COMISSÃO NACIONAL DE ENERGIA NUCLEAR · PDF fileCOMISSÃO NACIONAL DE ENERGIA...

17
COMISSÃO NACIONAL DE ENERGIA NUCLEAR The Importance of a Management System in Nuclear Facility Maintenance The Brazilian Overview Eduardo Motta Technical Meeting on Grading of the Application of Management System Requirements (23-27 January 2012)

Transcript of COMISSÃO NACIONAL DE ENERGIA NUCLEAR · PDF fileCOMISSÃO NACIONAL DE ENERGIA...

COMISSÃO NACIONAL DE ENERGIA NUCLEAR

The Importance of a Management System in Nuclear Facility Maintenance

The Brazilian Overview

Eduardo Motta

Technical Meeting on Grading of the Application of Management System Requirements (23-27 January 2012)

Introduction Brazilian Nuclear Facilities

QA standards in Brazil and IAEA

Fuel cycle facility QA System

QA System relevance in facility maintenance

Grading of QA Requirements Fuel cycle facility example, difficulties encountered and strategies to overcome those difficulties

Brazilian trends

Conclusions

Summary

2 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Brazilian Nuclear Facilities Mining

Caetité – operating

Santa Quitéria – site licensing started

Poços de Caldas – in decommissioning process

Resende city site Enrichment, UO2 conversion, pellets fabrication, fuel components fabrication and fuel assembly

NPP, Angra city Angra 1 – 640 MW, WH design

Angra 2 – 1350 MW, SIEMENS design

Angra 3 – 1350 MW, SIEMENS/AREVA design, under construction

Research institutes and reactors

Introduction

3 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

QA standards in Brazil and IAEA evolution

50-C-QA, 1978 – QA for Safety in NPP CNEN-NE-1.09, 1980 – Standard Format of FSAR

One chapter is QAP, based on 50-C-QA

CNEN-NN-1.16, 2000 – QA for safety in NPP and other facilities

The main focus is safety and the grading of QA requirements is mentioned

TRS 328, 1991 – Grading of QA Requirements GS-R-3, 2006 – The Management System for Facilities and Activities

Management in an integrated system

QA standards in Brazil and IAEA

4 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012)

Time

28 years

2000

/17

CNEN-NN-1.16, 2000 – QA for safety in NPP and other facilities

Safety is the main focus (in all facilities stages: construction, operation...)

QA requirements grading is based on: Safety;

Complexity;

Supervision necessity;

Compliance with inspection / test;

Quality history and;

Repair difficulty;

QA standards in Brazil and IAEA

5 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Fuel cycle facility QA System references Based on CNEN-1.16, ISO 9001, ISO 14001 and OSHAS 18001

QAP

Instructions

Fuel cycle facility QA System

6 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Importance of QA System in maintenance

CNEN-NN-1.16 – Safety in all facility stages Operation Maintenance is relevant to keep (or improve) the design safety requirements

CNEN-NE-1.21, 1991 – Maintenance in NPP Safety related items listed Preventive maintenance and periodical inspections / tests Training (activities, radioprotection, specific potential risks and QA) Activity procedures (administrative and technical) Modification control (including documents) Corrective maintenance – historical data Responsibilities Records control Analysis Audits Continuous improvement

QA System relevance in facility

maintenance

7 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Maintenance in a fuel cycle facility

Safety related items listed √ ok

Preventive maintenance and periodical inspections / tests √ GR and LV Training (activities, radioprotection, specific potential risks and QA) √ IM, annual radioprotection and industrial safety training and QA annual week (trend to integrate all issues)

Activity procedures (administrative and technical) √ GR annual plan, LV and IM

Modification control (including documents) √ ok

Corrective maintenance – historical data √ software maintenance database

Responsibilities √ manager, supervisor and execution employee

Records control √ maintenance software database periodical backup

Analysis √ maintenance supervisor and support staff

Audits √ internal and external

Continuous improvement √ based on analysis / audits results

QA System relevance in facility

maintenance

8 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility Fuel cycle facility example UO2 conversion plant

Grading of QA Requirements

9 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility: an example for maintaining the designed safety requirement UO2 conversion plant Vaporization system

Vaporization system Safety analysis

Safety analysis UF6 leakage

UF6 leakage Conductivity of vapor increases and the cylinder valve is closed

Safety item Condensate vapor conductivity analyzer

Grading of QA Requirements

10 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility: an example for maintaining the designed safety requirement

Condensate vapor conductivity analyzer QA grading (TRS-328)

Safety item

Mature – supplied by manufacturers with extended experience in the field and also, if possible, the original one or supplier of other similar nuclear installation

Complexity – the design, manufacture and installation do not differ from other installations

Mature and not complex safety item

Grading of QA Requirements

11 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility: an example for maintaining the designed safety requirement

Condensate vapor conductivity analyzer Mature and not complex safety item

QA requirements must ensure adequate: Transport

Incoming inspection

Identification

Storage

Periodical inspections / tests using procedures (LV and IM)

Periodical preventive maintenance using procedures (IM)

Continuous improvement

Grading of QA Requirements

12 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility: an example for maintaining the designed safety requirement

Condensate vapor conductivity analyzer NOT Mature New supplier (nationalization)

QA requirements must ensure adequate: Supplier history (other factories / not in safety items)

Evidential quality assurance documents

Audits in the supplier installation

Item tests in operational conditions

Transport

Incoming inspection

Identification

Storage

Periodical inspections / tests using procedures (LV and IM)

Periodical maintenance using procedures (IM)

Continuous improvement

Grading of QA Requirements

13 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Grading of QA Requirements in a Fuel Cycle Facility: an example for maintaining the designed safety requirement

Difficulties encountered and strategies to overcome those difficulties

Most standards were issued to NPP Adapt and use them

Imported items lead to interaction difficulties Import from known suppliers and interaction with other similar nuclear fuel factories

Small amount of necessary item procurements Interaction with other similar (but larger) nuclear fuel factories

Nationalization having only one fuel factory in the country Interaction with other similar (but larger) national non nulclear factories

Grading of QA Requirements

14 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Brazilian trends in QA System Based on CNEN-1.16, ISO 9001, ISO 14001 and OSHAS 18001

SIG – Integrated Management System In accordance to GS-R-3

Safety, health, environment, security, quality and economic aspects

Brazilian trends

15 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

Conclusions

National standards improvement underway (the licensing process is changing year by year to consider safety in an integrated way);

Importance of maintaining the safety of the installation during its life cycle;

Importance of desmonstrating the relevance of QA concerning safety for all the operators, including, employees Satefy Culture improvemnts;

NPP is not the only one! In some countries there are also fuel cycle facillities;

IAEA has a very important role in enhancing the safety culture.

Conclusions

16 Technical Meeting on Grading of the Application of Management

System Requirements (23-27 January 2012) /17

www.cnen.gov.br

Thank you for your Attention!

e-mail: [email protected]

Technical Meeting on Grading of the Application of Management