G.I. Joe v. Jim Crow: Legal Battles Over Off-Base School ...
Comparison of Hardware Tests with SIMULINK Models of UW...
Transcript of Comparison of Hardware Tests with SIMULINK Models of UW...
![Page 1: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/1.jpg)
1
Comparison of Hardware Tests with SIMULINK Models of UW Microgrid
Introduction This report includes a detailed discussion of the microsources available on the University-‐of-‐Wisconsin microgrid. This includes details of the SIMULINK models and their comparison with actual dynamic tests.
Critical model parameters are also provided. The microsources include inverter based sources, AC storage and a field wound synchronous generator. The appendix includes SIMULINK models and the
network parameters for the network studies in Phase VIII. Note there is a significant differences in the system presented at the start of this project. The loads are different representing the actual loads available in at Wisconsin.
Current UW Microgrid Parameters This section documents the current actual microgrid circuit used a University of Wisconsin. This includes
line impedances and transformer data. This is the system for providing the hardware test data of the system’s dynamics.
Figure 1 shows the UW Microgrid diagram.
Power CableStatic SwitchGrid
(4.16 kV)
PC1 SS
T1 T 2 Power Cable
PC 2
Resistive Load Bank
R1
ES
Power Cable
PC 3
Resistive Load Bank
R2
Power Cable
PC4
Power Cable
PC5
SynchronisationCircuit
SC
R3
GENSET
IC SM
MS
UPC1
UPC2
UPC3Power Cable
PC6
SW
Resistive Load Bank
n nn
4.16 kV / 0.48 kV 0.48 kV / 0.208 kV
Figure 1. Three Phase Diagram of UW Microgrid
![Page 2: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/2.jpg)
2
Impedances of microgrid lines and transformers are listed in Table 1 and 2 respectively.
Table 1. Line impedances of UW microgrid
Line Impedance Length [ft] R [Ω] XL [Ω] XC [Ω]
PC1 366 0.093400 0.025500
PC2 18 0.002810 0.000679
PC3 175 0.027352 0.006600 288.6
PC4 108 0.016880 0.004070 336.7
PC5 17 0.002657 0.000641 2020.2
PC6 105 0.065600 0.002100 345.6
Table 2. Transformer impedances of UW microgrid
Tag Volt-‐Amp Rating
Impedance HV Side
Resistance[Ω] HV Side
Reactance[Ω] LV Side
Resistance[Ω] LV Side
Reactance[Ω]
T1 2500 kVA 5.50% 0.04707123 0.1882849 0.000627 0.0025068 T2 75 kVA 4.40% 0.01689600 0.0675840 0.003173 0.0126908 T3 45 kVA 4.20% 0.02688000 0.1075200 0.005047 0.0201899 T4 45 kVA 4.20% 0.00671900 0.0268800 0.005047 0.0201899 T5 45 kVA 4.20% 0.02688000 0.1075200 0.005047 0.0201899
Inverter Microsource Details Microsource (MS) is illustrated in Figure 2.
!" VDC
Inverter
Inverter Firing System
m
!(t)
CF3
LF3
Ideal Source
CKMS
Controller
Lt3PC3 UPC3T5
Ia ,
Vab ,Vcb
Ic
n
0.48 kV / 0.208 kV
MS
Figure 2. MS components
Inverter voltage and currents have a fundamental component and higher harmonics due to the turn-‐on/off effects of the switches. Harmonics are significantly eliminated by means of LC filter and the 10kHz switching frequency. The inverter is represented from the microgrid point of view as an ideal, balanced voltage source with only fundamental components. The output of the inverter is modeled as a controlled voltage source as shown in Figure 3.
![Page 3: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/3.jpg)
3
Uab
Ubc
Uca
Ideal Source
m
!(t)
PC3
Figure 3. Ideal source model
Instantaneous voltages of the controlled voltage sources can be written as following;
The quantities m and θ(t) are the outputs of the control block. The quantity m is a modulating index, a
scalar coefficient that when is multiplied by the DC voltage yields the magnitude of the desired voltage
at the inverter terminals. The quantity θ(t) is the desired instantaneous value of angle for the voltage at
the inverter terminals.
Control quantities used in this model are voltage (Vmeas), real power (Pmeas) and reactive power (Qmeas). Detail of the controller is shown in Figure 4.
![Page 4: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/4.jpg)
4
Calculation of Control Quantities
from Measurements
Voltage (V)Real Powers (P)
Reactive Power (Q)
FILTERS
+ --
mQ
- ++ ++
++
-+
-+
V*
Q*
P*
m
Vreq
Preq
!base
"(t)
Pmax
Pmin
1s
- #!
