DEPARTMENT OF PLANNING & OPERATIONS  Saving Lives and Supporting Development for Cambodia Page 1 of 32 CAMBODIAN MINE ACTION CENTRE CMAC ANNUAL DEMINING ACHIEVEMENT REPORT JANUARY – DECEMBER 2017 1. General Situation Landmine and Explosive Remnants of War (ERW) problems in Cambodia occur across the country and present a constant risk and area real barrier to development in both town and the country, especially for agricultural activities in rural areas. Most of the infrastructure and resources that were broken during the war need to be restored and strengthened to assist in developing all parts of the agriculture and natural resource sectors.

Transcript of CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of...

Page 1: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 1 of 32

CAMBODIAN MINE ACTION CENTRE

CMAC ANNUAL DEMINING ACHIEVEMENT REPORT

JANUARY – DECEMBER 2017

1. General Situation

Landmine and Explosive Remnants of War (ERW) problems in Cambodia occur across the country and present a constant risk and area real barrier to development in both town and the country, especially for agricultural activities in rural areas. Most of the infrastructure and resources that were broken during the war need to be restored and strengthened to assist in developing all parts of the agriculture and natural resource sectors.

Page 2: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 2 of 32

CMAC, as the national humanitarian demining operator, is working hard on this matter in order to save lives and support development of the Cambodian people. Today, CMAC continues to undertake a number of bilateral and counterpart projects in order to support its demining management plan, as set out in the annual integrate work plan 2017, as well as in CMAC’s 5-year strategic work plan from 2015-2019. However, from January to December 2017, 237 working days were assigned and limited for all CMAC Demining Unit (DU), Technical Institute of Mine Action (TIMA), and Development Demining Unit (DDU) and CMAC Central Headquarter to respond the demining tasks to all communities’ needs, local authorities, stakeholders, Royal Cambodian government and NGOs for safe environments, development and risk reduction from the threats of landmines/ERW in Cambodia. Within this period, 148-day was for public holiday, weekend and compulsory annual leave days. 2. Deployment Tools (Asset) From January to December 2017, CMAC demining resources were assigned to the various CMAC’s Demining Unit, Head Quarter, Development Demining Unit (DDU) and CMAC Technical Institute of Mine Action (TIMA). However, all CMAC demining teams are still working to support many landmine/ERW high priority clearance tasks selected through the National Planning Mechanism, often refers to as MAPU process, as participatory and bottom up approach methods to mine action planning; and urgent humanitarian and development supported tasks requested by local authorities and mine/ERW affected communities. The following table 1 shows us the demining tools (asset) by each Demining Unit for December 2017.

Page 3: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 3 of 32

Table 1: (Deployment in December 2017)

Demining Unit

Actual Demining Assets (Tools)

MP

BA

C-L

EO

D

NT

S

TSC

-(5

staf

f)

TSC

-( 7

st

aff)

SLD

(4 d

ogs)

SLD

(2 d

ogs)

LL

D

ED

D

DM

BC

(2 S

taff

)

BC

( 9

Staf

f)

BA

C-S

ER

WI

BA

C-M

TT

MD

R

CB

MR

R

IED

-Dog

Div

ing

DU#1(BMC) 3 - - - - 1 - 2 - - 2 - 4 1 1 - - 5 - -

DU#2(BTB, PLN, PST) 7 - - - 1 14 2 4 1 - 8 4 3 3 2 - - 16 - - DU#4 (SRP, Kg. Thom, PVH, OMC) - 1 - - 1 2 - - - - - 1

-- 1

- 1 1 - -

DU#5 (Eastern provinces) - 4 - - - - - - - 4 - 1 - 13 - 5 - - - -

DU#6 (SRP & OMC) - - - - - - - - - - - - - - - - - - - Development Demining Unit (DDU) 3 - - - 1 5 - - - - - 8 - - - - - - - -

CMAC HQ (Phnom Penh) - - 2 - - - - - - - - - - 1 - 1 - - - -

CMAC Technical Institute of Mine Action (TIMA)

- - - 1 - - - - - - - - - - 3 - - - 1 1

Community Development. Center (CDC) - - - - - - - - - - - 4 - - - - - - - -

Total teams deployed 13 5 2 1 3 22 2 6 1 4 10 17 7 18 7 6 1 22 1 1

Note: Movements:

4BC (BC#10 15 20 and BC#23), TSC#30 and MPL#142 of DDU-DNR5-3 starts operational clearance mine/UXO along National Road No.5 from 01 January to 31 December 2017.

