CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976 · CO2 Capture from Prentiss2 for EOR,...
Transcript of CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976 · CO2 Capture from Prentiss2 for EOR,...
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Version 3.0 Offset Verification Report Form
Verification Report for:
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
Proponent:
AlphaBow Energy Ltd.
Prepared by:
Amberg Environmental and Regulatory Consultants
Prepared for:
AlphaBow Energy Ltd.
Version:
Final
Date:
April 2, 2020
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 2 of 36
Table of Contents
1.0 Summary – Offset Project ...................................................................................... 3 2.0 Introduction ......................................................................................................... 5
2.1 Objective ............................................................................................................. 5 2.2 Scope .................................................................................................................. 5 2.3 Level of Assurance ................................................................................................ 5 2.4 Criteria ................................................................................................................ 5 2.5 Materiality ............................................................................................................ 5
3.0 Methodology ......................................................................................................... 5 3.1 Procedures ........................................................................................................... 6 3.2 Team ................................................................................................................... 8 3.3 Schedule .............................................................................................................. 9
4.0 Results ................................................................................................................ 9 4.1 Assessment of Internal Data Management and Controls ............................................. 9 4.2 Assessment of GHG Data and Information ................................................................ 9 4.3 Assessment against Criteria .................................................................................. 10 4.4 Evaluation of the GHG Assertion ............................................................................ 12 4.5 Summary of Findings ........................................................................................... 12 4.6 Opportunity for Improvement ............................................................................... 14
5.0 Closure .............................................................................................................. 14 5.1 Verification Statement ......................................................................................... 14 5.2 Limitation of Liability ........................................................................................... 14 5.3 Confirmations ..................................................................................................... 14
6.0 References ......................................................................................................... 14 Appendix A: Final Verification Plan and Sampling Plan ............................................................ 15 Appendix B: Statement of Qualifications................................................................................ 22 Appendix C: Findings and Issues .......................................................................................... 25 Appendix D: Statement of Verification .................................................................................. 29 Appendix E: Conflict of Interest Checklist .............................................................................. 32 Appendix F: Supplemental Diagrams/Tables/Figures ............................................................... 35
List of Tables
Table 1: Offset Criteria Assessment ...................................................................................... 10 Table 2: Summary of Findings ............................................................................................. 13 Table 3: Detailed Findings and Issues Log ............................................................................. 26
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 3 of 36
1.0 Summary of Offset Project
Item Description
Project Title CO2 Capture from Prentiss2 for EOR
Project Description
The Project is an enhanced oil recovery
(EOR) operation that processes previously
vented industrial process CO2 from the
neighbouring MEGLobal ethylene glycol
plant for injection into oil wells.
Project Location
The CO2 Capture Site is located North East
of Red Deer, Alberta:
52.382969, -113.5986407
5-30-39-25 W4
The injection wells are located in the
Chigwell/Viking Field at 16-32-043-26 W4
and the Nelson Field at 08-24-042-26 W4.
Project Start Date January 1, 2006
Offset Start Date January 1, 2006
Offset Crediting Period January 1, 2006 to December 31, 2018
Offset Reporting Period January 1, 2017 to December 31, 2018
GHG Assertion (Actual Emission
Reductions/Sequestration Achieved)
2017: 12,642 tonnes
2018: 5,569 tonnes
Total: 18,211 tonnes
Government Approved Quantification
Protocol
Quantification Protocol for Enhanced Oil
Recovery, version 1, October 2007
Ownership AlphaBow Energy Ltd.
Project Activity
This activity meets the eligibility criteria
listed in the Quantification Protocol for
Enhanced Oil Recovery as described in
Section 2 of the Offset Project Plan.
Project Contact
AlphaBow Energy Ltd.
Jay Kleinsasser, P.Eng.
1700, 222 – 3rd Ave SW
Calgary, AB T2P 0B4
(587) 393-6668
Verifier Klym Bolechowsky, P.Eng.
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 4 of 36
ClearSky Engineering Inc.
1-221 Drake Landing Lane
Okotoks, AB T1S 2M4
(403) 982-5596
Verification Team Members
Lead Verifier: Klym Bolechowsky, P.Eng.
Completed CSA ISO 14064-3 training: July
29 - 31, 2013 - Certificate #0000432380
Peer Reviewer: Ashley Mathews, EIT
Completed ISO 14064-3 training: Feb. 7-8,
2017- Certificate #50064648-50067754
Designated Signing Authority Klym Bolechowsky, P.Eng.
Verification Strategy
The verification strategy is a mixed
approach of predominantly substantive
procedures and some controls reliance.
Verification Conclusion The verification conclusion is: Positive
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 5 of 36
2.0 Introduction
Amberg Environmental and Regulatory Consultants (Amberg) was engaged by AlphaBow Energy
Ltd. (AlphaBow) to verify 2017 to 2018 vintage year offset credits generated by the CO2 Capture
from Prentiss2 for EOR Offset Project located North East of Red Deer, Alberta. The offset project
was verified at a reasonable level assurance against the flagged Quantification Protocol for
Enhanced Oil Recovery, version 1, October 2007, the Offset Project Plan and the program
requirements of the Alberta Emission Offset System. This is the first third-party verification
completed for this project by the verifier. Klym Bolechowsky of ClearSky Engineering Inc. was
subcontracted by Amberg in the role of Lead Verifier.
The baseline condition is dynamic based on the volume of CO2 injected annually which would
have been vented in absence of the project.
