ACG CxA WORKSHOP WEBINAR
Commissioning Webinar Commissioning Webinar Thursday, December 1, 2011Thursday, December 1, 2011
2:30 2:30 –– 5:00 p.m., EST5:00 p.m., EST
Instructor: Jim Magee, CxA, LEED-APImmediate Past President, ACG
President, Facility Commissioning Group
ACG CxA WORKSHOP WEBINAR
AIA Continuing Education CourseThe AABC Commissioning Group (ACG) is a Registered
Provider with The American Institute of Architects Continuing Education System (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material or construction or any method or manner of handling, using, distributing, or dealing with any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
ACG CxA WORKSHOP WEBINAR
Course Description
This 2 ½ hour Commissioning Webinar will cover the commissioning process as described in the ACG Commissioning Guideline, as well as valuable practical insight on skills, strategies, and communication and documentation protocols essential to applying the process on “real- world” projects.
ACG CxA WORKSHOP WEBINAR
Learning Objectives d
At the end of this program, participants will be able to:
Explain the purpose, methodology, and benefits of the commissioning process as it relates to construction projects.
Identify and distinguish between the five phases of commissioning – (1) Pre-Design, (2) Design, (3) Construction, (4) Acceptance, and (5) Post-Acceptance – and the activities carried out in each of them.
Describe the documentation and deliverables that are essential to the delivery of quality commissioning services.
Identify the roles and responsibilities of all commissioning team members within the commissioning process, with particular emphasis on the role of the commissioning provider.
ACG CxA WORKSHOP WEBINAR
OverviewOverview
CxCx Advocacy, Economics, BenefitsAdvocacy, Economics, Benefits
Associations, Certifications, GuidelinesAssociations, Certifications, Guidelines
Commissioning TeamCommissioning Team
Commissioning (Commissioning (CxCx) Process) Process
CxCx Team Roles and ResponsibilitiesTeam Roles and Responsibilities
Commissioning Website ResourcesCommissioning Website Resources
DiscussionDiscussion
ACG CxA WORKSHOP WEBINAR
CommissioningCommissioning Advocacy, Advocacy, Economics, & BenefitsEconomics, & Benefits
ACG CxA WORKSHOP WEBINAR
Why Commission?Why Commission?
Better Buildings
Building owners are finding that the energy, water, and productivity savings achieved by commissioned buildings can offset the cost of the commissioning process. Studies indicate 8 to 20 percent savings in building operating costs over those in a non-commissioned building.
(Building Commissioning Guide, Version 2.2, GSA/DOE, dated July 30, 1998)
ACG CxA WORKSHOP WEBINAR
Why Commission?Why Commission?
Better PeopleBetter People
Aside from achieving documented cost savings and cost avoidance, commissioning enhances customer satisfaction by promoting proper training of the owner’s Operations & Maintenance staff, which increases the longevity and efficient operation of building systems.
ACG CxA WORKSHOP WEBINAR
What is Commissioning?What is Commissioning?
A process of documentation, adjustment, testing, verification, and training, performed specifically to ensure that the finished facility operates in accordance with the owner’s documented project requirements and the construction documents.
It begins in pre-design and continues through design, construction, and the life of the facility.
(BCA draft document, 2004.)
ACG CxA WORKSHOP WEBINAR
What is Commissioning?What is Commissioning?
Design Intent Document
Details functional requirements and Owner’s expectations of how a building will be used and operated - OWNER’S PROJECT REQUIREMENTS
Basis for building commissioning
Basis of Design
The concepts, calculations, decisions, and product selections used to meet the OWNER’S PROJECT REQUIREMENTS
ACG CxA WORKSHOP WEBINAR
What Commissioning is NOT?What Commissioning is NOT?
Completing Standard Forms
Contractors’ QA/QC Program
Verification of the Contractors’ QA/QC Program
Construction Inspection
Construction Management Substitute
ACG CxA WORKSHOP WEBINAR
DesignIntent
Commissioningvalidates the design!
That the design works and meets the “design intent”
Commissioning
“retro” ; “re”; or
“ongoing”Cx
Design Construction O & M
“Inspections” validate
constructionThat the construction is installed correctly per the “design”
Changing Needs
What is Commissioning?(validates the “design”!)
This is not commissioning!
