COMFIRSTNCDINST 4355.1B N3 COMFIRSTNCD INSTRUCTION 4355.1B From: Commander, FIRST Naval Construction Division Subj: CONSTRUCTION QUALITY PROGRAM Ref: (a) Unified Facilities Guide Specifications (UFGS) (b) NAVFAC Business Management System (BMS) B-1 Design and Construction (b) Corps of Engineers EP 415-1-261, Vols 1-4, Quality Assurance Representative Guide (d) COMFIRSTNCDINST 3502.2 Encl: (1) Sample Appointment Letter (2) Quality Control Inspection Plan (3) Construction Trade reference Library (4) Required Submittals Form (5) Quality Control Checklist examples (6) Preparatory Phase Checklist Form (7) Initial Phase Checklist Form (8) Daily QC Inspection (Follow up Phase) Checklist Form (9) Quality Deficiency Report (10) Design Change Directive (11) Field Adjustment Request (12) Definable Features of Work Submittal Form (13) Sample Project Package Disposition Letter 1. Purpose . To prescribe the policy, objectives, and procedures to ensure required quality construction is achieved on projects assigned to Naval Construction Force (NCF) units. 2. Cancellation . COMFIRSTINST 4355.1A. This instruction is a major revision and should be reviewed in its entirety. 3. Definition . Quality control (QC) and quality assurance are management systems of published and enforced standards which ensure construction projects are completed with a specified minimum quality. Quality construction is just as important as project execution. A product that falls below standards will not satisfy its intended purpose and may require excessive recurring maintenance costs. A product that exceeds the standards generally consumes more resources than planned. A project which costs a life or serious injury is not a "quality" project. Job

Transcript of COMFIRSTNCDINST 4355.1B From: Commander, …navybmr.com/study material/COMSECONDNCB COMTHIRDNCBINST...

COMFIRSTNCDINST 4355.1B

N3

COMFIRSTNCD INSTRUCTION 4355.1B

From: Commander, FIRST Naval Construction Division

Subj: CONSTRUCTION QUALITY PROGRAM

Ref: (a) Unified Facilities Guide Specifications (UFGS)

(b) NAVFAC Business Management System (BMS) B-1 Design and

Construction

(b) Corps of Engineers EP 415-1-261, Vols 1-4, Quality

Assurance Representative Guide

(d) COMFIRSTNCDINST 3502.2

Encl: (1) Sample Appointment Letter

(2) Quality Control Inspection Plan

(3) Construction Trade reference Library

(4) Required Submittals Form

(5) Quality Control Checklist examples

(6) Preparatory Phase Checklist Form

(7) Initial Phase Checklist Form

(8) Daily QC Inspection (Follow up Phase) Checklist Form

(9) Quality Deficiency Report

(10) Design Change Directive

(11) Field Adjustment Request

(12) Definable Features of Work Submittal Form

(13) Sample Project Package Disposition Letter

1. Purpose. To prescribe the policy, objectives, and procedures

to ensure required quality construction is achieved on projects

assigned to Naval Construction Force (NCF) units.

2. Cancellation. COMFIRSTINST 4355.1A. This instruction is a

major revision and should be reviewed in its entirety.

3. Definition. Quality control (QC) and quality assurance are

management systems of published and enforced standards which

ensure construction projects are completed with a specified

minimum quality. Quality construction is just as important as

project execution. A product that falls below standards will not

satisfy its intended purpose and may require excessive recurring

maintenance costs. A product that exceeds the standards

generally consumes more resources than planned. A project which

costs a life or serious injury is not a "quality" project. Job

2

safety and good project base house-keeping are important elements

toward obtaining a finished product of acceptable quality.

4. Background. Reference (a) provides the business processes of

the Naval Facilities Engineering Command (NAVFAC) Construction

Quality Control (CQC) program. The NAVFAC philosophy establishes

a mutual effort between the construction agent and the Resident

Officer in Charge of Construction (ROICC)/Facility Engineering &

Acquisition Division (FEAD) to deliver a facility which is

acceptable as defined by the plans and specifications. Projects

and Camp Maintenance assigned to the NCF are monitored by the

ROICC/FEAD and Naval Construction Regiment (NCR) Camp Czar in

accordance with normal CQC surveillance procedures which are set

forth in reference (a). Oversight by the ROICC/FEAD or a

designated representative does not relieve the construction agent

of the responsibility to ensure projects meet the standards in

the plans, specifications, and accepted construction practices.

This instruction outlines procedures to help establish these

programs. The program will require the assignment of personnel

to non-direct labor billets. An effective inspection staff,

working within an established command program, will yield the

desired results.

5. Policy. The Commander, FIRST Naval Construction Division

(COMFIRSTNCD) requires that all work tasked to NCF units is

accomplished under an active CQC program. The entire chain of

command is responsible to ensure quality work is put in place.

Quality will be the normal not the exception for projects

executed by the NCF. To prevent discrepancies where the quality

of workmanship and materials fail to match the requirements in

the plans and specifications each unit executing construction

will establish and maintain an active CQC program. The NCF will

utilize the three phases of control as the method of QC of work

performed. The quality of all construction work done by NCF

units will be closely monitored and the requirements of this

instruction will be enforced through daily project QC

inspections, ROICC/FEAD inspections, Quality Deficiency Reports

(QDR) and all division or regimental visits or inspections.

Results and feedback of these visits will be a significant factor

when evaluating the unit’s overall performance. In conjunction

with the above policy the following requirements are established:

a. Roles and responsibilities

(1) Echelon V commands:

(a) The NCR is responsible for the identification,

development, and oversight of all construction projects executed

as unit tasking regardless of location or when they occur in the

Fleet Readiness Training Plan (FRTP) cycle. The NCR will provide

3

construction management and quality oversight for: construction

projects executed in the regimental deployed area of operations;

Innovative Readiness Training projects; and pre-deployment

construction projects. The NCR provides constructability reviews

for assigned projects, coordinates with the local public works

for the execution of quality assurance inspections, performs

quality assurance inspections during project visits, and analyzes

unit reporting. It also provides feedback on the performance of

the unit's QC staff and CQC Program as part of the unit’s Unit

Level Training Readiness Assessment-Sustainment (ULTRA-S).

(b) The Seabee Readiness Group (SRG) is responsible

for providing project management and quality oversight for

projects that are constructed as part of Advanced Base Functional

Component team training and Fleet Training Exercise training

evolutions (i.e., projects that will be deconstructed upon

completion of the training period.) The SRG provides direction

and quality feedback during classroom periods of instruction and

during execution of construction projects in the training

environment.

(2) Echelon VI Commanding Officers will perform all

duties of a construction contractor for job accomplishment. The

Commanding Officer is responsible for providing a quality product

on time within the programmed cost in accordance with plans and

specifications for the specific project. Units engaged in

construction will organize to carry out an effective CQC program

for all projects. NCF units will have as part of their

Operations Department staff; construction inspection and material

testing personnel specifically assigned and trained to perform

these functions as their primary duty. Units that do not perform

material testing are not required to man and train personnel for

that skill. Normally personnel assigned as construction

inspectors will be E-6 or above and fully trained to act as

inspectors. Inspectors should be familiar with all aspects of

construction. The Quality Control Branch will be led by a Chief

Petty Officer or above and reports directly to the Operations

Officer (S3). The establishment of the QC staff does not relieve

the company organization from having an active and responsive CQC

program which functions through the normal chain of

command/organization. Each detachment (DET) will establish a QC

organization tailored to the size and staffing of the DETs

manning and tasking. The unit will consider the following items

when establishing the CQC organization:

(a) The QC staff is a valuable source of information

and expertise. In addition to their quality oversight duties the

QC staff should provide training and/or demonstrate proper

construction techniques and methods to the project crews as

needed. In order to ensure continuity and synergy of the CQC

4

program, once established, the QC organization will be maintained

for a minimum of one FRTP cycle.

