Commissioning and Utilisation of ERLP
description
Transcript of Commissioning and Utilisation of ERLP
Commissioning and Utilisation of ERLP
David HolderASTeC, Daresbury Laboratory
• Introduction to ERLP;Introduction to ERLP;
• ASTeC’s contribution to ERLP;ASTeC’s contribution to ERLP;
• ASTeC’s plans for ERLP ASTeC’s plans for ERLP exploitation.exploitation.
Content
ERLP• Energy Recovery Linac Prototype
• Demonstrating skills and technologies for 4GLS:
– Operation of photo injector electron gun;
– Operation of superconducting electron linac;
– Energy recovery from a FEL-disrupted beam;
– Synchronisation of gun and FEL output.
Parameters
• Nominal Gun Energy 350
keV
• Injector Energy 8.35 MeV
• Circulating Beam Energy 35 MeV
• Linac RF Frequency 1.3 GHz
• Bunch Repetition Rate 81.25 MHz
• Max Bunch Charge 80 pC
• Max Average Current 13 µA
• Laser system nearly ready;
• IOTs under test on site;
• Gun ceramic – major source of delay – now expected
March 2006 (~1 year late);
• Accelerator modules arriving April/June 2005 (~6
months late);
• 4 K commissioning Feb 06.
Machine Status
• Dedicated diagnostic beamline designed by ASTeC
to fully characterise the gun and benchmark the
codes used for design; e.g. predicted effect of
spacecharge:
Gun Commissioning April to June
0 0.5 1 1.5 2 2.50
1
2
3
4
z [m]
x (r
ms)
[m
m]
200 G205 G210 G215 G
0 0.5 1 1.5 2 2.50
1
2
3
4
z [m]
norm
. em
ittan
ce (
rms)
[ m
]
0 0.5 1 1.5 2 2.50
2
4
6
z [m]
bunc
h le
ngth
(rm
s) [
mm
]
Comparison and benchmarking of beam dynamics code for injectors - ASTRA and GPT
buncher solenoid booster
Gun Commissioning April to June
Photoinjector Laser - Collaboration with CLF
• Complete machine ready September 06;
• Aim to demonstrate energy recovery with wiggler-
disrupted beam early 2007;
• Very challenging technical and timescale issues;
• ASTeC has overall responsibility for successful
planning and execution.
Machine Commissioning 1
Confirming suitability of TBA arc design chosen for 4GLS:
Machine Commissioning 2
Confirming 4 dipole chicane bunch compression scheme:
Machine Commissioning 3
4-dipole chicane4-dipole chicane
LBLB
LDLD
• Modeling of FEL interaction using in Genesis 1.3;
• Major tool used for design of 4GLS sources;
• Commissioning measurements will confirm validity of code and other calculations.
Machine Commissioning 4
before FEL
after FEL
1
23
4
Machine Commissioning 5Measurements
to verify start
to end
simulations
results
First case of complete S2E modelling of
an ERL with a FEL and energy recovery
Machine Commissioning 6
Operation of 2 K cryosystem - vital to operation of 4GLS
ERLP Exploitation 1
• Accelerator test bed:– advanced accelerator operation, diagnostics,
photocathode guns, SCRF, electron beam/laser synchronisation;
• science– THz– X-ray (NWSF grant £2.9M, 3 years)– combined sources/synchronisation.
As an R&D exercise NOT as a user facility.
Compton backscattering X-ray source Time resolved X-ray diffraction studies aimed at probing the mechanisms of shock compression of matter on sub picosecond (ps) timescales.
THz beamline and a tissue culture facility. To use the ultrahigh intensity, broadband THz radiation for the study of biological systems.
ERLP Exploitation 2
The end