ACG CxA WORKSHOP WEBINAR
Objections To CommissioningObjections To Commissioning
““HavenHaven’’t I already paid for a quality building t I already paid for a quality building in my design and construction fees?in my design and construction fees?””
Designer’s (A/E) services typically do not include field verification that their design works as intended.
Construction Manager’s services typically do not include functional verification that the installed systems meet design intent.
ACG CxA WORKSHOP WEBINAR
Objections To CommissioningObjections To Commissioning
“Isn’t the Commissioning Authority just a ‘bigger hammer’ for the owner to use to
pound the designer and contractor?”
No. The CxA must be a team builder by using the commissioning process to the benefit of all.
No. The CxA should respect the traditional construction disciplines. The CxA has a distinct responsibility to owner for system quality and performance.
ACG CxA WORKSHOP WEBINAR
Objections To CommissioningObjections To Commissioning
“Isn’t commissioning just another layer of inspection?”
The CxA is not a layer, but a catalyst for communication that makes quality solutions possible.
The CxA is not inspector (fault finder, accuser).
The commissioning process provides verification that Owner’s Project Requirements implemented in design and construction.
ACG CxA WORKSHOP WEBINAR
Commissioning (Commissioning (CxCx))(New Construction)
0.5 to 1.5 Percent of Total Construction Cost
RetrocommissioningRetrocommissioning ((RetroCxRetroCx))(Existing Construction)
3.0 to 5.0 Percent of Total Operating Cost
Source: Building Commissioning Guide, Version 2.2, DOE/GSA, July 30, 1998
Wha
t Doe
s Com
mis
sion
ing
Cos
t?
ACG CxA WORKSHOP WEBINAR
Commissioning CostsCommissioning Costs
Commissioning New ConstructionCommissioning New Construction
Approximately 2%-3% of Mechanical System Construction Cost – (BCA Case Studies)
Approximately 1%-2% of Electrical System Construction Cost – (BCA Case Studies)
Approximately 2%-5% of Comprehensive HVAC Construction Cost – (ACG Commissioning Guideline)
ACG CxA WORKSHOP WEBINAR
The Economics of CommissioningThe Economics of Commissioning
* Based on research findings from University of Wisconsin,ASERTTI Training Module, 1998
If planned correctly and implemented early enough in the design process, commissioning can be included with little or no cost impact*.
Without Commissioning
With CommissioningDesign Phase Costs
Construction Phase Costs First Year Warranty Period Costs
Design Phase Costs
Construction Phase Costs First Year Warranty Period Costs
Wha
t Doe
s Com
mis
sion
ing
Cos
t?
ACG CxA WORKSHOP WEBINAR
BenefitsBenefits
Better bid documents
More accurate budgets
More “control” of project
Projects delivered on time
Fewer change orders
Fewer warranty issues
Satisfied Client
ACG CxA WORKSHOP WEBINAR
Associations, Certifications, & Guidelines Associations, Certifications, & Guidelines
ACG CxA WORKSHOP WEBINAR
AssociationsAssociations
AABC Commissioning Group (ACG)
ASHRAE
Building Commissioning Association (BCxA)
Institute of Electrical & Electronic Engineers (IEEE)
International Society For Pharmaceutical Engineering (ISPE)
National Environmental Balancing Bureau (NEBB)
Sheet Metal and Air Conditioning Contractors' National Association / Testing Adjusting and Balancing Bureau (SMACNA / TABB)
University of Wisconsin
Association of Energy Engineers (AEE)
ACG CxA WORKSHOP WEBINAR
CertificationsCertifications
AABC Commissioning Group (ACG)
ASHRAE (Process Management Certification)
Building Commissioning Association (BCxA)
Institute of Electrical & Electronic Engineers (IEEE)
International Society For Pharmaceutical Engineering (ISPE)
National Environmental Balancing Bureau (NEBB)
Sheet Metal and Air Conditioning Contractors' National Association / Testing Adjusting and Balancing Bureau (SMACNA / TABB)
University of Wisconsin
Association of Energy Engineers (AEE)
ACG CxA WORKSHOP WEBINAR
The Need for GuidelinesThe Need for Guidelines
Uniform delivery of services
Cx adoption as standard practice
Owner procurement / selection of providers
Continuing education
Benchmarking of Cx Benefits
Training competent Cx service providers
Client education and cooperation
Efficient Cx interface with designers, contractors, vendors, etc
ACG CxA WORKSHOP WEBINAR
GuidelinesGuidelines
ACG Commissioning Guideline – 2005
ASHRAE Guideline 1 –1996: The HVAC Commissioning Process
ASHRAE Guideline 1.1 – 2007: HVAC&R Technical Requirements for the Commissioning Process
ASHRAE Guideline 0-2005: The Commissioning Process
NECA90-2004: Recommended Practices for Commissioning Building Electrical Systems
ISPE Pharmaceutical Engineering Guide Volume 5: Commissioning and Qualification
ACG CxA WORKSHOP WEBINAR
ACG Commissioning Guideline1. Independent 3rd party direct for owner Cx services
2. Cx process intended for provider application
3. Useful for owners, designers and constructors, but intended for training Cx providers
4. Defines 5-Phase process:
a) Pre-Design
b) Design
c) Construction
d) Acceptance
e) Post-Acceptance
ACG CxA WORKSHOP WEBINAR
ASHRAE Guideline 11. Cx responsibilities statement in request for A/E design
services.
