1 North Island Hospitals Project Comox Valley Hospital Community Meeting June 11, 2013

Transcript of Comox Valley Community Meeting June 11, 2013

Page 1: Comox Valley Community Meeting June 11, 2013

1

North Island Hospitals Project

Comox Valley Hospital

Community Meeting

June 11, 2013

Page 2: Comox Valley Community Meeting June 11, 2013

2

Agenda

1. Project description, schedule and timelines

2. Hospital design and new features

3. Project Objectives, Guiding Principles, Design Guidelines

4. Procurement – PPP (P3 Process)

5. Community Issues: What we’ve heard

6. Community Benefits and Engagement

Page 3: Comox Valley Community Meeting June 11, 2013

3

• 29,000 m2

• 153 beds

• $334 million

• Comox Strathcona Regional Hospital District 40%

o $133.6 million

• MRI

• University of British Columbia (UBC) Academic Teaching Space

• 71% growth

3

Comox Valley Hospital

Page 4: Comox Valley Community Meeting June 11, 2013

4

Comox Valley Hospital Proposed Design

4

Page 5: Comox Valley Community Meeting June 11, 2013

5

Comox Valley Site Area

Page 6: Comox Valley Community Meeting June 11, 2013

6

Hospital Design and Construction

• Project and Program Design:

o Initial design decisions for RFP made with direct consultation from over 20 user groups (300 people)

Physicians, nurses, food services, laundry, housekeeping, management

o Future design decisions with proponent to include:

User Champions and Super Users Meeting

User groups (physicians, nurses, food services, laundry, housekeeping, management, public/patient)

Evidence Based Planning

Process Flow Mapping

Page 7: Comox Valley Community Meeting June 11, 2013

7

New Hospital Features

• Standardization:

o Office space, meeting rooms, lounges

o In Patient rooms, Intensive Care rooms, Operating Rooms

o Maternity - Labour – Delivery – Recovery – Post-Partum (LDRP’s)

• Space saving:

o Washrooms – no longer staff and gendered (with exception of bathrooms in staff areas)

Page 8: Comox Valley Community Meeting June 11, 2013

8

• Acute Care Community Hospitals – Fully Functional

• 315,000 sq feet

• 153 Acute care beds

• 105 In-Patient Units

• 8 Intensive Care Units

• 9 Telemetry

• 9 LDRP

• 6 Pediatrics

• Psychiatry 11, 4 PICU

Comox Valley Hospital

Page 9: Comox Valley Community Meeting June 11, 2013

9

• 6 OR’s, 18 Surgical Daycare, 13 PARR

• 5 Procedure rooms

• Outpatient clinics

o Chemo 7, Medical Daycare 7

• 31 Emergency

• Lab (including autopsy)

• Medical Imaging

• Rehab

• Pharmacy

Comox Valley Hospital

Page 10: Comox Valley Community Meeting June 11, 2013

10

Public Private Partnerships (PPP)

● Long term, performance-based contract between government and a private partner to deliver infrastructure and facility management services:

o Design, build, finance, maintain into one contract

o Transfers key risks: schedule, cost, lifecycle, design

o Innovation and competition

o Enables VIHA to focus on core business - healthcare

Page 11: Comox Valley Community Meeting June 11, 2013

11

Private partner Public sector

Own Land

Own Building

Finance Project

ProgramPlan

Design Build Maintain

Facility Management Services

Program Delivery

Manage Project

Page 12: Comox Valley Community Meeting June 11, 2013

12

Project Procurement – PPP Process

Business

Case &

Design

Concept

Construction

Issue

RFQ

Issue RFP Negotiate

Maintenance2 to 4 years

5 months

to 2 years

Design

Concept

Plan

Contract Term

30 years

2 to 4

months

We are here

Page 13: Comox Valley Community Meeting June 11, 2013

13

Project Proponents

Team: Arbutus Healthcare Partners

• Carillion Canada Inc.

• Bird Capital Limited

• Concert Infrastructure Ltd.

• Bird Design-Build Construction Inc.

• Campbell Construction Ltd.

• Kasian Architecture Interior Design and Planning Ltd.

