COMBINED HEAT AND POWERLessons Learned from the Implementation of Projects Across the Country
Kevin Fox, PE, CEM | Principal, Jacobs Energy & Power Solutions
![Page 2: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/2.jpg)
2JACOBS 2
Background
• Extensive topic
• Perspective from:
– Designing and implementing for 10+ years
– Successes
– Bruises
– Scores of flameouts…
• Not CHP 101
• Addressed toward private CHP, not utility
• Names changed to protect the guilty
![Page 3: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/3.jpg)
3JACOBS
Lesson #1CHP is not for everyone!
Industrial Enhanced Oil Recovery
20 MW CHP
![Page 4: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/4.jpg)
4JACOBS 4
CHP is Not for Everyone
Big Idea
• Understand what is driving your project
• Accept that the right answer might be:
– Maybe later
– NO
– NEVER!
Words of Wisdom
• If all your friends jumped off a bridge,
would you jump too? – Your Mother
![Page 5: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/5.jpg)
5JACOBS 5
CHP is NOT:
• A means to beat your utility at their
own game
– Frustration with your utility is a poor
motivating force
– The utility will always win, one way or another
• Standby charges
• Departing load charges
• Interconnection fees
• Time (they dictate this)
• Always the cleanest form of electricity
– Comparisons can be confusing
![Page 6: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/6.jpg)
6JACOBS 6
CHP is NOT:
• A universal solution
– Every system is unique
– Beware of keeping up with the Jones’
• The California Highway Patrol
– Understand your audience
– Understand their motivation
• 95% of time = $$$
• Fast, cheap or easy!
– See remaining lessons…
![Page 7: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/7.jpg)
7JACOBS 7
CHP might be right when:
• Electricity is costly, fuel is cheap
• Coincident thermal and electrical demands
• Consistent thermal demand baseline
• Coal is a target
– Carbon valuation?
• Resiliency is in play
• Financial and policy incentives exist
![Page 8: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/8.jpg)
8JACOBS 8
Application
Case Study
• Client 1
• Client 2
• Client 3
Application
• Understand project drivers, opportunities
• Seek qualified assistance to advance development
• Apply Lesson #2
![Page 9: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/9.jpg)
9JACOBS
Lesson #2CHP projects require
intense due diligence!
The University of Texas at Austin
32 MW CHP
![Page 10: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/10.jpg)
10JACOBS 10
CHP Projects Require Intense Due Diligence
Big Idea– EARLY is when to do the
project right
– Do your homework
– Ask the right questions
– Be realistic with input and results
Words of Wisdom– Give me six hours to chop down a
tree, and I’ll spend the first four hours sharpening the axe. – Abraham Lincoln
![Page 11: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/11.jpg)
11JACOBS 11
Invest in a Rigorous and Detailed Study
• Detailed thermodynamic model
– Quality (hourly, metered) data
– Caution re: future projections
– Explore and optimize:
• Economizers
• Inlet air cooling
• Condensate pre-heaters
• Low grade heat recovery
• Water usage
![Page 12: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/12.jpg)
12JACOBS 12
Invest in a Rigorous and Detailed Study
• Understand requirements of finance department
• Sensitivities
• Value for carbon/GHG?
• Full project cost– Construction
– Permitting
– Utility interconnect
– Design
– Existing conditions
– Permits
– Owner contingency
– Commissioning
– Training
– Project
management
![Page 13: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/13.jpg)
13JACOBS 13
Application
Case Study
– University of Minnesota
• LCC Savings - $94M
• GHG Savings – 35,700 tons annually
– Redacted Client(s)
• Growth into system size
Application
– Understand financial metrics necessary for approval
– Growing into a project is risky
– A screening does not a project make
![Page 14: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/14.jpg)
14JACOBS
Lesson #3CHP projects take time. LOTS of time.
Longer than you expect. Plus more.
University of Oklahoma
15 MW CHP
![Page 15: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/15.jpg)
15JACOBS 15
CHP Projects Take Time
Big Idea
– Understand the steps of
developing a CHP opportunity
– Have reasonable expectations
– You are not in control
Words of Wisdom
– Overnight success stories take
a long time. – Steve Jobs
![Page 16: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/16.jpg)
16JACOBS 16
Application
Case Studies
Application– EPA permitting = 9-12 months
– ISO permitting = 9-12 months (before paralleling)
– Set realistic expectations for all stakeholders
– Time = $$$
– Beware of project fatigue
![Page 17: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/17.jpg)
17JACOBS 17
Steps for Development
Idea Approval Design Construction Closeout
![Page 18: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/18.jpg)
18JACOBS
Lesson #4Design and coordination of systems.
Beyond the power island.
Texas A&M University
43.5 MW CHP
![Page 19: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/19.jpg)
19JACOBS 19
Design and Coordination of Systems
Big Idea
• Selection and Optimization of the Power Island is important
• So is everything else…
• Pre-purchase is a must
Words of Wisdom
• The whole is more than the sum of its parts. – Aristotle
![Page 20: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/20.jpg)
20JACOBS 20
Design Tips
• LIDAR scans in existing plants
• Plant interface with existing systems– Condensate return
– Controls
• Consider early control system integrator involvement– Efficient design
– Integration of vendor systems to plant DCS
• Turbine foundation design - dynamic– ACI 351.3R, Ch. 4 – Analytical Methods
for Calculating Soil Impendence
![Page 21: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/21.jpg)
21JACOBS 21
Design Tips
• Specifications and vendors
– Plan around standard options
– Controls interface
• ISO/FERC regulations
• Air intakes
– Corrosion
– SCR reaction
• Water treatment coordination
• Hazardous location requirements
![Page 22: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/22.jpg)
22JACOBS
Lesson #5CHP plants don’t have to be ugly.
But don’t make them pretty first.
University of California Santa Cruz
5 MW CHP
![Page 23: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/23.jpg)
23JACOBS 23
Plant Aesthetics
Big Idea
– The engineer gets to drive!
– Think from inside to out
Words of Wisdom
– Beauty is only skin deep. But ugly goes
clean to the bone. – Dorothy Parker
![Page 24: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/24.jpg)
24JACOBS 24
Design Tips
• CHP = Engineered System– Start with PFD, not rendering
– Engineering led
– Architecturally supported
• Design from the inside out– Plan around largest equipment
– Stacks, air intakes, vents, rooftop equipment
– Electrical gear
• Single source
• Remember the operators!
![Page 25: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/25.jpg)
25JACOBS 25
Application
Case Study
– University of Oklahoma
– University of Minnesota
Application
– Engineering first
– Safe and functional second
– Aesthetics third
![Page 26: COMBINED HEAT AND POWER - District Energy](https://reader031.fdocuments.us/reader031/viewer/2022020706/61fd424c56d5981d92737bf6/html5/thumbnails/26.jpg)
26JACOBS
Other Lessons:6. CHP plants and safety.
7. Natural gas compressors. You don’t want one.
8. Issues with electrons.
9. Project delivery methods; choose wisely.
10. Your contractor probably hasn’t built one of these before.
11. CHP projects are tough to commission. But worth it every time.
12. Train your operators!
Oregon State University
6.5 MW CHP