1. The QC Chief is S3’s direct representative

and is responsible for the CQC program. He/she reviews and

directs action on each inspector’s daily report as required,

ensures the ROICC/FEAD receives reports and test results, and

coordinates with the ROICC/FEAD to resolve any deficiencies in

plans, materials, or workmanship on any project. QC Chief has

"By direction" authority to stop forward progress on any project

when work is not performed per plans, specifications or industry

standards. This may be delegated to the QC Inspectors as

required. QC Chief duties include, but are not limited to:

a. Coordinate and review all QC plans.

b. Coordinate and review all Project

Inspection Plans.

c. Ensure daily inspections are done

professionally and efficiently. Review reports daily and ensure

they are promptly routed, and follow up on any discrepancy,

comment, or other issue noted.

d. Coordinate with the NCR Camp Czar and/or

the Camp Maintenance staff to determine which Maintenance Control

Division (MCD) projects will require CQC oversight. Once an MCD

project has been identified as requiring CQC oversight, all

reporting and monitoring requirements that apply to an assigned

project apply to the MCD project. Forward daily reports to the

Camp Czar and the Camp Maintenance Chief. A Safety plan and QC

plan will be submitted to QC Chief and approved prior to MCD

project commencement. Abbreviated project files are authorized

and will include a QC plan, Safety plan, all daily reports, and

will be kept by the Camp Maintenance staff.

e. Ensure that proper logs and reports are

maintained for all projects.

f. Maintain weekly contact with DET QC

Inspectors and Assistant Officers in Charge (AOIC). Discuss

project quality and inspection methods.

g. Generating QDRs when quality deficiencies

are brought to light.

2. Quality Control Inspectors

a. QC Inspector staff manning will be

consistent with the nature and location of the workload. Ensure

5

that only highly competent Petty Officers with demonstrated

technical expertise are assigned as inspectors. Commands will

appoint each QC Inspector by letter that clearly defines all

authority and responsibilities. The appointment letter is

provided in enclosure (1). Provide copies of the letter to the

ROICC/FEAD and maintain copies on file. Assign QC Inspectors to

specific projects in order to ensure continuity and

accountability. Do not assign duties to QC Inspectors which

detract from their primary responsibility of inspecting project

quality.

b. Construction Inspectors will be trained in

accordance with reference (e) and should be able to identify

deficiencies and make recommendations on material quality,

workmanship, and construction practices. Units may request

additional training for specific tasking through their chain of

command. QC Inspectors will be familiar with the unit QC and

safety program instructions. QC inspectors should also possess

experience to recognize safety violations on project sites and

recommend corrective actions.

c. The QC Inspector’s job is project quality,

not resource scheduling and availability. They report directly

to QC Chief. They are responsible for daily QC inspections,

phase checks, and coordinating any special tests or inspections.

They advise Project Supervisors on construction techniques and

suggest better or more efficient methods if available. They

visually inspect and report on the progress and quality of all

work-in-place. They report and correct all safety violations,

ensure proper material use and conservation, and can assist

Project Supervisors in determining work-in-place for reporting

purposes. If an inspector lacks knowledge about a particular

aspect of the construction, it is solely his/her responsibility

to get assistance from QC Chief, another inspector, the

ROICC/FEAD, or any other qualified source. QC Inspector

responsibilities also include but are not limited to:

d. To be completely familiar with plans,

specifications, and manufacturers recommendations for assigned

projects. Assist Project Supervisors in developing QC plans.

e. Develop a Project Inspection Plan that

details all al QC inspections for the project and provides

quantitative measurement. Specific care will be taken in

plotting critical QC points. The inspection plan will be

developed independently of the QC plan, but will be coordinated

prior to project start to align inspection dates with activity

start dates. The inspection plan will detail objectives for each

project visit regardless of milestones. The inspection plan

format is included as enclosure (2).

6

f. Become familiar with the unit safety

instruction and acquire proper training to identify safety

hazards/violations on projects.

g. Visit all projects daily and submit daily

reports. Proper documentation is a must. Daily reports must

identify all discrepancies and solutions. Reports become the

record and show how quality was measured and confirmed throughout

construction. Without proper documentation all construction

quality is suspect. The daily inspection form is found in

enclosure (3).

h. Discuss job progress and construction

methods with the Company Operations Chiefs, Project Supervisors,

and Crewleaders.

i. Immediately notify QC Chief or Operations

Chief (S3C) if questionable construction or safety practices are

observed.

j. Advise prime and subcontractor companies

in project planning and project file maintenance.

k. Review and coordinate all requests for

information (RFI), field adjustment requests (FAR), excavation

requests, utility outages, road closures, and concrete form

designs for constructability and make initial recommendations.

Ensure all RFI have been FULLY researched prior to submitting to

ROICC/FEAD.

l. Be present during all phase checks and

certified system tests to ensure compliance with plans/specs and

manufacturer recommendations.

m. Brief QC Chief daily on inspections

scheduled, project visits, inspection reports.

n. Route daily inspection reports to

ROICC/FEAD, QC Chief, and the Project Supervisor.

o. Inspect project materials received at the

job site and Material Liaison Office (MLO) to verify that they

meet project specifications.

p. Ensure timely delivery of any prints,

specs, Bill of Material, or any other information to the prime

contractor company.

7

q. Become familiar with local construction

practices used at deployment sites.

r. Maintain copies of all project

correspondence, i.e., FAR, RFI, design change directive (DCD),

utility requests, etc. Ensure all information is current and

correct. Maintain a tickler on all unanswered correspondence.

Ensure all reports and correspondence are properly logged and

filed.

s. Create and maintain a significant events

calendar that will be placed in a conspicuous place to notify all

interested personnel of project milestones (concrete placement,

asphalt work, punch list inspections, beneficial occupancy date

(BODs), ribbon cuttings, etc.)

t. Review project submittals prior to

submission to ROICC/FEAD.

u. Ensure project files and as-built drawings

are updated continuously (at least every two weeks) and are

complete upon project completion. QC Inspectors will draft

closeout letters and submit to the S3 Yeoman for typing. Project

packages will be updated for all turnover projects to provide the

relieving unit with as much information as possible. All

operations and maintenance manuals will be turned over to

ROICC/FEAD after project completion.

3. DET QC Inspectors duties are the same as

noted in paragraph 5.a.(2)(a)2.c. thru u. DET QC Inspectors

shall report to the DET AOIC or QC Chief (as appropriate) for

daily review. DET QC Inspectors shall maintain as close a

liaison as possible with the QC Chief for professional advice and

guidance.

4. Engineering Chief is responsible for, but not

limited to:

a. Maintaining a complete laboratory, with

all required testing equipment, to perform required tests.

Ensure all required calibrations and certifications are up to

date and properly recorded in logs.

b. Performing all scheduled or required tests

per established methods set forth by the specifications and

accepted industry standards.

c. Maintain accurate and complete test

records and promptly deliver results to QC inspectors.

8

d. All surveying, project layout, and

elevations.

e. All drafting, as-built drawings, designs,

and sketches on FARs and RFIs.

f. Maintaining project history files for all

projects completed at the Main Body site. Additionally, the

engineering chief will maintain a list of all projects completed

at DET sites associated with the Main Body site. Additional

details provided in

g. Maintain the unit construction trade

library.