2.1 Objective
The objective of this verification is to develop a conclusion at a reasonable level of assurance as
to whether the greenhouse gas emission reduction assertion is free from material
misstatement, and is presented fairly in accordance with the Technology Innovation and
Emissions Reduction (TIER) Regulation and the Alberta Emission Offset System.
2.2 Scope
The scope of the verification is the GHG Emission Reduction Assertion presented in the Offset
Project Report dated February 24, 2020 for the period January 1, 2017 to December 31, 2018.
The geographical scope is the CO2 Capture Site and associated well injection sites all located in
Alberta. The Offset Project Plan dated Feb. 24, 2020 for the period up to Dec. 31, 2018 is also
included in the scope of the verification.
2.3 Level of Assurance
The verification was conducted to a reasonable level of assurance. The verification was planned
and executed accordingly.
2.4 Criteria
Technology Innovation and Emissions Reduction (TIER) Regulation, Alberta Regulation
133/2019
Standard for Verification, Version 4.0, November 2019
Standard for Greenhouse Gas Emission Offset Project Developers, Version 3.0,
November 2019
Quantification Protocol for Enhanced Oil Recovery, Version 1, October 2007
Carbon Offset Emission Factors Handbook, Version 1.0, March 2015
2.5 Materiality
The materiality threshold is 5% of emission offsets generated as the project generates less than
500,000 tonnes of emissions offset credits.
3.0 Methodology
This verification was carried out in accordance with the following standards:
ISO 14064 Part 3 – Greenhouse Gases: Specification with guidance for the validation
and verification of greenhouse gas assertions
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 6 of 36
ISO 14064 Part 2 – Greenhouse Gases: Specification with guidance at the project level
for quantification, monitoring and reporting of greenhouse gas emission reductions or
removal enhancements. Six principles:
1. Relevance: include all relevant GHG sources & sinks
2. Completeness: include all relevant emissions and removals
3. Consistency: enable meaningful comparisons in GHG related information
4. Accuracy: reduce bias and uncertainties as far as is practical
5. Transparency: disclose sufficient and appropriate GHG related information to
allow users to make decisions with reasonable confidence
6. Conservativeness: use conservative assumptions, values, and procedures to
ensure GHG emission reductions are not over estimated
3.1 Procedures
The first task completed was a conflict check which is documented in the Conflict of Interest
Checklist included in Appendix E of this report. A date for the site visit was established and the
following information was requested from AlphaBow:
Main Documents:
2017-2018 offset quantification files
Offset Project Report - “OPR CO2 Capture from Prentiss 2 for EOR 2017-2018 (Final
ver.7) (dated Feb 24, 2020)”
Offset Project Plan - “OPP V3 CO2 Capture from Prentiss 2 for EOR (Final ver.6) (dated
Feb 24, 2020)”.
Supporting Documents:
daily gas injection volumes
fuel consumption reports
gas analysis reports
electricity bills
Review on-site: calibration records for project meters
A risk assessment was completed:
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 7 of 36
Risk Assessment
Line Item Attributes Inherent Risk Control Risk Detection Risk
Design
Verification Procedure
GHG Assertion
Level
Completeness Low – mature
project with
multiple
verification and a
reverification audit
from AEP
Medium – new staff
responsible for
offset quantification
Medium Conduct a site tour to view all
project sources/sinks
Accuracy
Baseline –
B3b Venting at
Capture Site
Occurrence Medium – major
contributor to
baseline emissions
Low – gas captured
and injected is
directly metered by
a calibrated device
Medium Review meter calibration
records and certificates
Check all emission factors
and unit conversions
Recalculate baseline
emissions
Completeness
Accuracy
Cut-off
Classification
Completeness
Accuracy
Cut-off
Occurrence
Project -
P12 Injection Gas
Transport
P16 Venting at
Injection Site
P12 Injection Gas
Transport
P20 Electricity
Consumption
P21 Fuel Extraction
/ Processing
Occurrence Medium –
multiple
contributors to
project emissions
Medium – sources
are spread out
geographically
Medium Check data for outliers and
anomalies
Check meter calibration
records
Review any noted corrections
to raw data
Recalculate significant
contributors to project
emissions
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 8 of 36
The site visit occurred on November 14, 2019 with the following individuals in attendance at the
CO2 Capture Site:
Klym Bolechowsky, P.Eng., Lead Verifier, ClearSky Engineering Inc.
Jay Kleinsasser, P.Eng., Director of Production, AlphaBow
Marvin Wieler, Production Foreman, AlphaBow
The purpose of the site visit was to perform the following tasks:
Review the details of project operation and performance in 2017-2018 with operating
personnel
Tour the project site to corroborate the GHG sources/sinks, facility description and
boundaries, and details of the calculation methodology described in the Project Plan;
including review of:
capture site equipment and metering
injection site equipment and metering
confirm project boundaries
Assess the reliability of the data used as input to the GHG offset calculations and the
overall approach
An initial meeting was held to get on overview of the CO2 capture site process. This was
followed by an inspection of the capture site to view the process equipment, project meters,
and gas sample location. The process was viewed starting with the gas inlet flange,
dehydrators, and compressors. The plant HMI system was viewed and meter calibration
records were reviewed. This was followed by a visit to the pump station located at 4-17-41-24
W4 and the CO2 injection sites located at the following oil & gas field batteries:
8-24-42-26 W4, 14-13-42-26 W4.