BAV#03 and BAC-S#01 at former HQ-CMA-17 were moved to work with DDU under NR5-3 project

from 01 February 2017.

2TSC (TSC#07&19) at former DDU-EDC2 were moved to work with DDU under NR5-3 project from 01 February 2017.

ERWi#22 at former DDU in NR5-3 project was moved to work with APOPO project in DU4 from 01

February 2017. TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb

2018.

BAC#19 is recreated and deployed at DU2-CFR14 from 01 March 2017 to 28 February 2018.

5BC(BC#03,13,15,20,23), 3TSC(TSC#07,12,19) and BAC#01 of former DDU-NR5-3 moved to work along National Road No.4 of DDU-ALEX-02 from 15 March until 30 July 2017.

4MPL(MPL#101,102, 103 and MPL#104) are recreated and deployed the operational mine/UXO

clearance along National Road No.4 under DDU-AlEX-02 from 15 March until 31 July 2017. TSC#21 of DDU-ECD2 starts working on 27 March 2017. 2 NTS (NTS#01 and 04) of DU1-CFR have been deployed an operation in Banteay Meanchey province

from 01 April to 31 October 2017.

Page 4: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 4 of 32

3 NTS (NTS#02, 03 and 14) of DU2-CFR have been deployed an operation in Battambang and Pailin provinces from 01 April to 31 October 2017.

2 TSC (TSC#08 and 30) of DDU-NR5-3 have been moved to work at DDU-ALEX2 from 01 May to 31 July 2017.

TSC#18 of DDU-NR5-3 have been moved to work at DU4-RGC12 22 May 2017 until new notice.

2TSC(TSC#07&08) of DDU-NR5-3 were transferred to work for EDC-2 of DDU from 24 Jun to 31 Oct

2017.

BC#10 of former DDU_NR5-3 West moved to work at DU1_CFR13 (Top Up) 0n 01 December 2017.

NTS#03 of former TIMA_Golden West moved to work at CMAC HQ_CMA17 0n 01 December 2017

Anyway, during the report in 2017 signaled some changes in the CMAC’s deployment. First, Mobile Platoons were recreated which each Mobile Platoons consisted of 17 deminers to deployed the operations under DDU-Alex02 project for four and half months from 15 March 2017 until now. 5 non-Technical Survey/Basline Survey teams (NTS/BLS-5) were also recreated to provide land reclamation non-technical survey and Basline survey services under DU1 (2teams) and DU2 (3teams) CFR projects for 6 months from 01 April to 30 September 2017 and 2 teams continued their tasks for 2 months from October to November 2017and another team worked at TIMA_Golden to survey underwater ERW West for 2-month from October-November, this team moved to work at CMAC HQ_CMA17 on 01 December 2017. Other hands, 3 SLD teams which were recreated and deployed operation at DU1 (1team) and DU2 (2teams) on 01 August 2017.

The below table 2 is showing the real mine action teams for year 2017:

Page 5: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 5 of 32

Demining Tools 

Deployment from January to December  2017

Jan 

Feb 

Mar 

Apr 

May 

Jun 

Jul 

Aug 

Sep 

Oct 

Nov 

Dec 

Mobile Demining Platoon (MP27)  9  9  9  9  9  9  9  9  9  9  10  10 

Mobile Demining Platoon (MP17)  ‐  ‐  4  4  4  4  4  4  4  4  3  3 

Battle Area Clearance‐Large Team (BAT‐16)  4  4  4  4  4  4  4  5  5  5  5  5 

 Technical Survey and Clearance Team (TSC7)  25  25  23  23  23  23  23  23  23  23  22  22 

