Construction Timeline Update
• 30,000 square-foot Atrium (Labor Day 2013)
• 40,000 square-foot Grand Ballroom and 25,000
square-feet of new meeting rooms (Labor Day ‘13)
New Food Court/Cyber Café
8,000 square foot kitchen with tasting room
• Level 3 Function Space and Offices (12/2013)
• Two exterior video walls (12/2013)
• Project completion early 2015