COMMISSIONING MANAGEMENT · The Commissioning Management is a quality-oriented process for...

97
Converting Energy to Synergy COMMISSIONING MANAGEMENT ROLE, PROCESS AND IMPACT

Transcript of COMMISSIONING MANAGEMENT · The Commissioning Management is a quality-oriented process for...

  • Converting Energy to Synergy

    COMMISSIONING MANAGEMENT

    ROLE, PROCESS AND IMPACT

  • OUTLINE

    ABOUT CSI, WHO WE ARE

    WHAT IS COMMISSIONING, WHY IS IT NEEDED?

    COMMISSIONING MANAGEMENT TOOLS, VIDENTIUM REVEALED

    ADDED VALUE FOR COMMISSIONING MANAGEMENT, WHAT TO EXPECT

    COMMISSIONING STAGES AND PROCESS, WHEN TO GET INVOLVED

    ENERGY CONSUMPTION IMPACT, IT WORTHS

    CONCLUSION, SO WHAT SHOULD WE DO?!

    2

  • ABOUT CSI, WHO WE ARE

  • THE IDEA, HOW CSI STARTED

    • Established and based in Istanbul, Turkey in 2004 asthe small commissioning department of its MEPmother company MEGA MEP.

    • It was in 2010 when the new founders met working together in New Doha International Airport project that the ambitious idea and dream of an engineering company dedicated to MEP Commissioning Management with high caliber staff emerged.

    • After multiple plans and attempts for businessdevelopment, CSI had its breakthrough in 2015 withfirst awarded project in Qatar and Turkey.

    • By end of 2018, CSI reached total manpower in alloperations of 200 staff

    • Qatari branch office was made under the name CSICommissioning Services in October 2018 withdedicated core staff of 40 staff.

    4

  • CSI CONTACTS, WHERE TO FIND CSI

    5

  • CSI MANPOWER

    Technicians

    100

    Senior and Field Engineers

    120

    Projects Mangers and Commissioning

    Mangers

    20

    Management and Admin Team

    20

    CSI has a massive directly employed manpower of about 260 staff members. The managerial and senior staff members, number of 20, and 240 total dedicated to Testing and Commissioning, TAB and Energy Auditing ranging from 6 to 22 years of experience.

    6

  • CSI BOARD OF DIRECTORS

    Over 40 years of experience in the MEP construction field, with wide experience in Mega prestigious projects in MENA and Europe. Mr. Tuncer Selim is the Founder and Chairman of MEGA MEP, one of the leading MEP companies in Turkey and the backbone co-founder of CSI.

    CSI Managing Director and Co-founder , Yuksel Caglar has over 25 years of MEP construction experience working for Mega projects in MENA and Europe. Yuksel has an extensive experience in managing MEP works and is leading CSI management team from its base in Warsaw, Poland.

    CSI General Manager and Co-founder with more than 15 years of dedicated experience in the TAB and Commissioning field. Holding Project Management Diploma from American University in Cairo when at 25, gaining strategic planning for new markets experience Ahmed is managing the executive part of CSI business planning and operation.

    CSI Operations Manager and Co-founder, with more than 14 years of experience in the field of testing and commissioning in mega projects in GCC and Turkey. Mustafa is the dynamic heart of the company with his experience in leading the growing number of staff and client

    CSI Business Development Manager and Co-founder, EfeSelim worked in two mega projects of Hamad & Abu Dhabi International Airport developing 10 years of experience in IT & Business Development. Efe is leading the continuous development of CSI software VIDENTIUM and its branched applications.

    7

  • CSI KEY MANAGEMENT PERSONS

    CSI Technical Manager, Mohammed Ghannam is CEM, CMVP certified and experienced technical engineer with over 7 years of experience in energy management and commissioning field.Mohamed is developing CSI internal processes among the departments to enable a smooth company operation.

    CSI Technical Office Manager and CSI Egypt Co-Founder and General Manager, Mahmoud Saleh is NEBB Certified with over 13 Years experience in TAB Service and completed over 100 project . With his Station in Cairo Mahmoud is also devlopongthe training of new recruited staff technical abilities

    CSI Qatar Operations Manager who joined CSI team in January 2018, Ibrahim spent all his professional life in Dar Al Hadasah for extensive 8 years in supervising and commissioning big projects. Ibrahim is leading Qatar assigned staff of 40 staff members and providing the quality control of the contractual obligations of CSI to its clients.

    CSI Egypt Operations Manager, Hany is a big added value to CSI team since joining CSI team in August 2016. With his extensive field experience in electrical testing, Hany managed to deliver mega projects works operational to clients and developed the hands on skills of CSI staff.

    CSI Projects Manager and acting as Jordan Operations Manager, Zaid has extensive 12 years of experience in contracting field running his own private business in Jordan.Since joining CSI team in September 2016, he played a key role in helping establishing CSI Operations in Jordan and managing the projects in Jordan, Turkey and currently in Abu Dhabi.

    CSI Projects Manager and acting as Saudi Arabia Operations Manager, Mohammed is NEBB Certified with 10 years of experience in TAB and Commissioning fields in GCC and Central Asia.Sincejoining CSI in Februay 2017, Mohammed has shown great skills in managing projects,deliveringon time all the targets with the highest performance leading his teams.

    CSI Projects Manager and acting as Turkey and Central Asia Operations Manager, Nasser is NEBB Certified with 8 years of experience in the fields of TAB and Commissioning in GCC, Central Asia and Turkey.Nasser joined CSI in April 2016 and became one of the first pillars on which CSI build its plans on. He had a great influence finishing the works in Emaar Mall in Istanbul project and currently managing the operation in Central Asia, Kazakhstan.

    CSI Operation Technical and Development Manager, Mohamed is NEBB CertifiedProfessional Reg. No 24211 Since March 2018 with over 10 years of experience in TABand Commissioning Services completing and managing over 150 projects.Mohammed is providing technical support and quality control to the whole CSI operationsto ensure the standard procedures are followed through the entire commissioningprocesses.

    CSI commissioning Professional with two valid certificates from NEBB (NEBB BSC CxP and NEB CxPP) and demonstrated history of working in the construction industry. Skilled in Whole Building Systems Technical Commissioning, Commissioning Management, and Energy efficiency. Highly knowledgeable & experienced in USACE / NAVFAC / USAF projects as well as high-rise building projects and LEED requirements.