5. Material Testing Personnel

a. There will be a sufficient number of

trained personnel to conduct/coordinate required tests on

concrete, asphalt, soils, and other materials, as required and to

maintain equipment needed to perform these tests.

b. Upon the completion of the project QC

plan, the QC staff will develop an inspection plan incorporating

required testing. This is the time to identify on-site testing

requirements and capabilities. If a required testing capability

is not available within the unit, the Operations Department

should contact other government agencies and coordinate necessary

testing services.

c. During construction, testing personnel

will conduct required tests in accordance with the inspection

plan. All test results will be attached to the QC report for the

date the work was put in place. For example, concrete cylinder

break results at the seven, fourteen, and twenty-eight day point

will be attached to the QC report filled out on the date of the

concrete placement. The QC reports and attached test results

will be signed by both the QC Inspector and Project Supervisor

and two copies forwarded to the ROICC/FEAD. Provide copies of QC

reports and test results to the NCR as requested for review.

After ROICC/FEAD review, the report will be routed through the

project chain of command and remain as part of the project

package. For onsite tests, the designated ROICC/FEAD

representative will be notified in advance to allow the

opportunity to observe the test.

6. Company Commanders/DET OICs assign Project

Supervisors and Crewleaders. They ensure that all planning

documents, including specific QC plans for each project are

complete, publicized, and understood prior to project start for

9

all assigned projects, in homeport or on deployment. He/she will

ensure that experienced people are in charge and that crews have

the necessary skills to complete the project. DET OICs and

Company Commanders will monitor construction quality and efforts

through QC reports and regular project visits. The Company or

DET Chain of Command will take a proactive stance in project

quality and are responsible for:

a. Ensuring that Project Supervisors and

Crewleaders share command concern for safe, high quality

execution of work.

b. Conducting a constructability review for

each assigned project.

c. Reviewing project plans and

specifications, and submitting a report of all errors and

omissions to QC Chief.

d. Reviewing QC plans prior to submittal to

the QC Staff.

e. Making regular project visits to ensure

that the job sites are safe, productive, and that crews are

producing a quality project.

f. Review and validate all FARs and RFIs

prior to submission.

7. Company/DET Operations Chief/Project Chief is

directly responsible to the Company Commander/DET OIC for all QC

matters. These individuals will give added attention to training

Project Supervisors and Crewleaders in developing QC plans and

using the three phases of inspection.

8. Project Supervisors are responsible for the

overall quality and workmanship on his/her job site including

work performed by all subcontractors. A Project Supervisor

typically is responsible for the supervision of two or more

Crewleaders of various ratings engaged in the completion of a

project. Assisted by the QC staff, he/she develops a specific QC

plan for the assigned project. He/she will accompany QC

Inspectors during job site visits and assist in completing daily

reports. Upon completion of the rework make arrangements for re-

inspection. Project Supervisors are also responsible for:

a. Conduct daily QC lectures to review

Definable feature of work (DFOW) or activity QC requirements for

that day.

10

b. Using the preparatory and initial phase

checklist before starting each DFOW.

c. Maintaining a continual job-site presence

to ensure maximum quality and productivity.

d. Maintaining a log for all DCDs, FARs, and

RFIs in the project package, folder 4B.

e. Reviewing the five-folder project package

with the lead QC Inspector upon project completion. Ensure that

all project information required for the project completion

letter is current, accurate and in the file.

f. Inspect and verify work before specific

requested QC inspections occur, i.e., Concrete Placement, stack

tests, etc. Identify all key inspections as milestones on the

project schedule.

g. Research all RFIs prior to submission.

h. Ensure that project crews are familiar

with daily/weekly construction schedules by posting them and/or

discussing during daily project QC meetings.

8. Crewleaders will become familiar with project

plans and specifications and ensure that the proper tools and

equipment are available for the job. A Crewleader typically

supervises a crew of two or more persons generally of the same

rate in the completion of a phase or section of a project.

He/she is responsible to the Project Supervisor to provide the

highest quality workmanship possible from his/her assigned crew.

He/she will keep the Project Supervisor updated on progress,

potential delays or problem areas, required tests, and any and

all changes necessary to the as-built drawings. The Crewleader

will inspect his crew’s work and ensure it meets the required

quality level.

9. Crewmembers will become familiar with project

quality requirements. They will develop a complete understanding

of work methods and question Crewleaders about any activity that

they do not fully understand. The entire CQC Program hinges

around the Crewmember and their ability to perform construction

in accordance with plans, specifications, and accepted

construction practices.

10. Material Expediters: The material expeditor

along with the project supervisor and the QC Inspector will

inspect all material when received by the MLO. These inspections

ensure materials meet all the conditions set forth in the plans

11

and specifications. Further, the material expeditor will re-

inspect at least one month prior to planned use and materials

received months in advance of their intended installation date.

This re-inspection identifies expired shelf life, storage damage,

and usability of material. The Material Testing Personnel will

inspect mineral products upon delivery and reject them when they

do not comply with the project specifications.

b. Quality Control Implementation Guidance

(1) Pre-Construction

(a) Plans and specifications establish construction

standards and accepted construction practices. Because of

varying site conditions, intended purpose, and the life

expectancies of various facilities, construction standards may

vary from project to project. Units will use references

(a) through (d) as the minimum acceptable standards when other

defined standards are absent.

(b) Commands will coordinate with the NCR to receive

plans and specs. NCRs will coordinate with the Public

Works/Design Agent to receive plans and specs approximately 10

months prior to project execution. Project planning should be

done using the final signed version of plans and specs. During

planning process the unit will develop a QC plan which will be

submitted to the QC Staff for approval and incorporation into the

inspection plan.

(c) In cases where materials do not meet

specifications, i.e., Theater Security Cooperation Plan (TSCP)

missions the project leadership will coordinate with the chain of

command and NCR to identify suitable local materials.

(d) FARs and RFIs: Review plans and specifics to

identify conflicts in construction methods and materials. Submit

RFIs and FARs for clarification or adjustment in construction

method. Changes which exceed 50 man-days of additional effort or

$500 in additional cost must be approved by the appropriate NCR

prior to submission to ROICC/FEAD.

(e) Units will develop a QC Plan for each project.

The QC Plan will identify quantifiable QC inspection points for

each activity. Enclosure (5) is a QC checklist. The reference

list in enclosure (10) is provided as a resource to assist the

crew in developing valid inspection criteria.

(f) Inspection Plan: Unit QC staffs will develop a

construction inspection plan for each project specifically tasked

to the unit. The construction inspection plan will identify each

12

item/phase of the project which requires a quality check (i.e.,

phase inspections, material tests, utility tests, etc.), and

highlight critical inspection points. The frequency of required

tests must be shown. The QC staff will prepare inspection plans

per enclosure (2). The QC inspector will prepare the plan with

sufficient detail to identify specific plans and specification

requirements for each phase of work. The QC inspection plan will

be developed using the current project schedule and QC plan.

This is a required submittal to the ROICC/FEAD.

(g) Hold a preconstruction conference with the

ROICC/FEAD or designated representative, public works, customer,

and project QC inspector, to discuss the scope of the project,

construction schedule, utility requirements, the QC plan, and any

other items which may affect construction. Maintain regular

contact with the ROICC/FEAD representative throughout the life of

each construction project until it is totally completed.

(2) Project Execution:

(a) QC will be accomplished utilizing the three

phases of inspections; preparatory, initial, and follow-up.

These inspections are based on definable features of work (DFOW).

DFOW is defined as a task that is separate and distinct from

other tasks and requires separate QC requirements. A DFOW is

identified by different trades or disciplines and is an item or

activity on the construction schedule. Each specification

section could be considered a definable feature of work, but,

there frequently is more than one definable feature of work under

a particular section. A Construction Activity may be a DFOW,

depending on the activities scope, quantity of work, skill

intensity and/or resulting quality required for its completion.

The three phases of inspection are defined as follows:

(b) Preparatory Phase. Prior to starting the project

and before the start of each DFOW the Project Supervisor will

hold a QC preparatory phase meeting. This meeting will include

all pertinent Crewleaders, QC staff, Project Manager, and

FEAD/ROICC representative. The purpose of this meeting is to

inform all personnel involved with the activities of the QC

requirements. The meeting will also address all submittals,

materials, tools, and equipment needed to accomplish the

activities. These items should correlate directly with the

project QC plan and applicable areas in the specifications.

