Community presentation for Beverly Hills, Feb. 13, 2013

download Community presentation for Beverly Hills, Feb. 13, 2013

of 25

Transcript of Community presentation for Beverly Hills, Feb. 13, 2013

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    1/25

    Purple Line ExtensionCommunity Meeting: La Cienega Station Construction

    February 13, 2014

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    2/25

    Agenda

    Project Overview & Schedule

    Pre-Construction & Construction Overview

    Questions & Answers

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    3/25

    Project Overview & Schedule

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    4/25

    Approved Project

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    5/25

    Approved Project - SchedulePlanned Schedule Forecasted Schedule

    Sect ion 1 Sect ion 2 Sect ion 3

    Length 3.9 Miles 2.6 Miles 2.9 Miles

    New Stations

    Wilshire/La Brea

    Wilshire/Fairfax

    Wilshire/La Cienega

    Wilshire/Rodeo

    Century City

    Westwood/UCLA

    Westwood/VA

    Hospital

    Pre-Construction

    ActivitiesCurrent - 2014 2017 - 2018 2025 - 2027

    Construction 2014 - 2023 2019 - 2026 2027 - 2035

    Operations 2023 2026 2035

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    6/25

    La Cienega Station Activities

    Now: Pre-construction

    Selecting Design-Build contractor

    Utility relocations

    Real estate acquisitions

    Pre-construction surveys & business profiles

    Later 2014: Construction begins

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    7/25

    Pre-Construction & Construction

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    8/25

    Wilshire/La Cienega Station

    Work activities largely

    contained within station

    box area La Cienega to

    Tower

    2 construction staging sites: NE corner Wilshire/La

    Cienega

    NW corner Wilshire/Gale

    Tunnel Boring Machine

    (TBM) removal site at

    conclusion of Section 1

    tunneling

    Entrance at NE Corner of

    Wilshire and La Cienega

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    9/25

    Pre-Construction:

    Utility Relocation

    Utility relocations: Clears the way for station

    construction

    Ensures continued utility service Typical process:

    Maintain at least 2 lanes of traffic

    in each direction along Wilshire

    Blvd during the day

    Full or partial closures at night Truck/crew leave and lanes

    reopen at the end of each work

    period

    Typical cross-section of underground utilities

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    10/25

    Subway Construction Overview

    Tunnels: Pressurized twin tunnel boring machines (TBMs)

    maintain ground pressure

    Concrete tunnel liners installed as TBM proceeds

    Little surface activity

    Stations: Excavated from the ground down

    Initial surface activity (~3 years): Utility relocation

    Pile installation Decking installation

    Station construction continues below ground (~5years)

    Tunnel Boring Machines breaking through

    Station Excavation

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    11/25

    Station Box Construction:

    Soldier Pile Installation

    Initial excavation support

    Piles installed around the perimeter of

    the station box

    3 diameter hole is augured to 90 depth Steel pile is lifted and placed into the hole

    Hole is back-filled with concrete

    Work occurs behind k-rail

    Heavy equipment stays on the street

    until all piles are installed

    Sidewalks remain open

    2 lanes of traffic remain open in each

    direction

    Business access maintainedSoldier pile installation in Hollywood duringMetro Red Line construction (1995)

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    12/25

    Station Box Construction:

    Initial Excavation and Decking Installation

    Deck

    Beam

    Concrete

    Decking

    Requires full street

    closure

    Generally over a series of

    weekends

    Crews work around theclock from Friday evening

    to Monday morning

    Business access and

    sidewalks maintained

    Streets reopen in time forMonday morning rush

    hour

    Placement of beams for deck installation

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    13/25

    Traffic Control Plans

    During Full and Partial Street Closures

    Work

    Zone

    Final Traffic

    Control Plans are

    done by the

    Design-Builder

    Traffic Control Plans to be approved by Cities of Los Angeles & Beverly Hills

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    14/25

    Station Box Construction:

    Below Concrete Deck

    Completed decking at

    Hollywood/HighlandStation

    Street remains fully open with

    concrete decking

    Little difference from driving on aregularly paved street

    Station construction continues

    beneath concrete decking for

    about 5 years

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    15/25

    Extended Work Hours

    Minimizes overall duration of most significant construction impacts

    Maximizes efficiency

    Ensures Section 1 completion in early 2023

    Extended hours allows for work during: Peak Hours: Street construction during AM & PM peak periods

    Night-time: Overnight work within designated noise limits

    (not seeking variance to noise limits)