    8

  • 9

    CSI SERVICES, WHAT WE DO

  • • The idea of CSI Board of Directors wasalways to fill the gap between theconstruction team and owners’representatives and cover the handingover process needs.

    • The approach is applied by leading theCommissioning Management and applythe process with the team members aspartners not witnesses, to deliver thesystems following the standard template

    • Software(s) were created by longexperienced staff tailored to the needs ofeach project. Hence, CSI become the focalpoint of contact of the CommissioningTeam(s) in each level CSI is involved in

    CSI BUSINESS APPROACH

    10

  • SELECTED PROJECTS

    Scope Of Work : MEP Commissioning Management ,TAB Service and Facility Management

    Abu Dhabi Airport ( Medfield Terminal Project ) UAE – Abu Dhabi

    Scope Of Work : Commissioning Management

    Doha Metro – Red Line South Elevated StationsQatar – Doha

    Scope Of Work : Handing Over Documents

    Preparation and Compilation

    Msherib Downtown Doha – Phase 1C, Phase 3Qatar – Doha

    Scope Of Work : Commissioning Management

    Doha Metro – Red Line South DepotQatar – Doha

    Scope Of Work : MEP Systems Commissioning Close

    Out Management

    Doha Metro – Msheireb Central StationQatar – Doha

    Scope Of Work : Commissioning Management

    New Doha Port Project Doha – Qatar

    Scope Of Work : Commissioning Management and Electrical Testing

    Scope Of Work : Commissioning Management

    Almaza City Center MallEgypt – Cairo

    Emaar Square Development Istanbul – Turkey

    Scope Of Work : Commissioning Management, TAB Service and Electrical Testing

    Abu Dhabi Plaza Astana – Kazakhstan

    11

    https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwi50uualunaAhUGSBQKHQCzAAQQjRx6BAgBEAU&url=https://www.airport-technology.com/projects/bahrain-airport/attachment/bahrain-airport1/&psig=AOvVaw3N8-D77Tx6l3QtJ1zPDKN2&ust=1525424220824993https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwi50uualunaAhUGSBQKHQCzAAQQjRx6BAgBEAU&url=https://www.airport-technology.com/projects/bahrain-airport/attachment/bahrain-airport1/&psig=AOvVaw3N8-D77Tx6l3QtJ1zPDKN2&ust=1525424220824993https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.ae/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiIkPiak-naAhXMXhQKHdimBtMQjRx6BAgBEAU&url=http://www.constructionweekonline.com/article-33343-qatari-pm-visits-doha-metro-red-line-north-project/&psig=AOvVaw1TzAPcYN43UQ1vGOXRORUb&ust=1525423405957196https://www.google.jo/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwifxcuC5MLXAhUQ66QKHWUpDFUQjRwIBw&url=https://www.pinterest.com/pin/366199013432562005/&psig=AOvVaw1NEwxrKO3fBXWa5OakzmS_&ust=1510910941991057https://www.google.jo/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwifxcuC5MLXAhUQ66QKHWUpDFUQjRwIBw&url=https://www.pinterest.com/pin/366199013432562005/&psig=AOvVaw1NEwxrKO3fBXWa5OakzmS_&ust=1510910941991057

  • WHAT IS COMMISSIONING?WHY IS IT NEEDED?

  • • COMMISSIONING MANAGEMENT AND

    PROCESS AS A DEFINITION

    WHAT IS COMMISSIONING, WHY IS IT NEEDED?

    • HOW IT WORKED BEFORE COMMISSIONING?

    • THE SPECIALIST PERSPECTIVE “SECOND EYE” CONCEPT

    • HOW THE NEED FOR COMMISSIONING WAS DEVELOPED

    • ASSIGNMENT APPROACHES “CASE STUDY”

    13

  • COMMISSIONING MANAGEMENT AND PROCESS AS A DEFINITION

    The Commissioning Management is a quality-oriented process for achieving, verifying anddocumenting that the performance of facilities, systems and assemblies meets definedobjectives and criteria. (1)

    Commissioning process and its assignedmanagement team are not separated from theconstruction and project management team(s).The Commissioning Management team areinteractive within the project managementteam(s) to ensure the smooth flow chart till thehanding over of the process is completed.

    The Commissioning Process is a quality-basedmethod that is adapted by an Owner to achievesuccessful construction projects. It is not anadditional layer of construction or projectmanagement. In fact, its purpose is to reduce thecost of delivering construction projects andincrease value to owners, occupants, and users. (1)

    14

  • • Basic organization with mixed responsibilities

    • No focal specialist point for systems readiness, commissioning and handing over

    • No clear tracking for commissioning processes and activities

    • Wide spectrum of knowledge required to cover all the activities needs.

    HOW IT WORKED BEFORE COMMISSIONING?

    Client

    ConsultantContractor

    15

  • • The more sophisticated the systems get, thegreater the need for commissioning managementspecialist.

    • The rapid development of new guidelines andstandards to cover the new technologies testingand commissioning requirements.

    • The volume of the project is such a crucial factorto hire a dedicated commissioning managementexpert(s)

    • The need to assign clear responsibilitiesaccording to responsibility matrix

    HOW THE NEED WAS DEVELOPED

    16

  • • Different fresh perspective from the commissioning-abilitypoint of view

    • Filling the gap between design and constructionperspectives

    THE SPECIALIST PERSPECTIVE “SECOND EYE” CONCEPT

    17

  • The Commissioning Management and process add a tangible value to the project and its effect could be easily realized/evaluated by the various stakeholders

    The following shows the benefits of commissioning management asmeasured during the observation of the five case study projects. Thecase studies can be classified by the contractual arrangements of thecommissioning management: (2)

    • Project A: Commissioning management organization employed by the project management company (2)

    • Project B: No commissioning management organization employed (2)

    • Project C: Commissioning management staff employed by the design and management contractor (2)

    • Project D: Commissioning management organization employed directly by the client (2)

    • Project E: Commissioning manager employed directly by the M&E installing contractor. (2)

    ASSIGNEMENT APPROACH – CASE STUDY

    18

  • Project A: Commissioning management organizationemployed by the project management company

    Commissioning Arrangements

    The commissioning management organization was independent, produced a detailedcommission-ability design review, and had a positive input throughout installation,commissioning, proving and post-handover.

