The Wyoming Enhanced Oil Recovery Institute’s
2008 Wyoming EOR/IOR Conference
“CO2 EOR, Reservoir Sweep and CO2 Storage”
Steve Melzer
![Page 2: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/2.jpg)
2
CO2 EOR, Reservoir Sweep and CO2 Storage
• Background and Growth of CO2 EOR
• The Concept of and Experience with Reservoir Sweep
• Incidental Storage of CO2 in EOR
• The Converging Worlds of CO2 EOR and CO2 Storage
![Page 3: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/3.jpg)
3
GROWTH OF PERMIAN BASIN & WORLDWIDE CO2 PROJECTS
1984 - 2008
0
20
40
60
80
100
120
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
YEAR
NO. O
F PR
OJE
CTS
WW Projects PB Projects
Melzer Consulting - 5/08* Ref: O&GJ Biennial EOR Editions & UTPB
BACKGROUND (OF CO2 EOR PROJECT GROWTH*)
* Includes Only CO2 Miscible Floods
![Page 4: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/4.jpg)
…..and Growth Even with Languishing Oil Pricing
GROWTH OF PERMIAN BASIN & WORLDWIDE CO2 PROJECTS1984 - 2004
0
20
40
60
80
1988
1990
1992
1994
1996
1998
2000
YEAR
NO
. OF
PRO
JEC
TS
WW Projects PB Projects
Melzer Consulting - 8/04
WTI Posted Oil Prices - 1988-2000
$0
$10
$20
$30
$40
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
YEAR
OIL
PR
ICES
IN $
/bbl Average
Price = $18.80 (U.S.)
Average Growth > 2 Projects/Yr
![Page 5: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/5.jpg)
5
BACKGROUND (OF CO2 EOR PRODUCTION GROWTH*)
WW & PERMIAN BASIN CO2 EOR PRODUCTION1986 - 2008
0
50
100
150
200
250
30019
86
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
YEAR
CO
2 EO
R P
RO
DU
CTI
ON
- kb
opd
Permian Basin Worldwide
* Ref: O&GJ Biennial EOR Editions & UTPBP t I d t Alli
Melzer Consulting - 5/08
* Includes both CO2 Miscible & Immiscible Floods
![Page 6: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/6.jpg)
HOW BIG IS THE CO2 EOR BUSINESS?
NOV 2005
* Source: Oil & Gas Journal (Mar ’08) and CO2 Flooding Conference (2007)
Annual Production Rev Figures**
U.S. $8.0 billion*
PB $5.3 billion*
* @ $80/bbl
** Does not take into account the NGLs produced from the recycle volumes6
![Page 7: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/7.jpg)
ENHANCED OIL RECOVERY AND CO2 EOR
![Page 8: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/8.jpg)
8
BEYOND PRIMARY (AND WATERFLOODS)
• IMPROVE SWEEP– INFILL DRILLING– PATTERN MODIFICATION– AUGMENTED WATERFLOODING (POLYMER, ETC)– LOW SALINITY WATERFLOODING
• REDUCE WATERFLOOD RESIDUAL– THERMAL (CYCLIC STEAM, STEAM DRIVE, SAGD, FIRE)– CHEMICAL (ALKALINE/POLYMER/SURFACTANT)– MISCIBLE GAS INJECTION
• HYDROCARBON MISCIBLE FLOODING (HCMF)• NITROGEN• CO2
![Page 9: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/9.jpg)
9
EOR METHODS
![Page 10: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/10.jpg)
10
TODAY’S VIEW THE PRODUCING LIFE OF A RESERVOIR
‘IN-FILL’ DRILLING
* Average for San Andres Dolomites (PB)
![Page 11: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/11.jpg)
The Concept of and Experience with Reservoir Sweep
![Page 12: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/12.jpg)
12
WATERFLOODING & SWEEP EFFICIENCY
![Page 13: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/13.jpg)
13
SWEEP EFFICIENCY
WF Swept Area
![Page 14: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/14.jpg)
14
WATERFLOOD RECOVERY
R = Es * (SOi – SORwf ) / SOiSOi = 0.80SORwf = 0.35Es = 0.70
R = .70 * (.80 – .35) / 0.80 = 0.39ROIP (SWEPT REGION ) = 0.70 * (0.45) / 0.80 = 0.39ROIP (UNSWEPT REGION ) = 0.30 * (0.80) / 0.80 = 0.30ROIP (TOTAL) = 0.69
![Page 15: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/15.jpg)
15
SWEEP EFFICIENCY
CO2 Swept Area
WF Swept Area
![Page 16: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/16.jpg)
16
CO2 FLOOD RECOVERY CALCULATIONS MISCIBLE PROJECTS