Enclosure (6) is the Preparatory Phase checklist.

(c) Initial Phase. When construction starts on an

activity, the QC Inspector and Project Supervisor will monitor

the initial material installation to validate adherence to the

plans ands specifications as agreed upon during the Predatory

13

Phase meeting. Any discrepancies in workmanship will be

corrected immediately. Enclosure (7) is the Initial Phase

checklist.

(d) Follow up Phase. The Project Supervisor, QC

Inspector, and chain of command will conduct continual

inspections of the activities in progress. The QC Inspector will

conduct daily checks during this phase and annotate findings on

the daily QC reports, shown in enclosure (8). This will ensure

that all work is done in accordance with the drawings and

specifications. QC Inspector will submit the report to the

Operations Officer or Detail OIC via the chain of command for

final review, approval, and/or continuing action, as appropriate.

QC will route a copy of the daily QC inspection report to the

ROICC and the prime contractor company commander.

(e) NCF units are required to make submittals for

materials and construction methods used in the execution of

projects. Submittals will be generated and provided to the

FEAD/ROICC/Design Agent as identified in enclosure (4).

(f) Operations Department personnel will review the

original QC report daily. Provide a copy of each report to the

ROICC/FEAD on the first working day following the period covered

by the report. When discrepancies are noted in the report,

immediately initiate action to correct the discrepancy. Note

corrective actions taken on the QC report for the day during

which corrective measures were taken. In addition, note the

corrective actions taken and the date the actions were completed

on the QC report which initially noted the discrepancy. Make

copies of all inspection reports and test results a permanent

part of the project records.

(g) Quality Deficiency Reports will be generated when

work in place fails to meet acceptable standards as set forth in

the plan, specifications, references (a) through (d), and

accepted industry standards. Un-reported, un-documented, or

otherwise hidden quality defects found during follow-up

inspections and/or turnovers may result in disciplinary action.

Enclosure (12) is the form for the QDR. The following limits are

established for the submission of QDRs.

1. Quality deficiencies or rework up to $2,500

are at the Commanding Officers discretion as to whether or not a

QDR is submitted to the chain of command.

2. QDRs identifying poor quality or rework in

excess of 50 mandays or between $2,500 and $5,000 in material

costs require the QDR to be forwarded to the operational

regimental commander for review and disposition. The

14

circumstances surrounding the QDR may require a Judge Advocate

General (JAG) investigation to determine the facts.

3. QDRs identifying rework in excess of 100

mandays or $5,000 in material costs require a JAG investigation

to determine the facts. The results of the JAG will be forward

to the division Commander for review and disposition.

(h) Conduct the final inspection of a completed

facility with the ROICC/FEAD and correct any discrepancies.

After all discrepancies are corrected and inspected during the

acceptance inspection, forward a completion letter to the

ROICC/FEAD along with a set of "as built" drawings, all

manufacturer's literature, copies of Design Change Directives

(DCDs) or change orders, operations and maintenance instructions,

or other correspondence requested by the ROICC/FEAD. Enclosure

(13) is a sample completion letter.

(i). Forward a copy of all project completion

letters to the appropriate regiment and COMFIRSTNCD.

(j). Maintain completed project packages at main

body and detachment sites for a period of three years to include

a one year warranty period. At the end of the three year period

forward a disposition request (Enclosure 13)to the operational

regiment for guidance on disposal.

R.E. CELLON

Commander

K. Gregory

Chief of Staff

Distribution:

Enclosure (1)

1306

CO

From: Commanding Officer, U. S. Naval Mobile Construction Battalion XXXX

To: BU1(SCW) P. J. xxxxxxx, USN, 000-00-xxxx (Last four only)

Subj: DESIGNATION AS QUALITY CONTROL INSPECTOR FOR PROJECT ####-###

Ref: (a) COMFIRSTNCDINST 4355.1A

(b) **Unit QC level instruction**

(c) ** Unit level safety instruction**

1. You are hereby designated as the Quality Control inspector for (NMCB or

Detachment xxxxxxx project ####-###). You are responsible for all matters

of Construction Quality Control associated with projects.

2. You will familiarize yourself with the provisions of references (a)

thru (c) in the performance of your duties.

3. This designation is effective immediately and expires upon the

completion and acceptance of the project or if the project is turned over

once the turnover is complete.

J. R. WAYNE

Copy to:

S3

S3C

S3QC

Project Package

RIOCC/FEAD

Enclosure (2)

Construction Reference Library

Enclosure (3)

Reference Title Author ISBN

Basic Construction Management: The

Superintendent's Job

Leon Rogers ISBN-10: 0867184523

ISBN-13: 978-0867184525

Basic Concrete Engineering for

Builders

Max Schwartz ISBN-10: 1572180919

ISBN-13: 978-1572180918

Residential & Light Commercial

Construction Standards

RS Means & Contributing

Authors

ISBN-10: 0876296584

ISBN-13: 978-0876296585

Ten Steps To Jobsite Productivity James J. Adrian ISBN-10: 0867185236

ISBN-13: 978-0867185232

A Manual of Best Practice Volume 1

Exteriors

Journal of Light Construction ISBN-10: 1928580246

ISBN-13:978-1-928580-24-9

A Manual of Best Practice Volume 2

Interiors

Journal of Light Construction ISBN-10: 1928580289

ISBN-13:9781928580287

JLC's Construction Tips &

Techniques

Journal of Light Construction ISBN-10: 1928580319

ISBN-13: 978-1928580317

Finish Carpentry Gary Katz ISBN-10: 1928580076

ISBN-13: 978-1928580072

Installing and Hanging Doors Gary Katz ISBN-10: 1561586358

ISBN-13: 978-1561586356

Masonry Skills, 5th Edition Richard T. Kreh ISBN-10: 0766859363

ISBN-13: 9781418037536

Building with Masonry: Brick, Block

and Concrete

Dick Kreh ISBN-10: 1561583367

ISBN-13: 9781561583362

Masonry Problem Clinic The Aberdeen Group ISBN-10: 0924659254

ISBN-13: 9780924659256

Building Tips & Techniques Fine Home Building ISBN-10: 1561586870

ISBN-13: 9781561586875

Best Practices Guide to Residential

Construction

Steve Bliss ISBN-10: 0471648361

ISBN-13: 978-0471648369

Basic Engineering for Builders Max Schwartz ISBN-10: 0934041830

ISBN-13: 9780934041836

Construction Principles, Materials,

and Methods Sixth Edition

Harold Olin, John Schmidt

Walter Lewis

ISBN-10: 0471714054

ISBN-13: 9780442006051

Basic Lumber Engineering for

Builders

Max Schwartz ISBN-10: 1572180420

ISBN-13: 9781572180420

Building with Engineered Lumber John Spier ISBN-10: 1561586978

ISBN-

13: 9781561586974

Pocket Guide to the ADA : Americans

with Disabilities Act Accessibility

Guidelines for Buildings and

Facilities

Terry Edwards Associates Ed. ISBN-10: 0471181374

ISBN-13: 9780470108703

JLC's Guide to Moisture Control Journal of Light Construction ISBN-13: 9781928580362

Moisture Control Handbook :

Principles and Practices for

Residential and Small Commercial

Buildings

Joseph Lstiburek & John

Carmody

ISBN-10: 0471318639

ISBN-13: 9780471318637

Builder’s Guide to Mixed-Humid

Climates

Joseph Lstiburek ISBN-13: 9780975512722

Estimating with Microsoft Excel Jay P. Christofferson ISBN-10: 086718549X

ISBN-13: 9780131719835

Exterior Siding, Trim & Finishes Fine Home Building ISBN-10: 1561586528

ISBN-13: 9781561586523

Windows & Sky lights Fine Home Building ISBN-13: 9781561581276

Construction Surveying & Layout Paul Stull, Ph.D., P.E., P.S. ISBN-10: 1557013632