    However, the nature of the design and build contract meant that the M&E installer couldignore this input at their own risk until final proving. This meant that severalmodifications identified early on by the commissioning management organization had tobe carried out after handover, when it would have been more cost effective to makethem prior to or during installation.

    Results

    The commissioning management organization did not have as much influence as theywould have liked, but fed information to the project management company and theclient. Overall the project was a success, was handed over on time with few minordefects, and the client was satisfied.

    Conclusion

    The independence of the commissioning management organization is of paramountimportance but this can be undermined if their advice is ignored. Failure to act uponadvice received from the commission-ability design review resulted in post-handoversystem modifications needing to be carried out. That problem apart, it can be concludedthat the overall effect of the involvement of a commissioning management organizationwas highly beneficial to the project.

    7.5

    8

    P LA NNED A CTUA L

    MONTHS

    Months

    ASSIGNEMENT APPROACH – CASE STUDY

    19

  • Project B: No commissioning management organizationEmployed

    Commissioning Arrangements

    Project B did not use a commissioning management organization. This resource was cut out due to a cost saving exercise, and the project management company took on the responsibility for managing the commissioning process. A commissioning-abilty design review was not carried out, and there was no co-ordination of the commissioning program. Installation was delayed by three months, and the hands-on commissioning engineers spent two months snagging the installation when they first arrived on site.

    Results

    Overall the project was not a success, it was handed over five months late, with over 3000 snags. The majority of snags were due to incomplete installation of the BMS and electrical systems. Six months after handover 300 snags were still to be resolved, several claims were outstanding and the client was not satisfied.

    Conclusion

    The project management company took on responsibility for the commissioning management activities, but did not have the time or assigned teams to plan and co-ordinate them. The delays and installation problems were compounded by the lack of a commission-ability review and coordinated planning and control.Without the input from an experienced commissioning managementresource to oversee these activities, the project was unsuccessful.

    2.3

    5

    P LA NNED A CTUA L

    MONTHS

    Months

    (2)

    ASSIGNEMENT APPROACH – CASE STUDY

    20

  • Project C: Commissioning management staffemployed by the design and management contractor

    Commissioning Arrangements

    A commissioning-ability design review was carried out, and a detailed commissioning program was drawn up. The design review was taken on board, but the program was soon superseded following delays to the construction and installation.

    The commissioning management organization was not given authority or status with the M&E installers to highlight and guide them towards resolving problems, but instead were treated as just another sub-contractor.

    Results

    The project was handed over four and a half months late, with several outstanding items. Five months after handover, the design and management contractor still had a presence on site to resolve problems.Overall, the project was a success (if late), and the client was satisfied.

    Conclusion

    The commissioning management process could have been more effective and prevented some of the delays if the commissioning management organization had been given more independence and real authority.

    4.5

    7.5

    P LA NNED A CTUA L

    MONTHS

    Months

    (2)

    ASSIGNEMENT APPROACH – CASE STUDY

    21

  • Project D: Commissioning management organizationemployed directly by the client

    Commissioning Arrangements

    The commissioning management organization was fully independent and a commission-ability design review was carried out as was a detailed commissioning program. Both were fully taken on board by all parties, and the commissioning program was drawn up early enough to directly influence the M&E installation program. The M&E installers followed both programs, and installation and commissioning were carried out on time. The commissioning manager had the authority and status with the M&E installers to highlight and guide them towards resolving problems

    Results

    The project was handed over on time with few minor defects. Overall it was a great success, and the client was satisfied. The only minor problem was that a fit-out contract for part of the project was outside the control of the commissioning management, which caused some delays.

    Conclusion

    The timely handover and success of the project was largely a result of the high level of influence given to the commissioning management team. The full benefits of commissioning management were realised, and made possible by the procurement route.

    4.5

    4.5

    P LA NNED A CTUA L

    MONTHS

    Months(2)

    ASSIGNEMENT APPROACH – CASE STUDY

    22

  • Project E: Commissioning manager employed directly bythe m&e installing contractor

    Commissioning Arrangements

    The commissioning manager was appointed too late to influence the design, but was responsible for planning the commissioning program. The design review was carried out by the project management company, and most of the points were acted upon by the design and build M&E installer. The commissioning manager had authority over the installers and the hands-on commissioning engineers, but was not truly independent due to the nature of the procurement.

    Results

    Installation and commissioning went largely to program and the project was handed over on time, with few minor defects. Overall this simple project was a success, and the client was satisfied.

    Conclusion

    The project benefited from a dedicated resource to oversee the commissioning process. However, his influence was limited by thedesign and build contract and the needs of the M&E installingcontractor, and was never truly independent.

    3.2

    3.8

    P LA NNED A CTUA L

    MONTHS

    Months(2)

    ASSIGNEMENT APPROACH – CASE STUDY

    23

  • Title JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB

    Acctual

    Project A

    Project B

    Project C

    Project D

    Project E

    Planed

    The below chart shows the summary for the previous five examples and the value of the commissioning over the projects time schedule and execution

    (2)

    ADDED VALUE FOR COMMISSIONING

    24

  • Project Case Study

    Type Of Commissioning Management Issue Solution Result

    Project A Commissioning management organization employed by the project management company

    The commissioning management organization did not have as much influence as it should have been

    The commissioning management organization should have the authority to influence the project team

    Overall the project was a success,was handed over on time with few minor defects, and the client wassatisfied.

    Project B No commissioning management organization employed

    Commissioning-abilty design review was not carried out, and there was no co-ordination of the commissioning Programme.

    commissioning management should be hired

    Overall the project was not a success, it was handed over five months late, with over 3000 snags

    Project C Commissioning management organization employed by the design and management contractor

    was not giventhe authority over the m&e installers to chase them and resolve problems,

    commissioningmanagement organisation had been given more independence and realauthority

    The project was handed over four and a half months late, with severaloutstanding items.

    Project D Commissioning management organisationemployed directly by the client

    The only minorproblem was that a fit-out contract for part of the project was outsidethe control of the commissioning management, which caused somedelays.