R = Et * (SOS – SORM )where: R = Recovery FactorSOS = Oil Saturation at Flood StartSORM = Miscible Residual Oil Saturation
Es > Et
R = Et * (SORWF – SORM ) where: SORWF = Waterflood Residual Oil Saturation
![Page 17: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/17.jpg)
17
PRIMARY + WATERFLOOD AND CO2 SWEEP EFFICIENCY
• PRIMARY + WATERFLOOD RECOVERYR = E(p+s) * (SOi – SORwf )E(p+s) = R / (SOi – SORwf )
![Page 18: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/18.jpg)
18
CO2 MISCIBLE FLOODING
EXPECTED RECOVERY
R = ET * (SORwf - SORm ) / SOiSORwf = 0.38 SOi = 0.85SORm = 0.10 ET = 0.35
R = .35 * (.38 – .10) / 0.85 = 0.115
![Page 19: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/19.jpg)
19
PHASE I RESERVOIR SCREENING RULES OF THUMB: CO2 MISCIBLE INJECTION
• PERCENT OF OOIP8 TO 18 (12)
• RATIO – TERTIARY / (P + S)20 TO 35 (25)
• SWEEP EFFICIENCY25 TO 50 (35)
• RATIO – Et / E(P+S)50 TO 60 (50)
![Page 20: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/20.jpg)
20
RULE OF THUMB EXAMPLES (1) EUR FROM CO2 INJECTION
FIELD A FIELD BSWi (% PV) 15.0 23.7SOi (% PV) 85.0 76.3SORwf (% PV) 38.0 26.0(P+S) Target (% PV) 47.0 50.3(P+S) (% OOIP) 41.8 55.2 (P+S) (% PV) 35.5 42.1E(P+S), % 75.6 83.7
![Page 21: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/21.jpg)
21
RULE OF THUMB EXAMPLES (2) EUR FROM CO2 INJECTION
FIELD A FIELD BSOi (% PV) 85.0 76.3SORwf (% PV) 38.0 26.0SORm (% PV) 10.0 10.0Tertiary Target (% PV) 28.0 16.0Tertiary, % OOIP 14.6 10.0 Tertiary, (% PV) 12.4 7.6ET 44.3 47.7ET / E(P+S), % 58.6 57.0
![Page 22: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/22.jpg)
22
RULE OF THUMB EXAMPLE (3) EUR FROM CO2 INJECTION
TERTIARY SUMMARYFIELD A FIELD B
%OOIP (SORwf ) 38.0 26.0ET 44.3 47.7T / (P+S) 35.4 18.1ET / E(p+s), % 58.6 57.0Tertiary, % OOIP 14.6 10.0
![Page 23: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/23.jpg)
23
PRIMARY, WF AND TERTIARY RECOVERY FROM THE W. TX SAN ANDRES EXPERIENCE
BUT BEWARE OF AVERAGES!!
WITH A RANGE OF VALUES OF 8-18%
![Page 24: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/24.jpg)
24
CO2 FLOODING: MISCIBILITY
• FIRST CONTACT• DYNAMIC OR MULTIPLE CONTACT• RESIDUAL OIL FOR CO2 FLOODING• IMMISCIBLE CHARACTERISTICS OF CO2
• WHY CO2 ?• OIL RECOVERY FROM CO2 INJECTION
![Page 25: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/25.jpg)
25
DEFINITIONS OF MISCIBILITY
• Two fluids are "first-contact miscible" if they form only one phase when mixed in any proportions.
• A process that relies on "Developed" or "Multiple-Contact" miscibility is based on the transfer of components between phases to generate mixtures that avoid the two-phase region. Such processes really involve chromatographic separations of components as phases with different compositions flowing at different rates. Displacement processes may be described as:
– Vaporizing Gas Drives– Condensing Gas Drives– Condensing/Vaporizing Gas Drives
![Page 26: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/26.jpg)
26
MISCIBILITY CONCEPTS
![Page 27: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/27.jpg)
CORRELATIONS FOR MINIMUM MISCIBILITY PRESSURE CO2 AND CRUDE OIL MIXTURES
(Selected References)
1. Holm, L.W. and Josendal, V.A. (1974), “Mechanisms of Oil Displacement by Carbon Dioxide,” JPT (Dec 74), pp. 1427-38
2. Holm, L.W. and Josendal, V.A. (1982), “Effect of Oil Composition on Miscible Oil Displacement by Carbon Dioxide,” SPEJ (Feb. 1982), pp. 87-89
3. Yellig, W.F. and Metcalf, R.S. (1980), “Determination and Prediction of CO2 Minimum Miscibility Pressures,” JPT (Jan 1980), pp. 160-168.
4. Johnson, J.P. and Pollin, J.S. (1981), “Measurement and Correlation of CO2 Miscibility Pressures,” SPE paper 9790 presented at the SPE/DOE Enhanced Oil Recovery Symposium, Tulsa, April 5-8, 1981.
