence together with authenticated logbook entries: • documented meeting

minutes • signal sighting committee

evidence • report and design

submissions for client approval and acceptance

• address client review comments

• design log to capture issues during design development

• provide client clarifications in relation to design decision using an agreed design log mechanism

E5 Follow process and document decisions made during design development

Company management system - follow prescribed company process and produce requisite design documentation

Company management system - follow prescribed company process and produce requisite design documentation

E6 Demonstrates the relevant skills and knowledge to undertake design works unsupervised

Authenticated logbook entries - has carried out three previous projects similar in nature and has documented evidence

Authenticated logbook entries - has carried out three previous projects similar in nature and has documented evidence

E7 Demonstrates knowledge and experience working unsupervised in tasks and activities relative to assignment May perform more complex tasks unsupervised where previous experience can be demonstrated Has the relevant experience to execute the duties in a senior position as a leader and has the ability to solve problems Can interpret and apply relevant domain standards and principles Considered to be an SME and has the ability and experience to provide mentorship

Can provide documented evidence together with authenticated logbook entries: • maintenance of design

logs throughout the design, test and commission life cycle

• can demonstrate use of domain standards

• can demonstrate some level of innovative applications to provide successful outcomes

• can demonstrate longevity and good all-round knowledge base in signalling principles application

• endorsement of workplace evidence and verification

Can provide documented evidence together with authenticated logbook entries: • maintenance of design

logs throughout the design, test and commission life cycle

• can demonstrate use of domain standards

• can demonstrate some level of innovative applications to provide successful outcomes

• can demonstrate longevity and good all-round knowledge base in signalling principles application

• endorsement of workplace evidence and verification

© State of NSW through Transport for NSW Page 29 of 39

Page 30: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Reference Type of evidence Typical evidence required

for concept design (deliverables)

Typical evidence required for detailed design (deliverables)

E8 Demonstrates knowledge and experience working unsupervised in tasks and activities relating to assignment May perform more complex tasks unsupervised where previous experience can be demonstrated Requires mentorship to perform more complex activities and tasks where experience cannot be demonstrated

Can provide documented evidence together with authenticated logbook entries: • maintenance of design

logs throughout the design, test and commission life cycle

• can demonstrate use of domain standards

• can demonstrate some level of innovative applications to provide successful outcomes

• can demonstrate a good all-round knowledge base in signalling principles application

Can provide documented evidence together with authenticated logbook entries: • maintenance of design

logs throughout the design, test and commission life cycle

• can demonstrate use of domain standards

• can demonstrate some level of innovative applications to provide successful outcomes

• can demonstrate a good all-round knowledge base in signalling principles application

E9 Demonstrate academic record to include relevant industry training or qualification, for example: • Intermediate Signalling

Technology (IST) Layouts

• Intermediate Signalling Technology (IST) Control Tables

• Advanced Signalling Technology (AST)

• Australian Quality Training Framework equivalent

Can provide documented evidence together with authenticated logbook entries: • academic achievements

by provision of certification

• relevant industry training by provision of certification

Can provide documented evidence together with authenticated logbook entries: • academic achievements

by provision of certification

• relevant industry training by provision of certification

8. Signalling commissioning generic competencies The signalling commissioning is the systematic process of ensuring that all equipment and

systems perform interactively according to the design intent and the operational and user

requirements.

The signalling personnel undertaking works on behalf of the AEO during the signalling

commissioning phase shall demonstrate sufficient competence and understanding of minimum

requirements detailed in T MU AM 04001 PL; however, the size and complexity of the work

being carried out should be considered.

Table 25 through to Table 30 describes the minimum generic competence requirements for the

signalling testing and commissioning phase. These tables also indicate when the applicable

RIM is required to seek further evidence of domain and product competency requirements and

minimum evidence requirements. © State of NSW through Transport for NSW Page 30 of 39

Page 31: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

The signalling personnel shall have the ability to produce the following key deliverables during

the testing and commissioning phase:

• inspection and test plans

• commissioning work packages

• input into the assurance process in accordance with ASA configuration management

process

The information provided in Table 25 to Table 30 can also be used as a guide or template for

the AEOs to gather evidence of assessment to satisfy the AEO's CMS and their claim for

competence to the applicable RIM for licensing.