Technical Survey and Clearance Team (TSC7)  2  2  2  2  2  2  2  2  2  2  3  3 

Non‐Technical Survey/Based line Survey team  ‐  ‐  ‐  5  5  5  5  5  5  3  3  3 

Short Leash Detection Dog (SLD‐4dogs)  2  2  2  2  2  2  2  2  2  2  2  2 

Short Leash Detection Dog (SLD‐2dogs)  3  3  3  3  3  3  3  6  6  6  6  6 

Long Leash Detection Dog (LLD)  1  1  1  1  1  1  1  1  1  1  1  1 

Explosive Detection Dog (EDD)  4  4  4  4  4  4  4  4  4  4  4  4 

Improvised Explosive Detection Dog (IED_DOG)  1  1  1  1  1  1  1  1  1  1  1  1 

Brush Cutter Team (BC9)  3  3  3  3  3  3  3  3  3  4  6  7 

Brush Cutter Team (BC‐2)  20  20  20  20  20  20  20  20  20  19  17  16 

Demining Machine ( DM‐2)  2  2  2  2  2  2  2  2  2  2  2  2 

Demining Machine ( DM12)  3  3  3  3  3  3  3  3  3  3  3  3 

Demining Machine ( DM21)  5  5  5  5  5  5  5  5  5  5  5  5 

Battle Area Clearance By Village (BAV)  1  1  1  1  1  1  1  ‐  ‐  ‐  ‐  ‐ 

Battle Area Clearance‐Small Team  (BAC‐5)  16  16  18  18  18  18  18  18  18  18  18  18 

Battle Area Clearance‐Multi Technical Team  (ERWI‐5) 

6  6  6  6  6  6  6  6  6  6  6  6 

Explosive Remnants of War Intervention (ERWI) 7  7  7  7  7  7  7  7  7  7  7  7 

Explosive Ordnance Disposal (EOD3)  2  2  2  2  2  2  2  2  2  2  2  2 

Community Based Mine Risk Reduction (CBMRR) 21  21  21  21  21  21  21  21  21  21  21  21 

CMAC Salvage Dive Unit  1  1  1  1  1  1  1  1  1  1  1  1 

Explosive Harvesting Program  1  1  1  1  1  1  1  1  1  1  1  1 

Note:

6 ERWI(ERWI#08,10,14,16,23 and 28) of DU5-USA20 renamed as Battle Area Clearance –Small Team (BAC-S) on 1 November 2016.

4 BAT(BAT#01,02,03 and 04) of DU5-USA20 renamed as Battle Area Clearance –Large Team (BAC-L) on 1 November 2016.

2 SLD teams that consisting of 4 dogs are rented for MAG in whole year.

All staff of BAV resigned on 31 July 2017.

4 Mobile Demining Platoon that consisting of 17 deminers were recreated on 15 March 2017. All these MP were deployed to have operational clearance mine/UXO for DDU-Alex-02 project until 31 July 2017.

5 Non-Technical Survey/Based line Survey were deployed to provide the reclamation and cancellation services in DU1(2team) and DU2 (3teams) from 01 April to 30 September 2107. The rest 2 teams continued their tasks until 30 November 2017.

Page 6: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 6 of 32

1 Area Clearance –Large Team (BAC-L) was created and deployed to have operational clearance mine/UXO on 01 August 2017.

Table 2:

To clarify the real locations of CMAC demining resources throughout the country in 2017, the following map is showing the CMAC tools deployment as of December 2017.