The following tasks were completed after the site visit:
Follow-up data requests including CO2 injection volumes reported to Petrinex
Recalculation of baseline and project emissions
Phone and email communications to clarify information provided
Detailed review of the Offset Project Report against the Offset Project Plan
Detailed review of GHG emission reduction calculations
Meeting at AlphaBow Calgary office on Dec. 3, 2019 to review initial findings
3.2 Team
Lead Verifier and Designated Signing Authority: Klym Bolechowsky, P.Eng.
Completed CSA ISO 14064-3 training: July 29 - 31, 2013 - Certificate #0000432380
Peer Reviewer: Ashley Mathew, EIT
Completed CSA ISO 14064-3 training: February 7-8, 2017- Certificate #50064648-50067754
Klym Bolechowsky, P.Eng. – Lead Verifier
Mr. Klym Bolechowsky, as Project Manager and Lead Verifier, will be the main contact with
AlphaBow. Klym is a registered Professional Engineer in the province of Alberta and is an
experienced third-party verifier having completed numerous verification projects under the CCIR
and SGER. He has his Certificate of Completion for the CSA GHG Verification Using ISO 14064
three day training course. He has twenty years of experience in the air quality field both as a
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 9 of 36
consultant and in industry. Klym has completed over 100 GHG verifications in Alberta, BC, and
SK.
Association of Professional Engineers and Geoscientists of Alberta (APEGA) member #: 95630
ClearSky Engineering Inc. APEGGA Permit to Practice: P11255
Ashley Mathew, EIT – Peer Reviewer
Ms. Mathew is an Environmental Engineer and has undertaken CSA training in the use of the
ISO 14064-3 standard. She has six years of experience in the Environmental and Regulatory
field. She has participated in the peer review of several verifications of compliance reports and
offset projects and has knowledge and experience in GHG calculations. She has also
participated in several on-site verifications. Through other consulting work, she has gained
knowledge of metering systems and operational controls. As Peer Reviewer, Ms. Mathew will
review the subject matter to be audited, ensure the testing of the validity of findings developed,
and check for accuracy and completeness.
Association of Professional Engineers and Geoscientists of Alberta (APEGA) member #: 112547
Amberg Corp. APEGA Permit to Practice: P8926
3.3 Schedule
Kick-Off Meeting: November 4, 2019
Site Visit: November 14, 2019
Meeting in Calgary: December 3, 2019
Draft Verification Report: December 12, 2019
Peer Review: December 16, 2019; revised April 2, 2020
Final Verification Report: December 17, 2019; revisions up to April 2, 2020
4.0 Results
4.1 Assessment of Internal Data Management and Controls
The project relies on electronic data capture for project monitoring and daily production reports
of CO2 injection gas received and vented volumes.
The list of meters measuring the above parameters and their maintenance and calibration
requirements is provided in Table 7 of the Offset Project Plan. The meter calibration records
and certificates of calibration were reviewed and confirmed to be within manufacturer
specifications.
4.2 Assessment of GHG Data and Information
The Quantification Protocol lists the sources/sinks (SS) that may be applicable to a project of
this type. The following baseline (B) condition and project (P) condition SS’s were included in
the GHG emission reduction quantification for the project.
Emission Reduction = EmissionsBaseline – EmissionsProject
EmissionsBaseline = sum of the emissions under the baseline condition
= Emissions from B3b Capture Vent
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 10 of 36
EmissionsProject = sum of the emissions under the project condition
= Emissions from P3b Venting at Capture Site
+ Emissions from P7b Gas Processing
+ Emissions from P12 Injection Gas Transport
+ Emissions from P16 Venting at Injection Site
+ Emissions from P12 Injection Gas Transport
+ Emissions from P20 Electricity Consumption
+ Emissions from P21 Fuel Extraction / Processing
The equations for each of the above SS’s are documented in the Protocol and it was confirmed
that the correct Protocol equations and constants were applied in the GHG emission reduction
calculations. The quantification methodologies used by the project proponent are the same as
those described in the Offset Project Plan. The Protocol includes the density of CO2 and CH4 at
standard temperature and pressure (0°C and 1 atmosphere) which were corrected to project
meter reference conditions (15°C and 101.3 kPa) by AlphaBow (see Finding 19-10). The
equations and units were checked for accuracy. The annual offset calculation spreadsheets
were checked thoroughly for correctly functioning links and formulas, and unit conversions.
The sources of the emission factors referenced in the calculations were checked and confirmed.
Baseline and project emissions were recalculation for confirmation.
4.3 Assessment against Criteria
Table 1: Offset Criteria Assessment
Offset Eligibility
Criteria
Assessment
Reduction or
sequestration occurs in
Alberta
Satisfactory - the Project is physically located North East
of Red Deer, Alberta.
Result from actions not
required by Law at the
time the action is taken
Satisfactory - the Project is not required by law.
Result from Actions
taken on or after
January 1, 2002 and
occur on or after January
1, 2002
Satisfactory - the Project began operation after this date.
Reduction or
sequestrations is real
and demonstrable
Satisfactory - the Project has been verified according to
the verification criteria, listed in Section 2.4 of this report.
Quantifiable and
measureable
Satisfactory – the Project has an Offset Project Plan
describing quantification and measurement per the
Quantification Protocol.
The specified gas
emissions that were
Satisfactory
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 11 of 36
reduced or the carbon
dioxide that was
sequestered must not
have had an effect on
the determination of a
regulated facility’s total
regulated emissions
under section 13(3) or
(4).