5. Alston, R.B., Kokolis, G.P., and James, C.F. (1985), “CO2 Minimum Miscibility Pressure: A Correlation for Impure CO2 Streams and Live Oil Systems,” SPEJ (April 1985), pp. 268-74.
6. Sebastian, H.M., Wenger, R.S., and Renner, T.A.(1985), “Correlation of Minimum Miscibility Pressure for Impure CO2 Streams,” JPT (Nov. 1985). Pp. 2076-82.
![Page 28: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/28.jpg)
28
WHY CO2 ?
• MISCIBLE AT LOWER PRESSURES THAN NITROGEN OR METHANE
• CHEAPER AND MORE PLENTIFUL THAN LPG/ENRICHED HYDROCARBON GAS
• DENSITY (IN DENSE PHASE) CLOSER TO RESERVOIR FLUIDS – OIL/WATER
![Page 29: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/29.jpg)
29
KEY (MINIMUM) REQUIREMENTS FOR CO2 MISCIBLE PROJECTS
• RESERVOIR CHARACTERISTICS– CARBONATES / SANDSTONES– GRAVITY SEGREGATION– STRATIFICATION/FRACTURES– CONTINUITY – WELL SPACING– POROSITY / PERMEABILITY– RESERVOIR THROUGHPUT (INJECTIVITY)– WATERFLOOD PERFORMANCE
![Page 30: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/30.jpg)
IDEALIZED FLOODING
![Page 31: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/31.jpg)
31
Fluid Mobility Issues Can Reduce Recoveries And Increase CO2 Recycling
High Mobility Ratio DisplacementAreal “Breakthrough”
• Initial Radial Flow at Injector, Mobile Oil Bank Develops
• Preferential Flow Paths Encountered, Recovery Diminished
OPTIONS:• WAG Injection Design• Thickening Agents• Selective Injection• Profile Modification
• Cement• Liners
Re: T. Bradley, EOR CM Workshop, Dec 2006
![Page 32: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/32.jpg)
32
HETEROGENEITY* IN A VERTICAL SENSE
* Re: T. Bradley, EOR CM Workshop, Dec 2006
![Page 33: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/33.jpg)
33
HETEROGENEITY IN A HORIZONTAL (AREAL) SENSE
![Page 34: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/34.jpg)
34
![Page 35: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/35.jpg)
35
Fractured Reservoir Model
![Page 36: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/36.jpg)
36
Naturally Fractured Reservoirs
• Can Prove Difficult for Flooding (i.e., “short-circuiting” injector-producer pairs)
• Can be Useful to establish line drive pattern flooding if unidirectional
![Page 37: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/37.jpg)
37
Naturally Fractured Reservoirs
![Page 38: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/38.jpg)
38
Increased Sweep Efficiency from Line Drive Patterns
5-SPOTS LINE DRIVE
![Page 39: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/39.jpg)
Atypical CO2 Flooding
![Page 40: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/40.jpg)
40
IMMISCIBLE CO2 FLOODING
• CO2 Solubility and Oil Swelling– Oil Volume Increase (can be ~50%)– Oil From Dead End Pores– Incremental Oil Below MMP
• Viscosity Reduction (Over that of Water)– Better Injection Rates– Reduces Mobility Ratio– Improves Relative Permeability– Improves Sweep Efficiency
![Page 41: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/41.jpg)
41
CO2 SECONDARY FLOODING
• Poor Waterflood Performance (e.g., Clay Swelling)
• Stratification / Continuity• Poor Water Injectivity• High Connate Water• Viscous Oil• Attic Drive
RULES OF THUMB NOT WELL ESTABLISHED
![Page 42: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/42.jpg)
42
Residual Oil Zones aka Transition Zones
![Page 43: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/43.jpg)
Hess’ Seminole Field Gaines County, West Texas
![Page 44: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/44.jpg)
![Page 45: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/45.jpg)
45
BALANCING THE PATTERNS
• With CO2 , substantial oil can be trapped because the producing well may become uneconomic before the oil bank from the other injectors arrives. Pattern balancing is difficult and conflicts with other stated goals such as maximizing injection.
• In a waterflood, we were able to live with more unbalanced patterns because of the favorable mobility ratio and the relatively low cost of the water.
• Of course, practical compromises must be made.
![Page 46: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/46.jpg)
46
BALANCED INJECTION THE INACHIEVABLE IDEAL (5-SPOT EXAMPLE)
![Page 47: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/47.jpg)
47
PATTERN BALANCING ’REAL’ EXAMPLE
![Page 48: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/48.jpg)
48
MAINTAINING A CONTINUOUS OPTIMIZATION PROGRAM
Regardless of the detail or the quality of the pre- deployment study and the thoroughness of the plan of operation, performance will indicate changes that will be needed. Opportunities may range from the small and simple to major breakthroughs as the result of new learnings and new technology.
