    miningcommissioning capabilities

    CNMANAGEMENTCommissioning Management Solutions

  • 8/9/2019 CN AU Mining Capabilities

    2/5

    commissioning

    Why is Commissioning Important?

    Commissioning ensures that the

    systems and materials that comprise

    the Plant meet the Clients project

    requirements and result in successful,

    better built Plants. Therefore it is

    critical that commissioning is involved

    in both design and construction

    phases in order to minimise costs

    and maximise benefits. With an

    increased focus on sustainability and

    the consequences of insufficient

    design review, inadequate equipment

    capacity , inferior equipment

    installation, insufficient maintenance

    and improper system operation;

    early commissioning should be

    implemented into each Project stage

    in order to realise cost savings and

    successful Project delivery. Over time,

    continuous commissioning is the best

    way to determine whether controls

    and equipment function properly.

    Ensur ing Pro jec t Del ivery

    Early review of design systems Input into Commissioning strategies

    and the ability to represent the Client

    as a professional team

    Strategies for ensuring maintenancepractices are picked up early to

    prevent breakdown maintenance

    Ensure documentation requirementsare completed by the D&C team in a

    format designed for the Client

    Lead D&C teams to gain a smoothtransition for the O&M team

    Detailed communication at all levelsthrough to the Clients Management

    Integration of systems for best forproject outcomes

    Understanding of Trainingrequirements for Operations Sta. Online/Real time reporting through

    the life of the project (live dashboard

    reporting utilising our CVRS system)

    We are a community in commissioning, engaging on all levels as part of a

    TEAM to ensure that commissioned means commissioned! Through our

    people, systems and lessons learnt throughout various industries across the globe,

    we deliver innovation, rectication and robust commissioning reviews and solutions.

    As reinforced by our client base which has remained consistent over 15 active years,

    we are able to make a dierence. Aside from constantly monitoring our knowledge

    and ability, we have provided many solutions for dicult designs or process conditions

    leaving clients satised they have a manageable and optimised plant to operate.

    What is Commissioning?

    Commissioning is defined as the process

    by which an equipment, facility, or plant

    (which is installed, or is complete or

    near completion) is tested to verify

    if it functions according to its design

    objectives or specifications. It is essentially

    an independent verification of the

    Clients project requirements from

    project inception through to handover

    and can continue for the life of the

    project. Commissioning typically begins

    during the project design phase and

    continues for at least one year after

    construction is complete. It requires

    thorough documentation of system

    design, construction quality, functional

    performance tests, and operation and

    maintenance requirements. The training

    of facility operators and staff is also a key

    component of commissioning as they will

    be responsible for plant operations and

    maintenance.

    Increased in-house knowledge and improved equipment operation

    Better planning and coordination for smoother equipment start-up

    Better up-front performance accountability

    Improved Plant control and performance

  • 8/9/2019 CN AU Mining Capabilities

    3/5

    Commissioning Innovations demonstrated by using

    software, procedural guidelines and our own system;

    AUTOCOMM

    Experienced and skilled personnel - Mechanical, Electrical,

    I&C, SCADA/PLC, Process and QA disciplines all of which

    have operational and commissioning experience across

    various industries

    Defect Management Clear understanding of Plant elements

    and groups whilst ensuring precise defect reporting and

    priority management.

    Documentation Experience in production, review &

    processing of Commissioning/Design Documentation

    Operations experience to ensure risks are minimised, with

    added value of Process science skill to avert any incidents.

    GAP analysis provided across the board from Design to

    Handover enhancing the risks associated with overdesign,

    incorrect procurement, abortive operational costs and

    OPEX variance.

    CNManagment is a local Australian company with links to an international network of capabilities, predominantly within the

    UK. Founded in 1995, under the CNGroup of companies, our proven capabilities are based on decades of research and hands-

    on practical experience culminating in a broad and continuing client database. Employing approximately 300 people across 3

    countries, we have proven success in areas of commissioning, client tenders, innovation studies, project engineering, concept of

    design and rectication of design and construction GAPS.

    Andrew Rogers CommissioningManager

    Recently completinga successful roleas

    CommissioningManagerfortheSouthern

    RegionalWaterPipeline Alliance;oneof

    thelargestwaterinfrastructureprojectsin

    Australia,AndrewRogershassincejoined

    CNManagementinaseniorroletoguide

    their Queensland operations. With an

    extensiveknowledgeof water andwaste

    waterprocesses,Andrewsawarenessand

    experience within the Australian Water

    Industryishighlyvaluedandrecognized.

    Clive NeameManagingDirector

    Creatorand ownerof the CNGroupof

    companies,Clivehasover15 yearsof

    managementandcommissioningexperience

    acrossa numberof continents.Renowned

    forhis ability to innovate commissioning

    programmes,he brings a rich blend of

    commercialandpersonalexperienceanda

    proventrackrecordindeliveringsuccessful

    resultsonaglobalscale.

    Andr Bosch OMTechnicalManager

    Backed by extensi ve exper ience in

    the maintenance, const ruct ion and

    telecommunica tion indus tr y. Andr

    has exper ience in the development

    o f Maintenance S trategies and the

    Computerised MaintenanceManagement

    S ys tem (CMMS) a s t he v ehi cle t o

    deliver the vision of various service and

    manufacturing industries. Prior positions

    includeMaintenanceEngineerforBrisbane

    Water,JohnHollandConstructions,Capral

    AluminiumandBoralPlasterboard.