3. Summary of Progress Achievement The progress achievements, from 01 January to 31 December 2017, were ranged from the delivery of large scale mine clearance, community development, grass roots community education activities, and international training programs to cutting edge technological research. Up to December 2017, CMAC has achieved significant operational clearances, which are described below: Total released Landmine/UXO contaminated area: 104,052,429m2 and divided into 3 categories as

below: Mined Field: 50,340,922m² UXO Field: 38,352,356m² Areas Survey and Safety principle: 15,359,151m2

Total Mine/UXO found and destroyed: 45,253 items

APM: 5,277 items ATM: 108 items UXO: 39,739 items

Page 7: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 7 of 32

AXO 20 items Improvised mine: 109 items Small Arms found and destroyed: 1,852 Kg Fragment: 1,786,155 pieces

Cutting grass: 6,202,984m² Liner of marking: 1,470,281 m Responded to 3,974 tasks of 3,977 EOD calls (requests) Conducted MRE sessions to: 159,132 audiences

Men: 55,499 persons Women: 47,713 persons In school children: 35,976 persons, Out-of school children: 19,944 persons

Number of villages visited: 5,122 times Number of MRE session: 9,330 courses Number of household visited: 6,071 households

4. Land Release Achievement Analysis for January-December 2017 From January to December 2017, at least 104,052,429m² of landmine/UXO areas have been released throughout the country. This includes 50,340,922m² of minefield areas, and 38,352,356m² of UXO field areas and 15,359,151m2 of areas cleared as called Survey and Spot Check for Safety without sketches, which is 103.53% compared to yearly target of 100,500,000m² in 2017. In total from January – December 2017, all teams were able to release 104,052,429m², while the total accumulative progress for the same period in 2016 is 86,964,505m2 that is 19.65% more than the progress of yearly progress in 2016. The below Chart.1 is presented the yearly target Vs progress achievement accomplished in 2017. Anyway, during the yearly progress report, in response to this land release as mentioned above; at least 5,277 AP mines, 108 AT mines, 109 IMP and 39,759ERW were found and destroyed safely. By comparing these items (mines and Explosive Remnants of War) which were found and destroyed for 1 year (As of 45,253 items) to the yearly target in 2107 (as of 50,000 items), it is 90.51%. The Chart.2 below is presented the devices found and destroyed by comparing to yearly target of mine/UXO in 2017.

50,000

45,253

42,000

43,000

44,000

45,000

46,000

47,000

48,000

49,000

50,000

51,000

Yearly Target Actual year Items

Chart 2: Comparison between Yearly target and actual items (Device) found 

and destroyed  in Jan‐Dec 2017

Year‐Actual: 104,052,429

Yearly Target: 

100,500,000

Chart1: Comparison between  yearly Target and Actual yearly  clearance  in  Jan‐Dec  2017

Page 8: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 8 of 32

5. Allocation of Demining Tools (Assets) by Project: In addition to the deployment by each Demining Units (DU) and by month, CMAC also deployed its demining resources (assets) to support each project so that they may respond to the projects’ target as said within the project agreement and also to meet the project’s requirement as the following resources in Table 3:

Overview of the Committed Assets by Project Table 3: a)- From January to June 2017

S/N Project's name Jan-17 Feb-17 Mar-17 Apr-17 May-17 June-17 Remarks

1 CFR11-DU1 1MPL, 1SLD

1MPL, 1SLD

1)-CFR-11project has started from 01-March 2016 to 28 –February 2017. 2)-TSC#02 Moved to worked at DDU-NR5-3 since 01 January 2017.

2 CFR13-DU1

1MP,1SLD,1BC,1BAC,1PC-CBMRR

1MP,1SLD,1BC, 1BAC,1PC-CBMRR

1MP,1SLD, 1BC,1BAC ,1PC-CBMRR

1MP,1SLD, 1BC,1BAC ,1PC-CBMRR

This project starts form 01 March 2017 to 28 February 2018.

3 NTS-CFR-DU1 2 NTS 2 NTS 2 NTS

1)- NTS#04 starts form 01 April to 30 September 2017. 2)- NTS#01 starts form 01 April to 30 November 2017.

4 DU1-CMA-17 Some Office staff

Some Office staff

Some Office staff

Some Office staff

Some Office staff

Some Office staff

5 CFR12-DU2

1MPL, 3TSC, 2BC, 1SLD, 1BAC,

1MPL, 3TSC, 2BC, 1SLD, 1BAC,

1)-CFR12- project has started from 01-March 2017 to 28 –February 2017. 2)- TSC#16 of former DU1-CFR11 moved to work at DU2-CFR12 on 31 December 2016.