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 12 of 36
4.4 Evaluation of the GHG Assertion
The verification assessment is that the GHG Assertion meets the requirements of the
Technology Innovation and Emissions Reduction (TIER) Regulation.
Based on the verification review of the calculated emission reduction offset credits, no evidence
of material discrepancies were identified. The Offset Project Plan, Offset Project Report, and
GHG Assertion were found to be reliable, complete and in compliance with the requirements of
the TIER.
4.5 Summary of Findings
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 13 of 36
Table 2: Summary of Unresolved Findings
Result
#
Type Summary Description of Finding Source Category or
Source/Sink
Understatement
/Overstatement
Tonnes CO2
eq % net
Tonnes
CO2 eq %
absolute
19-01 quantitative Completeness – Gas Analyses
The protocol requires quarterly gas composition
measurements at a minimum. This requirement was not
met for: 2017, the first three quarters of 2018.
unknown unknown unknown
19-04 quantitative Accuracy – Wet Gas vs. Dry Composition
The volume of gas vented at the inlet is a wet gas stream.
The CO2 and CH4 content of the gas is determined by gas
compositional analysis on a dry basis. This introduces
inaccuracy in the calculation of CO2 and CH4 content in the
wet gas stream as the mole fractions to not account for the
H2O in the gas. AlphaBow acknowledges the inaccuracy,
however, this is mitigated by the fact that this vented
volume is reported in both the baseline condition (B3b) and
the project condition (P3b) so there is not quantitative
impact.
none 0.0 0.0 %
19-05 qualitative Transparency – Process Flow Diagram
The process flow diagram in the Offset Project Plan does not
clearly identify the project meter tags and gas analysis
sample locations.
n/a n/a n/a
19-06 qualitative Transparency – Offset Calculation Files
The summary of baseline and project emissions in the 2017
and 2018 calculation files are incorrectly labelled as 2019.
n/a n/a n/a
19-08 qualitative Transparency – Revisions
Revisions to project documents were not clearly identified.
AlphaBow should adopt a consistent and clear file naming
convention.
n/a n/a n/a
Total Error 0.0 tonnes
0.0 %
0.0 tonnes
0.0 %
Note: A positive value represents a quantitative overstatement, a negative value represents a quantitative understatement.
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 14 of 36
4.6 Opportunity for Improvement
Instances of transcription errors of CO2 volumes from the monthly production reports would be
reduced by linking directly to the monthly totals in the spreadsheet formulae.
5.0 Closure
5.1 Verification Statement
The verification conclusion is:
Positive
5.2 Limitation of Liability
Due to the inherent limitations in any internal control structure, it is possible that fraud, error,
or non-compliance with laws and regulations may occur and not be detected. Further, the
verification was not designed to detect all weaknesses or errors in internal controls so far as
they relate to the requirements set out above as the verification has not been performed
continuously throughout the period and the procedures performed on the relevant internal
controls were on a test basis. Any projection of the evaluation of control procedures to future
periods is subject to the risk that the procedures may become inadequate because of changes
in conditions, or that the degree of compliance with them may deteriorate.
5.3 Confirmations
Confirmations are required by the ACCO to ensure that required data and information in offset
project plans and reports are completed and accurate. The following is a list of confirmations
completed by the verifier:
Formatting issues in the Offset Project Report
Correct entry of administrative fields such as facility codes and legal locations
Offset Project Report is provided and consists of the required components
Simplified process flow diagram
Project report information details as required
6.0 References
AEP. 2015. Carbon Offset Emission Factors Handbook, Version 1.0.
AEP. 2007. Quantification Protocol for Enhanced Oil Recovery, Version 1.0.
Government of Alberta. 2019. Standard for Greenhouse Gas Emission Offset Project
Developers, Version 3.0.
Government of Alberta. 2019. Standard for Validation, Verification and Audit, Version 4.0.
Government of Alberta. 2019. Technology Innovation and Emissions Reduction (TIER)
Regulation, Alberta Regulation 133/2019.
ISO. 2006. 14064 Part 2 – Greenhouse Gases: Specification with guidance at the project level
for quantification, monitoring and reporting of greenhouse gas emission reductions or removal
enhancements.
ISO. 2006. ISO 14064 Part 3 – Greenhouse Gases: Specification with guidance for the
validation and verification of greenhouse gas assertions.
Page 15 of 36
Appendix A: Final Verification Plan and Sampling Plan
Page 16 of 36
Scope & Objectives
Amberg Environmental and Regulatory Consultants (Amberg) was engaged by AlphaBow Energy
Ltd. (AlphaBow) to verify 2017 to 2018 vintage year offset credits generated by the CO2 Capture
from Prentiss2 for EOR Offset Project located North East of Red Deer, Alberta. The offset project
was verified at a reasonable level assurance against the flagged Quantification Protocol for
Enhanced Oil Recovery, version 1, October 2007, the Offset Project Plan and the program
requirements of the Alberta Emission Offset System. This is the first third-party verification
completed for this project by the verifier.
Alberta Environment and Parks (AEP) has described the key requirements of the verification
plan in their document entitled Standard for Verification, Version 4.0, and these elements are
addressed in the following sections of this Verification Plan. The first draft of the verification
plan was sent to the project developer on Nov. 4, 2019.
