Collaboration and Competition Glenn Ballard AOM 2010 Montreal, Canada

description

Collaboration and Competition. Glenn Ballard AOM 2010 Montreal, Canada. How maintain productive tension between collaboration and competition?. Externally imposed demands Self-imposed goals “Lower the river to reveal the rocks.” (Taiichi Ohno, Chief Engineer, Toyota). - PowerPoint PPT Presentation

Transcript of Collaboration and Competition

Page 1: Collaboration  and  Competition

Collaboration and Competition

Glenn BallardAOM 2010

Montreal, Canada

Page 2: Collaboration  and  Competition

How maintain productive tension between collaboration and competition?

• Externally imposed demands• Self-imposed goals

“Lower the river to reveal the rocks.” (Taiichi Ohno, Chief Engineer, Toyota)

Page 3: Collaboration  and  Competition

2005 CURRENT

Proposed Building Area: 1,298,500 BGSF 914,757 BGSF

Number of Stories (incl. below grade Parking and CUP):

21 18

Total No. of Beds: 620 555

Total No. of LDRs: 24 24

Total No. of ORs: 19 19

Total No. of ER Treatment Rms:

34 34

Loading Dock Location: Access off Post St. Access off Franklin St.

Ambulance Location: Access off Franklin St.

Access off Post St.

Total No. of Parking Spaces:

620 555

90% of the program in 70% of the space.Initial target cost for construction=$911 million, 14% below market

Page 4: Collaboration  and  Competition
Page 5: Collaboration  and  Competition

Innovation – Making Creativity and Learning Safe

The “Patient Boom” – Combined Patient Lift and Medical Boom