Company Overview - Basrah Eurolane · Company Overview Basrah Eurolane ... Eni, Ministry of Oil,...

19

Transcript of Company Overview - Basrah Eurolane · Company Overview Basrah Eurolane ... Eni, Ministry of Oil,...

Company Overview

Basrah Eurolane Company (BECO) was established in Basrah, Iraq in 2003 and is the Engineering ,Procurement and

Construction (EPC) Contracting division of Mesopotamia Group of Companies with head office in Basrah and branch offices

in Baghdad, London and Dubai .

BECO is an ISO 9001:2015 (Quality Management System), ISO 14001:2015 (Environmental Management System) and an

OHSAS 18001:2007 (Occupational Health and Safety) certified organization.

BECO delivers client satisfaction on the strength of a first-class construction arm of Mesopotamia Group. We value our

professional staff, quality of work, exceptional work safety record, good reputation and high environmental standards.

With over a decade of experience in the region, our continued expansion and fast growth is attributed to our high standards

in the delivery of our work and good reputation built up over the years with effective allocation of resources via our high

profile companies, partners and clients including Shell, British Petroleum (BP), Eni, Ministry of Oil, NGOs including United

Nations UNDP, CPA, NCA and various Governmental institutions.

Vision

• To be a world class construction contractor, offering performance without compromise to services.

• To continue to serve Iraq in execution of their respective missions and contribute towards building a Prosperous future for

Iraq and its people.

Mission

• To satisfy the expectations of our shareholders, customers, employees and the world society.

• To assist and continue to build strong working partnerships with NGOs, we are particularly proud of our charitable arm of

Mesopotamia Group comprising of Iraq University College, Mesopotamian Cultural Association and Basrah Society for

Social & Civic Development.

• To continue to benefit and utilize the Group’s training and education arm via the University of Iraq College, its Consultancy

Bureau and ‘Engineering & Management Service Centers' and to build strong links with other academic institutions for the

creation of highly professional strategic studies and expertise.

• To continue to strengthen our competitiveness by continuously improving our cost effectiveness.

• To continue to adopt a “one big family” business philosophy and a shared sense of purpose.

• To continue to focus our value on trust, dedication and performance.

Achievements We have successfully and consistently achieved the highest quality of work in Commercial, Government and Investment contracts in the following fields: 1. EPC Turnkey Projects 2. Heavy Civil works 3. Water System networks/plants, Sewage & Sanitation 4. Power Generation 5. Infrastructure Projects 6. Mechanical maintenance and provisions

Strategic Alliances & Partnerships

BECO has steadily evolved from a project-specific company in Iraq to a full turnkey service operation provider.

BECO has formed several strategic alliances and partnerships with internationally renowned architectural design,

construction and project management teams based in Ireland, Jordan, Turkey, United Kingdom, UAE, China and USA

giving us a dynamic international network and extensive global experience in often highly demanding and complex projects.

Financial capacity

A statement of overall turnover during the last five (6) financial years in USD$:

2010 $ 89,505,000.00 USD

2011 $ 92,550,000.00 USD

2012 $154,600,000.00 USD

2013 $160,113,000.00 USD

2014 $196,130,000.00 USD

2015 $186,170,000.00 USD

Projects Reference List

Work Period

Value

Number

of workers

Location

Work

Description

Client

Item No.

60 days (June 2005 –

August 2005)

360,700,000.00 Iraqi Dinars

18 Basra Rehabilitating Al Qurna

sewage system General Directorate for Basra Sewerage 1

45 days (Dec 2004 – Feb

2005)

800,000,000.00 Dinars

25 Basra Rehabilitating hay Al Husain+

Al jamiyat sewage system General Directorate for Basra Sewerage 2

95 days (Mar 2005 – June

2005) 2,500,000.00 USD 15 Basra

Rehabilitating Ashar sector sewage system

General Directorate for Basra sewerage 3

280 days (May 2004 –

Feb 2005)

1,750,402,250.00 Iraqi Dinars

35 Basra Installing 7 water distribution

plants Coalition Provisional Authority (CPA) 4

120 days ( Aug 2004 – Dec 2004)