The objective of the verification is to provide AEP with assurance that the Offset Project Report
accurately represents the greenhouse gas (GHG) emission reductions associated with the
project and that the process is being carried out in accordance with TIER and the Quantification
Protocol for Enhanced Oil Recovery, Version 1.0.
The scope of the verification is the GHG Emission Reduction Assertion presented in the Offset
Project Report dated February 24, 2020 for the period January 1, 2017 to December 31, 2018.
The geographical scope is the CO2 Capture Site and associated well injection sites all located in
Alberta. The Offset Project Plan dated February 24, 2020 is also included in the scope of the
verification.
Level of Assurance
The verification will be conducted at a reasonable level of assurance.
Materiality
The materiality threshold is 5% of emission offsets generated as the project generates less
than 500,000 tonnes of emissions offset credits.
Verification Standards
This verification was carried out in accordance with the following standards:
ISO 14064 Part 3 – Greenhouse Gases: Specification with guidance for the validation
and verification of greenhouse gas assertions
ISO 14064 Part 2 – Greenhouse Gases: Specification with guidance at the project level
for quantification, monitoring and reporting of greenhouse gas emission reductions or
removal enhancements. Six principles:
1. Relevance: include all relevant GHG sources & sinks
2. Completeness: include all relevant emissions and removals
3. Consistency: enable meaningful comparisons in GHG related information
4. Accuracy: reduce bias and uncertainties as far as is practical
5. Transparency: disclose sufficient and appropriate GHG related information to
allow users to make decisions with reasonable confidence
6. Conservativeness: use conservative assumptions, values, and procedures to
ensure GHG emission reductions are not over estimated
Verification Criteria
The verification criteria include:
Technology Innovation and Emissions Reduction (TIER) Regulation, Alberta Regulation
133/2019
Standard for Verification, Version 4.0, November 2019
Page 17 of 36
Standard for Greenhouse Gas Emission Offset Project Developers, Version 3.0,
November 2019
Quantification Protocol for Enhanced Oil Recovery, Version 1, October 2007
Carbon Offset Emission Factors Handbook, Version 1.0, March 2015
Risk Assessment
A risk assessment identified areas of focus for the verification. Three categories of risk were
assessed:
1. Inherent Risk – the likelihood of a material error, omission, or misrepresentation
because of inherent challenges in the subject matter
2. Control Risk – the likelihood that the organization’s control procedures will fail to
prevent, detect, or correct an error or omission
3. Detection Risk – the risk that the procedures applied by the verifier do not detect a
misstatement in the GHG assertion. There is an inverse relationship between the
inherent and control risks, and the detection risk. If the inherent and control risks are
high, the verifier must design and perform procedures that result in a low detection risk
so that the overall verification risk is low.
The risk assessment was conducted during the planning stage and finalized during the
execution phase of the verification and is summarized in the following table:
Page 18 of 36
Risk Assessment
Line Item Attributes Inherent Risk Control Risk Detection Risk
Design
Verification Procedure
GHG Assertion
Level
Completeness Low – mature
project with
multiple
verification and a
reverification audit
from AEP
Medium – new staff
responsible for
offset quantification
Medium Conduct a site tour to view all
project sources/sinks
Accuracy
Baseline –
B3b Venting at
Capture Site
Occurrence Medium – major
contributor to
baseline emissions
Low – gas captured
and injected is
directly metered by
a calibrated device
Medium Review meter calibration
records and certificates
Check all emission factors
and unit conversions
Recalculate baseline
emissions
Completeness
Accuracy
Cut-off
Classification
Completeness
Accuracy
Cut-off
Occurrence
Project -
P12 Injection Gas
Transport
P16 Venting at
Injection Site
P12 Injection Gas
Transport
P20 Electricity
Consumption
P21 Fuel Extraction
/ Processing
Occurrence Medium –
multiple
contributors to
project emissions
Medium – sources
are spread out
geographically
Medium Check data for outliers and
anomalies
Check meter calibration
records
Review any noted corrections
to raw data
Recalculate significant
contributors to project
emissions
Completeness
Accuracy
Cut-off
Classification
Page 19 of 36
A contribution analysis was conducted to assess the relative contribution of each line item to
the overall GHG assertion. This was useful in the risk assessment phase to identify priority line
items.
