Cogeneration & Carbon Management - CMC Research...

18
January 28 th and 29 th , Calgary, Alberta, Canada Cogeneration & Carbon Management Paula McGarrigle Managing Director Solas Energy Consulting Inc. Suite 119, 2137 33 Avenue S.W. Calgary Alberta T2T 1Z7 T: (403) 542-9463 E: [email protected] Key Issues in the Design of Carbon Management Policies and Regulations in Alberta

Transcript of Cogeneration & Carbon Management - CMC Research...

January 28th and 29th, Calgary, Alberta, Canada

Cogeneration & Carbon Management

Paula McGarrigle Managing Director Solas Energy Consulting Inc. Suite 119, 2137 33 Avenue S.W. Calgary Alberta T2T 1Z7 T: (403) 542-9463 E: [email protected]

Key Issues in the Design of Carbon Management Policies and Regulations in Alberta

Ove

rvie

w

• History of Cogeneration in Alberta

• Drivers behind Cogeneration development in Alberta

• Economics of Cogeneration

• The future of Cogeneration in Alberta

2 Solas Energy Consulting

Defining Cogeneration

Cogeneration produce electricity and steam

Facilities often integrate waste energy into the production of power or steam. Facilities are built to either match steam or match power requirements.

Solas Energy Consulting 3

Standalone

Integrated

TransCanda Carseland

Alberta has experienced significant growth in Cogeneration 4,588 MW of installed capacity ~ 30% of total generation capacity

Oil Sands development & Cogen Represents 67% of total installed Cogen capacity

Other applications for Cogen in AB Chemical industry, conventional oil and gas, pulp and paper as well as hospitals, educational institutions

Co

gen

era

tio

n In

Alb

ert

a

Solas Energy Consulting 4

Alberta’s Cogen focused on Oil Sands in the North East

Solas Energy Consulting 5

Central 12%

Edmonton 1%

NE 78%

NW 2%

South 7%

Geographic Area

0

100

200

300

400

500

600

700

800

900

1000

Sun

cor

ATC

O

Syn

cru

de

Tran

sCan

ada

Do

w C

hem

ical

s

Nex

en

Me

dic

ine

Hat

CN

RL

MEG

Imp

eri

al O

il

Air

Liq

uid

e

Ce

no

vus

Un

iver

sity

of

Alb

erta

She

ll

Alt

aGas

Sou

ther

n P

acif

ic

Co

nn

ach

er

Talis

man

Un

iver

sity

of

Cal

gary

Pe

nn

We

st

SAIT

Cogeneration Capacity (MW) by Owner

Ow

ner

ship

& L

oca

tio

n o

f C

oge

n

21 owners

REF: AESO

REF: AESO

Solas Energy Consulting 6 Dri

vers

fo

r C

oge

n

Cogen driven by 3 main factors

1. Regulatory changes,

2. Improved economics, and

3. Demand growth requiring reliable power sources

225

475

768

1037.5 1133.5

30.6

322.6

902

16 35 100 133 294

164 185

531

210

0 160

60

342

101 68 12

399

101

603

1505

2247

2963

3836

4315

4588

19

75

19

76

19

77

19

78

19

79

19

80

19

81

19

82

19

83

19

84

19

85

19

86

19

87

19

88

19

89

19

90

19

91

19

92

19

93

19

94

19

95

19

96

19

97

19

98

19

99

20

00

20

01

20

02

20

03

20

04

20

05

20

06

20

07

20

08

20

09

20

10

20

11

20

12

20

13

20

14

Additions (MW)

De

re

gu

latio

n

Alberta Upgrading Capacity (MBPD)

Alberta SAGD Production (MBPD)

Class 43.2

SGER

Alberta Cogeneration (MW)

#1 Changing Regulatory Landscape

Electricity market deregulation, and “industrial site designation” were major drivers

#2 Improved Economics

Solas Energy Consulting 8

ATCO - Muskeg River Plant

Federal Tax Changes Accelerated capital cost depreciation; Class 43.2 - depreciation rate increased to 50% until 2020.

High Heat Rates Alberta’s market heat rates have been above cogeneration physical heat rate and therefore cogeneration facilities have generated positive cash flow.

Industrial Site Designation Reduction in the ancillary service costs associated with power generation or load

Alberta Specified Gas Emitters Regulation (SGER) – Emissions Performance Credits • SGER compares stand alone cogeneration to a reference technology. The use of the

reference technology method has resulted in EPCs for cogeneration facilities. • Combined Cycle electricity plant is compared to a target of 0.418 tonnes CO2e/MWh. • No reduction target is placed on the emissions associated with the electricity generated. • The baseline for heat calculation assumes an 80% efficient boiler.

#3 Demand Growth & Reliability

Solas Energy Consulting 9

Cogen concentrated in industries with high power demand

Oil Sands upgrading, Steam Assisted Gravity Drainage (SAGD) and the chemical industry in Alberta have significant requirements for steam and power. SAGD has experienced exponential growth CAGR of 34.2% Oil Sands upgrading has more than doubled since 2001

ATCO Scotford Cogeneration Facility

Eco

no

mic

s o

f C

oge

ner

atio

n

10 Solas Energy Consulting

$55

$84$92

$114

$157$163

$172

$44

$68$74

$92

$127$132

$139

$0

$20

$40

$60

$80

$100

$120

$140

$160

$180

$200

Cogen Wind Coal CCGT SCGT CoalwithCCS Hydro

Levelized

Cost($/M

Wh)

LevelizedCost

FirstYearCostofPower

Cogeneration has the lowest levelized costs compared to alternatives in Alberta. (2016) Levelized cost of energy from a new cogeneration facility is higher than the Alberta forward power pool price.