2. Owner’s Program development and commitment.
3. Assign O&M personnel to the commissioning process.
4. Review and approve the Design Intent Document.
5. Review and approve the construction documents.
6. Provide competent documenting of training sessions (video, etc.)
7. Record construction progress (photo, video, narratives, etc.)
8. Review and comment on CxA verification report.
9. Review and accept the commissioning report
ACG CxA WORKSHOP WEBINAR
Guideline 0:1.1. CxCx responsibilities statement in request for A/E design responsibilities statement in request for A/E design
services.services.2.2. Develop and commit to OwnerDevelop and commit to Owner’’s Project Requirements.s Project Requirements.3.3. Assign O&M personnel to the commissioning process.Assign O&M personnel to the commissioning process.4.4. Review and approve changes made in the OwnerReview and approve changes made in the Owner’’s Project s Project
Requirements.Requirements.5.5. Review and approve the Construction Documents.Review and approve the Construction Documents.6.6. Provide competent documenting of training sessions (video, Provide competent documenting of training sessions (video,
etc.)etc.)7.7. Review and comment on the Review and comment on the CxCx Process Progress Reports.Process Progress Reports.8.8. Review and comment on the Review and comment on the CxCx AuthorityAuthority’’s verification s verification
reports.reports.
ACG CxA WORKSHOP WEBINAR
What is the key difference between Guideline 1 and Guideline 0?
Design Intent Document
Vs.
Owner’s Project Requirements
ACG CxA WORKSHOP WEBINAR
ASHRAE Guideline 1.11. Aligns Guideline 1.1 with Guideline 0 terminology
2. Greater emphasis on Owners Project Requirements (OPR)
3. Eliminate DID terminology
4. Suggests challenging design for achieving OPR
5. Promotes sampling over 100% verification and testing
6. Includes more technical process details (specific tasks)
7. Enhanced appendix of sample forms and procedures
8. Advocates extensive training for owner personnel
9. Promotes team building to accomplish commissioning
ACG CxA WORKSHOP WEBINAR
Owner’s Project Requirements
Program requirements
Community context
Codes and regulations
Site and climate
Facility context and function
Facility technology
Sustainability
Cost
Schedule
Client’s needs and capabilities
ACG CxA WORKSHOP WEBINAR
Commissioning DefinitionsCommissioning Definitions
Commissioning Authority (CxA):Commissioning Authority (CxA):
A person (or firm) representing the facility owner
Leader of the Commissioning Team
Authority of Cx Process – not design or means and methods
CxA not in chain of command – preserves objectivity
ACG CxA WORKSHOP WEBINAR
Commissioning DefinitionsCommissioning Definitions
Commissioning Provider (CP):Commissioning Provider (CP):
Independent Third-Party Commissioning Firm
A/E Firm
General Contractor
Construction Manager
Owner's Personnel
ACG CxA WORKSHOP WEBINAR
Commissioning DefinitionsCommissioning Definitions
EXISTING BUILDING COMMISSIONINGEXISTING BUILDING COMMISSIONING
RetroRetro--Commissioning (Commissioning (RetroCxRetroCx):):
Commissioning an existing building that has never been commissioned
ReRe--Commissioning (Commissioning (ReCxReCx):):
Commissioning a building that has been previously commissioned
Continuous Commissioning (Continuous Commissioning (CCxCCx):):
Owner continues to collect and compare baseline data on selected building systems to ensure that the building functions optimally throughout its operating life
ACG CxA WORKSHOP WEBINAR
Commissioning DefinitionsCommissioning Definitions
Total Building Commissioning (Total Building Commissioning (TBCxTBCx))
Emphasizes that Commissioning is NOT only for the Mechanical and HVAC system, or any single system
Commissioning TeamCommissioning Team
Experts who, through coordinated actions, are responsible for carrying out the Commissioning Process
Commissioning PlanCommissioning Plan
A strategy overseen by the Commissioning Authority and prepared by the Commissioning Team
ACG CxA WORKSHOP WEBINAR
Systems Typically CommissionedSystems Typically Commissioned
Mechanical SystemsMechanical Systems