Contribution Analysis
2017
2018
SSR CO2
(t CO2e)
CH4
(T CO2e)
N2O
(t CO2e)
CO2e
(t Co2e)
Total
(t CO2e)
% of Total Offset
2017 Baseline 20,520 187 20,707 100% of baseline
2017 Project 4,348 266 22 3,429 8,065 63.8%
Vent Inlet 412 4 416 3.3%
Vent Outlet 61 1 61 0.5%
Process Fuel Extraction
and processing 69 0 0 69 0.5%
Process Fuel Emission 5 2 0 7 0.1%
Process Elec 2,824 2,824 22.3%
Venting Pipeline 0 0 0.0%
Pipelin Elec 3 3 0.03%
Venting Upstream Facility59 139 198 1.6%
Venting Stock Tanks 0 0 0 0.0%
Venting Wells 0 0 0 0.0%
EOR Fuel gas (emission)3,500 2 18 3,520 27.8%
EOR Fuel gas (extraction
and process)243 119 4 365 2.9%
EOR Electrical Cons 602 602 4.8%
Net Emission Reductions 16,172 -79 -22 -3,429 12,642
CO2 Capture from Prentiss2 for EOR
SSR CO2
(t CO2e)
CH4
(T CO2e)
N2O
(t CO2e)
CO2e
(t Co2e)
Total
(t CO2e)
% of Total Offset
2018 Baseline 8,247 67 8,314 100% of baseline
2018 Project 1,620 103 6 1,016 2,745 49.3%
Vent Inlet 313 3 316 5.7%
Vent Outlet 109 1 110 2.0%
Process Fuel Extraction and
processing16 0 0 16 0.3%
Process Fuel Emission 1 1 0 2 0.0%
Process Elec 835 835 15.0%
Venting Pipeline 0 0 0.0%
Pipelin Elec 2 2 0.04%
Venting Upstream Facility9 62 70 1.3%
Venting Stock Tanks 0 0 0 0.0%
Venting Wells 0 0 0 0.0%
EOR Fuel gas (emission) 1,096 1 6 1,102 19.8%
EOR Fuel gas (extraction
and process) 76 37 1 114 2.1%
EOR Electrical Cons 178 178 3.2%
Net Emission Reductions 6,627 -36 -6 -1,016 5,569
CO2 Capture from Prentiss2 for EOR
Page 20 of 36
Sampling Plan
Based on the risk assessment and contribution analysis, the sampling plan was developed to
include review and sampling of all available data for the volume of CO2 gas stream captured, all
gas analyses, all electricity invoices, all venting records, all emission factors, representative
samples of lower contributors to project emissions, as well as recalculating baseline and project
emissions. This included recalculating the GHG Assertion, and assessing consistency with the
Project Plan, Protocol, and AEP guidance.
Verification Procedures
The subject matter pertaining to this verification is described in the Quantification Protocol for
Enhanced Oil Recovery. The verification will employ substantive procedures consisting of
analytical tests and tests of detail - inspection of facility, documents, and inquiry. The verification
procedures are described previously in the Risk Assessment table. The verification process will
also include the following procedures:
Confirmation of ownership of offset credits
Inspect the facility and interview project staff
Review raw data collected from project meters
Review the emission factors utilized in the calculations and compare to source
publications to ensure appropriate factors are utilized. Recalculate emission reductions.
Assess the data management system during the site visit
A thorough understanding of the GHG Offset Project drives the verification approach. The
verification process will commence with gaining an understanding of the entity, business and
industry by reviewing the Offset Project Report and background information provided. The review
of these items will then direct the area of focus for the site visit, and the assessment of the
GHG quantification method and accuracy of emission reduction calculations.
The review of the data management system will assess how the inputs to the offset credit
calculation are determined and will consist of discussions with project management and review
of project documentation and records. A description of the data management system and
controls is included in the main body of the verification report.
The objective of the verification is to provide reasonable assurance that the emission reduction
calculations are not materially misstated. A positive statement of verification will be issued if
there is sufficient and appropriate evidence to support the GHG assertion at a reasonable level
of assurance. A reasonable assurance conclusion is a positive factual statement that says the
GHG emission reduction assertion is correct.
Site Visit
The site visit was completed on November 14 at the AlphaBow CO2 Capture facility. Safety
requirements for the site visit include: Nomex coveralls, hard hat, safety glasses, CSA safety
boots.
Verification Report
A verification report will be prepared summarizing procedures and findings. Detailed
documentation of the verification process will be maintained and described in the final verification
report. The documentation will include a description of activities during the verification and a
description of any findings and observations. A Statement of Verification will be prepared and
signed by the Lead Verifier. A signed Conflict-of-Interest checklist and Statement of Qualification
will also be provided.
Verification Schedule
The verification schedule is summarized as follows:
Kick-Off Meeting: November 4, 2019
Site Visit: November 14, 2019
Page 21 of 36
Meeting in Calgary: December 3, 2019
Draft Verification Report: December 12, 2019
Peer Review: December 16, 2019; revised April 2, 2020
Final Verification Report: December 17, 2019; revisions up to April 2, 2020
Verification Team
The verification team will include the following members:
Klym Bolechowsky, P.Eng., ClearSky Engineering Inc. (Lead Verifier, Designated Signing
Authority)
Ashley Mathew, EIT (Peer Reviewer)
Klym Bolechowsky, P.Eng. – Lead Verifier
Mr. Klym Bolechowsky, as Project Manager and Lead Verifier, will be the main contact with
AlphaBow. Klym is a registered Professional Engineer in the province of Alberta and is an
experienced third-party verifier having completed numerous verification projects under the CCIR
and SGER. He has his Certificate of Completion for the CSA GHG Verification Using ISO 14064
three day training course. He has twenty years of experience in the air quality field both as a
consultant and in industry. Klym has completed over 100 GHG verifications in Alberta, BC, and
SK. Some of his recent projects relevant to the oil & gas industry include:
2013, 2015 – 2019 SGER / CCIR verification for Peyto Oldman Gas Plant
2012 - 2016 SGER compliance report verification for Inter Pipeline Cochrane Extraction
Plant
2016 – 2018 SGER & CCIR compliance report verification of Suncor Oil Sands, SAGD,
and Edmonton Refinery Facilities in association with Cheminfo Services Inc.
2016 Government Audit of Imperial Oil Kearl Oil Sands Project in association with
Cheminfo Services Inc.