ISBN-13: 9780934041256

Wells and Septic Systems, Second

Edition

Max & Charlotte Alth ISBN-10: 0830621369

ISBN-13: 9780830621361

Excavation & Grading Handbook Nick & John Capachi ISBN-10: 1572181737

ISBN-13: 9781572181731

Building Layout W.P. Jackson ISBN-10: 0910460698

ISBN-13: 9780910460699

Inspecting A House Rex Cauldwell ISBN-10: 1561584622

ISBN-13: 9781561584628

Construction Reference Library

2 Enclosure (3)

Mold Survival Guide Jeffrey May ISBN-10: 080187937X

ISBN-13: 9780801879388

Gypsum Construction Handbook United States Gypsum Company ISBN-10: 0963686224

ISBN-13: 9780963686206

Finish Carpenter's Manual Jim Tolpin ISBN-10: 0934041822

ISBN-13: 9780934041829

Tiling: Planning, Layout &

Installation

Fine Homebuilding Editors ISBN-10: 1561587885

ISBN-13: 9781561587889

Drywall - Professional Techniques

for Walls & Ceilings

Myron Ferguson ISBN-10: 1561585297

ISBN-13: 9781561581337

Basic Stair building Scott Schuttner ISBN-10: 1561583227

ISBN-13: 9781561583225

1001 Ideas for Trim work Wayne Kalyn ISBN-10: 1580112609

ISBN-13: 9781580112604

Setting Ceramic Tile, Second

Edition

Michael Byrne ISBN-10: 1561580805

ISBN-13: 978-1561580804

For Pros by Pros Plumbing Rex Cauldwell ISBN-10: 1561583332

ISBN-13: 978-1561583331

The Plumber's Trouble-Shooting

Guide

R. Dodge Woodson ISBN-10: 007071777X

ISBN-13: 9780070717770

Remodel Plumbing Rex Cauldwell ISBN-10: 1561586986

ISBN-13: 9781561586981

The Rafter Book - A Modern Handbook

for Roof Framers

David Mahin McIntire ISBN-10: 0964778408

ISBN-13: 9780964778405

Roof Cutter's Secrets Will Holladay ISBN-10: 1928580327

ISBN-13: 9781928580089

Roof Framing Marshall Gross ISBN-10: 091046040X

ISBN-13: 9780910460408

Construction Foreman's Safety

Handbook

George Kennedy ISBN-10: 0827378823

ISBN-13: 9780827378827

NAHB-OSHA Jobsite Safety Handbook NAHB ISBN-10: 0867185295

ISBN-13: 978-0867185294

The OSHA Answer Book Mark Moran ISBN-10: 1890966657

ISBN-13: 9781890966652

Advanced Framing Techniques Steven Bliss ISBN-10: 1928580211

ISBN-13: 9781928580218

The Lead Carpenter Handbook Tim Faller ISBN-10: 0963226878

ISBN-13: 9780963226877

Construction Nightmares from Hell Arthur F. O'Leary FAIA, MRIA

& James Acret, Esq.

ISBN-10: 1557013977

ISBN-13: 9781557012982

Production Checklist For Builders

and Superintendents

John J. Haasl and Peter

Kuchinsky II

ISBN-10: 0867185155

ISBN-13: 9780867185157

Residential Construction

Performance Guidelines, 2nd Ed.

NAHB

Daily Field Guide, a Log Book for

Builders

Tom Hrin ISBN-13: 9780867185164

Carpentry in Commercial

Construction

Byron W. Maguire ISBN-10: 0934041334

ISBN-13: 9780934041331

Commercial Metal Stud Framing Ray Clark ISBN-10: 157218079X

ISBN-13: 9781572180796

Painter's Handbook Bill McElroy ISBN-10: 0934041288

ISBN-13: 978-0934041287

UGLY'S Electrical Handbook George V Hart ISBN: 978-0-9623229-8-3

National Electrical Code NFPA ISBN: 0-87765-790-4

International Building Code ICC ISBN: 1580017258

ISBN13: 9781580017251

2009 International Mechanical Code ICC ISBN: 1580017312

ISBN13: 9781580017312

2009 International Plumbing Code ICC ISBN: 0071606068

ISBN13: 9780071606066

ACI Ascc-1(05) Contractors Guide To

Quality Concrete Construction

ASCC/ACI ISBN: ASCC105

ACI 318-08 Building Code Requirements For Structural Concrete

Construction Reference Library

3 Enclosure (3)

ACI 530/530.1-08 Building Code And

Specs For Masonry

American Concrete Institute

(ACI)

ISBN - 53008

ACI Sp-4 Formwork For Concrete M. K. Hurd ISBN: SP47TH

Asphalt Handbook Asphalt Institute

Required Submittals

Enclosure (4)

Quality Control Checklist Examples

Enclosure (5)

1. Paving

a. Sub-grade

(1) Sub-grade is to proper elevation and cross-section.

(2) Sub-grade is dense and properly compacted.

(3) All drains, utilities and other underground construction are

in place.

(4) Trench backfill is performed as required.

(5) Testing sub-grade is performed and recorded to include OMC

(opt moisture content).

(6) Material delivered is of uniform quality.

(7) Hauling equipment does not produce ruts in sub-grade.

(8) Location of manholes, outlets and surface features are known.

b. Priming and Tack Coats

(1) Prime coat properly seals the surface voids and

provides adhesion.

(2) Prime coat is applied to water free surface free from

objectionable substances.

(3) Prime coat is applied uniformly and receives proper curing

time.

c. Asphalt Paving

(1) Concrete against which paving is to be placed is to be at

least seven days old.

(2) Asphalt mix is proper and approved for this work.

(3) Temperature of mix when delivered is within limits required

and when laid in mat.

(4) Weather limitations are observed.

(5) Materials are properly spread, raked and placed for

thickness and uniformity. Joints are properly formed and

tight.

(6) All edges are straight and curves uniform.

Quality Control Checklist Examples

2 Enclosure (5)

(7) Rollers are operated within speed range and have proper

backup features, drum scrapes and wetting devices. Roller is

backed only over compacted areas.

(8) Correction of humps and depressions to obtain smoothness

and uniformity is to be performed before the start of

compaction.

(9) Damage to adjacent surfaces is corrected.

2. Concrete

a. Formwork

(1) Location, dimensions and grades are as required.

(2) Formwork is properly sealed, oiled (prior to placing RST),

or wetted and treatment is compatible with other materials to

be applied.

(3) Re-used formwork is properly reconditioned and treated for

re-use.

(4) Construction provides mortar-tight condition, free from

offsets, defects and free of debris. Joints may be taped not to

allow more than +/- 3/16”.

(5) Observe type of form ties and bracing used to see if

adequate for form design.

(6) Sleeves for pinning and conduits are provided as required.

(7) Forms are secured against movement during placing

operations. Screens are set to prohibit movement during

placing phase.

(8) Chamfer strips are accurately placed and aligned.

(9) Clean-outs are provided at ends and low points of forms.

Ports are provided in high forms. Verify number and

location.

(10) Expansion, construction and contraction joints are

provided as required or indicated and installed or planned

properly.

(11) Form cut-offs and bulkheads are established in locations

approved.

(12) Forms are in alignment, especially at top of walls.

Quality Control Checklist Examples

3 Enclosure (5)

(13) Keys are provided in construction joints.

(14) Forms allow sufficient space and openings for placing

concrete.

(15) Forms provide for openings (doors, windows, ductwork,

etc.). Cross bracing is provided in formed openings to prevent

bowing.

(16) Proper provisions are made during pour for tools,

equipment and personnel.

(17) Note appearance of obvious defects in formwork that might

impair its ability to withstand concrete pressure without

excessive deflection.