Heating, Ventilation and Air Conditioning (HVAC)
Building Automation Systems (BAS)
Fire ProtectionElectrical SystemsElectrical Systems
Switchgear and Transformers
Grounding/Bonding, Circuitry
Generators and UPS Systems
Lighting and Lighting ControlsSpecialty SystemsSpecialty Systems
Security Systems and Fire Alarm
Voice/Data Systems
ACG CxA WORKSHOP WEBINAR
Future Commissioned SystemsFuture Commissioned Systems
The National Institute for Building Sciences (NIBS) is currently developing commissioning requirements for the following systems:
Exterior Envelope
Roofing Systems
Structural Systems
Interior Systems
Elevator Systems
Plumbing Systems
Lighting Systems
Electrical Systems
Fire Protection Systems
Telecommunication Systems
ACG CxA WORKSHOP WEBINAR
LEED EA Prerequisite 1LEED EA Prerequisite 1
Experienced, independent, CxA to owner
Review OPR and DID
Incorporate Cx requirements into CD’s
Create/execute Cx Plan
Verify installation and performance of Systems to be Commissioned
Complete and submit a Cx Report
ACG CxA WORKSHOP WEBINAR
EA Credit 3 Enhanced CommissioningEA Credit 3 Enhanced Commissioning
Independent 3rd Party CxA
Review OPR, BOD and Design by mid-CD’s
Independent submittal review
Systems Manual
O&M and Occupant Training Verification
10th Month Review of Building Operation
ACG CxA WORKSHOP WEBINAR
Team EffortTeam Effort
Commissioning succeeds whenCommissioning succeeds when……
Team members understand and carry out their responsibilities
Team members cooperate and coordinate with each other and third-party agencies
Communication and accountability essential for effective teamwork – and they are the responsibility of the commissioning agent.
ACG CxA WORKSHOP WEBINAR
Commissioning Team MembersCommissioning Team Members
Owner / OperatorOwner / Operator
ArchitectArchitect
Design ConsultantsDesign Consultants
Commissioning AgentCommissioning Agent
Construction Manager (or General Contractor)Construction Manager (or General Contractor)
Mechanical ContractorMechanical Contractor
Electrical ContractorElectrical Contractor
Temperature Controls ContractorTemperature Controls Contractor
Test and Balance ContractorTest and Balance Contractor
ACG CxA WORKSHOP WEBINAR
Commissioning Team MembersCommissioning Team Members
Potential Team Members:Potential Team Members:
Equipment Vendors
Specialty Trades
Specialty Consultants
Program Manager
Service Contract Providers
BAS Specialists
IT Support Groups
ACG CxA WORKSHOP WEBINAR
Elements of CommissioningElements of Commissioning
Design Intent Documents (DID or OPR)Design Intent Documents (DID or OPR)
Design ReviewsDesign Reviews
Submittal ReviewsSubmittal Reviews
Site Observations and Site MeetingsSite Observations and Site Meetings
Resolution Tracking Forms (Resolution Tracking Forms (RTFRTF’’ss))
System Verification Checklists (System Verification Checklists (SVCSVC’’ss))
Organized Systems StartOrganized Systems Start--UpsUps
Functional Performance Tests (Functional Performance Tests (FPT'sFPT's))
Operation and Maintenance (O&M) trainingOperation and Maintenance (O&M) training
O&M DocumentationO&M Documentation
Commissioning ReportCommissioning Report
Warranty Review of Building OperationWarranty Review of Building Operation
ACG CxA WORKSHOP WEBINAR
Approaches to CommissioningApproaches to Commissioning
Comprehensive Commissioning
Construction Phase Commissioning
ACG CxA WORKSHOP WEBINAR
Phases of CommissioningPhases of Commissioning
PrePre--Design PhaseDesign Phase
Design PhaseDesign Phase
Construction PhaseConstruction Phase
Acceptance PhaseAcceptance Phase
PostPost--Acceptance PhaseAcceptance Phase
ACG CxA WORKSHOP WEBINAR
PrePre--Design PhaseDesign Phase
Establish commissioning Establish commissioning
Select a Commissioning Agency (CxA)Select a Commissioning Agency (CxA)
Develop commissioning scopeDevelop commissioning scope
CxA review of DID or OPRCxA review of DID or OPR
ACG CxA WORKSHOP WEBINAR
PrePre--Design PhaseDesign Phase
Establish commissioning:Establish commissioning:
Allocate funds in budget
Comprehensive or Construction
Independent 3rd Party , Design Team, or Construction Team
HVAC, Electrical, Etc.