2,850,000,000.00 Iraqi Dinars

60 Basrah Rehabilitating Fao water

system Mott Macdonald + Coalition Provisional

Authority (CPA) 5

5 years construction since 2004

6,300,000,000.00 Iraqi Dinars

58 Basra Supply & Installation of 6 R.O

Plants Basrah water Authority 6

90 days (2005)

1,800,000.00 USD 29 Basra Installing R.O plants CPA 7

180 days (2005)

660,000.00 USD 65 Basra Basrah sewer jetting,

cleaning, repairing for sector 1 &2

CPA 8

90 days (2006)

3,770,033,000.00 Iraqi Dinars

22 Basra EPC Sewage Treatment Plant Basrah Municipality 9

90 days (2005)

183,015.00 USD 21 Basra R.O. Water distribution

through tanking Norwegian Church Aid (NCA) 10

70 days (2007)

192,000.00 USD 12 Basra Al khalij district streets

paving Basra reconstruction Unit 11

60 days (2007)

184,000.00 USD 11 Basra Al Abbas distract streets

paving Basra reconstruction Unit 12

120 days (2007)

284,650.00 USD 34 Basra Inspecting, clearing &

repairing of Area 5 sewer system

FLUOR A Y C 13

180 days (2008)

3,730,705.00 USD 87 Baghdad

Installing diesel generator sets, Electricity Supply, O&M

and Capacity Building at Health Care facility

United Nations Development Program (UNDP) 14

180 days (2008)

3,730,705.00 USD 62 Samara, Iraq

Installing diesel generator sets, Electricity Supply, O&M

and Capacity Building at Health Care facility

United Nations Development Program (UNDP) 15

185 days (2006-2007)

508,216 .00 USD 85 Basra Rehabilitating electrical

distribution network in Um Qaser

UNDP 15

180 days (2007)

800,000.00 USD 63 Basra EPC Housing Al Kefah Co. 16

300 days (2008)

500,000.00 USD 15 Missan EPC School construction Missan Governorate 17

April 2011 – April 2012

11,400,000,000 Iraqi Dinars

92 Basrah

Building and executing underground piping & sewer system for (Hay Al Qaem in

Qibla district) in Basra

Basra Reconstruction Unit 18

March 2010 – Feb 2013

1,670,000,000 Iraqi dinars

50 Basrah Youth and Sport Directorate

Building & Infrastructure Ministry of Youth and sport 19

Jan 2011 – Feb 2012

1,339,500 USD 65 Basrah EPC Police station building -

Asmaee United Nations Development Program (UNDP) 20

Dec 2010 – Feb 2012

1,439,000 USD 71 Basrah EPC Police station building-

Ashar UNDP 21

Mar 2012 – Mar 2014

Call Off 55 Zubair Piping Maintenance Eni Iraq B.V 22

Apr 12 – Apr 14

Call Off 30 Zubair Fire Fighting System Network Eni Iraq B.V 23

Feb 2012 – Dec 2013

2,500,000.00 USD 126 Majnoon Well Pad Construction, Auger

Boring & Piping works Shell Iraq B.V 24

Feb 2012 – Jan 2014

1,083,000.00 USD 68 Majnoon Road Maintenance, Crossing

& HDD works Shell Iraq B.V 25

May 2012 – August 2013

79,310.00 USD 35 Majnoon Building & Sewage

Improvement Works Shell Iraq B.V 26

Sep 2012 – June 2013

1,197,487.00 USD 136 Majnoon, CPF

Erection of 6 Buildings

including piping infrastructure works

Shell Iraq B.V 27

March 2010 – March 2013

5,600,000.00 USD 98 Rumailla Well Pad Construction & Pipe

sleeves British Petroleum (BP Iraq/ROO) 28

June 2006 – April 2008

1,330,000.00 USD 46 Kubbaisa,

Basrah

Design, Construction of 12KM Water Pipeline -

Size 10” Council of the governorate of Basra 29

Jan 2010 - Present

25,000,000.00 USD

212 Basrah

Residential housing units &

Infrastructure including pipeline works

Council of the governorate of Basra 30

April 2011 - `Mar 2013

11,000,000.00 USD

89 Basrah

Reconstruction of town of Al-Jamhoorea including sewer &

water system network underground piping

Council of the governorate of Basra 31

June 2010 – Feb 2012

7,000,000.00 USD 112 Basrah

Olympic Building in Hakimiya region including piping works

for infrastructure Council of the governorate of Basra 32

June 2011 - `Mar 2012

1,000,000.00 USD 45 Basrah Construction of Al-Bader tourism complex Council of the governorate of Basra 33