(18) Consider personnel movement on the formwork during the

placement phase when inspecting bracing.

(19) Shoring is checked for location and bearing. Check shores

for settlement during pouring and ensure mud-sills are used

when posts are set on bare ground.

(20) Drain clean-outs, flanges, etc. are set at proper

elevation and sufficient anchorage is provided to avoid

movement.

(21) Scaffolds or other accessories appear adequate and do not

affect formwork.

(22) All embedded items are securely anchored in place and in

the proper location.

b. Form Removal

(1) Concrete is sufficiently strong before removal of forms.

Check specifications.

(2) All formwork is completely removed above and below grade.

(3) Preparations for grouting are made as soon as practicable

after removal of forms.

c. Reinforcement

(1) Steel is installed in accordance with approved drawings.

(2) Required clearance of steel from earth and forms is

provided.

(3) Splice lapping, length of splices and staggering is

performed as required

Quality Control Checklist Examples

4 Enclosure (5)

(4) Additional bars, such as at wall intersections, openings

and at corners are provided.

(5) Reinforcement is clean of all loose or flaky rust, oils or

other foreign materials that might reduce bond.

(6) Reinforcement is tied and supported to prevent displacement

during placement.

(7) Conductors are separated from other conduits and re-bar by

a minimum of three (3) conduit diameters.

(8) No contact of bars is made with dissimilar metals.

(9) Bars are not placed near surfaces that might allow rusting.

(10) Adequate space and clearance is provided for proper

deposit of concrete and use of vibrators.

(11) Avoid bending re-bar excessively.

d. Concrete Placement, Finishing, and Curing

(1) Concrete hard card has been submitted and approved.

(2) EA’s on site with equipment for testing.

(3) All areas to receive concrete are cleaned, wetted, or

otherwise prepared prior to arrival of first truck.

(4) All necessary tools are on hand and in working condition.

Vibrators and stand-by vibrators are available and in working

condition.

(5) Adequate manpower is available for timely placement.

(6) Arrangements have been made for specific curing, sawed

joints and protection from the elements.

(7) Delivery of concrete and sequence of delivery is scheduled

to allow for continuous placement to prevent cold joints.

Delivery tickets are checked for time limits.

(8) Layers are kept approximately horizontal and do not exceed

required lifts.

(9) Bolts and loose items to be embedded are properly located

and installed.

(10) Grades, elevations, alignments are being checked during

placement.

Quality Control Checklist Examples

5 Enclosure (5)

(11) Time delay is made for concrete in columns, piers, walls

and openings to allow concrete to settle before placing

concrete above them; however, initial set is to be avoided.

(12) Vibration is performed properly.

(13) Cylinders are cast and stored, slump tests performed.

(14) Type of finish on surfaces is checked and provided as

required. (verify type of surface required).

(15) Screens are provided and removed when they are no longer

required.

(16) Overworking the surface is to be avoided.

(17) Ensure that all joints, edges, and corners are carefully

finished and/or match.

(18) Curing methods are to be started as soon as possible.

(19) When plastic or burlap is used as a curing method, avoid

disfiguring the surface finish by dragging or dropping weight

on the surface when securing it.

3. Masonry

a. Layout of work, coursing and dimensions are as required or

indicated.

b. Joint size, type and tooling method is understood.

c. Type of bond (pattern) is in accordance with prints.

d. Joints are tooled to provide a dense surface.

e. Mortar is applied to block/brick and is not “slushed” into

the head joints.

f. Cutting of units is as required.

g. Clean-outs/weep holes are provided as required.

h. Reinforcement as required, is of type, sized, splicing and

spacing required.

i. Bending of re-bar for site access is to be kept to a

minimum.

j. Door frames are secured and braced in position (plumb and

square).

Quality Control Checklist Examples

6 Enclosure (5)

k. All embedded materials are on site and available.

l. Provisions for flashing, cutouts and later installation of

other items are made.

m. Expansion and control joints are located and provided, as

indicated or required.

n. Prior to pouring the cores ensure they are properly cleaned

out. Ensure that cores are filled on a maximum of 6 courses of

block at a time. RST not resting against block/brick to allow is

in proper placement of grout.

o. Pipes, conduits, and boxes are located, secured and

protected as required.

p. Hollow metal frames are filled solid.

q. Methods of final cleaning are as required.

4. Structural Steel

(1) Size and type of bolts, washers, and hole diameters are, as

required.

(2) Delivered steel is new, undamaged, and free of rust and

distortions.

(3) Steel is properly stored, blocked off ground and covered

where prolonged storage occurs.

(4) Observe setting of base and bearing plates. See that full

engagement of nut occurs and bending of anchor bolts or undue

chipping of concrete does not occur.

(5) Verify clearances required for finish coverings or materials

are provided.

(6) Drift pins are used to bring together parts but should not

damage or distort metal.

(7) Steel members are not cut for passage of pipe conduit, etc.,

unless so indicated on shop drawings.

(8) Type, size and length of bolt, size and type of washer and

size of hole are as required.

(9) All bolt heads and nuts are resting squarely against metal and check to see that bolts have been drawn tight. Check

specification.

Quality Control Checklist Examples

7 Enclosure (5)

(10) Holes are properly aligned. Burning to correct

misalignment is not permitted.

5. Thermal and Moisture Protection

a. Roofing

(1) Surfaces are free from foreign material.

(2) Excess mortar or concrete is removed; all holes, joints

and cracks are pointed, and rough and high spots are ground

smooth.

(3) Surfaces are dry to receive heated asphalt, coal tar and

petroleum solvent asphalt mastics.

(4) Hot applied bituminous materials are not overheated.

Method and sequence of transporting and application of

bituminous material are adequate.

(5) Surfaces are properly primed if required.

(6) Pipes and other items penetrating membranes are flashed

or made watertight as required.

(7) Ensure membrane lapping details are understood.

(8) No work proceeds during damp weather. Allow no moisture

to be present between layers.

(9) Stand roll roofing on end and keep free of moisture and

earth. Protection/covering for roofing materials should be

vented so condensation will not occur.

(10) Felts are applied as required. Broom and laid so that

each layer is free of air pockets, wrinkles and buckles. Do

not allow “flopping” of roofing felts.

(11) All sheet metal and roof accessories are in place or on

hand as required, to be installed in conjunction with

roofing.

(12) Felts for asphalt bitumen are asphalt-saturated; felts

for tar pitch are coal tar-saturated.

(13) Under no condition allow exposure of insulation or

organic overnight without mopping.

(14) Aggregates spread over flood coat of quantity required,

while pitch or asphalt is hot.

(15) Cap sheet is utilized, is of weight, finish and color

Quality Control Checklist Examples

8 Enclosure (5)

as required.

(16) Operations are done in a neat and workman like manner

so as not to damage adjoining areas.

b. Insulation

(1) Method of installing over surface is as required.

(2) Wood nailers/stops are provided and installed in

accordance with the drawings.

(3) Joints are staggered.

(4) Insulation is installed in conjunction with roofing

felts and sealed in for the night.

(5) Runway over the insulation are required to support

mechanical or heavy equipment.

(6) Insulation remains dry until covered by roofing.

c. Flashing

(1) Isolation provisions are made for dissimilar metals. Do

not allow copper and aluminum flashing to be in contact with

each other or with ferrous metal.

(2) Flashing does not interfere with structural

requirements.

(3) Generally see that the metal is lapped a minimum of four

(4) inches.

(4) All edge metal laps are coated with plastic cement on

horizontal flange and vertical rise. Coating covers entire

lap and is sandwiched between.

(5) Lengths of flashing are as long as possible.

(6) Installation is coordinated with roofing installation.

(7) Flashing is embedded in roof membrane assembly.

(8) Method of anchoring lower edge of fascia is as required;

observe alignment, stiffness, etc.