ACG CxA WORKSHOP WEBINAR
PrePre--Design PhaseDesign Phase
Select a Commissioning Agency (CxA):Select a Commissioning Agency (CxA):
Request for Qualifications
Request for Proposal
ACG CxA WORKSHOP WEBINAR
PrePre--Design PhaseDesign Phase
Develop commissioning scope:
Match scope to budgetMatch scope to budget
Needs basedNeeds based
Past experiencePast experience
EndEnd--user needsuser needs
Maintenance prioritiesMaintenance priorities
ACG CxA WORKSHOP WEBINAR
PrePre--Design PhaseDesign Phase
CxA review of DID or OPR:CxA review of DID or OPR:
Defined usage
Defined goals
Short term needs
Long term needs
ACG CxA WORKSHOP WEBINAR
Design PhaseDesign Phase
Review design for commissioning, testing and O&M access and provisions
Prepare commissioning specification
Write the commissioning plan
Establish commissioning in the project schedule
ACG CxA WORKSHOP WEBINAR
Design PhaseDesign Phase
Review design for commissioning, testing and O&M access and provisions:
Adequate testing access
Adequate access for valves, dampers, control
Quantity and location of service valves
Coil pull access
Ladders and catwalks
Conformity to Owner’s Design Standards
ACG CxA WORKSHOP WEBINAR
Design PhaseDesign Phase
Prepare commissioning specification / plan:Prepare commissioning specification / plan:
Develop commissioning plan
Commissioning team
Systems to be commissioned
Define approximate extent of testing
Contractor roles and responsibilities
ACG CxA WORKSHOP WEBINAR
Design PhaseDesign Phase
Establish commissioning in the project schedule:Establish commissioning in the project schedule:
General and Supplemental ConditionsGeneral and Supplemental Conditions
Define commissioning activities in scheduleDefine commissioning activities in schedule
Note blocks of time for Note blocks of time for FPTFPT’’ss in schedule in schedule –– especially for phased projectsespecially for phased projects
Define frequency of Define frequency of CxCx meetingsmeetings
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Review submittals
Update commissioning plan
Coordination including site observation, Cx Meetings, Resolution Tracking Forms (RTF’s), and System Verification Checklists (SVC’s)
Equipment and systems start-ups
TAB HVAC systems
Verify Building Automation System (BAS) installation and start-up
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Review submittals:Review submittals:
Checklist based on specification and OwnerChecklist based on specification and Owner’’s s Design StandardsDesign Standards
Check options Check options –– especially accessespecially access
Check size for spatial applicationCheck size for spatial application
Check valve sizing and applicationCheck valve sizing and application
Check for integration of componentsCheck for integration of components
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Update commissioning plan:Update commissioning plan:
Include revised schedule
SVC’s based on current information
Draft FPT’s for review
Discuss O&M Documentation
Provide construction observation procedures
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Coordination:Coordination:
Site observationSite observation
CxCx MeetingsMeetings
Resolution Tracking Forms (Resolution Tracking Forms (RTFRTF’’ss))
System Verification Checklists (System Verification Checklists (SVCSVC’’ss))
Functional Performance Tests (Functional Performance Tests (FPTFPT’’ss))
O&M Training ProvisionsO&M Training Provisions
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Equipment and systems startEquipment and systems start--ups:ups:
Contractor start-up
Factory start-up
Documentation chain of submission
Temporary conditions
Maintenance responsibility
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
TAB HVAC systems:TAB HVAC systems:
Systems properly started
Systems under full control
Appropriate hardware and software interface
Coordination with other trades, especially TCC
Access to space
ACG CxA WORKSHOP WEBINAR
Construction PhaseConstruction Phase
Verify Building Automation System (BAS):Verify Building Automation System (BAS):
Installation complete per design
Installation complete per submittal / drawings
Start-up performed and documented
Project specific programming
Point-to-point checklists
Safeties tested and documented
ACG CxA WORKSHOP WEBINAR