Klym has presented papers on GHG verification at the following conferences:
Air & Waste Management Association conference in Calgary on June 24, 2010:
http://www.clearskyeng.com/docs/AWMA_GHG_Presentation.pdf
EPA Emission Inventory Conference in Baltimore, MD, April 15, 2009:
Paper: http://www.epa.gov/ttn/chief/conference/ei18/session7/bolechowsky.pdf
Presentation:
http://www.epa.gov/ttn/chief/conference/ei18/session7/bolechowsky_pres.pdf
Association of Professional Engineers and Geoscientists of Alberta (APEGA) member #: 95630
ClearSky Engineering Inc. APEGGA Permit to Practice: P11255
Ashley Mathew, EIT – Peer Reviewer
Ms. Mathew is an Environmental Engineer and has undertaken CSA training in the use of the
ISO 14064-3 standard. She has six years of experience in the Environmental and Regulatory
field. She has participated in the peer review of several verifications of compliance reports and
offset projects and has knowledge and experience in GHG calculations. She has also
participated in several on-site verifications. Through other consulting work, she has gained
knowledge of metering systems and operational controls. As Peer Reviewer, Ms. Mathew will
review the subject matter to be audited, ensure the testing of the validity of findings developed,
and check for accuracy and completeness.
Association of Professional Engineers and Geoscientists of Alberta (APEGA) member #: 112547
Amberg Corp. APEGA Permit to Practice: P8926
Page 22 of 36
Appendix B: Statement of Qualifications
Page 23 of 36
Statement of Qualifications
Offset Report
Project Name Offset Project ID
CO2 Capture from Prentiss2 for EOR 3482-7976
Reporting Company Legal Name Report Type Reporting Period
AlphaBow Energy Ltd. Offset Project Report from
January 1, 2017 – December 31, 2018
to
Signature of Third Party Verifier
I , Klym Bolechowsky (Third Party Verifier), meet or exceed the qualifications of
third-party verifiers described in Section 29 of the Carbon Competitiveness Incentive Regulation.
Verifying Company Name
Amberg Environmental and Regulatory Consultants Per:
Signature of Third Party Verifier Date
April 2, 2020
Training Received Under ISO 14064 Part 3
Certificate of Completion for the “CSA GHG Verification Using ISO 14064” three day training course, July 29-31, 2013. Certificate #0000432380
First Name Last Name
Klym Bolechowsky
Professional Designation E-mail Address Phone Number
P.Eng. [email protected] (403) 982-5596
Lead Verifier
☒ Same as third party
verifier??
First Name Last Name
Professional Designation E-mail Address Phone Number
Training Received Under ISO 14064 Part 3
Page 24 of 36
Peer Reviewer
First Name Last Name
Ashley Mathew
E-mail Address Phone Number
[email protected] (403) 247-3088
Training Received Under ISO 14064 Part 3
Completed ISO 14064-3 training: Feb. 7-8, 2017- Certificate #50064648-50067754
Page 25 of 36
Appendix C: Findings and Issues
Page 26 of 36
Table 3: Detailed Findings and Issues Log
Item
(YR-
##)
Description of the Issues Investigated
During the Verification
Summary of information
exchanged between verifier
and client
Resolution Conclusion
(including %
discrepancy if
applicable)
19-01 Completeness – Gas Analyses
The protocol requires quarterly gas
composition measurements at a minimum.
This requirement was not met for: 2017, the
first three quarters of 2018.
Gas analysis reports unresolved unknown
19-02 Completeness – Venting Volume
A volume of vented gas in May 2017 was not
included in the 2017 GHG emission reduction
calculations.
May 2017 production report
2017 GHG emission reduction
calculation file
resolved 0.0 tonnes
0.0 %
19-03 Completeness – Project Electricity
The annual GHG emissions associated with
electricity consumption at the injection sites
was quantified but missed in sum formulae
for total project emissions. This was corrected
by AlphaBow.
2017 GHG emission reduction
calculation file
2018 GHG emission reduction
calculation file
resolved 0.0 tonnes
0.0 %
19-04 Accuracy – Wet Gas vs. Dry Composition
The volume of gas vented at the inlet is a wet
gas stream. The CO2 and CH4 content of the
gas is determined by gas compositional
analysis on a dry basis. This introduces
inaccuracy in the calculation of CO2 and CH4
content in the wet gas stream as the mole
fractions to not account for the H2O in the
gas. AlphaBow acknowledges the inaccuracy,
however, this is mitigated by the fact that
this vented volume is reported in both the
baseline condition (B3b) and the project
condition (P3b) so there is no quantitative
impact. AlphaBow clarified that this stream is
2017 – 2018 production reports
Gas analysis reports
unresolved 0.0 tonnes
0.0 %
Page 27 of 36
not metered, the volume is estimated based
on the time venting and average productions
rates.
19-05 Transparency – Process Flow Diagram
The process flow diagram in the Offset Project
Plan does not clearly identify the project
meter tags and gas analysis sample locations.
Offset Project Report unresolved n/a
19-06 Transparency – Offset Calculation Files
The summary of baseline and project
emissions in the 2017 and 2018 calculation
files are incorrectly labelled as 2019.