(9) Gravel stops are pitched to provide for drainage.

(10) Gutters are pitched to provide for drainage.

Quality Control Checklist Examples

9 Enclosure (5)

(11) Gutter and downspout joints are lapped in direction of

flow.

(12) Gutter and downspouts are installed plumb.

(13) Base flashing extends up sufficiently; flange is

embedded at least four (4) inches in roofing membrane.

(14) Cap flashings are installed to provide secure

anchorage, allow movement and have sufficient laps and

spacing.

(15) Review drawings and specifications for sheet-metal

items called for in one and not the other.

6. Doors and Windows

a. Doors

(1) Doors are approved-size, type design, etc., and have no

defects such as dents, buckles, and warps.

(2) Additional reinforcement is provided for hardware.

(3) Fire rated doors have labels and proper identification.

Keep free of paint or stain.

(4) Observe installation and verify proper clearances

provided.

(5) Doors function smoothly and easily and hardware is

properly adjusted.

(6) Factory prime is retouched; factory finish is not

damaged and surfaces are adequate to receive applied finish.

(7) Doors are cleaned. Report all doors that cannot be

properly cleaned. Protection is provided as required to

avoid marring and other damage.

(8) Proper type and number of anchors for frames are

provided; verify adequate anchorage is made during

installation.

(9) Frames are grouted during installation if required and

caulked if required.

(10) Frames are installed straight, level, and plumb and

adequately braced where “built in”.

b. Windows

Quality Control Checklist Examples

10 Enclosure (5)

(1) Delivered windows are of type, size, finish, operation,

etc., as required.

(2) Windows are properly stored until installed.

(3) Special items are furnished, such as bolts, pull down

hooks, trim, etc.

(4) Required type of glazing beads or stops are provided and

are suitable to receive glass thickness.

(5) Windows are set plumb, square, and level in alignment.

(6) Windows have provision for suitable anchorage and it’s

provided during installation, windows are adequately braced

where built in.

(7) Finish is protected and maintained during and after

installation.

(8) Windows are installed to be weather tight.

(9) Dissimilar metals are isolated.

(10) Windows are properly adjusted for operation before

glazing.

(11) Cleaning of metal and glass is properly performed.

(12) Screens of type, mesh and size are provided.

c. Hardware and Specialties

(1) Hardware is installed in accordance with manufacturer’s

templates and instructions.

(2) Finishes are as required and finishes match in each

area.

(3) Hardware is removed and/or protected during painting and

cleaning operations.

(4) Recommended order or inspection:

a. In storage room before installation.

b. Door butts and hinges during and after installation.

c. Door closers after installation.

Quality Control Checklist Examples

11 Enclosure (5)

d. Doorstops, holders and push, pull, and kick-plates

after installation.

(5) Mortise-type hinges are mortised flush.

(6) Lock-set cylinder cores are installed with tumbles up.

(7) Observe operation of closers as soon as possible after

installation for proper operation, silent closing and smooth

operation. Panic devices latch properly.

(8) Closers are adjusted after air moving system is

operational.

(9) Every door is provided with a doorstop to protect doors,

walls and hardware.

(10) All hardware is complete and with required type and

number of screws, bolts and fastening devices properly

installed.

7. Finishes

a. Gypsum Drywall

(1) Stud spacing is as required. Studs are doubled-up at

jambs. Nailers/sleepers are in place.

(2) Studs are securely anchored to walls and columns and

fastened to securely anchored floor plates.

(3) Location, layout and plumb of framing system is

verified.

(4) Metal studs are secured with proper fasteners. Washers

will be used for bottom plate and cuts are properly painted

before gypsum is hung.

(5) Wood materials are sufficiently dry to avoid “nail

popping” due to shrinkage.

(6) Wallboard type, thickness and length are as required.

Verify if horizontal or vertical application is to be

required.

(7) Wallboard is not erected until building is closed in.

(8) Wallboard is held up from floor 3/8 inch minimum.

(9) Wallboard is installed with staggered application.

(10) Nailing/screwing or fastening performed as required.

Quality Control Checklist Examples

12 Enclosure (5)

Begin nailing from center outward, paper surfaces not

broken, sheets not driven together, etc.

(11) Check for excessive piercing or jointing.

(12) Tapping system is as required; observe number of coats,

feathering out 12” to 16”, check for high spots and dimples.

b. Tile

(1) Wall tile is set straight, plumb, perpendicular and with

uniform joints. Design is per plan/spec.

(2) Accessories are provided and firmly anchored.

(3) Walls are installed before floors.

(4) Floor tile slopes to drains.

(5) Proper type of grout and/or sealant is used.

(6) Tile/grout coloration is consistent.

(7) Proper trim shapes are provided and used as required.

(8) Tile pattern is correct as per plan/spec.

(9) Layout starting points are correct.

c. Suspended Ceiling Systems

(1) Layout of system is coordinated with rates and work

crews to allow adequate workspace and avoid interference.

(2) Hangers are of proper material and spacing.

(3) Perimeter and edge conditions are provided and installed

as required. Joint treatment is consistent.

(4) System is installed and adjusted in true alignment, even

and level.

(5) If more than one lot of tile is used for one area,

ensure tiles are taken from several packages for random

distribution.

d. Resilient Flooring

(1) Type, size, thickness, pattern, and color of materials

are as required.

Quality Control Checklist Examples

13 Enclosure (5)

(2) Primer, adhesive, or cement is as required.

(3) On slabs, surface is free of cracks, holes, trowel

marks, and other defects. Surface primed if required.

(4) On slabs, all patching, grinding and correction of

defects is performed before installation. All areas are

clean, dry, and hard.

(5) Floor material is installed in proper sequence to

minimize damage by other crews.

(6) Direction of tile is as specified. Layout is as

specified, allow ½ tile minimum at border.

(7) Joints and seams are tight and level.

(8) Excess adhesive material and stains are removed

immediately after installation.

(9) Temporary protective cover is provided if required.

e. Painting

(1) Color schedule is complete and understood.

(2) Surface to receive paint is dry. Damp (not wet)

surfaces are allowed for water thinned paints.

(3) Surfaces to receive paint are properly prepared. Holes

filled and sanded, pitch pockets and knots sealed.

(4) Protection for adjacent areas, surfaces and items are

provided.

(5) Required number of coats is provided.

(6) Texture and method of application is understood.

(7) Painting is done in a neat and workmanlike manner.

(8) No runs, drops, brush marks, color variation, etc. are

permitted.

(9) Curing time between coats is provided.

(10) Hard to get at places are painted.

f. Cabinets

(1) Blocking is provided during framing to mount cabinets.

Quality Control Checklist Examples

14 Enclosure (5)

(2) Visually inspect product for correct finish.

(3) Doors are properly fitted. Countertops are per finish

schedule.

Enclosure (6)

Unit ?? PREPARATORY PHASE CHECKLIST (CONTINUED ON SECOND PAGE)

Specification

Section:

Date:

Project No. Definable Feature of Work: Schedule Activity

No.

Index No.

Personnel

Present

Name Position Company

Submittals

Review submittals and/or submittal register. Have all submittals been approved? Yes No

If no, what items have not been submitted?

Are all materials on hand? Yes No If no, what items are missing?

Check approved submittals against delivered material. (This should be done as material arrives.)

Comments:

Material

Storage

Do materials on hand meet contract drawings and specifications? YES NO If no, what

discrepancies are present?

Are materials stored properly? Yes No If no, what action is taken?

Tools Are necessary tools on hand to complete activity? Yes No If no, what action is taken?

Is working condition of tools adequate to complete activity? Yes No If no, what action is taken?

Specifications

Review each paragraph of specifications.

Discuss procedure for accomplishing the work.

Clarify any differences.

Preliminary

Work &

Permits

Ensure preliminary work is correct and permits are on file. If not, what actions are taken?