Acceptance PhaseAcceptance Phase
Review TAB Report
Functional Performance Tests (FPT’s)
O&M Training and Documentation
Commissioning Report
ACG CxA WORKSHOP WEBINAR
Acceptance PhaseAcceptance Phase
Review TAB Report:Review TAB Report:
Pages are numbered with index
All equipment is accounted for in report
No “extra” equipment shown in report
Performance is per design (± XX %)
Problems sufficiently documented in footnotes
ACG CxA WORKSHOP WEBINAR
Acceptance PhaseAcceptance Phase
Functional Performance Tests (Functional Performance Tests (FPTFPT’’ss):):
Systems tested as noted in the Cx Plan
“Failure” modes for valves and dampers are not software driven
System is properly networked
Workstation graphics show appropriate response
Occupied / Unoccupied / Optimal Start
ACG CxA WORKSHOP WEBINAR
Acceptance PhaseAcceptance Phase
O&M Training and Documentation:O&M Training and Documentation:
Manuals contain useable maintenance documentsManuals contain useable maintenance documents
Proper indexing and tabsProper indexing and tabs
Training agenda tailored for ownerTraining agenda tailored for owner’’s needss needs
Documentation provided prior to trainingDocumentation provided prior to training
Additional documentation provided at trainingAdditional documentation provided at training
Training for systems and componentsTraining for systems and components
ACG CxA WORKSHOP WEBINAR
Acceptance PhaseAcceptance Phase
Commissioning Report:Commissioning Report:
Proper indexing and tabsProper indexing and tabs
Documentation for all phasesDocumentation for all phases
Executive SummaryExecutive Summary
Provide supporting documentation (Sequence of Provide supporting documentation (Sequence of Operation, Control Drawings, Etc.)Operation, Control Drawings, Etc.)
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
Correct unresolved deficiencies and conduct required re-tests
Carry out specified off-season testing
Perform specified post-occupancy monitoring
Review usage changes
Update commissioning documentation
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
Correct unresolved deficiencies:Correct unresolved deficiencies:
Unresolved RTF issuesUnresolved RTF issues
Uncompleted CM/Owner punch listsUncompleted CM/Owner punch lists
Conduct required reConduct required re--teststests
Outstanding or additional trainingOutstanding or additional training
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
Carry out specified offCarry out specified off--season testing:season testing:
FPT’s per the Commissioning Plan
Choose near-design day
Build on completed FPT’s
Utilize BAS trending
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
PostPost--occupancy monitoring:occupancy monitoring:
Scheduled site visits
Remote (web) monitoring
Warranty items
Owner conference
User conference
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
Review usage changes:Review usage changes:
Computers / office machines
Furniture placement
Occupancy change
Closet to office
Energy saving methodology
ACG CxA WORKSHOP WEBINAR
Post Acceptance PhasePost Acceptance Phase
Update commissioning documentation:Update commissioning documentation:
Resolved issuesResolved issues
OffOff--Season testsSeason tests
Usage ChangesUsage Changes
Provide additional volume for Provide additional volume for CxCx ReportReport
ACG CxA WORKSHOP WEBINAR
Commissioning Team Commissioning Team
Roles and ResponsibilitiesRoles and Responsibilities
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Owner / OperatorOwner / Operator
Assign Assign CxCx Team Member and attend meetingsTeam Member and attend meetings
Retain a commissioning agentRetain a commissioning agent
Communicate project requirements to the design Communicate project requirements to the design teamteam
Coordinate facilities and staff participationCoordinate facilities and staff participation
Conduct regular site observationConduct regular site observation
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
ArchitectArchitect
Assign Cx Team Member and attend meetings
Coordinate work of design consultants
Consider spatial requirements
Consider room naming convention
Conduct regular site observation
Coordinate design and changes with owner and end-users
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Design ConsultantsDesign Consultants