Many companies feel “the plan” is fixed and never have learned this lesson
![Page 49: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/49.jpg)
49
MONITORING PROGRAM GOES HAND-IN-HAND WITH THE OPERATING PLAN
• Strong communication between field and office• Pattern injectors and producers in same pay – DA! But…..• Metering and documentation system for injected and produced fluids• Periodic pressure measurements (falloffs and buildups)• Initial and (possibly) followup step-rate tests• Fluid level program for pumping wells• Water quality monitoring• Periodic profile measurements• Pattern balancing program• Program to monitor and adjust WAG ratio and WAG cycles
![Page 50: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/50.jpg)
50
TOOLS (1)
• GRAPHICALe.g., DIMENSIONLESS PLOTS CAN ID PROBLEM PATTERNS
![Page 51: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/51.jpg)
51
TOOLS (2)
![Page 52: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/52.jpg)
52
TOOLS (3)
• SIMULATORS– SOME COMMERCIAL– SOME PROPRIETARY IN-HOUSE
![Page 53: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/53.jpg)
53
CO2 FLOODING RECAP (1)
• PROVEN TO BE TECHNICALLY VIABLE IN MISCIBLE AND IMMISCIBLE RESERVOIR CONDITIONS
• MOST PROVEN OF THE PROCESSES FOR LIGHT OILS
• LOW RELATIVE COST OF CO2 (EXCLUDING TRANSPORTATION - MORE ON THIS LATER)
![Page 54: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/54.jpg)
54
CO2 FLOODING RECAP (2)
• REDUCES REMAINING OIL IN PLACE VERY EFFECTIVELY BUT SWEEPS SMALLER VOLUME DUE TO GAS-LIKE VISCOSITY
• A POOR WATERFLOOD (POOR SWEEP EFFICIENCY) WILL MAKE A POOR CO2 FLOOD
• IF PROLIFERATION OF CO2 SOURCES ARE COMING AND REMOVE (TO A DEGREE) THE OBSTACLES OF DEVELOPMENT OF A PIPELINE NETWORK, THIS WILL COMMERCIALIZE THE:– DEVELOPMENT OF LESS EFFICIENT FLOODS– IMPLEMENTATION OF SLOWER RESPONDING FLOODS
![Page 55: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/55.jpg)
55
KEY REFERENCES
![Page 56: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/56.jpg)
The CO2 Conference
Week of Dec 8th 2008 with Houston and Midland Venues
![Page 57: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/57.jpg)
57
Key Reference Work (1) The Annual CO2 Flooding Conference
• Held Each December in Midland, Texas – Home to 53 Active CO2 Floods
• Concentrates on Actual Case Histories• Includes a CO2 Flood Field Visit• Includes a CO2 Shortcourse• Includes an EOR Carbon Management Workshop • Great Networking Opportunity
Visit: www.spe-pb.org or call 432-552-2430
![Page 58: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/58.jpg)
58
Key Reference Work (2)THE CO2 FLOODING CONFERENCE SHORTCOURSES
1. Making Money on CO2 Flooding...Some Innovative Development Concepts for Independents..., May 1995.
2. Is My Field a Candidate for CO2 Flooding?, September 19953. Equipping and Day-to-Day Operations of a CO2 Flood, December 19954. How CO2 Flood Surveillance Helps Assure a Successful EOR Program, May 19964a. CO2 Flood Surveillance and Monitoring, December 20045. How to Put Together a CO2 Flood, December 19966. CO2 Measurements and Metering, December 19977. CO2 Facilities and Plants, December 19988. CO2 Flooding: Sandstones vs. Carbonate Reservoirs, December 19999. Issues for Beginning CO2 Flooders, December 200010. Reservoir Modeling and Simulation for CO2 Flooding, December 200111. Wellbore Management in CO2 Floods, December 200212. Carbon Dioxide Health And Safety, December 200413. CO2 Sourcing for Enhanced Oil Recovery, Dec 2006
(http://www.utpb.edu/ceed/co2/shortcourses.html) or phone 432-552-2430
![Page 59: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/59.jpg)
59
Key Reference Work (3)
• Practical Aspects of CO2
Flooding, Society of Petroleum Engineers Monograph Volume 22, 2002
(https://www.spe.org/mbrservices/ShopperProductDetail.cfm?ProdCompanyPa ssed=SPE&ProdCdPassed=SPE%2DPROD%2DMONO022)
![Page 60: “CO2 EOR, Reservoir Sweep and CO2 Storage” · EOR, Reservoir Sweep and CO 2 ... • Fluid level program for pumping wells ... FLOODING RECAP (1) • PROVEN TO BE TECHNICALLY VIABLE](https://reader031.fdocuments.us/reader031/viewer/2022012923/5b5b86077f8b9a905c8e3067/html5/thumbnails/60.jpg)
Thank you
Questions?