2017 GHG emission reduction
calculation file
2018 GHG emission reduction
calculation file
unresolved n/a
19-07 Consistency – Gas Densities
The Protocol specifies the following densities
to be applied in the GHG emission reduction
calculations:
CO2 density = 1.98 kg/m3 at STP
CH4 density = 0.717 kg/m3 at STP
2017 GHG emission reduction
calculation file
2018 GHG emission reduction
calculation file
resolved n/a
The Protocol does not specify the standard
temperature & pressure (STP) conditions but
the above values apply for T = O°C, P = 1
atmosphere. This is inconsistent with the STP
conditions used by Canadian industry for
gases: T = 15°C, P = 1 atmosphere. The
values applied by AlphaBow are consistent
with STP conditions used by Canadian
industry:
CO2 density = 1.86 kg/m3 at STP (T = 15°C,
P = 1 atmosphere)
CH4 density = 0.679 kg/m3 at STP (T = 15°C,
P = 1 atmosphere)
Therefore, it is the opinion of the verifier that
AlphaBow does not need to submit a
deviation request to Alberta Environment in
this case.
Page 28 of 36
19-08 Transparency – Revisions
Revisions to project documents were not
clearly identified. AlphaBow should adopt a
consistent and clear file naming convention.
OPP and OPR files unresolved n/a
Note: A positive value represents a quantitative overstatement, a negative value represents a quantitative understatement.
Page 29 of 36
Appendix D: Statement of Verification
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 30 of 36
Statement of Verification
Associated TIER Submission
Offset Project Protocol Project ID #
CO2 Capture from Prentiss2 for
EOR
Quantification Protocol
Enhanced Oil Recovery,
Version 1, October 2007 3482-7976
Project Developer
Serial
Range Start
Report
Period
AlphaBow Energy Ltd.
January 1, 2017
– December 31,
2018
Serial
Range End
Statement of Verification
GHG Assertion
Value Units
Total Baseline
Emissions 29,021
tonnes
CO2eq
Total Project
Emissions 10,810
tonnes
CO2eq
Other
tonnes
CO2eq
Net Reductions
18,211
Tonnes
CO2eq
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 31 of 36
Statement of
Assertion
For the period of January 1, 2017 to December 31, 2018, the Project
resulted in GHG emission reductions of 18,211 tonnes CO2e.
Responsibilities of Project Developer and Third Party Verifier
Our responsibility is to develop a conclusion with a reasonable level of assurance as to whether
the GHG Assertion is free from material misstatement, and is fairly presented in accordance with
the Quantification Protocol for Enhanced Oil Recovery, version 1.0, and the program
requirements of the Alberta Emission Offset System under the TIER system.
Conclusion
Based on our work, it is our opinion at a reasonable level of assurance that the GHG Assertion
presented in the Offset Project Report for the CO2 Capture from Prentiss2 for EOR Project is
materially correct and presented fairly and accurately in accordance with the TIER system
criteria.
Signature of Third Part Verifier
Verifying Company
Name
Amberg Environmental and Regulatory Consultants Per:
Signature of Third
Party Verifier Date:
April 2, 2020
First Name
Last
Name
Klym Bolechowsky
Professional
Designation E-mail Address Phone Number
P.Eng. [email protected] (403) 982-5596
Page 32 of 36
Appendix E: Conflict of Interest Checklist
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 33 of 36
Conflict of Interest Checklist
Associated TIER Submission
Offset Project Protocol
CO2 Capture from Prentiss2 for EOR
Quantification Protocol for Enhanced Oil Recovery, Version 1, October 2007
Project Developer Report Type
Report Period
AlphaBow Energy Ltd. Offset Project Report
January 1, 2017 to December 31, 2018
Checklist
Respond either "True" or "False" to each of the following statements:
1. The relationship between my firm and this reporting company poses unacceptable threat to or compromises the impartiality of my firm.
False
2. The finances and sources of income of my firm compromise the impartiality of my firm.
False
3. The personnel my firm has scheduled to participate in the verification may have an actual or potential conflict of interest.
False
4. My firm participated in some manner in the development or completion of the associated offset submission for this reporting company.
False
5. My firm provided greenhouse gas consultancy services to this reporting company.
False
6. My firm will use personnel that have, are, or will be engaged or previously employed by the reporting company.
False
7. My firm will outsource the Statement of Verification for the associated offset submission.
False
8. My firm offers products or services that pose an unacceptable risk to impartiality.
False
Important: If you have checked "True" to any of the above, you may not fulfill the "independence" requirement for
third party verifiers. Please contact Alberta Environment and Parks for further instruction. If the potential conflict of interest is a sufficient threat to impartiality (perceived or actual), or cannot be effectively managed, you Third Party Verification Report will not be acceptable to Alberta Environment and Parks.
Signature of Third Party Verifier
CO2 Capture from Prentiss2 for EOR, Project ID: 3482-7976
April 2020
Page 34 of 36
I , Klym Bolechowsky (Third Party Verifier), have personally examined and am familiar
with the information contained in this Conflict-of Interest Checklist, and can demonstrate freedom from any conflict of interest related to the reporting company for which the verification was performed. I hereby warrant that the information submitted in this Conflict-of Interest Checklist is true, accurate and complete to the best of my knowledge, and that all matters affecting the validity of this Conflict-of-Interest Checklist have been fully disclosed. Impartiality shall be monitored over the duration of the verification and any identified actual or potential conflict-of-interest situations will be communicated to AEP directly.
Verifying Company Name
Amberg Environmental and Regulatory Consultants Per:
Signature of Third Party Verifier Date
April 2, 2020
First Name Last Name
Klym
Bolechowsky
Professional Designation E-mail Address Phone Number
P.Eng. [email protected] (403) 982-5596
Page 35 of 36
Appendix F: Supplemental Diagrams/Tables/Figures
Page 36 of 36
Aerial view of the CO2 Capture Site
Source: Google Maps