Table 25 - Commissioning – application of principles generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

1.1 Application of general signalling principles

ET1, ET2, ET3, ET4, ET6, ET7, ET8

Application of domain signal design principles and signalling practices

1.2 Understanding and application of signalling principles in factory acceptance test process and final onsite system commissioning

ET7, ET9, ET10

Knowledge of domain inspection and testing of signalling process

1.3 Pre-planning of test activities and commissioning strategy: • assigning testing resources to

appropriate task or activity • programming testing activities

during the pre-testing and commissioning phases

• cataloguing and issuing of appropriate testing equipment for tasks or activities

ET7, ET9, ET10

Application of domain inspection and testing of signalling process

1.4 Management and distribution of the test documentation during pre-testing and commissioning

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

Application of domain inspection and testing of signalling process Application of domain signalling documentation and drawings standards

1.5 Verify the veracity of documentation: • collation and acceptance of

installation or construction documentation

• collation and acceptance of design documentation

• collation and acceptance of testing documentation

ET1, ET2, ET3, ET6, ET7, ET8, ET9

Application of domain inspection and testing of signalling process

© State of NSW through Transport for NSW Page 31 of 39

Page 32: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

1.6 Implementation and management of the test log and modification process during pre-testing and commissioning

ET8, ET9, ET10

Application of domain inspection and testing of signalling process

1.7 Consideration and interpretation of domain standard requirements Certify domain standards and requirements have been applied in the design and warrant the application during the testing and commissioning phase

ET7, ET9, ET10

Application of domain inspection and testing of signalling process

1.8 Consideration and interpretation of products requirements Implementation of product into service, incorporating all functional interfaces with other systems

ET7, ET9, ET10

Knowledge of domain signalling systems For example, signalling power supplies, traction return interfaces, lightning and surge protection requirements, compressed air systems and so on

Table 26 - Commissioning – general technical skills and experience generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

2.1 Creates and manages test log index including supporting evidence for test decisions

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

Application of domain inspection and testing of signalling Process

2.2 Interpret and analyse project scope, relevant functional and interface specifications, other documents determining the impacts of the project interfaces

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

No specific domain or product requirements

2.3 Demonstrated experience performing signal testing – as a guideline, six projects under mentorships or four projects as lead

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

No specific domain or product requirements

2.4 Worked at a senior level within the rail signalling environment, with an emphasis on inspection and testing of infrastructure

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

No specific domain or product requirements

© State of NSW through Transport for NSW Page 32 of 39

Page 33: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 27 - Commissioning – railway operations generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

3.1 Apply and interpret SRS in relation to railway operations

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

Knowledge of producing domain SFS

3.2 Plan and program all testing activities relating to operating railway and occupation schedule requirements

ET1, ET2, ET3, ET4, ET6 ET8, ET9, ET10

Application of domain inspection and testing of signalling process

3.3 Understand and apply the railway operating rules and regulations pertaining to the signalling infrastructure

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

Knowledge of domain signalling practices, for example, signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008), Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

Table 28 - Commissioning – IDR generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

4.1 Communicate and discuss the signal testing requirement at pre-commissioning and post-commissioning review meetings

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

No specific domain or product requirements

4.2 Interact with other disciplines to coordinate pre-testing and commissioning, for example, track, overhead, civil structures and bridges

ET1, ET2, ET3, ET6, ET7, ET8, ET9

Knowledge of domain design management process.

4.3 Apply and interpret SRS in relation to testing and commissioning requirements

ET1, ET2, ET3, ET4, ET5, ET6, ET7, ET8, ET9, ET10

No specific domain or product requirements

4.4 Has been involved in the IDR process or meetings and applied outcomes

ET1, ET2, ET3, ET4,

No specific domain or product requirements

© State of NSW through Transport for NSW Page 33 of 39

Page 34: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Table 29 - Commissioning – safety assurance generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

5.1 Apply signalling safeworking requirements for testing and commissioning phase Pre-commissioning briefings to disseminate signalling commissioning requirements during testing and commissioning phase

