Better Performing Commissioning for Energy Savings Presented To: AEE / ASHRAE / USGBC 2013 Energy Expo St. Paul RiverCentre, St. Paul, Minnesota October 2, 2013 Presented By: Rebecca T. Ellis, PE LEED AP BD+C, CCP, CPMP CxA President, Questions & Solutions Engineering

Transcript of Commissioning for Energy Savings - MN...

Better Performing Buildings™

Commissioning

for Energy Savings

Presented To:

AEE / ASHRAE / USGBC

2013 Energy Expo

St. Paul RiverCentre, St. Paul, Minnesota

October 2, 2013

Presented By:

Rebecca T. Ellis, PE

LEED AP BD+C, CCP, CPMP CxA

President, Questions & Solutions

Engineering

Introduction

Rebecca Ellis

• Mechanical Engineer (HVAC & Controls)

• Evolved from Design to Commissioning

• Passion for High Performance Building Systems Operations

• President of Questions & Solutions Engineering

Agenda Commissioning Overview

Energy Conservation Projects

Case Studies

Preparing for Sustained Energy Savings

Post-Project Operations

Commissioning Overview

What is Commissioning?

Systematic process of assuring by

verification and documentation, from the

design phase to a minimum of one year

after construction, that all building facility

systems perform interactively in

accordance with the design documentation

and intent, and in accordance with the

owner’s operational needs, including

preparation of operation personnel.

Commissioning Overview

Commissioning is Always:

• Documentation

• Testing

• Training

Energy Conservation Projects

Energy Conservation Retrofits

Control System Replacements/Upgrades

Major Renovations and/or New

Construction

Energy Conservation Projects

Other Topics Today

• Energy Efficiency as an Investment: The Value of Investing in Energy Efficiency at your Facility

• Innovative Systems for Energy and Water Conservation

• Large Chiller Plant Optimization

Energy Conservation Projects

Building Owner Chooses to Invest $$$

in Anticipation of Saving Energy $$$

Long Term

• New types of equipment

• New types of control strategies – more points, more programming

• New types of instrumentation

• Integration of all of the above

Energy Conservation Projects

Third Party Commissioning is a Smaller

$ Investment to Confirm Intended

Energy Savings will be Achieved

• Set points

• Operating schedules

• Sensor calibration

• Control sequence verification

Case Studies

Warehouse - Design

• Gas-fired heating-only air turnover units

• Energy recovery ventilators with heating and dehumidification (CO-controlled)

Case Studies Warehouse - Findings

• Gas-fired air turnover units

Occupied and unoccupied temperature set points higher than design

Occupied time schedule longer than needed

• Energy recovery ventilators with heating and dehumidification (CO-controlled)

Heating discharge air temperature 78F instead of 50F

Cooling discharge air temperature 55F instead of 59F

Exhaust air intakes blocked

Case Studies

High Rise Condominium - Design

• Revised HVAC system controls

Case Studies

High Rise Condominium - Findings

• Revised HVAC system controls

Entire system forgotten

Existing makeup air system dehumidification set point

Case Studies

New School - Design

• Differential air flow building pressure control

• Energy recovery wheels with bypass dampers

Case Studies

New School - Findings

• Differential airflow building pressure control

Missing return airflow measuring stations

• Energy recovery wheels with bypass dampers

Bypass damper around wheel and heating and cooling coils

Case Studies

New Museum - Design

• Heat recovery chiller for summer reheat hot water

Case Studies

New Museum - Findings

• Heat recovery chiller for summer reheat hot water

Reheat coils not sized for the low temperature hot water generated by the heat recovery chiller

Case Studies

New Office Building - Design

• Network lighting control system for all spaces (no manual light switches)

Case Studies

New Office Building - Findings

• Network lighting control system

Lighting control system not programmed

Preparing for Sustained Energy

Savings

Documentation (from the Project for

Operations)

• Operational intent

Space conditions

Light levels

Operating schedules

Seasonal differences

Why the systems were designed the way they were

Preparing for Sustained Energy

Savings

Documentation (from the Project for

Operations)

• Schematic diagrams

Preparing for Sustained Energy

Savings

Documentation (from the Project for

Operations)

• Sequences of operation

• Description of interactions between systems

HVAC

Fire alarm

Lighting controls

Security

Preparing for Sustained Energy

Savings

Documentation (from the Project for

Operations)

• As-built plans showing component locations

All equipment

Manual shut-off valves

Smoke/fire dampers

Control system dampers & valves

Control system sensors

Post-Project Operations

On-going Operations

• Buildings do not run themselves (even if they have computers)

• Day-to-day operations look different in sustainable buildings

Post-Project Operations

Preventive Maintenance is Always

Required

• All equipment maintenance activities

• Control system sensor calibrations

• Control system device operational checks

• Accessibility is key!

Post-Project Operations

Avoiding Trouble Calls • Monitoring & trending

• Proactive data analysis

Use data to discover trouble spots before the occupants do

Analyze data clues to understand the root causes that need to be addressed

Identify wasted energy not otherwise detected