CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference...

53
CNS CONFERENCE Qinshan Project - June 2003 Dr. Ken Petrunik

Transcript of CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference...

Page 1: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

CNS CONFERENCEQinshan Project - June 2003

Dr. Ken Petrunik

Page 2: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 2

CANDU CONSTRUCTION IN CHINAAhead of Schedule – Under Budget

Page 3: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 3

ContentsReference DataParticipantsChallengesHow We Did ItQinshan Phase 3 – Project Management; Quality; Construction Methods; Integrated Schedules; World RecordsConclusionsQ3R

Page 4: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 4

Qinshan CANDU Site (Haiyan)Qinshan CANDU

Site (Haiyan)

Site - Detailed Location in China

Page 5: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 5

Reference Data• Qinshan III CANDU NPP

− 2 x 728 MWe by AECL and TQNPC− Zhejiang Province, China

• Contract effective – 1997 Feb 12• Start construction – 1998 Jun 8• Scheduled in-service:

− Unit 1: 2003 Feb 12 – Actual 2002 Dec 31− Unit 2: 2003 Nov 12- Predicted 2003 July

Page 6: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 6

October 1997

Page 7: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 7

Major Participants

• AECL overall project manager, designs & supplies NSP, manages NSP construction

• Third Qinshan Nuclear Power Company (TQNPC) owner, manages BOP construction & executes commissioning

• Chinese Construction Contractors CNI-23, HXCC, CNI-22, ZTPC

• Consortium of Hitachi/Bechtel for BOP design and supply

Page 8: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 8

Contract StructureNSP BOP

BOP ConsortiumDesign & Supply SubcontractEngineering Design

NSSS DesignAECL

Supply

CANATOM NPM NSP Supply Subcontract

TQNPCCANATOM NPMProject Management Subcontract

Site Construction Management

Heavy Water and Fuel AECL

BNSP DesignCANATOM NPMBNSP Subcontract

HitachiNSP Supply Subcontract

HANJUNGNSP Supply Subcontract

Training Hydro Quebec NSP Training Subcontract

BOP ConsortiumDesign & Supply Subcontract

Commissioning TQNPC under guidance and direction by AECL

BOP Construction Contractors(under TQNPC direction)

NSP Construction Contractors(under AECL direction)

Construction

AECL

BOP ConsortiumDesign & Supply Subcontract

Project Management

Page 9: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 9

CHALLENGES• Many participants-not worked together before on a

project• Unfamiliarity with China• Shortest schedule of any NPP committed in China• First CANDU in China• Regionalized construction not able to benefit from prior

PWR experience• Smallest site in China with water on three sides• Internal focus on jobs in government companies, not

on best for task - structural steel had large schedule impact

Page 10: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 10

• Chinese planning milestone based• Different country and company cultures – AECL –

Chinese – Bechtel - Hitachi• Young inexperienced Chinese commissioning staff• Complex execution model; owner manages BOP

construction, AECL directs NSP contractors - owner pays

• CONTRACT- LUMP SUM with LDs• AECL first time use of CADDs, Open Top and all

electronic document systems---”on the run”• Needed to take site construction quality from a paper to

effective program.

Page 11: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 11

HOW WE DID IT

Page 12: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 12

TEAMWORK

Page 13: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 13

Meeting the Schedule – Qinshan Phase III• Good people and teamwork among participants• Project management leadership and culture with good

support from head office and freedom to do job within context of total Contract – focal point accountability

• Good client (TQNPC) and local construction contractors• State of the Art Project Management Tools • Early planning, integrated schedules and parallel activities• Improved construction methods-open top

Page 14: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 14

• Large part of design ready at CED for NSP• Team in place at CED to produce all project procedures at

Rev 0 before work started.• Design by area not system to match actual construction

program• Effective training and support from Hydro Quebec Gentilly 2

CANDU 6 station• Excellent commissioning by integrated Chinese and

Canadian Teams

NOTE: PROJECT decisions on CADDS, open top, electronic tools made after Contract signing based on dealing with RISKS and CHALLENGES

Page 15: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 15

Quality a Priority• Promoted NCR culture• Used NCRs to control and stop work on a localized

area• Used stop work orders to set policy and direction• Electronic document system supported quality records

and processes• “All” expat site staff were quality surveyors• Quality was a LINE responsibility• Client and contractors evolved to accepting

International Quality Program-cultural shift• Independent Chinese QS body on NSP program

Page 16: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 16

State of the Art Project Management Tools

• CADDs – LESS errors and better understanding of overall design and equipment to support easier installation – MANY interferences eliminated

• CANDU Material Management System (CMMS) − tracks equipment and materials from RFQ to issue for

construction− system supports ongoing plant operation & maintenance− items bar coded for inventory control and reduced costs

Page 17: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 17

• Asset Information Management (AIM) - all “formal” project records in electronic format− on-line and common access to official drawings and

documents by all parties − reduces errors − real time access by all parties

• dramatically improves quality & efficiency• reduces costs

• IntEC – Integrated database for wiring/cabling and Instrument calibration with real time access.

State of the Art Project Management Tools (contd.)