Assign Cx Team Members and attend meetings
Provide Basis of Design and Design Intent
Respond to RFI’s and CO’s
Conduct regular site observation
Coordinate design and changes with owner and end-users
Review O&M manuals, as-built drawings and other specified documentation
Provide HVAC training on the design intent
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Commissioning AgentCommissioning Agent
Assign Cx Team Leader and attend meetings
Review Design
Provide Commissioning Plan and Specification
Conduct regular site observation visits
Provide System Verification Checklists
Monitor system start-ups
Conduct Functional Performance Tests
Review O&M documentation and training
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Construction ManagerConstruction Manager
Assign Cx Team Member and attend meetings
Project Scheduling
Manage overall completion of work
Manage project documentation
Coordination of contractors
Maintaining specified building conditions
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Mechanical ContractorMechanical Contractor
Assign Cx Team Member and attend meetings
Manage subcontractors and vendors
Document Progress (SVC’s)
Coordinate equipment start-up
Operate systems as required for Functional Performance Tests
Plan and deliver O&M staff training
Provide O&M manuals, as-built drawings and other specified documentation
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Electrical ContractorElectrical Contractor
Assign Assign CxCx Team Member and attend meetingsTeam Member and attend meetings
Coordinate electrical installation with mechanical Coordinate electrical installation with mechanical workwork
Attend meetingsAttend meetings
Document Progress (Document Progress (SVCSVC’’ss))
Operate systems as required for Functional Operate systems as required for Functional Performance TestsPerformance Tests
Plan and deliver O&M staff trainingPlan and deliver O&M staff training
Provide O&M manuals, asProvide O&M manuals, as--built drawings and built drawings and other specified documentationother specified documentation
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Temperature Controls ContractorTemperature Controls Contractor
Assign Cx Team member and attend meetings
Design and complete controls installation as required by DID/OPR
Document Progress (SVC’s)
Coordinate with TAB agency
Operate systems as required for Functional Performance Tests
Plan and deliver O&M staff training
Provide O&M manuals, as-built drawings and other specified documentation
ACG CxA WORKSHOP WEBINAR
Commissioning Team RolesCommissioning Team Roles
Test and Balance ContractorTest and Balance Contractor
Assign Assign CxCx team member and attend meetingsteam member and attend meetings
Review design for adequate testing provisionsReview design for adequate testing provisions
Submit TAB data sheets for approvalSubmit TAB data sheets for approval
Coordinate work with master scheduleCoordinate work with master schedule
Review site conditions prior to field workReview site conditions prior to field work
Submit complete and accurate TAB ReportSubmit complete and accurate TAB Report
Participate in verification of TAB ReportParticipate in verification of TAB Report
ACG CxA WORKSHOP WEBINAR
ResourcesResources
www.commissioning.org for AABC Commissioning Group
www.ashrae.org for American Society of Heating, Refrigerating, and Air-Conditioning Engineers
www.bcxa.org for Building Commissioning Association
www.buildingamerica.gov for U. S. Dept. of Energy Building America Program
www.facomgrp.com for Facility Commissioning Group
ACG CxA WORKSHOP WEBINAR
ResourcesResources
www.ieee.org for Institute of Electrical & Electronic Engineers
www.ispe.org for International Society For Pharmaceutical Engineering
www.nebb.org for National Environmental Balancing Bureau
www.peci.org for Portland Energy Conservation, Inc.
www.smacna.org for Sheet Metal and Air Conditioning Contractors' National Balancing Bureau
www.usgbc.org for United States Green Building Council
ACG CxA WORKSHOP WEBINAR
Q&A
This concludes The American Institute of Architects Continuing Education Systems Course.
ACG National Headquarters 1518 K Street, NW, Suite 503 Washington, DC 20005 (ph) 202-737-7775 www.Commissioning.org [email protected]