0
VBASE
SBASE
mP
++ Kvi
s
Kvp
0
PI
PI
PI
++
Kpis
Kpp
++
Kpis
Kpp
#!
Vab,Vcb
Ia,Ic
Vmeas
Qmeas
Pmeas
Pmeas
Figure 4. Detailed MS controller scheme, CKMS
Real and reactive power (in pu) injected from MS and terminal voltage (in pu) are calculated by signal processing block illustrated in Figure 5.
Vab-cb
Ia-c
)( qddq IVIV !23
Vdq
Idq
V*
P*
Q*..
..
.
.
Vbase
Sbase
)( qqdd IVIV +23
+
22qd VV +
+
"#
$%&
'"#
$%&
'
!="
#
$%&
'
cb
ab
q
d
ff
ff
/30
1/2-2
132
"#
$%&
'"#
$%&
'
!!="#
$%&
'
c
a
q
d
ff
ff
/
3/23230
32
Figure 5. Control quantities calculation block
![Page 5: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/5.jpg)
5
Instantaneous P, Q and V are calculated using the rotating d-‐q reference frame. Instantaneous voltage (current) magnitude is calculated by obtaining the in-‐phase (direct) and out of phase (quadrature)
voltages (current) with respect to phase-‐a.
The calculated V, P and Q quantities are passed through the low pass filters to attenuate the high frequency components which occur at step load or power changes. Filter diagram is shown in Figure 6.
s11
VQP!+
V* Vmeass1
1VQP!+
s11VQP!+
Q* Qmeas
P* Pmeas
Figure 6. Filter diagram
Experimental vs. Simulation Results for MS
Experimental setup in which MS is island mode and grid-‐connected mode is shown in Figure 7.
Figure 7. Experimental setup diagram for MS
MS parameters are listed in Table 3.
![Page 6: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/6.jpg)
6
Table 3. MS parameters
VDC 750 V SBASE 15 kVA VBASE 208 V ωbase 376.9911 (2π60) Δω 3.1416 (2π0.5) Pmax 15 kW (1 pu) Pmin 0 kW Preq 4 kW (0.2667 pu) Vreq 208 V (1 pu) Kpp 3 Kpi 30 Kvp 0.01 Kvi 5 mQ 0.05 mP 3.1416 τVQP 0.01
In this islanded case study the inverter has two resistive loads .
R2=10.8Ω R3=22.2Ω
Initially the load R3 is supplied by the inverter. R2 is switched in at t1≅1.7 sec and out at t2≅ 6.8.
Results of simulation and experiment are shown in Figure 8 through 11.
Figure 8. Real and reactive power variation of MS
![Page 7: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/7.jpg)
7
Figure 9. Frequency variation of MS
Figure 10. Voltage variation of MS during load step up
Figure 11. Current variation of MS during load step up
![Page 8: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/8.jpg)
8
Energy Storage, ES, Details Energy storage (ES) modeling details are illustrated in Figure 12. ES is also modeled as a controlled voltage source.
ES
!" VDC
Inverter
Inverter Firing System
m
!(t)
CF1
LF1
Ideal Source
CKES
Controller
Lt1PC1 UPC1T3
Ia ,
Vab ,Vcb
Ic
n
0.48 kV / 0.208 kV
Figure 12. ES components
Detailed controller of ES is shown in Figure 13. As shown, the controller is same as that of MS. However, Pmin can have negative value which correspond that of battery charging.
Calculation of Control Quantities
from Measurements
Voltage (V)Real Powers (P)
Reactive Power (Q)
FILTERS
+ --
mQ
- ++ ++
++
-+
-+
V*
Q*
P*
m
Vreq
Preq
!base
"(t)
Pmax
Pmin
1s
- #!
0
VBASE
SBASE
mP
++ Kvi
s
Kvp
0
PI
PI
PI
++
Kpis
Kpp
++
Kpis
Kpp
#!
Vab,Vcb
Ia,Ic
Vmeas
Qmeas
Pmeas
Pmeas
Figure 13. Detailed ES controller scheme, CKES
![Page 9: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/9.jpg)
9
2.1. Experimental vs. Simulation Results for ES
Experimental setup for ES is illustrated in Figure 14.
Figure 14. Experimental setup diagram for ES
ES parameters are listed in Table 4.