ET1, ET2, ET3, ET6, ET7, ET8, ET9

Application of domain requirements for signalling safeworking procedures

5.2 Validation of documentation: • collate and accept design

documentation • collate and accept installation or

construction documentation • collate and accept testing

documentation

ET1, ET2, ET3, ET6, ET7, ET8, ET9

Application of domain inspection and testing of signalling process

5.3 Understand the operator’s safety requirements Interpret and apply these requirements in relation to testing and commissioning of the signalling systems

ET10 Knowledge of domain signalling practices, for example, signalling practices and configuration standards (ESG 001 to ESG 005, ESG 007 and ESG 008), Network Rules and Network Procedures Domain requirements for signalling safeworking procedures

5.4 Understand the safety requirements in relation to signalling infrastructure maintenance through the asset life cycle

ET10 Knowledge of domain requirements for signalling safeworking procedures

Table 30 - Commissioning – commission systems into service generic competency requirements

Item reference

Evidence criteria Generic evidence (in Section 8.1)

Domain and product evidence

6.1 Apply and implement final designs into service in line with the domain specific requirements

ET7, ET9, ET10

Application of domain inspection and testing of signalling process

6.2 Sign-off system in accordance with operational rules

ET7, ET9, ET10

Application of domain inspection and testing of signalling process

© State of NSW through Transport for NSW Page 34 of 39

Page 35: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

8.1. Signalling commissioning - evidence requirement guidelines Table 31 provides the reference to evidence requirements, type of evidence and the

deliverables required for each type of evidence for signalling commissioning competence.

Table 31 – Commissioning – evidence requirement guidelines

Reference Type of evidence Typical evidence required (deliverables)

ET1 Assessment of logbook and currency of entries; these typically include work experience, storyboards detailing particulars of work carried out, training records (academic or industry) and so on

Authenticated logbook entries: • signalling scheme construction management • testing the application of system requirements • implementation of requirements in the SFS • equipment installation and set to work

ET2 Continue self-assessment and maintenance of work experience logbook

Authenticated logbook entries - detailing specific requirements for ET1

ET3 Competency assessment to be demonstrated through continued professional development

Authenticated logbook entries: • installation and set to work of equipment under

supervision • training in applicable industry requirements • keeping abreast of new equipment • continuous development in self instruction and

standards updates

ET4 Manage client interface and communicate requirements relating to proposed signalling infrastructure detailed in the signalling requirements specification, functional specification, and design and test documentation

Provision of documented evidence together with authenticated logbook entries: • pre-planning and submission of testing

documentation for approval and acceptance • testing certification management • provision and management of client interface log • demonstrate programming and planning of

possession and occupation scheduling in relation to client requirements and railway operations

ET5 Follow process and document strategy decisions made during testing and commissioning phase

Company management system - follow prescribed company process and produce requisite testing and planning documentation

ET6 Demonstrates the relevant skills and knowledge to undertake testing works unsupervised

Authenticated logbook entries - has carried out five projects previously, similar in nature and has documented evidence

© State of NSW through Transport for NSW Page 35 of 39

Page 36: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Reference Type of evidence Typical evidence required (deliverables)

ET7 Demonstrates knowledge and experience working unsupervised in tasks and activities relating to assignment May perform more complex tasks unsupervised where previous experience can be demonstrated Requires mentorship to perform more complex activities and tasks where experience cannot be demonstrated

Can provide documented evidence together with authenticated logbook entries: • maintenance of test logs and design

modifications throughout testing and commissioning life cycle

• can demonstrate use of domain standards • can demonstrate some level of innovative

applications to provide successful outcomes • can provide or demonstrate a good all-round

knowledge base in the application of signalling principles testing

ET8 Demonstrate academic record to include relevant industry training, for example: • Intermediate Signalling

Technology (IST) Layouts • Intermediate Signalling

Technology (IST) Control Tables

• Advanced Signalling Technology (AST)

Provide documented evidence together with authenticated logbook entries: • demonstrate all academic achievements by

provision of certification • demonstrate all relevant industry training by

provision of certification

ET9 Certified qualifications Provide documented evidence - provision of certified copies of documentation relevant to activities and tasks being carried out

ET10 Demonstrates knowledge and experience working unsupervised in tasks and activities relative to assignment May perform more complex tasks unsupervised where previous experience can be demonstrated Has the relevant experience to execute the duties in a senior position as a leader and has the ability to solve problems Can interpret and apply relevant domain standards and principles Is considered to be an SME and has the ability and experience to provide mentorship

Provide documented evidence together with authenticated logbook entries: • maintenance of test logs and design

modifications throughout test and commission life cycle

• demonstrate use of domain standards • demonstrate some level of innovative applications

to provide successful outcomes • demonstrate longevity and good all-round

knowledge base in the application of signalling principles testing

© State of NSW through Transport for NSW Page 36 of 39

Page 37: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Appendix A Process flow for claiming competence

The process flow diagram depicts the steps to be followed to assess the competency of a

signalling person and obtain the authorisation to work from the RIM.