    Holiday Moratorium: Construction during non-holiday periods between

    Thanksgiving and New Years

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    16/25

    Anticipated Timing of Activities for

    Wilshire/La Cienega StationAbove Ground (now till 2017):

    Advance Utility Relocation

    Pile installation

    Decking installation

    Below Ground (2017-2021): Station excavation

    Station construction

    Above Ground (2021):

    Deck removal & street restoration

    Below Ground (Late 2022-2023):

    Systems & testing

    Pre-revenue service

    Revenue service (2023)

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    17/25

    Optimal Schedule Without Restrictions

    (Assumes extended work hours)

    Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

    SURFACE BENEATH STREET DECKING SURFACE

    Utility Relocations

    20182013 2014 2015 2016 2017 2019 2020 2021 2022 2023

    La BREA

    FAIRFAX

    La CIENEGA

    Shoring

    Street Decking

    StationExcavation

    Revenue

    Service

    Tunneling

    Station

    DeckRemoval and

    Street Restoration

    Systems

    Installation

    & Testing

    Pre-Revenue Service

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    18/25

    La Cienega Work Hours and Provisional Schedule:

    Advanced Utility Relocation

    Night Time Work: Less impact to vehicles and pedestrians

    Mitigations can be adopted to restrictnoisy work to before 11pm (saw cutting,

    jack hammering)

    Day Time Work: No on street parking will be available in

    work zone. May be more appropriate for noisy

    activities than week day nights Provides back to back to back shifts on

    Sundays Some incidental utility work is expected

    during non-peak daytime hours

    Note: Durations assume Holiday Moratorium ExemptionNote: Durations assume Holiday Moratorium Exemption

    Work

    Period

    Time of

    Day

    Detailed Work Hours Effective

    Work Hours

    per Week

    Duration

    Night-

    time and

    week-endwork

    Nights Sun-Thurs 8pm - 6am

    48 30 months

    Days Sun 8am-6pm

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    19/25

    2014 Utility Schedule

    Wilshire and La Cienega

    30 Months Total

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    20/25

    Beverly Hills Permit Requests

    Currently Pending October 15, 2013: Metro submitted 2 permit requests: fiber relocation

    and well monitoring

    December 11, 2013: City staff approved permits, pending Council

    approval

    January 21, 2014: Council deferred permit requests pending additional

    information about fiber relocation work

    February 12, 2014: Metro provided information including

    No interruption in service

    Exact locations of street closures and work zones

    Mitigation measures for access, noise and dust

    Inventory of affected parking, including revenue impact

    Outreach Plan

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    21/25

    Beverly Hills Permit Process

    Metro provides presentation to Section 1 Advisory Group Information on recently completed work

    3-6 month look-ahead for anticipated work

    Metro applies for permit with City of BH

    Once approved, Metro schedules work and proceeds with

    notices General Construction Notice sent 3 weeks in advance of pending work

    Via email, website, social media

    Detailed Construction Notice sent 3 days in advance of work, which includes Street closure details and work hours

    Detours and alternate routes

    Estimated time frame of activity

    Parking restrictions and alternatives, if necessary

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    22/25

    Mitigation Plan

    5 Step Noise Mitigation Plan1. Training

    All employees must take Noise Awareness Training

    Training offered monthly

    2. Schedule

    Schedule loudest activities during day time, weekend or early evening hours

    3. Noise Control

    Low impact back-up alarms used on trucks

    Temporary sound enclosures used at worksite

    Solar powered generators being used

    Place of equipment and steel plates gently

    Noise absorption materials placed in truck beds

    4. Monitoring

    Independent acoustical engineers, Metro, and the Contractor take night time noise

    readings for real time corrections

    5. Response

    24 hour hotline and email

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    23/25

    Mitigation Plan

    Dust

    Must follow Southern California Air Quality Management District (SCAQMD)

    standards for construction

    Access

    Access to all businesses and residents will be maintained, except when approved

    by business or resident

    If access needs to be blocked, Metro will arrange the appropriate time with the

    business or resident

    Detour maps will be provided, if necessary

    Traffic

    Traffic control plans are developed by Traffic Control Engineers and reviewed and

    approved by the City Traffic Control Plans are designed to minimize traffic disruptions, but allow the

    required work to be safely performed by our contractors and provide safe passage

    by the public

  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    24/25

    Stay in Touch

    metro.net/purplelineext

    [email protected]

    Infoline: 213.922.6934

    Twitter.com/purplelineext

    Facebook.com/purplelineext

    mailto:[email protected]:[email protected]
  • 8/13/2019 Community presentation for Beverly Hills, Feb. 13, 2013

    25/25

    Questions?