6 CFR14-DU2

1MP,2BAC,1TSC,1BC, 1PC-CBMRR

1MP,2BAC,1TSC,1BC, 1PC-CBMRR

1MP,2BAC,1TSC,1BC, 1PC-CBMRR

1MP,2BAC,1TSC,1BC, 1PC-CBMRR

This project starts form 01 March 2017 to 28 February 2018.

7 NTS-CFR-DU2 3 NTS 3 NTS

3 NTS 1)- NTS#03,1 start form 01 Apr to 30 Sept 2017. 2)- NTS#02 starts form 01 Apr to 30 Nov 2017.

8 CMA17-DU2 2PC, 1TMO, 10 CBM

2PC, 1TMO, 10 CBM

1PC, 1TMO, 10 CBM

1PC, 1TMO, 10 CBM

1PC, 1TMO, 10 CBM

1PC, 1TMO, 10 CBM

This project starts from 01 March 2017 until new notice. 2)- 2CBM of DU2 (Samlot&rattanak mondol districts) transferred their project DU2-CFR12 to DU2-IMV3 from 01 Nov 2017 to 31

Page 9: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 9 of 32

S/N Project's name Jan-17 Feb-17 Mar-17 Apr-17 May-17 June-17 Remarks

Oct 2019.

9 CAC(IMCCD) 1TSC 1TSC 1TSC 1TSC1TSC

This project is just renewed for a new agreement from 15 August 2016 to 15 August 2017.

10 IMV3-DU2

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

1)-IVM3 project starts from 01 Nov 2016 to 31 Oct 2019

11 JMAS-CBPD, DU2

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

This project is just renewed for a new agreement from 08 October 2016 to 07 October 2017.

12 SVC (Infrastructure), DU2

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

This project is just renewed for a new agreement from 01 Apr il 2017 to 31 March 2018.

13 DU2-MAG 2SLD 2SLD 2SLD 2SLD 2SLD 2SLD

1)- SLD#12 starts operation from 01 Feb 2016 to 31 Jan 2017. 2)- SLD#03 starts operation from 01 Aug 2016 to 31 Jul 2017.

14 DU4-CMA-17 DU4 some office

DU4 some office

DU4 some office

DU4 some office

DU4 some office

DU4 some office

15 DU4-MDR-APOPO 1BC, 2TSC,

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1)-This project starts on 01 Jan to 31 Dec 2017(MRD#01, TSC#22 , BC#25 and 5 staff). 2)- TSC#20 starts on 01 June 2016 to 30 April 2017. 3)-ERWI#22 moved from DDU-NR5-3 to work at DU4-APOPO since 01 February 2017

16 DU4-RGC12 1TSC 1TSC This project just starts on 22 May 2017.

17 USA-DU5 & HQ

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

This Project is renewed for a new agreement from 1 Nov 2016 to 31 Oct 2017.

18 DDU-DNR#5-3 1MPL, 9BC,2TSC

1MPL, 9BC,4TSC, 1BAV, 1BAC

1MPL, 4BC,4TSC, 1BAV

1MPL, 4BC,4TSC, 1BAV

1MPL, 4BC,1TSC, 1BAV

1MPL, 4BC,1TSC, 1BAV

1)-This project start operation on 01 January to 31 December 2017. 2)- TSC#02 of former DU1-CFR11 moved to work at DDU-

Page 10: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 10 of 32

S/N Project's name Jan-17 Feb-17 Mar-17 Apr-17 May-17 June-17 Remarks

NR5-3 since 01 January 2017.

19 DDU-ALEX-02 4MP,3TSC,5BC,1BAC, 1BAV

4MP,3TSC,5BC,1BAC, 1BAV

4MP,5TSC,5BC,1BAC

, 1BAV

4MP,5TSC,5BC,1BAC,

1BAV

1)- This project starts from 15 Mar to 30 Jun 2017. 2) 4MPL(MPL#101, 102, 103, 104) are recreated and deployed operation on 15 March 2017. 3)-5BC(03,13,15,20, 23). 3TSC(07,12,19) and BAC#01 of former DDU-NR5-3 moved to work at DDU-ALEX-02 on 15 March 2017.