N/A

2 Enclosure (6)

UNIT ?? PREPARATORY PHASE CHECKLIST

(CONTINUED FROM FIRST PAGE)

SPEC SECTION DATE

CONTRACT NO DEFINABLE FEATURE OF WORK SCHEDULE ACT NO. INDEX #

TESTIN

G

IDENTIFY TEST TO BE PERFORMED, FREQUENCY, AND BY WHOM.

WHEN REQUIRED?

WHERE REQUIRED?

REVIEW TESTING PLAN.

HAS TEST FACILITIES BEEN APPROVED?

SAFETY

ACTIVITY HAZARD ANALYSIS APPROVED? YES NO

REVIEW APPLICABLE PORTION OF EM 385-1-1.

MEETIN

G COMMENTS

NAVY PWD/ROICC COMMENTS DURING MEETING.

OTHER ITEMS O

R

REMARKS

OTHER ITEMS OR REMARKS:

QC MANAGER DATE

Enclosure (7)

INITIAL PHASE CHECKLIST

CONTRACT NO DEFINABLE FEATURE OF WORK

PERSONNEL PRESENT GOVERNMENT REP NOTIFIED______ HOURS IN ADVANCE YES NO

NAME POSITION COMPANY/GOVERNMENT

PROCEDURE

COMPLIANCE IDENTIFY FULL COMPLIANCE WITH PROCEDURES IDENTIFIED AT

PREPARATORY, COORDINATE PLANS,SPECIFICATIONS, AND SUBMITTALS. COMMENTS:

PRELIMINARY

WORK

ENSURE PRELIMINARY WORK IS COMPLETE AND CORRECT. IF NOT WHAT

ACTION IS TAKEN?

WORKMANSHIP

ESTABLISH LEVEL OF WORKMANSHIP. WHERE IS WORK LOCATED?

IS SAMPLE PANEL REQUIRED? YES NO WILL THE INITIAL WORK

BE CONSIDERED AS A SAMPLE? YES NO (IF YES, MAINTAIN IN PRESENT CONDITION AS LONG AS POSSIBLE AND DESCRIBE LOCATION OF SAMPLE)

SOLUTI

ON

RESOLVE ANY DIFFERENCES. COMMENTS:

CHECK

SAFETY

REVIEW JOB CONDITIONS USING EM 385-1 AND JOB HAZARD ANALYSIS COMMENTS:

OTHER OTHER ITEMS OR REMARKS

Enclosure (8)

DAILY

QUALITY CONTROL

INSPECTOR’S REPORT

Route to Initial Date Remarks

S3

S3C

S3QC

00S

Prime

Sub

Date: Time: Project No.: Report No.:

Prime Co.: Project Title:

Sub Co.: Weather:

Supervisor: Inspector:

Activity Rate Description of work performed

Activities Started: Activities Completed:

QC Meetings Held: Yes No

Construction Inspection Plan Items Checked: Results:

Delays Safety Hazards Present:

Remarks

Materials

On behalf of the government I certify that all work is IAW the drawings and specifications.

Project Supervisor Quality Control Inspector Quality Control Branch Head

Dist: 1. ROICC/FEAD 2. QC File via S3 3. Prime Contractor 4. Crewleader

2 Enclosure (8)

The following explanation and information is provided for completion of the Quality Control Report.

a. Date: Self-explanatory.

b. Time: Self-explanatory.

c. Inspector: The name and rate (or rank) of the individual filling out the report.

d. Report Number: Start and maintain a numerical system for each project. If two or more visits are conducted in one day’s time, fill out a report and number each time an inspection is made.

e.Project Supervisor: This will be the job supervisor, the person directly responsible for the particular project.

f. Project Number: Self-explanatory.

g. Project Title and Location: Self-explanatory.

h. Prime Company: This is the company assigned as the prime contractor. In the case of Det/DFT, the Det/DFT is the prime contractor.

i. Sub Company: Self-explanatory.

j. Weather Conditions: Self-explanatory.

k. Preparatory Section: Lists Construction Activity Number and Definable Feature Of Work (DFOW) of Preparatory Phase activities started on this days report.

l. Initial Section: Lists Construction Activity Number and Definable Feature of Work (DFOW) of Initial Phase activities started on this days report.

m. Follow-Up Section: Lists Construction Activity Numbers, Description of Work performed for Follow-Up phases of each Definable Feature of Work to include specifications references, locations, etc.

n. Material Received Section: Material received since last QC inspection only. The construction inspector has the responsibility of checking on-site materials. A remark will be made in this block about material compliance with plans and specifications, proper stowage, protection from the elements, etc. If a substitution is made, a statement is required regarding the circumstances leading to the substitution and the authority for making the substitution.

o. Delays/Safety Hazards Present: Anything that creates a delay to the scheduled completion of the project should be recorded here, such as inclement weather, transportation of materials, equipment breakdowns, etc. List specific safety hazards that require correction.

p. Remarks: This is the catch-all-block. Record the Construction Activity Number, Crew Members assigned to the activity and the description of work performed. Any item of particular interest is recorded here. In this block, tell how it is being done, site conditions, job conditions, quality of work (good, bad, acceptable), and any items found unsatisfactory. Briefly explain what action was taken or will be taken to correct the deficiencies.

q. Description of Work Performed: Do not write down the name of the construction activity, give the actual description of

3 Enclosure (8)

the work that is being performed (i.e. hanging drywall, taping drywall, applying finish coat of compound to drywall, etc.).

r. Percent Complete: Previous WIP% complete and Current WIP% complete for the construction activity as reported to the prime company on project SITREP.

s. Signatures: Self-explanatory

t. Routing Block: This area of the QC Report is designated for internal battalion routing comments as well as ROICC Quality Assurance Representative remarks.

Enclosure (9)

Enclosure (11)

FIELD ADJUSTMENT REQUEST (FAR)

FAR Number: Page_______ of_______

Project Number: Project Title:

Submitted By: Date:

Description of and reason for request: (include drawing and sheet numbers

and attach drawings as necessary for description)

Route

to:

Approved:(In

itial)

Disapproved:(I

nitial)

Date: Estimated Additional Cost:

Prime

Co.

QC Estimated Additional

Mandays: Eng.

S3

ROICC As

Built:____________Date:_____ROICC

Signature:__________________________________

(Initial)

Notes: 1. Route original and 3 copies to ROICC.

2. ROICC returns original and 2 copies.

Enclosure (12)

LIST OF DEFINABLE FEATURES OF WORK (DFOW) PREPARATORY MEETING DATE INITIAL MEETING DATE

SPEC SECTION

SCHEDULE ACTIVITY ID DESCRIPTION PLANNED ACTUAL INITIALS PLANNED ACTUAL INITIALS

16200 Rough Electrical 22JAN09 22JAN09 23JAN09 23JAN09

09220 Hang Drywall Unit 4 30JAN09 22JAN09

09800 Apply Text Coat Unit 3

09810 Apply Text Coat Unit 4

10600 Install Cabinets Unit 3

10610 Install Cabinets Unit 4

16700 Finish Electrical

15110 Finish Plumbing

08200 Install Doors and Closets

09700 Install Laminate Flooring Unit 3

09710 Install Laminate Flooring Unit 4

Enclosure (13)

From: Commanding Officer, U. S. Naval Mobile Construction Battalion XXXX

To: Commander XXXXXXX Naval Construction Regiment

Subj: DISPOSITION OF PROJECT DOCUMENTATION ICO (Enter project number and title)

Ref: (a) COMFIRSTNCDINST 4355.1A

1. The subject project was completed (Enter Completion Date) and the prescribed

project package archive period has elapsed. In accordance with reference (a), request

disposition guidance for the project documentation.

2. XXXXXXXX is the command point of contact and can be reached at XXXXXXXXX.

J. R. WAYNE