Collaboration meetingMaiori
June 4th , 2007
Spokesperson reportYves Déclais
today status: Electronic Detectors Brick production and detector filling Outcome from the committees and CNGS schedule OPERA sensitivity updated
Conclusions
![Page 2: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/2.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 2
1. Electronic Detectors :
• all electronic detectors installed • commissioning completed
( except HPT/SM2 and VETO : in progress )• DAQ stabilized and the Virtual Control Room system operative• Electronic detectors Analysis Software stabilized
( except for the HPT )
![Page 3: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/3.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 3
HPT installation completed
![Page 4: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/4.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 4
VETO installation completed
![Page 5: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/5.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 5
2. Brick Production and Detector Filling
![Page 6: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/6.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 6
Detector filling in progress
![Page 7: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/7.jpg)
7
Brick Production and Detector filling schedule
Rate run start (sept 15th) run stop (nov 15th) det. completed
(+21 weeks) (+30 weeks) 150000 bricks
2 drums/day 50680 68986 sept 12th 08(2034 bricks/week) ( 372 evts)* (+70 weeks)
2.5 drums/day 58315 81202 June 20th 08(2543 bricks/ week from june 1st 07) ( 441 evts)* (+58 weeks)
3 drums/day 59334 86802 May 2nd 08(3052 bricks/week from sept 1st 07) ( 465 evts ) * (+41 weeks)
* : number of CNGS events in the bricks for 1019 pot
As discussed at the Funding agency meeting and the committees
![Page 8: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/8.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 8
Detector filling
2 drums/day achieved in a steadily mode for the BAM and the BMS
BUT:• lack of shifters from the collaboration !• lack of funds (and administrative bottlenecks)
+ to insure the needed upgrade for the BAM in due time+ to hire the needed manpower ( BAM & BMS) in due time
![Page 9: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/9.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 9
3. Outcome of the committees
• SPSC (17/04/07) :
SPSC supports a commissioning CNGS beam in 2007 (2-3 weeks) which will enable OPERA to test the experiment further. A decision on a physics run has been delayed to the June 26th SPSC meeting. The brick installation progress reported at that time will be an important piece of information for the discussion.
• LNGSC (18-19/04/07) : no feed back …
![Page 10: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/10.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 10
CNGS commissioning already scheduled ( Hoping horns fixing will be in time ):
• week 38 (1 CNGS cycle)• weeks 39 and 41 (3 CNGS cycles), break during week 40.
![Page 11: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/11.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 11
3. OPERA sensitivity revisitedfinal number of films available:
( 1 box = 36 packs (57 films), 1 brick = 57 + 2 films )
• 24 boxes including each 2030 unrefreshed films 825 bricks• 4409 boxes refreshed at Tono mine
maximum number of bricks : 154,111 ( losses are being investigated ) ~70 % of the initial target mass
• Visit (March 14-17) of the inspector (head of the administration office) from Nagoya University no feedback no funds available in Japan
• Funding Agency Meeting (March 23th) INFN-IN2P3-BMBF-CH-Be: no way for finding extra resources in Europe rely only on the proton intensity increase for sensitivity
recovery
![Page 12: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/12.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 12
OPERA sensitivity : nominal conditions
SK 90% CL(L/E analysis)
Opera nominal
Opera with beam upgrade and 30% bck reduction
Opera, with beam upgrade (1.5)
Opera with 30% bck reduction
90 % CL Sensitivity F&C
4 σ discovery potential
![Page 13: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/13.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 13
SK 90% CL(L/E analysis)
Opera nominal
Opera with 30% target mass reduction
Opera with 50%reduction
90 % CL Sensitivity F&C
OPERA sensitivity : revised conditions
4 σ discovery potential
![Page 14: Collaboration meeting Maiori June 4 th , 2007](https://reader038.fdocuments.us/reader038/viewer/2022103006/56813ad1550346895da2fe4c/html5/thumbnails/14.jpg)
June 4th , 2007 Spokesperson report Yves Déclais 14
Conclusions
Wait for the conclusions of the meeting …