Table 4. ES parameters
VDC 750 V SBASE 15 kVA VBASE 208 V ωbase 376.9911 (2π60) Δω 3.1416 (2π0.5) Pmax 15 kW (1 pu) Pmin -2.5 kW (-0.1667 pu) Preq 4 kW (0.2667 pu) Vreq 208 V (1 pu) Kpp 3 Kpi 30 Kvp 0.01 Kvi 5 mQ 0.05 mP 3.1415 τVQP 0.01
![Page 10: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/10.jpg)
10
In this case study, the ES inverter supplies the two resistive loads in islanding mode. The load values are fallowing:
R1=20.5Ω R2=10.8Ω
Initially the load R1 is supplied by the ES inverter. R2 switched in at t1≅4.12 sec and out at t2≅ 7.72,
respectively.
Results of simulation and experiment are shown in Figure 15 through 18.
Figure 15. Real and reactive power variation of ES
Figure 16. Frequency variation of ES
![Page 11: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/11.jpg)
11
Figure 17. Voltage variation of ES during load step up
Figure 18. Current variation of ES during load step up
![Page 12: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/12.jpg)
12
GENSET Details The GENSET block is shown in Figure 19. It comprises of an internal combustion (IC) engine driven and a 12.5 KW Kohler field wound synchronous generator.
ControllerCKG
PSG
GENSET
IC Engine
!meas
Fcmd
UPC2T4
I a ,
Vab ,Vcb
Ic
n
0.24 kV / 0.208 kV
CG
Exciter
Ecmd
Figure 19. GENSET components
Internal combustion (IC) engine is illustrated in Figure 20. The exciter model is shown in Figure 21. +-
cmdthr Ffvev KK!Fcmd"-e
Nm
base
mmeas
SN_
mKmeas2_
Limiter 1
Pmec
Time Delay
Figure 20. IC Engine model
s11
e!+
Exciter MachineLimiter 2
EfmeascmdE _Ecmd
Figure 21. Exciter model
Control quantities used in this model are voltage (Vmeas), real power (Pmeas), reactive power (Qmeas) and speed of generator (ωmeas). Detail of the controller is shown in Figure 22.
The speed of generator is directly measured from synchronous machine measurement terminal.
Therefore a speed observer model is not needed in this study.
![Page 13: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/13.jpg)
13
Calculation of Control Quantities
from Measurements
Voltage (V)Real Powers (P)
Reactive Power (Q)
Vab,Vcb
Ia,Ic
+ --
mQ
-+++
Vmeas
Vreq
Preq
!base
VBASE
SBASE
mP
Genset Controller Diagram
Qmeas
Pmeas
Exciter Voltage
Command ControllerGv
Voltage Regulator
-+Controller
Gg
Fuel Command
!meas
Governor
++
-+
-+Pmax
Pmin
" #!
0
0
PI
PI
++
Kpi
s
Kpp
++
Kpi
s
Kpp
#!
+
Pmeas
From Synchronous
Generator shaft
VerrEcmd
Fcmd !err
Figure 22. Detailed GENSET controller scheme, CKG
The controller Gv in the voltage regulator block is shown in detail in figure 23.
++
sK vi
vpK
++
PI1
EcmdVerr
Figure 23. Detailed diagram of controller Gv
The Gv controller is the sum of the PI controller and the feed-‐forward value. This is the expected value required for nominal voltage at the terminals. This feed-‐forward constant allows for quicker initial convergence without the integrator having to wind up.
![Page 14: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/14.jpg)
14
The controller Gg in governor block is shown in figure 24.
++
sK gi
gpK
PI
++
Limiter 3
eTtfKTe
Fcmd!err
Pmeas
Figure 24. Detailed diagram of controller Gg
The governor controller regulates the rotational speed of the genset primarily by a combination of fuel
commands calculated from the speed error and the output power that is used to decouple the loading of the machine.
The speed error is fed into a PI controller to modify the torque command. The output of the PI controller is the output power at the terminals of the machine. The limiter before the torque command
output (Te) is used to avoid unrealistic commands during large load transients. The torque command is translated into fuel unit command Fcmd.
Results for GENSET Simulation setup for the GENSET in island mode is illustrated in Figure 25.
Figure 25. Simulation setup diagram for GENSET
![Page 15: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/15.jpg)
15
ICE parameters and Synchronous generator parameters are listed in Table 5 and 6, respectively.
Table 5. GENSET parameters
SBASE 12.5 kVA ηthr 0.47 VBASE 208 V Kev 11.8238 ωbase 376.9911 (2π60) Kfv 3600 Δω 3.1416 (2π0.5) τ 0.022 Pmax 12.5 kW (1 pu) Km 0.36 Pmin 0 kW τe 0.001 Vreq 208V (1 pu) Kvp 100 Kpp 3 Kvi 30 Kpi 30 Kgp 10 mP 3.1416 Kgi 20
Ktf 0.625
Table 6. Synchronous generator parameters
xd 1.204 Td0’ 0.35523
xd’ 0.125 Td0
” 0.00015 xd
” 0.056 Tq0” 0.0067
xq 0.533 Rs 0.0217 xq
’ 0.051 H 0.19 xq
” 0.037
p 2
In this case study, the GENSET has two resistive loads.