    The project was handed over on time with few minor defects.

    Project E Commissioning manager employed directlyby the m&e installing contractor.

    The commissioning manager hadauthority over the installers and the hands-on commissioningengineers, but was not truly independent due to the nature of theprocurement.

    The project benefited from a dedicated resource to oversee thecommissioning process. However, his influence was limited by thedesign and build contract and the needs of the m&e installingcontractor,

    Installation and commissioning went largely to programme and theproject was handed over on time, with few minor defects.

    ASSIGNEMENT APPROACH – CASE STUDY

    25

  • ADDED VALUE OF COMMISSIONING MANAGEMENT, WHAT TO EXPECT

  • • COMMISSIONING MANAGEMENT SHOWCASE

    ADDED VALUE OF COMMISSIONING MANAGEMENT, WHAT TO EXPECT

    • FOCAL POINT ON THE ASSIGNED TEAM

    • RESPONSIBILITIES AND LIABILITIES SHARING

    • QUALIFIED STAFF AND PROJECTS CERTIFICATION

    • GUIDANCE TO SPECIFY TESTING AND COMMISSIONING REQUIREMENTS

    • CERTIFICATION TYPES AND POWER

    27

  • • One reference for the CommissioningActivities progress and weightage

    • Easier tracking of the pending works andapproach to cover

    • Linking other teams works into one unifiedapproach towards complete handing over

    • The Commissioning team becomes theobserver, reference and keeper of theprogress percentages.

    FOCAL POINT ON THE ASSIGNED TEAM

    28

  • • During the project period, the flow of theworks should be based on team work

    • Assignment of responsibilities andliabilities should go along with thecontractual obligations

    • Building the works responsibilities matrixmakes the default detection easier.

    • Easier to replace the responsible for thedelays without affecting other activities.

    • Distribution of activities and tasksresponsibilities are part of the major riskmanagement plan of any project.

    RESPONSIBILITIES AND LIABILITIES ASSIGNMENT

    29

  • • After the completion of the projectworks, the contractual liabilitiestowards each task will still be borne byits acting party.

    • Commissioning team liability will alwaysbe referenced to by the facilitymanagement teams and end users.

    RESPONSIBILITIES AND LIABILITIES SHARING

    • Huge technical responsibility sharing when the Commissioning team is assignedat the early design stages of the project.

    • Commissioning Plans and Commissioning-ability studies becoming part of thecontracts documents.

    • Sharing the liability leads to enhancement of the service and extra guaranteesto the quality of the works handed over to the clients/owners.

    30

  • • Having qualified specialized staff assignedto the Commissioning activities ensuresgetting special buildings certifications asper codes.

    • Certain experiences is an essentialprerequisites to enter into LEEDrequirements (LEED GuidelinesFundamentals)

    • Certain experience are required to obtainranks/points as per LEED Guidelines(Enhanced Commissioning Credits)

    • Qualified staff assignment gives moreguarantees to the owners and clientsabout quality of the works.

    • More efficient handing over process tofacilities management teams is assured.

    QUALIFIED STAFF AND PROJECTS CERTIFICATIONS

    31

  • • Projects specifications should specifythe qualification of the Testing andCommissioning team

    • Depending on the size and complexityof the project, the Testing andCommissioning to be decided if it canbe by inhouse assigned qualified team,a third party and/or a specializedcompany

    GUIDANCE TO SPECIFY TESTING AND COMMISSIONING REQUIREMENTS

    • Specifications should mention the certificates required, years of provendedicated experience and the level of engagement to the project activities.

    • Specifications should mention the list of deliverables required by theTesting and Commissioning team.

    • Specifications should mention the time of engagement and assignment ofthe Testing and Commissioning team to the project.

    32

  • • There are various organizations such asASHRAE, NEBB , AABC (USA), CIBSE,CSA, BSRIA (UK) the differentspecifications are referring to.

    • It worth saying that USA organizationsare certifying the firms and individualsin different discipline, however, theBritish organizations are offering eithera membership or qualifying theindividuals and the firms such as CSA

    • USA based specifications requirecertified people and firms plus“stamping” final reports.

    • UK based specifications requireadherence to CIBSE codes.

    GUIDANCE TO SPECIFY TESTING AND COMMISSIONING REQUIREMENTS

    33

  • • The client is best protected when hiringa certified company from an entity suchas NEBB or AABC.

    • Such organizations are trying tomaintain the quality of the providedservices by its certified companiesimposing a system called QAP (QualityAssurance Program).

    • The client could easily contact NEBB inany event when the provided servicesby the NEBB certified firm weren’t asper the procedural standard.

    GUIDANCE TO SPECIFY TESTING AND COMMISSIONING REQUIREMENTS

    34

  • STAFF CERTIFICATIONS TYPES AND POWERS

    35

  • STAFF CERTIFICATIONS TYPES AND POWERS

    36

  • STAFF CERTIFICATIONS TYPES AND POWERS

    37

  • • Issue in brief: In a prestigious Library Building, an Air Handling Unit (AHU) wasassigned to serve three different areas and applications.

    1- Rare Books Storage Area with sensitive humidity control requirements (20-25 RH).It was getting about 20% of the total system demand. The area was not Variable AirVolume controlled.2- Reading Area getting almost 20% of the total system demand. No VAV control.3- Offices Areas getting about 60% of the total system demand and the offices wereequipped with VAV boxes for control.• In partial operation, the uncontrolled areas will be pressure relief points that will

    make the AHU sensor not feeling back pressure.• VSD will always run at full speed of 50 Hz• Pressure relief uncontrolled areas will have high noise• Rare Books controls will be affected with the excess air• Overall disturbance to the AHU performance

    COMMISSIONING MANAGEMENT SHOWCASE

    38

  • • Action taken: Design review and Commissioning-ability studies were presentedduring the construction of the system as the Commissioning and TAB teams werenot involved in the early design stages.

    • Further Action and Response: The MEP Contractor technical office raised theissue to the designer without pushing too hard. Designer response was aninstruction to “stick to the design”.

    • Result: Works proceeded without considering the Commissioning and TABconcerns and remarks. Upon the completion of the works and while theintegration tests were applied in partial load, the scenario presented by theCommissioning and TAB teams was made into reality.