Solas Energy Consulting – Wind Vision Technical Overview Report

LEVELIZED COST OF POWER

Eco

no

mic

s o

f C

oge

ne

rati

on

11 Solas Energy Consulting

• Carbon revenue is positive (reducing levelized costs) however is not a significant factor.

• ISD’s calculate their tariff using “net generation” and this creates savings compared to a standalone generation facility.

-20

30

80

130

180

230

Wind - CF=40%

Simple C.- CF =20%

Comb. C.- CF =50%

Cogen -CF =95%

Coal - CF=93%

Coal wCCS - CF

=90%

Hydro -CF =50%

Lev

eli

zed

Co

st (

$/M

Wh

)

Levelized Cost of Power (2016)

Taxes

Repower Cost

Capex

CO2 Compliance Costs

Generator Losses

Fixed and Variable O&M

Fuel Costs

Offset Revenue

Solas Energy Consulting – Wind Vision Technical Overview Report

LEVELIZED COST OF POWER - Components

Oil Sands Growth Alberta’s cogeneration development is indirectly

dependent on Canada’s climate change regulatory regime, because Oil sands growth is dependent on market access that is linked to climate policy.

Transmission Availability/Reliability/Cost Northern AB could be susceptible to transmission contingencies. Delay in the Fort McMurray to Edmonton 500 kV Transmission line may increase the interest in self-generation, with cogen preferred. Transmission costs and therefore DTS charges are on the rise. This may stimulate additional cogeneration ISDs to reduce the cost of delivered power.

Regulatory Treatment Potential changes in the treatment of cogeneration at the Provincial or Federal level may have profound impacts on size and continued investment in cogeneration.

Air Quality Regional air shed limitations (Lower Athabasca) may impede extensive cogeneration development. Additional cogeneration in the region may tax the currently strained air shed.

Futu

re o

f C

oge

n in

AB

Solas Energy Consulting 12

603

2247

2963

3836

4315

5290

5885

6690

1975

1977

1979

1981

1983

1985

1987

1989

1991

1993

1995

1997

1999

2001

2003

2005

2007

2009

2011

2013

2015

2017

2019

2021

2023

2025

2027

2029

2031

Addi ons(MW)

Alberta Cogeneration (MW)

AESO Long Term Outlook

(2012)

Futu

re o

f C

oge

ne

rati

on

in A

B

13 Solas Energy Consulting

AESO Long Term Outlook (2012)

The Oil Sands Developers Group 2011 Co-Gen Survey resulted in an estimate of 3,500 MW of additional cogeneration by 2021. (Estimate is higher than the AESO)

Cogeneration capacity additions by 2022 are expected to total 6,200 MW or 29 per cent of supply mix. – Same as current mix.

Co

gen

& C

arb

on

Co

mp

lian

ce

14 Solas Energy Consulting

Cogeneration treatment under SGER is critical for Alberta compliance Cogeneration represents approximately 40 per cent (14,850 kT/39,930 kT) of the total avoided emissions since the SGER program was created.

ALL FACILITIES COMPLIANCE Alberta’s Carbon Compliance

Future AB SGER Treatment

• Current treatment uses the following as baseline. – 0.418 tonnes CO2e/MWh (Assumption for

Electricity) – 80% boiler efficiency

• Discussion on changing the assumptions – 0.375 tonnes CO2e/MWh – 85% boiler efficiency

• Impact – Reduced compliance or “avoided emissions” – Reduction in economics of cogeneration.

Solas Energy Consulting 15 Co

gen

& C

arb

on

Co

mp

lian

ce

Co

gen

& C

arb

on

Co

mp

lian

ce

16 Solas Energy Consulting

Nexen – Balzac Power Station

Federal Greenhouse Gas Emissions Regulations

• Cogeneration is considered a cross cutting issue since the technology is applied in multiple sectors.

• Treatment, or reduction required may vary by the type of industry that cogeneration is a part of.

• May result in cogeneration facilities also having an obligation to reduce emissions.

Key

Qu

esti

on

s to

Co

nsi

der

17 Solas Energy Consulting

• Are EPC’s critical for incenting cogeneration in the Oil Sands industry?

• Is cogeneration business as usual?

• If cogeneration is considered business as usual what are the implications for SGER and cascading ramifications such as oil sands economics and Alberta’s greenhouse gas emission reduction plan?

• Does the new Lower Athabasca Regional Plan (“LARP”) and pending federal air quality regulations restrict CCGT facilities as viable alternatives for oil sands upgrading and SAGD?

• Should Alberta policy makers

consider emphasizing higher efficiency heat and power generation technology? - Fuel cells?

• Should renewable energy

integration in oil sands be incented through policies directed at further reducing air quality and GHG emissions?

Recommendations

Solas Energy Consulting 18

Key

Qu

esti

on

s to

Co

nsi

der

• Integrity of the system is paramount.

– Evaluate if cogeneration meets business as usual.

– If so, look to include cogeneration into the baseline.

– If not, ensure baseline used for cogen is representative.