• NBBJ Architecture

13

Page 14: Comox Valley Community Meeting June 11, 2013

14

Project Proponents

Team: Plenary Health

• Plenary Group (Canada) Ltd.

• PCL Constructors Westcoast Inc.

• CEI Architecture Planning Interiors

• Parkin Architects Western Ltd.

• Johnson Controls Inc.

14

Page 15: Comox Valley Community Meeting June 11, 2013

15

Project Proponents

Team: Tandem Health Partners

• Balfour Beatty Capital – Canada Ltd.

• Gracorp Capital Advisors Ltd.

• Connor Clark & Lunn GVest Traditional Infrastructure LP

• Graham Design Builders LP

• Farmer Construction Ltd.

• Stantec Inc.

• Honeywell International Inc.

15

Page 16: Comox Valley Community Meeting June 11, 2013

16

Project Schedule‘Request for Proposal’ Package Finalized April, 2013

VIHA Site Preparation Work

Comox Valley Site – Leighton Contracting (2009)

Ltd.Campbell River Site – Palladian Development

March – November,

2013

Request for Proposal Phase

Collaborative Meetings (4)

April – December,

2013

Identify Preferred Proponent

Project Agreement Negotiations

January – March,

2014

Page 17: Comox Valley Community Meeting June 11, 2013

17

Project ScheduleFinancial Close

Ground Breaking Ceremony

March, 2014

Design and Construction of New Facilities April, 2014 – March,

2017

Service Commencement – Project Completion March, 2017

Commissioning and Transition Period April – September,

2017

Move-In Late Fall, 2017

Page 18: Comox Valley Community Meeting June 11, 2013

18

Six Month Look Ahead: What is going to happen?• Finalize VIHA site preparation – Comox Valley Hospital

• Collaborative meetings with three proponents

• User Groups:

o Process Flow Mapping

o Present State – Future State

o LEAN Process Redesign

o User Group Team Building

• Public meetings: October 29 and 30, 2013 (location TBD)

• Technical Evaluations – October – November, 2013

• Financial Evaluations – November – December, 2013

18

Page 19: Comox Valley Community Meeting June 11, 2013

19

Site Preparation: Schedule and Update

• Site preparation activity began March 2013

• Tree removal complete, site hydro seeded

• All work to be completed by October 2013

19

Page 20: Comox Valley Community Meeting June 11, 2013

20

• 2-4 foot berm being established in selected areas of the buffer zone

• Over 1000 trees being planted in buffer zones between NIC, hospital and Queneesh

• Coniferous, deciduous trees, Garry Oaks, shrubs and other plants

Site Preparation: Schedule and Update

Page 21: Comox Valley Community Meeting June 11, 2013

21

What We’ve Heard: Landscaping and Walkway

• The existing paved walkway to Lerwick will be closed as of July 1, 2013

• A new walkway is being created around the hospital site to Lerwick and Ryan roads– open as of July 1, 2013

• As of October 1, 2013 you can access Lerwick from two landscaped walkways:

o One route between the hospital site and NIC

o One route between the hospital site and Queneesh

• Walkway and pedestrian routes on hospital grounds will be built to ensure accessibility for:

o Individuals with mobility challenges, visually impaired and baby strollers

Page 22: Comox Valley Community Meeting June 11, 2013

22

v

What We’ve Heard: Landscaping and Walkway

Page 23: Comox Valley Community Meeting June 11, 2013

23

What We’ve Heard: Landscaping and Walkway

July – October 2013

Page 24: Comox Valley Community Meeting June 11, 2013

24

• Fencing around the one soccer field to be installed end of June

• Soccer fields on Queneesh property stay the same

• Soccer field on hospital property remains open until early 2014

• From July 1st through September 2013, the soccer field will be accessible only from Lerwick Rd.