    • The system performance was rejected by end supervision consultant and enduser. System was demolished and a separate AHU was assigned to the RareBooks Storage Area with high cost and time delays implications.

    • Conclusion: Commissioning and TAB team should be early involved and theircommissioning-ability studies should be seriously considered. Rectifying aproblem in early stages saves time, money and reputation of building owners andinvestors.

    COMMISSIONING MANAGEMENT SHOWCASE

    39

  • COMMISSIONING STAGES AND PROCESS, WHEN TO GET INVOLVED

  • TESTING & BALANCING (TAB) SCOPE OF SERVICE.

    • TAB works are basically related to HVAC systemonly, where the air and water systems have to betested, adjusted and balanced.

    • Testing and balancing as a scope of work is a partof whole MEP testing and commissioningactivities, it represents the hands on works that isrequired to be carried out on the HVAC system.

    • TAB contractor is usually a member of the Testingand Commissioning team which also includes:

    • Engineer representative , Contractor,Independent Commissioning Management Firm

    COMMISSIONING MANAGEMENT SHOWCASE

    41

  • • The major difference between TAB worksand Testing and commissioning lies withinthe responsibilities, the below exampleshould clear up the confusion:

    • For a chilled water system, TAB contractoris the one who carry out the requiredmeasurement for chillers, pumps andvalves in pursuit of achieving the designparameters to hand over the performanceand balancing reports to the engineer,thus, TAB contractor responsibilities arelimited to test, adjust and balance the airand water flow rates. However, achieving afully operational and efficient HVAC systemlies within the commissioningmanagement firm’s responsibilities

    COMMISSIONING MANAGEMENT SHOWCASE

    42

  • COMMISSIONING STAGES AND COMMISSIONING PROCESSES

    D

    C

    B

    A

    Pre-Commissioning and Construction Snagging

    Commissioning

    Handing Over

    Planning

    To achieve a smooth commissioning

    process the commissioning and

    handover activities should be

    divided into four main stages each

    stage is crucial to move to the next

    stage and these stages will

    intersect with each others along the

    project timeline

    43

  • COMMISSIONING STAGES AND PROCESS

    Testing & Commissioning Plan

    Testing and Commissioning Procedures

    Commissioning Program

    02

    01

    03

    Planning Stage

    44

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    The planning stage starts before the construction completion with a limited team to prepare the commissioning program, plans, and Procedures that will ensure a smooth work flow throughout the whole commissioning processes

    MA

    N P

    OW

    ER

    TIME

    Construction Work Commissioning Work

    Commissioning Planning and Core Team

    Document Preparation 45

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    Del

    iver

    able

    s o

    f th

    e P

    lan

    nin

    gCommissioning Plan

    Scope of Works

    Responsibilities & Responsibility Matrix

    Program & Progress Reporting Template

    System Descriptions

    Testing & Commissioning Procedures List

    Interfaces and Interlocked Systems

    Method Statement Templates

    Test Sheet Templates

    O&M Manual Templates

    Commissioning ProcedureHVAC System and Equipment

    Firefighting System and Equipment

    Plumbing System and Equipment

    Low voltage System and Equipment

    ELV System and Equipment

    Special systems such as kitchen, laundry, elevators,....

    Commissioning ProgramSystem Mapping and Interface

    Commissioning Logic Diagram

    Dependency Matrix

    Commissioning Activity Schedule & Tracker

    Manpower Histogram

    46

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    In order to create the right sequence for commissioning process, the interfaces between the systems and its linking with mechanical, electrical, and ELV systems have to be identified

    47

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    • Create the commissioning flow charts and logic diagrams (Sample)

    `

    Air System (AHU) Commissioning Process

    En

    gin

    eer/

    Co

    mm

    issio

    nin

    g

    Au

    tho

    rity

    Main

    Co

    ntr

    acto

    r

    Co

    mm

    issio

    nin

    g

    Team

    HV

    AC

    Co

    mm

    issio

    nin

    g

    Team

    TA

    B C

    on

    tracto

    r

    Ele

    ctr

    ical

    Co

    mm

    issio

    nin

    g

    Team

    Documentation Start Up Testing &

    Balancing Functional Test

    Final Commissioning

    ReportPre-Functional

    Ag

    ree A

    cc

    ep

    tan

    ce C

    rite

    ria

    Air

    Sys

    tem

    Fu

    ncti

    on

    al T

    est

    Review

    Specifications

    AHU Pre-

    Functional

    Test

    Final TAB

    Report

    Final AHU

    Cx Report

    Review

    MCC Pre-

    Functional

    Test

    Issu

    e F

    inal

    Ap

    pro

    val

    Fin

    al

    Syste

    m In

    sp

    ec

    tio

    n

    Final MCC

    Cx Report

    MCC Cx

    Procedure

    Air System

    TAB Work

    TAB

    Procedure

    Init

    ial S

    yste

    m In

    sp

    ecti

    on

    AHU Start

    Up

    Progressive Supervision

    MCC

    Functional

    Test

    AHU Cx

    Procedure

    DCC Cx

    Procedure

    DCC Pre-

    Functional

    Test

    DCC

    Functional

    Test

    Final DCC

    Cx Report

    48

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    • Create the commissioning systems dependency matrix

    Systems Dependency Matrix

    Building Systems Dependency

    Structural Architectural Electrical Mechanical

    Stru

    ctu

    ral w

    ork

    co

    mp

    lete

    d

    Co

    nst

    ruct

    ion

    of

    pad

    s

    Blo

    ck w

    ork

    s C

    om

    ple

    ted

    Bu

    ildin

    g En

    velo

    pe

    seal

    ed

    Pla

    ster

    wo

    rks

    Wal

    l pai

    nti

    ng

    Flo

    or

    pai

    nti

    ng

    Do

    or

    inst

    alle

    d a

    nd

    R

    oo

    m lo

    cked

    Cei

    ling

    inst

    alle

    d a

    nd

    co

    mp

    lete

    d

    Tile

    wo

    rk c

    om

    ple

    ted

    Lan

    d s

    cap

    ing

    Cle

    an E

    nvi

    rom

    ent

    (Du

    st

    Free

    )