Sep 2011 - `Jan 2013

580,000,000.00 Iraqi Dinars

62 Basrah Reconstruction of the Shatt

Al Arab College Faculty Council of the governorate of Basra 34

Aug 2013 – Present

3,600,000.00 USD 51 Basrah

Design, Procurement and Construction of 8 km fuel oil pipeline for Khor Al-Zubair

Port

Ministry of Oil 35

Jan 2010 – June 212

164,000,000.00 Iraqi Dinars

32 Basrah

Construction of a two-storey building including

underground utilities & pipeline services

South Oil Company 36

Jul 2011 – Feb 2012

250,000.00 USD 43 Basrah

Repair & Maintenance of

waterworks for Altoesa area

RTI Organization 37

Mar 2013 – Present

7,350,000.00 USD 169 Basrah

Design, Procurement and Construction of University

building including underground utilities &

infrastructure

Iraq University College 83

July 2013 – Present

00,000.05,6 0 USD 85 Basrah

Design, Procurement and Construction of 10 km gas

pipe for Musseib Power Station

Ministry of Electricity 39

December 2014 -

Present

21,650,000.00 USD

121 Basrah

Construction and procurement of 1000

residential housing units in Qibla region, Basrah, Iraq

Ministry of Housing 40

December 2014 -

Present

10,000,000.00

USD 64

Rumailla Oil

Field, Basrah, Iraq

Well Pad Construction BP Iraq/ Rumaila Operating Organisation

(ROO) 14

Examples of Completed Projects

Client: Basra Reconstruction Unit Project Description: Building and executing underground piping & sewer system for (Hay Al Qaem in Qibla district) in Basra Project Value: 11,400,000,000 Iraqi Dinars Completion Date: April 2012

Client : Ministry of Youth and sport

Project Description: Youth and Sport Directorate Building &

complete Infrastructure (EPC)

Project Value: 1,670,000,000 Iraqi dinars

Completion Date: February 2013

Client : British Petroleum / Rumaila Operating Organization (ROO)

Project Description: Well Pad Construction

Project Value: $5,600,000.00 US Dollars

Completion Date: March 2013

Client: Council of Governorate of Basrah Project Description: Complete Reconstruction of town of Al-Jamhoorea i.e Infrastructure including sewer & water system network and underground piping Project Value: $11,000,000.00 US Dollars Completion Date: March 2013

Client: Ministry of Oil Project Description: Design, Procurement and Construction (EPC) of 8 km fuel oil pipeline for Khor Al-Zubair Port Project Value: $3,600,000.00 US Dollars Completion Date: June 2015 (phase 1)

ISO CERTIFICATES:

1-ISO 9001:2015 (QMS) 2- ISO 14001:2015 (EMS) 3- OHSAS 18001:2007

HEADQUARTERS IN IRAQ:

BASRAH:

Basrah –Bradia, Near the Talimi Hospital

Tel: +964 618077

+964 7801077851

+964 7801398527

E-mail: [email protected]

BRANCH OFFICE IN THE UNITED KINGDOM:

UNITED KINGDOM - LONDON:

Wembley – London

Tel: +44 (0) 7957383233

Fax: +44 (0) 2089085288

E-mail: [email protected]

UNITED ARAB EMIRATES - DUBAI :

Dubai, United Arab Emirates

P.O. Box 9546,

Tel: +971 (0) 556621061

Fax: +971 (0) 4 3464100

E-mail: [email protected]

Website: www.basraheurolane.com