This process guides the AEOs in applying this standard through the different stages of

assessment and helps to achieve the following:

• identify the appropriate role and the relevant prerequisites / qualifications that a signalling

person should hold for the role they are being considered for

• identify if the signalling person is able to demonstrate compliance with the detailed generic

competency standards

The competency standards are expressed as a series of functional tasks and evidence criteria

and the objective evidence that the signalling person would be expected to present to support a

claim of competency in any area.

Figure 4 shows the process flow diagram for claiming competence and deploying a competent

person to discharge a particular function on the infrastructure.

Note: This is an indicative process that suits the existing situations of the current RIM

of the Sydney metropolitan area.

© State of NSW through Transport for NSW Page 37 of 39

Page 38: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Step 7 - AEO claim for competence to RIM – assess candidate against evidence criteria based on defined suitable evidence

requirements & assess to levels of proficiency

Step 1 – Assess candidate’s broad role for functions expected

to perform

Step 2 – Identify lifecycle phases applicable to the role

Step 3 – Determine which functions apply (Sections 6-8)

Step 4 – Determine the level of proficiency required for each

element of the role (refer section 5.6)

Step 5 – Identify the evidence requirements for applicable

functions

Can candidate complete the claim for competence? YES

No

Step 6 – Undertake gap analysis between role requirements and

level of proficiency and the assessment results and address

RIM Reviews Application

Generic ProductDomain

RIM comment on application and any additional domain and product

attributes clarified.

Candidate deemed fully competent?

Yes

No

Skills gap analysis and training needs identified. Candidate can be reassessed again in the future. Revised or restricted

competency issued in interim.

Issue Certificate of Competency for assessed scope

RIM reviews Certificate of Competency and validates

RIM issues authorisation to work

© State of NSW through Transport for NSW Page 38 of 39

Figure 4 – Process flow diagram

The following steps describe the process:

i. Assess the signalling person's broad role for the functions they are expected to perform.

Refer to Section 5.3 for more information on roles and functions.

ii. Identify the life cycle phases that are applicable to the role.

Refer to Figure 3 for the life cycle phases in the asset life cycle.

iii. Determine the functions that apply to the signalling person's role.

The tasks for each function are explained in Section 6, Section 7 and Section 8.

iv. Determine the level of proficiency required for each task of the role.

Refer to Section 5.6 for proficiency levels.

v. Identify the evidence requirements for applicable functions and determine if the signalling

person has sufficient evidence to complete the claim for competence.

vi. If the signalling person does not have sufficient evidence then undertake a gap analysis

between role requirements and level of proficiency and the assessment results.

Page 39: Competency Standard - Signalling · Competency Standard - Signalling T HR CY 03000 ST Standard . Version 01. Issued date: 15 June 2016 . Important Warning . This document is one of

T HR CY 03000 ST Competency Standard - Signalling

Version 1.0 Issued date: 15 June 2016

Address the gaps to then complete the claim for competence.

Or

If the signalling person has sufficient evidence then the AEO claims for competence to the

RIM to assess the signalling person against the criteria-based evidence across generic,

product, domain requirements and assess to levels of proficiency.

vii. RIM reviews application to determine if any additional domain and product attributes need

clarification and determine if the signalling person is deemed fully competent.

viii. If the signalling person is not deemed competent, identify the skills gap analysis and

training needs.

The signalling person can be reassessed in the future. A revised or restricted competency

certification can be issued in the interim.

Or

If the signalling person is deemed competent, then the Certificate of Competency is issued

for assessed scope of work.

ix. The RIM reviews and validates the Certificate of Competency and issues the authorisation

to work.

© State of NSW through Transport for NSW Page 39 of 39