20 DDU-EDC2 5TSC, 2BC 1TSC 1TSC 1TSC 1TSC 3TSC TSC#07&08 start working on 24 June 2107

21 DDU-CCB 1BC, 1TSC 1BC, 1TSC 1BC

1BC 1BC

1BC

This project commences from 01 Dec 2016 to 30 Nov. 2017.

22 CMA-17-HQ

2 EOD ,1EOD Sup , 1BAC, 1BAV

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD,1EOD Supervisor

2 EOD ,1EOD Supervisor

BAC#01 and BAV#03 of former HQ-CMA-17 moved to work at DDU-NR5-3 since 01 February 2017.

23 CBP-ERW-TIMA

3ERWI 3ERWI 3ERWI 3ERWI 3ERWI

3ERWI 1)-This project is started from 1 March 2016 until 28 February 2017.

24 CMA-17-MDD program in TC

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

This project is starts from 01 January 2017 until new notice.

25 CMA17-TIMA 1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

26 TC- Golden West foundation

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

Reference to Decision:057/ DG/CMAC/15 dated:26-Apr-2015, Those teams are under command, control and support by CMAC-TC.

27 Community Development Center (CDC)

4BC 4BC 4BC 4BC 4BC 4BC

B)- Period: July to December 2017

S/N Project's

name July-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Remarks

1 CFR13-DU1

1MP,1SLD, 1BC,1BAC ,1PC-CBMRR

1MP,2SLD, 1BC,1BAC ,1PC-CBMRR

1MP,2SLD, 1BC,1BAC ,1PC-CBMRR

1MP,2SLD, 1BC,1BAC ,1PC-CBMRR

2MP,2SLD, 3BC,1BAC, 1PC-CBMRR , 1TSC

2MP,2SLD, 4BC,1BAC, 1PC-CBMRR , 1TSC

1)- This project starts form 01 March 2017 to 28 February 2018. 2)- SLD#01 is recreated and deployed operations in DU1-CFR13 from 01 Aug to 30

Page 11: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 11 of 32

S/N Project's

name July-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Remarks

Oct 2017.3)- this project topped up 1MP, 1TSC and 1 BC from 01 Nov 2017 to 28 Feb 2018.

2 NTS-CFR-DU1

2 NTS 2 NTS 2 NTS 1 NTS 1 NTS -

1)- NTS#04 starts form 01 Apr to 30 Sep 2017. 2)- NTS#01 starts form 01 April to 30 Nov 2017.

3 DU1-CMA-17

Some Office staff

Some Office staff

Some Office staff

Some Office staff

Some Office staff

Some Office staff

4 DU1, PCD-JMAS - - -

1MP,1BC, 2DM, 1ERWI

1MP,1BC, 2DM, 1ERWI

1MP,1BC, 2DM, 1ERWI

This project starts from 08 Oct 2017 to 07 Oct 2018.

5 CFR14-DU2

1MP,2BAC,1TSC,1BC, 1PC-CBMRR

1MP,3BAC,1TSC,1BC, 1PC-CBMRR, 2SLD

1MP,3BAC,1TSC,1BC, 1PC-CBMRR, 2SLD

1MP,3BAC,1TSC,1BC, 1PC-CBMRR, 3SLD

3MP,3BAC,1TSC,2BC, 1PC-CBMRR, 3SLD

3MP,3BAC,1TSC,2BC, 1PC-CBMRR, 3SLD

1)-This project starts form 01 March 2017 to 28 February 2018. 2)- SLD#04, SLD#05 and BAC#18 are recreated and deployed operations in DU2-CFR14 from 01 August to 31 December 2017.