    Furn

    itu

    re In

    stal

    led

    Po

    wer

    ava

    ilab

    le

    CB

    S a

    vaila

    ble

    Ne

    two

    rk r

    ead

    y (A

    ctiv

    e N

    etw

    ork

    )

    Co

    ole

    d A

    ir A

    vaila

    ble

    Ch

    illed

    Wat

    er A

    vaila

    ble

    Domestic Water Filtration System

    Air Handling Unit

    Blower Coil Unit

    BMS Server

    Booster Pump

    Chemical Flushing

    Chilled Water Balancing & Demonstration

    Chilled Water Pump

    Condensate Pumps

    Condensing Unit

    Constant Air Volume

    CRAC Units

    DDC Panels

    Distribution Panel - AHU

    Domestic Electric Water Heater

    Domestic Water Storage Tank

    Door Curtain Units

    Drinking Fountain

    DX Units

    External Lift Dry Pit Sump Pump

    External Lifting Station Pump

    Extract Fans

    Fan Coil Unit

    Fire Pump

    Fire Smoke Damper

    Foam Deluge Fire Suppression System

    Fusible link Fire Damper

    Gas fire suppression system

    HOISTWAY EXHAUST

    Hot Water Circulating Pump

    49

  • COMMISSIONING STAGES AND PROCESSPLANNING STAGE

    • Develop the commissioning schedule and Histogram according to the current project status and the construction schedule

    Project Schedule

    Type Equipment Decription Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18

    Plumbing Domestic Water Filtration System 0 0 0 0 0 0 0 0 0 0 63.25 28.75 0 0 0 0 0

    HVAC Air Handling Unit 3.743989 0.08 36 348.4654 166.0013 418.5333 1451.648 1272.352 1531.6 2501.067 3421.788 2337.545 1862.067 2113.799 2279.023 981.111 0

    HVAC Blower Coil Unit 0 0 0 747 2096 150 1604 1715.5 258 5134.646 1164.354 1955.571 2915.36 2338.569 0 0 0

    ELV BMS Server 0 0 0 0 0 0 0 51.34884 84.63049 84.63049 84.63049 62.75969 0 0 0 0 0

    Plumbing Booster Pump 0 0 3 24.5 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Chemical Flushing 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Chilled Water Balancing & Demonstration 0 0 1648 0 0 0 0 0 0 0 1236 0 0 412 412 348.6154 402.6787

    HVAC Chilled Water Pump 0 0 476.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Condensate Pumps 0 0 0 0 0 0 54 0 0 0 0 0 0 0 0 0 0

    HVAC Condensing Unit 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Constant Air Volume 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC CRAC Units 28.6791 34.6791 0.940299 0 180 0 0 0 45 0 0 0 0 0 0 0 0

    Electrical DDC Panels 283 32.5 648.5 1609 977.5 1144.125 592.875 1559 1789.5 1465 979 747.5 357.5 956 195 146.25 243.75

    Electrical Distribution Panel - AHU 23 23 195.5 1000 613 632 348.5 609 869 621.5 455 325 65 0 0 0 0

    Plumbing Domestic Electric Water Heater 0 0 128 0 0 0 0 0 0 800 0 1616 0 1459.556 716.4444 0 0

    Plumbing Domestic Water Storage Tank 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Door Curtain Units 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    Plumbing Drinking Fountain 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC DX Units 0 0 0 0 0 0 0 0 0 105 0 0 332.5 0 0 0 0

    Plumbing External Lift Dry Pit Sump Pump 0 0 0 96 96 96 0 0 0 0 0 0 0 0 0 0 0

    Plumbing External Lifting Station Pump 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Extract Fans 0 0 2 84 154 0 168 466 298 508 310 565.6 430.4 378 325.5 304.5 84

    HVAC Fan Coil Unit 0 0 0 340.1667 462.8333 198.3 949.0594 1577.641 332.5 3364 607.5 1509.5 2535.351 3586.549 2053.1 105 0

    Fire Fire Pump 0 0 0 0 135 5 0 20 50 0 0 0 0 0 0 0 0

    HVAC Fire Smoke Damper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    Fire Foam Deluge Fire Suppression System 0 0 0 69.3 7.7 77 0 115.5 77 115.5 0 0 0 0 0 0 0

    HVAC Fusible link Fire Damper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    Fire Gas fire suppression system 0 0 199.95 85.69286 1105.714 1053.91 873.7958 421.9375 129 0 0 0 0 0 0 0 0

    HVAC HOISTWAY EXHAUST 0 0 0 78 0 0 0 0 0 195 117 0 78 78 0 0 0

    Plumbing Hot Water Circulating Pump 0 0 0 0 0 0 0 0 0 0 49 0 0 73.5 0 0 0

    Plumbing Irrigation Water Storage Tank 0 0 0 0 0 0 0 0 0 0 0 24.5 0 0 0 0 0

    HVAC Jet Fans (Tunnel Ventilation) 0 0 0 0 210 0 0 0 0 0 70 0 210 210 0 0 0

    HVAC Kitchen Extract Fans 0 0 0 0 0 0 0 0 42 0 0 0 126 109.2 198.8 112 0

    HVAC LIFTING STATIONS Fan 0 0 0 0 0 42 0 0 0 126 0 63 21 0 0 0 0

    HVAC Motorized Damper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC PCA Air Handling Units 0 0 0 0 126 344.4 666.6 924 84 588 756 756 504 0 0 0 0

    Fire Pre-Action Fire Suppression System 0 0 231 38.5 0 0 115.5 115.5 319 2200 335.5 726 1182.5 1331 992.75 805.75 38.5

    Plumbing Sanitary Fixtures (PR Station wise) 0 0 0 0 0 0 0 4.5 72 49.5 45 36 222 192 324 81 139.5

    Electrical SMOKE CONTROL PANEL 0 0 16.84375 60.15625 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Smoke Damper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    HVAC Smoke Exhaust Fan 0 0 0 0 0 0 126 84 126 0 207 0 84 252 84 916.5 160.5

    50

  • COMMISSIONING STAGES AND PROCESS

    Factory Acceptance Test (FAT)

    Installation Test (IT)

    Site Readiness and Construction Completion

    Pre-commissioning

    02

    01

    03

    04

    Construction and Pre-Commissioning Stage

    05

    Start Up

    51

  • COMMISSIONING STAGES AND PROCESSPRE-COMMISSIONING STAGE

    • The Pre-Commissioning process is the presentation of the completion of construction stage and the system delivery to the commissioning team.