Page 18: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 18

Construction Methods - Modularization & VHL (Open Top)• Shortens installation time • Work access from top and bottom• Reduces construction labor and interferences between

contractors • Gives schedule flexibility • Done on site for Qinshan after Contract signed• Improves quality• REDUCES COSTS• Compensated for other project delays

Page 19: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 19

Integrated Schedules• 76 event contract milestone schedule• 8500 event level 2 schedule shows

− design deliverables− equipment deliveries− construction & commissioning activities

• Integrated level 3 schedule by construction contractors

• Parallel activities between civil and installation – New for Chinese but shortened schedule

Page 20: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 20

Page 21: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 21

Page 22: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 22

Page 23: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 23Coffer Dam

Page 24: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 24

Page 25: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 25

January 1999

Page 26: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 26

Page 27: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 27

March 1999

Page 28: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 28

Page 29: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 29

March 1999

Page 30: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 30

June 1999Unloading Calandria

Page 31: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 31

Major Lifts (tons) - (70 lifts done)

• Steam generator - 220• Temporary roof - 150• Pressurizer - 103• Reactivity deck - 43• Feeder frames - 40 each,• Condenser shells - 270 each,• T/G stator - 280

Page 32: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 32

• Evolution of Reference Plant design by Chinese contractors and AECL for modularization of:− dousing steel and piping− lower dome formwork− spent fuel transfer

• AECL staffing featured hands on field staff to provide training for contractors. Unit 2 durations about 3/4 of Unit 1

Page 33: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 33

July 1999 Condenser Heavy Lift Unit 1

Page 34: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 34

December 1999

Page 35: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 35Dousing Module Lift November 2000

November 2000Dousing Module Lift

Page 36: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 36

April 2001

Page 37: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 37

January 2003

Page 38: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 38

Commissioning TEAM

• TQNPC - 1000 staff• AECL, Bechtel and Hitachi - 46 expat advisors• 232 TQNPC staff trained at Gentilly 2 NPP in

Canada• Full scope CANDU 6 simulator on-site• Control room operators licensed by NNSA• Integrated team very successful

Page 39: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 39

October 2001

Page 40: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 40

World Records by Chinese Nuclear Contractors CNI 23 and HXCC

• Slipforming Unit 1 18 days• Slipforming Unit 2 14 days• FC installation Unit 1 69 days• FC installation Unit 2 64 days• Steam generator installation 8 hours• Pressurizer installation 8 hours

Page 41: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 41

New Record for Chinese NPP Construction

57.5200255.5Ling’ao U254200251.5Qinshan III (U 1)

60.5200256.5Ling’ao U171.5199469.5Daya Bay U275.5199371.5Daya Bay U170200166Qinshan II (U 1)87199177Qinshan I

First Concrete to 100% Power

Criticality (Year)First Concrete to Criticality

(Months)

Page 42: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 42

Qinshan Early Completion

18Tianwan 2* MINATOM13Tianwan 1* MINATOM0Qinshan III-2* AECL0Qinshan III-1 AECL6Ling’ao 2 Guangdong6Ling’ao 1 Guangdong

>20Qinshan II-2* CNNC16Qinshan II-1 CNNC13Daya Bay 2 FRAMATOM17Daya Bay 1 FRAMATOM

Q3 earlier by months from CEDPlant

*predicted

Page 43: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 43

June 2003

• Owner’s staff: 900• Contractors direct site labour force: 500 (down

from 8000 peak)• AECL & offshore subcontractors: 60 expatriates

on site (peak of 180) • Unit 2 Criticality April 29, 2003• On Track to Full Power in summer 2003 – months

ahead of schedule

Page 44: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 44

Summary and Conclusions

• AECL CANDU 6 built to shortest construction schedule of any NPP in China even though it was first CANDU

• Experience and achievements of Chinese contractors and owners commissioning group show that with earlier design and procurement, and some added modularization, construction of the CANDU 6 which is an existing design and proven technology, can be shortened to give a 66 month project schedule from CED. NOTE: Much better possible for NEW design (ACR) which integrates design and construction and commissioning during design phase.

Page 45: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 45

HOW WE DID ITPROJECT MANAGEMENT AND TEAMWORK

Page 46: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 46

CANDU Q3R

• Replicate Qinshan III• Same design except pump house• China as project manager • Same Chinese contractors• AECL with Hitachi and Bechtel provide

equipment and technical support• Increased localization • China does commissioning

Page 47: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 47

• Cost about ¼ less than Q III (1500$ kw)• Schedule 66 months vs. 72 months for

QIII• Shortest schedule in China supports

faster connection to grid.

CANDU Q3R (CONTD.)

Page 48: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 48

The last 20 years: 7% p.a. growth China’s Electricity Generation

0200400600800

10001200140016001800

1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002Year

Gene

rati o

n , T

Wh

Gene

rati o

n , T

Wh

Average growth ~ 7% p.a.

Page 49: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 49

The next 50 years – 3.5% p.a. growth

0200400600800

100012001400160018002000

1980 1986 1992 1998 2004 2010 2016 2022 2028 2034 2040 2046Year

Gene

rati n

g Ca

p ac it

y, GW

TotalInstalledCapacityof:

China: Total Generating Capacity

USA

Canada

About 1,050 kW/capita –

same as Korea today

Page 50: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 50

Nuclear Potential in China

Generating Capacity AdditionsShort Term Long Term2003-2015 2003-2050

Total capacity added, MW/yr 30,000 36,000Nuclear market share 6% 16%Nuclear capacity added, MW/yr 1,800 6,000

Page 51: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 51

CANDU Opportunities in China

• CANDU advantage is short schedule, economic, fuel cycle flexibility

• Ongoing good performance of Qinshan supporting new projects

• Good Chinese Canadian partnership

Page 52: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 52

Page 53: CNS CONFERENCE Qinshan Project - June 2003 Library/20031801.pdf · 2010. 12. 8. · Pg 5 Reference Data •Qinshan III CANDU NPP −2 x 728 MWe by AECL and TQNPC −Zhejiang Province,

Pg 53