• October 1 there will be accessibility from Queneesh

o Working with soccer groups and city to ensure usage

• Baseball diamonds will be removed at the end of June after ball season ends

What We’ve Heard: Soccer Field and Baseball Diamonds

Page 25: Comox Valley Community Meeting June 11, 2013

25

What We’ve Heard: Fencing and Site Safety

• An 8ft construction fence will be in place for the entire period of time that there is work on the site

• An Emergency Management Contact List has been created in conjunction with School Advisory Committee

• WorkSafe BC

• Occupational Health & Safety

Page 26: Comox Valley Community Meeting June 11, 2013

26

What We’ve Heard: Noise and Dust Management

• During construction dust control practices will be utilized

• Once the hospital is in place, carefully designed building ventilation systems will be used to minimize noise and exhaust

• Noise lessening strategies from Royal Jubilee Project will be applied to areas such as refuse, recycling, loading, and service areas

• Noise reduction materials will be provided on parking structure walls within 200 metres of residential developments

Page 27: Comox Valley Community Meeting June 11, 2013

27

• During construction, workers and suppliers will not be allowed to park on any street within 1km of the site

• Currently, SJGH has 438 stalls on site, but those accommodate both acute care and residential care, staff and visitors

• New CV hospital will have 655 parking stalls including:

o 425 for physicians and staff

o 230 for patients and visitors including at least 24 stalls for disabled persons

What We’ve Heard: Parking and Traffic Management

Page 28: Comox Valley Community Meeting June 11, 2013

28

• In addition, the Project Agreement calls for:

o 50 motorcycle

o 50 secured bicycle

o 30 unsecured bicycle

o 2 Handy Dart bus stops

o 10 main door drop-off spaces

o 2 taxi stands

o 2 ambulance parking

o 3 Emergency drop-off

What We’ve Heard: Parking and Traffic Management

Page 29: Comox Valley Community Meeting June 11, 2013

29

• Stepped right turn facility

What We’ve Heard: Transportation and Traffic

Page 30: Comox Valley Community Meeting June 11, 2013

30

What We’ve Heard: Transportation and Traffic

• Pedestrian friendly

Page 31: Comox Valley Community Meeting June 11, 2013

31

What We’ve Heard: Community Engagement

• Quarterly open houses and information sessions

• Meetings with:

o School District and local Queneesh Elementary School

o Chamber of Commerce

o City Council

o Aboriginal Working Group

o Service clubs

o Construction association, and others

• Project newsletters, Website, Social Media

31

Page 32: Comox Valley Community Meeting June 11, 2013

32

• Industry Speed Dating:

o May 27, 2013 – Campbell River

o May 28, 2013 – Comox Valley

o 140 businesses attended in both communities, with over 225 people:

64 local Campbell River businesses attended

75 local Comox Valley businesses attended

What We’ve Heard: Community Engagement

Page 33: Comox Valley Community Meeting June 11, 2013

33

• Industry Speed Dating:

o Feedback from proponents overwhelmingly positive – excited about the capacity and level of service of local businesses

What We’ve Heard: Community Engagement

Page 34: Comox Valley Community Meeting June 11, 2013

34

Aboriginal and First Nations Engagement

• Aboriginal Working Group:o Kwakiutl District Council

o Nuu-chah-nulth Tribal Council

o First Nations Health Authority

o We Wai Kai Nation

o Wei Wai Kum First Nation

o K'ómoks First Nation

o Wachiay Friendship Centre

o VIHA Aboriginal Employment

o North Island Métis Nation

o MIKISW Métis Association

Photo courtesy of Comox Valley Echo

Page 35: Comox Valley Community Meeting June 11, 2013

35

Community Benefits

• Employment – direct and indirect

• Majority of construction hired locally

• Construction services and material procured locally

• BC Cancer Agency for the North

o 90% of trades came from North

o Majority of local companies hired as part of construction team

• Royal Jubilee Patient Care Centre:

• At the peak of construction, approximately 725 people were employed on the project

• The majority of them from Greater Victoria

Page 36: Comox Valley Community Meeting June 11, 2013

36

Community Benefits

Preliminary Employment Numbers – Direct Employment

2013 2014 2015 2016 2017 Total

Comox Valley

50 200 250 350 300 1150

Campbell River

30 175 225 325 275 1030

Page 37: Comox Valley Community Meeting June 11, 2013

37

Thank You!!

Questions?

37