    • During this stage construction team and commissioning team collaborate towards clearing installation issues representing the snags in order to have the systems ready for the next stage

    MA

    N P

    OW

    ER

    TIME

    Construction Work Commissioning Work

    Commissioning Planning and Core Team

    Pre- Commissioning Team

    Contractor Snagging Team

    Document Preparation

    FAT Test

    Installation Test

    52

  • COMMISSIONING STAGES AND PROCESSPRE-COMMISSIONING STAGE

    Installation Test (IT)

    • The Construction Team will arrange with the Quality Assurance / Quality Control Team visual

    inspections of all the equipment within the identified commissioning lot

    • the Construction Team will ensure all installations are checked prior to the inspection, and

    that they are as per the project requirements

    Factory Acceptance test (FAT)

    The Commissioning Manager will make sure that the test was conducted and its

    proof documents were submitted as requested in the owner’s project requirement

    and basis of design documents

    53

  • COMMISSIONING STAGES AND PROCESSPRE-COMMISSIONING STAGE

    Site Readiness and Construction Completion

    The installation section of the Checklist is utilized to verify and track the proper installation. It

    focuses on the ability of the installation to meet the commissioning requirement. For

    equipment, this section focuses on the physical installation and the completion of the full

    system to be commissioned

    Pre-Commissioning Test

    By finishing this test commissioning team confirms that the equipment or sub-system is pre-

    commissioned and can move to the next step.

    Start Up

    The commissioning team will invite the equipment supplier to visit the site and start up the

    equipment’s, during this visit the commissioning team will make sure that the supplier

    checklist is used following the manufacturer recommendations and that the results are

    documented for future use in the handing over stage.

    54

  • COMMISSIONING STAGES AND PROCESS

    Functional Test

    System Integration Tests (SIT)

    System Integration Tests (SIT)

    02

    01

    Commissioning Stage

    55

  • COMMISSIONING STAGES AND PROCESSCOMMISSIONING STAGE

    Once the commissioning activities started, the testing and commissioning teams shall be increased to supervise and control the whole commissioning activities.

    The commissioning activities will be tracked down and reported using the Commissioning Activity tracker and look ahead report.

    MA

    N P

    OW

    ER

    TIME

    Construction Work Commissioning Work

    Commissioning Planning and Core Team

    Pre- Commissioning Team

    Contractor Snagging Team

    Commissioning Team

    Document Preparation

    FAT Test

    Installation Test

    56

  • COMMISSIONING STAGES AND PROCESSCOMMISSIONING STAGE

    Commissioning Activity Tracker (Summary Charts)

    A summary report categorized per equipment/system/zone/building showing the current status of the project

    57

  • COMMISSIONING STAGES AND PROCESSCOMMISSIONING STAGE

    Look Ahead Report

    To provide a weekly look ahead report as per the commissioning program and the actual site readiness

    58

  • COMMISSIONING STAGES AND PROCESSCOMMISSIONING STAGE

    Functional Tests

    Functional tests start directly after the units start up, and it is performed to make sure that the design parameters are achieved for the whole system

    TAB (Testing adjusting and Balancing) is one example of those tests where the TAB contractor will make sure that the HVAC system. is achieving the design parameters.

    Another example is BMS point to point components tests prior to the system integration.

    59

  • COMMISSIONING STAGES AND PROCESSCOMMISSIONING STAGE

    Integration Tests

    After finishing the previous activities the building systems will be ready to interact with each other. The commissioning team will verify the communication between systems by testing the operation scenarios which already prepared in the test procedures, below are some examples:

    • Fire Scenario sequence of operation (Cause and Effect)• AHU unit Start Up faults and alarms• Power Shedding procedures during the high consumption periods.

    60

  • COMMISSIONING STAGES AND PROCESS

    02

    03

    04

    01

    Testing and Commissioning Reports

    Operation and Maintenance Manuals

    Training Manuals

    Asset Registers and Spare Part Lists

    Handover Stage

    61

  • COMMISSIONING STAGES AND PROCESSHANDING OVER STAGE

    MA

    N P

    OW

    ER

    TIME

    Construction Work Commissioning Work

    Commissioning Planning and Core Team

    Pre- Commissioning Team

    Contractor Snagging Team

    Within the handing over stage, Commissioning team starts compiling and preparing the close-out documents and proceeds with handing it over to the client

    The hand over phase starts during the construction phase and it lasts till the complete handing over to the building operator

    Commissioning Team

    Handing Over Team

    Document Preparation

    FAT Test

    Installation Test

    62

  • COMMISSIONING STAGES AND PROCESSD

    eliv

    erab

    les

    of

    the

    Han

    din

    g o

    ver

    Stag

    eTesting and commissioning Final Report

    Operation and Maintenance Manual

    Training Manual

    Asset Registers

    Spare Part Lists

    Client Training

    63

  • COMMISSIONING MANAGEMENT TOOLS, VIDENTIUM REVEALED

  • VIDENTIUM

    • VIDENTIUM is an online application with mobile support• Developed by CSI Software team with the technical input and enhancements of CSI

    Technical experiences• Supportive tools for construction & commissioning teams to record, follow, report

    and manage all site activities.

    • VIDENTIUM is designed to be compact, adaptable, modular, user friendly, live and less time-consuming.

    • CSI is able to use VIDENTIUM to have full live control and knowledge about project stages.

    65

  • VIDENTIUM• The whole application data is stored online on dedicated CSI Server• More secure, easy to synchronize, reachable for all parties (sub-contractor, main

    contractor, client etc.)• Collecting data from all parties, and guiding to the right response

    66

  • VIDENTIUMConstruction data updating became easy with VIDENTIUM

    • Easy to create the project (Excel Sheets Based)• Very fast to add project references and equipment (3 Seconds Maximum for Update)• Adaptable to any ongoing project in any stage• Flexible for checklist creation and follow up• Able to follow planning schedules and milestone requirements

    67

  • VIDENTIUMUploading data to VIDENTIUM• VIDENTIUM allows importing data from Excel files, then converting them to SQL

    database information.• Required Information: Equipment & location references, System Checklists

    Category Sample Checklist Sample

    68

  • VIDENTIUMUploading data to VIDENTIUM

    VIDENTIUM allows importing bulk information of the equipment in fast response time.