    KeySkills

    AboutUs

    OurLeaders

    Feasibility Studies

    Successful feasibility studies with accurate

    and experienced environments will reduce

    CAPEX and OPEX and prolong stable

    asset environment. Innovated systems and

    knowledge transfer enables us to collect

    and process data eciently.

    Pre-Commissioning

    In readiness for the commissioning of the

    system as a whole, individual pieces of

    equipment/instruments are required to

    function in isolation. This is a vital element

    in achieving successful commissioning.

    Process Commissioning

    A planned and structured approach

    by ensuring the process design is fully

    understood and reviewed.

    Reliability Performance

    A planned schedule for assessing the

    reliability of the system and understanding

    the resource requirements to prepare for

    unforeseen events.

    Commissioning Review

    An independent assessment of the

    commissioning process for the purpose of

    providing a review to the Client.This is vital

    to ensure that a robust commissioning

    management system is implemented and

    monitored.

    Defect Management

    A defect management system is required

    to ensure all defects are identied,

    recorded and recommendations are made

    for rectication.

    Design Challenge & Innovation

    Understanding the dierent stages of a

    project in order to realise savings. This is

    achieved through understanding the scope

    and development of strategies, focusing

    on increased eciency. Additionally,

    milestones are developed and documents

    produced by the O&M Documentation

    Team to ensure project timeframes are

    met.

    Project Commissioning Engineering

    Completion of Work Method Statements

    and Risk Assessments for all works and

    procedures for the site, prior to the Wet

    Testing using CN Equipment to bring

    services into a commissioned state. The key

    values include; Early Start Commissioning

    with Access Database System to record

    commissioning that eliminates out of date

    documents, direct commissioning that

    eliminates third parties attendance and

    repetitive costs incurred, as well as tamper

    proof systems tted on all equipment that

    prohibit changes by unauthorised parties.

    Process Support

    Following a review of the Commissioning

    Plan, the team are able to further support

    the project through; open communication

    with all project groups, ensure compliance

    of statutory requirements for b ulk transfer

    of water, supply technical reports &

    discussion papers, review process model,

    provide recommendations to analyse the

    requirements for control and targets for

    chemical dosing and optimised methods.

    PLC, SCADA & Telemetry

    The team are able to design, review and

    commission any conguration of work in

    the aspects of Data and I/O Management.

    The availability of PLC, Telemetry and

    SCADA engineers provides the client with

    signicant commercial potential and allows

    in-house management of these areas.

    cap

    abilities

  • 8/9/2019 CN AU Mining Capabilities

    4/5

    Tailored to P&IDs di rect interface with design using Asset and P&ID Tags.

    Live Status - for the Installation, Testing & Commissioning of the entire Plant.

    Central Resource - Live progress reports and project documentation.

    Online access portal - allows anywhere, anytime review

    Defect Management - provides a systematic method for documenting, tracking and following up on

    critical issues & defects.

    Multiuser access through designated logins to ensure access levels, tracking and accountability

    Avoids GAPS - created when fast tracking programmes

    Audit trail - allows continual audit, accountability & transparency

    Intelligent Systems

    Autocomm is a web based dashboard project

    management system for the Water/Oil & Gas industries

    that provides commissioning visibility throughout the

    projects life cycle. The program software is designed

    to ensure clients, project managers and the general

    public (at an agreed level of access) have access to

    real-time project programme information. The ability

    to readily access information from anywhere ensures

    that the client and project members are never apart.

    Clients have access to the project overview and are

    able to track as well as report on the projects progress,

    without the expense of managing extensive resource

    proles on sta or contractors. (Avoiding client gaps).

    Case Study - Adelaide Aqua

    Utilising Autocomm, the commissioning team was able to

    eectively realise the project requirements. The system was

    tailored to meet the needs of the multinational consortium,

    Adelaide Aqua. The following measures were implemented:

    Asset and P&ID tagging a compiled list of assets received

    from the project were able to be s treamlined into specic

    lters and uploaded to the database. Assets were then

    tagged specically to its P&ID Drawing and assigned its

    relevant OM Manual.

    First Water Review - Intelligent P&IDs were created with

    the ability to view isolation points

    Flow Level Display - Ability to view multiple commissioning

    ow levels

    HV-LV Display - Energisation of HV-LV Systems

    Reporting Each asset was assigned reports (Delivery,

    Installation, Pre-commissioning, Available). Each report

    was dependant on its previous to eliminate any fast-

    tracking and prevent future risks associated with it.

    Document Management - Operational Philosophies andGAs for each plant area were made available for quick

    referencing and download

    Defect Management Throughout the reporting phase,

    a defect option was linked to each report in order to

    highlight the number of defects and assign a priority.

    Project Outcome

    In implementing Autocomm, the project is able to; reduce its

    overall project risk prole and realise signicant time and cost

    value to all project control functions. Additionally, Clients have

    access to a live status overview of their project utilising the

    Dashboard function to display milestones.

  • 8/9/2019 CN AU Mining Capabilities

    5/5

    CNMANAGEMENT

    Australia

    Waterfront Place, Level 25, 1 Eagle Street, Brisbane QLD 4000Ph: (07) 3229 0255

    Email: [email protected]

    UK Scotland

    7 Woodstone Court, Pier Road, Rhu Scotland G848LH

    Ph: +44 (0) 7767845032

    Email: [email protected]

    UK Yorkshire

    9 The Wend, Carlton in Craven Yorkshire BD233EEPh: +44 (0) 7802518925

    Email: [email protected]

    www.cngmanagement.com