2012 PACIFIC AVIATION DIRECTORS WORKSHOPMarch 13 – 15, 2012
The Westin Resort Guam Tumon, Guam
CPA’s Outlook: CNMI will rebound because of our beautiful islands that attract
Asian travelers; Close coordination with visitors authority on marketing &
promotions to increase traffic by 100% over a 5 year period; Use the newly approved US DOT approval to convince foreign air
carriers to fly additional US points beyond CNMI; Closely work with existing carriers to maximize load factors and
to initiate new flights; Sichuan Airlines executed AUA with CPA for direct service to and
from different cities in China; Air Saipan inaugural flight scheduled for July 2012. Providing air
service between Saipan to Japan and other Asian destinations; and Arctic Airlines estimated to commence operations in May 2012
with cargo service between Saipan, Rota and Guam.
PROJECT:
Generator and Power Upgrade COMPLETED Runway 07/25 Rehabilitation Project Package II Phase I
COMPLETED Terminal Improvements
PA System Replacement Completed Restroom Renovations Design Phase High Roof & A/C Improvements Design Phase Commuter (Domestic) Terminal Renovations Design
Phase Runway 07/25 Rehabilitation Project Package II – Phase II
ONGOING ARFF Pacific Region Training Facility Improvements
ONGOING ARFF Building Expansion DESIGN PHASE Procurement of Runway Sweeper ACIP LISTED Procurement of Two (2) 1,500 Gallon ARFF Vehicles ACIP
LISTED Airport Master Plan Update ACIP LISTED Replacement of Two Passenger Loading Bridges ACIP
LISTED
SAIPAN INTERNATIONAL AIRPORT
Terminal Improvements Public Address System Replacement
Design/Build Contract awarded to RadioCom NTP – December 21, 2009 Completion Date – December 22, 2010
Restroom Renovations & Water Pump Upgrade Designer – GHD (formerly known as Winzler & Kelly) Construction Manager – GHD Project redesigned to accommodate additional restroom and drainage
issues
High Roof Drainage & A/C Improvements Designer – Hofschneider Engineering Construction Manager – SSFM Saipan Project redesigned to include replacement of holding room air-
conditioning units per FAA approval
Commuter Terminal Renovations Designer – Taniguchi Ruth Makio Architects Construction Manager – Pending Design completed. Pending completion of other projects to ensure
available funding.
Saipan Runway Rehabilitation Project: Project awarded to GPPC in September 2009 but
contract was put on hold due to SMS requirements SMS Panel convened in March 2010. Panel found
construction activities to be low risk On March 24, 2010, construction resumed with
electrical work Milling and paving work commenced in November
2010 at approximately 50% completion Work suspended to address issues with deeper
cracks CPA recently received FAA approval for
supplemental crack repairs to address issue and extend life expectancy
Redesign is underway but will extend completion date to end of 2012 or later
Contractor has resumed shoulder work, conduit laying and installation of new lighting fixtures
Saipan Runway Rehabilitation Progress Photos
Deep Cracks
Milling work
Tack coat application
Paving
ARFF Training Facility Improvements
Design/build contract awarded to GPPC, Inc.
NTP – June 13, 2011 For Phase I and II
Completion date – Pending issuance of 3rd NTP for physical construction Phase I – SAFT Manufacturing Phase II – Completion of Design Phase III - Construction of site works,
buildings, fuel spill burn area
SIA ARFF Training Facility Condition
Perspective of Future Training Facility
TINIAN INTERNATIONAL AIRPORT
PROJECT:
1. New Departure Building DESIGN PHASE2. Water Tank & Line for ARFF Rapid Refill DESIGN PHASE3. ARFF Building Relocation DESIGN PHASE4. 1,500 Gallon ARFF Vehicle ACIP LISTED5. Airport Master Plan Update ACIP LISTED6. ARFF Access Road ACIP LISTED7. High Speed Exit Taxiway “B” ACIP LISTED8. Security Access System Installation ACIP LISTED9. Perimeter Security Fence Replacement ACIP LISTED
Tinian Progress Photos
Existing ARFF Building to be relocated
New Departure Terminal
Existing ARFF Vehicles
New water tank to be installed for rapid refill of ARFF vehicles
ROTA INTERNATIONAL AIRPORT
PROJECT:
Repainting of Entire Terminal (Non-AIP) COMPLETED Runway Extension Project Phase II COMPLETED Airport Master Plan Update ACIP LISTED 1,500 Gallon ARFF Vehicle ACIP LISTED Perimeter Security Fence Replacement ACIP LISTED Existing Apron Treatment ACIP LISTED Security Access System ACIP LISTED
Rota Progress Photos
Ribbon Cutting Ceremony for Runway Extension Phase II (Shoulder and new
Generator) Project
New generator and building
Apron in need of treatment
Airport layout plan to be updated during Master Plan Update
Where CPA is at now… CPA working closely with FAA to complete all
AIP funded projects Management taking proactive steps to ensure
smooth operations for both air and seaports CPA exceeds the debt ratio in 2010 and 2011
for airport and seaport revenue bonds No questionable costs discovered during CPA’s
2009 and 2010 audits Procurement, Personnel, Airport and Seaport
Rules and Regulations being updated Master plans for all three airports and
seaports anticipated in order to improve all facilities
CPA working closely with Executive and Legislative branches of government for project coordination and funding of non-AIP projects
CONTACT INFORMATION:
MR. EDWARD M. DELEON GUERRERO Executive Director
Commonwealth Ports AuthorityPO Box 501055
Saipan, MP 96950Tel: (670) 237-6500/01
Fax: 234-5962Email: [email protected]
Website: www.cpa.gov.mp
HAFA ADAI AND THANK YOU VERY MUCH!!!