    69

  • VIDENTIUMUploading Checklist data to VIDENTIUM

    VIDENTIUM allows to importing bulk check list information of the equipment for ongoing projects in fast response time.

    70

  • VIDENTIUMUploading data to VIDENTIUMIt is very easy and fast via web interface to create category, add equipment and update bulk checklists

    71

  • VIDENTIUMTracking stages, equipment with VIDENTIUM

    VIDENTIUM is proving very rich and user friendly web base tracker, with this tracking interface, users are able to filter data, export to Excel, download or send an email the detailed site observations.

    72

  • VIDENTIUMAdvance filtering on Tracker

    Users are able to filter any single detail as per their references.

    73

  • VIDENTIUMTracking stages, equipment with VIDENTIUMAny single equipment information and stage progress with checklist details can be shown on web base or download as a pdf file.

    74

  • VIDENTIUMReporting on VIDENTIUM Dashboard

    Dashboard has many options to create reports to show required systems and equipment progress and status.

    75

  • VIDENTIUMReporting on VIDENTIUM Dashboard

    All progresses are calculated as per work completion and equipment weight.

    Over All, and Stages Progress report sample

    76

  • VIDENTIUMReporting on VIDENTIUM Dashboard

    Listing Equipment as per type with stage completion percentage.

    Stage Progress report sample as per Equipment Type

    77

  • VIDENTIUMReporting on VIDENTIUM Dashboard

    Equipment charts are available as per quantity or weightage.

    Chart Report Sample

    78

  • VIDENTIUMReporting on VIDENTIUM Dashboard

    Monitoring each type of equipment completion Report: all stages are should be completed to shown in this report.

    Equipment Report Sample

    79

  • VIDENTIUMAndroid Application

    It is available for any android phone or tablet to used by site teams to monitor, report, record all site activities.

    80

  • VIDENTIUMAndroid ApplicationApp is providing opportunities to download all project data to use offline while users are on site and with implemented QR Code scanner, users are able to reach equipment information and check list more faster and also with electronic signature, they are able to sign checklists if it is required.

    81

  • VIDENTIUMAndroid Application

    Users are able to update checklists, take site notes with pictures, and upload the system any time when they have internet connection.

    82

  • VIDENTIUMBenefits & Conclusion

    • VIDENTIUM is a complete online solution to observe and monitor work flow and manage reporting problems during construction phases of projects.

    • VIDENTIUM has an advantage as it can be fully customized according to actual needs.

    • VIDENTIUM combination between offline storage with online storage makes working anywherepossible. Data can be gathered from construction site where there is no Internet Access, yet it can be synchronized when access is granted with only 1 click.

    • VIDENTIUM is not a for sales package application created once and never gets updated. It’ll be always updated as the time and technology goes on.

    83

  • ENERGY CONSUMPTION IMPACT, IT WORTHS!

  • Construction Cost 20%

    Operation Cost 80%

    BUILDING LIFE CYCLE COST

    WHERE ARE WE NOW

    Buildings account for 40% of the world's primary energy consumption

    Buildings account for 42% of the world's water consumption and about 50% of raw materials

    Qatar is now consuming more energy per capita than other industrial countries including US and UK

    85

  • LEED V4

    LEED Rating system went through major updates in its recent version, and most of the energy related updates were in the commissioning section:

    Extending the scope to cover Plumbing and electrical systems in detail.

    Monitoring-based commissioning from design through post construction and occupancy.

    Building Envelope Commissioning during design and construction phases

    86

  • • Earlier review design documents for energy related items can improve the energy performance of the building.

    • The Energy Review can save the time and operation costs and can increase the human comfort in the building.

    TOOLS, ENERGY REVIEW

    87

  • TOOLS, ENERGY MODELING

    88

  • TOOLS, ENERGY AUDIT

    • Energy Audit: is a survey focused on finding out how a building is using it’s energy. This information is analyzed.

    • The energy related improvements are then prioritized according to the cost effectiveness.

    89

  • Infrared inspection or Thermography, is used throughout industry as a key diagnostic tool for finding problems. Infrared inspections are a non-destructive, non-contact and a cost effective way to detect and document defects.

    TOOLS, THERMAL IMAGING

    90

  • TOOLS, BUILDING TIGHTNESS TEST

    ‘Build tight – Ventilate right’.• Air leakage is the uncontrolled flow of air through gaps and cracks (often referred to as infiltration) , it leads to unnecessary heat loss and discomfort for the occupants

    • Air leakage test (Also known as blower door test) can be used to assess the building construction and compare to other building performance

    91

  • Lighting30%

    office Equipment

    10%

    Cataring5%

    Cooling & Pumping Plant

    17%

    Other HVAC Plant38%

    Energy Consuption

    For the Large air conditioned office buildings the HAVC plant may typically accounts for 55% of the total energy cost

    A proper Testing Adjusting and Balancing for the system may reduce the HVAC energy consumption.

    (3)

    TOOLS, HVAC SYSTEM PERFORMANCE RETEST

    92

  • CONCLUSION, SO WHAT SHOULD WE DO?!

  • • Commissioning Process and Management areessential scope of work that should not be cost cut

    • Commissioning is not an end of the line handingover scope, it is a live process that is implementedin each stage of the project.

    • Building and installing a system is a step, putting itto work is a different process.

    • Testing and Commissioning should be specified tobe carried out by dedicated team/organizationassigned in early design stages with given authorityand responsibilities.

    • Testing and Commissioning team should hold therequired certificates proving its capabilities.

    • Commissioning Management team deliverablesshould be considered by all parties in all stages.

    CONCLUSION, SO WHAT SHOULD WE DO?!

    94

  • LIST OF REFERENCES

  • 1. ASHRAE Guideline 0-2005 The Commissioning Process2. BSRIA APPLICATION GUIDE 5/2002 Commissioning Management3. BSRIA Guidance Note 11/97 4. CIBSE TM 23/2000

    LIST OF REFERENCES

    96

  • THANK YOU