CO2 transfer lines on YB0

9
CO2 transfer lines on YB0 5/16/13 1 N.Bacchetta o Review held on the 17 th of April was successful and this project has been endorsed as baseline. Thanks to all of you for this effort ! o Committee report outlined a few issues. In particular: a. Examining the possibilities of connecting the independent vacuum of the two jacketed lines at the connection box. b. It is much preferable if the vacuum jacketed transfer line can be continued into the inside of the vacuum tank. c. The currently scheduled windows for verifying design and for installation are too late/short. The Master schedule and coherent

description

CO2 transfer lines on YB0. Review held on the 17 th of April was successful and this project has been endorsed as baseline. Thanks to all of you for this effort ! Committee report outlined a few issues. In particular: - PowerPoint PPT Presentation

Transcript of CO2 transfer lines on YB0

Page 1: CO2 transfer lines on YB0

N.Bacchetta 1

CO2 transfer lines on YB0

5/16/13

o Review held on the 17th of April was successful and this project has been endorsed as baseline.

Thanks to all of you for this effort !

o Committee report outlined a few issues. In particular: a. Examining the possibilities of connecting the independent

vacuum of the two jacketed lines at the connection box.b. It is much preferable if the vacuum jacketed transfer line can

be continued into the inside of the vacuum tank. c. The currently scheduled windows for verifying design and for

installation are too late/short. The Master schedule and coherent placement of order/delivery are to be adapted accordingly in cooperation with TC. …the revision should include reasonable contingency.

Page 2: CO2 transfer lines on YB0

N.Bacchetta 2

Connecting vacuum at the intermediate junction box

o Seems do-able within the envelope of the present junction box

o It will be an option in the new offer from DeMaCo

5/16/13

PP1 -6 intermediate junction box

Page 3: CO2 transfer lines on YB0

N.Bacchetta 3

Pipes ending inside the vac-tank

o Top sectors have no issues.

5/16/13

PP1 +5

Page 4: CO2 transfer lines on YB0

N.Bacchetta 4

PP1+5CPP1+6A

EB/HB 5/6Pixel InletCold Dry Gas InletThermal Screen InletThermal screen Outlet

+5B

Vactank surface

Vactank surface

Vactank surface

Vactank surface

5/16/13

PP1 +5

Page 5: CO2 transfer lines on YB0

N.Bacchetta 5

CO2 transfer lines on YB0

5/16/13

PP1 +14C is the most challenging

Page 6: CO2 transfer lines on YB0

Before installation of YE-4 seems the best option (a few days staggering with +Z installation window):

1. Skip task “Install 2 sets of CO2 pipes (including supports) on -Z” (no gain) 2. Skip task “YB0- restore vac-tank environment” or partially skip it (gain of up to 2 weeks) 3. Scaffolding from YE-1 removed (currently Dec 6, 2013)4. Move YBs –Z away from vac-tank (new), (loss of 2 days)5. Install new CO2 pipes –Z (new), (loss of 5 days)6. Restore vac-tank environment, (loss of up to 2 weeks)7. Move YBs –Z on vac-tank and lock (new), (loss of 2 days)8. At this point back to same sequence as current schedule starting with “Move YE-1-2-3 towards IP”,

3 days

June July August September October November December January February

3 10 17 24 1 8 15 22 29 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24

YB0+ outside solenoid accessible

YE+4,YE+1,CCM+Z,VAX+Z

Maintain Endcap+Z (ME11,RE+,ME+)

YB0+ (DT,HO,RPC)

YB0+ restore vac-tank environment

YB+1 (HO,DT,RPC)

YB+2 (HO,DT,RPC)

YB0- outside solenoid accessible

YB0- (DT,HO,RPC)

YB0- restore vac-tank environment

YB-1 (HO,DT,RPC)

YB-2 (HO,DT,RPC)

YE-4,YE-1,CCM-Z,VAX-Z,GIS,TAS

Maintain Endcap-Z (ME11,RE-,ME-)

Create a later window for installation of CO2 pipes on YB0-

Dates from: CMS_LS1_20130410.mpp

here

2 weeks total lo

ss

Z+ installation (Dec 6)

Page 7: CO2 transfer lines on YB0

N.Bacchetta 7

Where we stand

5/16/13

o Need to finish the technical specifications (now ready to be circulated)

o Need to finalize the end points and specially find a decent solution for PP1 +14

o Agree on a later installation for the –Z endo Once the final offer is received, decide on the

vacuum connection at the junction box.o Define/specify the sample piece for welding

inspection in order to qualify DeMaCo work.

Page 8: CO2 transfer lines on YB0

N.Bacchetta 8

spare

5/16/13

Page 9: CO2 transfer lines on YB0

N.Bacchetta 9

What’s in the CMS LS1 schedule today

1. A window for verifying the 3D model on the vac-tank. June 17 and June 19, 1.5 days per end.

2. A window for installing the full –Z set of pipes, Aug 12, 5 days including test and certification.

3. A window for installing the full +Z set of pipes, Dec 10, 5 days including test and certification.

5/16/13

NB: above dates are obtained by adding 13 working days to the original dates from Dec. 2012 schedule. Subject to changes.