R2=10.8Ω R3=22.2Ω
Initially the load R3 is supplied by the GENSET. R2 is switched in at t1=3 sec and out at t2= 7, respectively.
Results are shown in Figure 26 through 29.
![Page 16: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/16.jpg)
16
Figure 26. Real and reactive power variation of GENSET
Figure 27. Frequency variation of GENSET
Figure 28. Voltage variation of GENSET during load step up
![Page 17: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/17.jpg)
17
Figure 29. Current variation of GENSET during load step up
![Page 18: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/18.jpg)
18
Appendix A: SIMULINK data A. Microsource MS & Energy Storage ES
Figure A1. MS (ES) components
a) MS (ES) controls and source models b) Ideal voltage source model
Figure A2. MS (ES) Controls and Source
![Page 19: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/19.jpg)
19
Figure A3. SIMULINK diagram of MS (ES) controller
Figure A4. SIMULINK diagram of measurement calculation
Figure A5. SIMULINK diagram of abc to αβ transformation
Figure A6. SIMULINK diagram of filters
![Page 20: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/20.jpg)
20
Figure A7. SIMULINK diagram of Q-‐V droop controller
Figure A8. SIMULINK diagram of voltage control
Figure A9. SIMULINK diagram of P-‐ω droop controller
![Page 21: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/21.jpg)
21
B. Genset KG
Figure B1. KG components
Note: See Figure A4-‐A5 for PQV_Calc block detail
Figure B2. SIMULINK diagram of Engine & Governor
IC Engine Model
Governor Model
![Page 22: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/22.jpg)
22
Figure B3. SIMULINK diagram of Exciter & Regulator
Exciter Model
Voltage Regulator
Model
![Page 23: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/23.jpg)
23
Appendix B Meshed Microgrid Figure 1 shows the UW Meshed Microgrid diagram for Task VIII test.
Figure 1. Single Phase Diagram of UW Meshed Microgrid
Impedances of microgrid lines and transformers are listed in Table 1 and 2 respectively.
Table 1. Line impedances of UW meshed microgrid
Line Impedance Length [ft] R [Ω] XL [Ω] XC [Ω]
PC1 366 0.093400 0.025500 82.7
PC2 18 0.002810 0.000679 2894.3
PC3 175 0.027352 0.006600 288.6
PC4 108 0.016880 0.004070 336.7
PC5 17 0.002600 0.000640 2020.2
PC6 75 0.013700 0.003300 577.2
From Outside Line
PC4
25yds PC3
75yds
PC5
15yds PC6
25 yds T
3
T4
2
SS
PC1
T1
PC2
20yds
Bus-2
Energy Storage (15 kW)
T
2
Bus-
1 L11
L12
L22 L21
Kohler Genset (12.5 kW)
Bus- 4
L41 L42
Micro-Source
Inverter based
(15 kW)
Bus-3
L31 L32
P3,Q3
P6,Q6 P5,Q5
P4,Q4
![Page 24: Comparison of Hardware Tests with SIMULINK Models of UW …lemmon/projects/Odyssian-2009/Vault/... · 2010. 11. 5. · 6" " Table"3."MS"parameters" V DC 750 V S BASE 15 kVA V BASE](https://reader036.fdocuments.us/reader036/viewer/2022071515/613745060ad5d206764882ff/html5/thumbnails/24.jpg)
24
Table 2. Transformer impedances of UW meshed microgrid
Tag Volt-‐Amp
Rating Impedance
HV Side
Resistance[Ω]
HV Side
Reactance[Ω]
LV Side
Resistance[Ω]
LV Side
Reactance[Ω]
T1 2500 kVA 5.50% 0.04707123 0.1882849 0.000627 0.0025068 T2 75 kVA 4.40% 0.01689600 0.0675840 0.003173 0.0126908 T3 45 kVA 4.20% 0.02688000 0.1075200 0.005047 0.0201899 T4 45 kVA 4.20% 0.00671900 0.0268800 0.005047 0.0201899 T5 45 kVA 4.20% 0.02688000 0.1075200 0.005047 0.0201899
Table 3. Loads of UW meshed microgrid
Tag Power Rating
L11-L12 4 kW L21-L22 4 kW L31-L32 4 kW L41-L42 4 kW