6 NTS-CFR-DU2

3 NTS 3 NTS 3 NTS 1 NTS 1 NTS -

1)- NTS#03 &14 start form 01 Apr to 30 Sep 2017. 2)- NTS#02 starts form 01 April to 30 Nov 2017.

7 CMA17-DU2 1PC, 1TMO, 10 CBM

1PC, 1TMO, 10 CBM

2PC, 1TMO, 13 CBM

2PC, 1TMO, 13 CBM

2PC, 1TMO, 13 CBM

2PC, 1TMO, 13 CBM

This project starts from 01 March 2017 until new notice. 2)- 2CBM of DU2 (Samlot&rattanak mondol districts) transferred their project DU2-CFR12 to DU2-IMV3 from 01 Nov 2017 to 31 Oct 2019.

8 CAC(IMCC) 1TSC 1TSC 1TSC 1TSC 1TSC 1TSC

This project is just renewed for a new agreement from 16 August 2017 to 15 August 2018.

9 IMV3-DU2

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

4MP, 8DM, 13TSC, 1LLD, 1SLD, 2ERWI, 4CBM, project staff

1)-IVM3 project starts from 01 Nov 2016 to 31 Oct 2019

10 JMAS-CBPD, DU2

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

2MPL, 2DM, 1BC

- - - These teams moved to work at DU1 on 07 November 2017.

11

SVC (Infrastructure), DU2

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

1Buldozer, 1 Compact roller, 1 dump truck, 1 Excavator

This project is just renewed for a new agreement from 01 Apr il 2017 to 31 March 2018.

12 DU2-MAG 2SLD 2SLD 2SLD 2SLD 2SLD 2SLD 1)- This project is renewed from 01 August 2017 to 30

Page 12: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 12 of 32

S/N Project's

name July-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Remarks

April 2018

13 DU4-CMA-17

DU4 some office

DU4 some office

DU4 some office

DU4 some office

DU4 some office

DU4 some office

14 DU4-MDR-APOPO

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI,

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1BC, 2TSC, 1ERWI

1)-This project starts on 01 Jan to 31 Dec 2017(MRD#01, TSC#22 , BC#25 and 5 staff). 2)- TSC#20 starts on 01 June 2016 to 30 April 2017.

15 DU4-RGC12 1TSC 1TSC, 1BAC-L

1TSC, 1BAC-L

1TSC, 1BAC-L

1TSC, 1BAC-L

1TSC, 1BAC-L

This project just starts on 22 May 2017.

16 USA-DU5 & HQ

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

14BAC-S, 4BAC-L, 6 BAC-MTT, 1BC, 4EDD, 3 EOD Sup and project staff

This Project is renewed for a new agreement from 1 Nov 2016 to 31 Oct 2017.

17 DDU-DNR#5-3

1MPL, 4BC,1TSC, 1BAV

4MPL, 6BC,2TSC

4MPL, 6BC,2TSC

4MPL, 6BC,2TSC

3MPL, 4BC,2TSC

3MPL, 4BC,2TSC

1)-This project start operation on 01 January to 31 December 2017.

18 DDU-ALEX-02

3MP,3TSC,3BC,1BAC, 1BAV

1BC, 5staff 1BC, 5staff 1BC, 5staff Only staff stand by

Only staff stand by

1)- This project starts from 15 Mar to 30 Jun 2017. 2) 4MPL(MPL#101,102, 103, 104) are recreated and deployed operation on 15 March 2017. 3)- This project has been extended from 01-31 Jul 2017. 5)- BC#20 and 5 staff are going on clearance.

19 DDU-EDC5 5TSC, 2BC, 1MPL

5TSC, 2BC, 1MPL

5TSC, 2BC, 1MPL

5TSC, 2BC, 1MPL 4TSC, 2BC 4TSC, 2BC

1)-TSC#07&08 start working on 24 June 2107. 2)- 2BC (BC#03&13), 2TSC (TSC#12&19) and MPL#102 of former DDU-Alex-02 were moved to work for DDU-EDC-2 on 14 July 2017.

20 DDU-CCB 1BC 1BC 1BC 1BC 1BC 1BC

This project commences from 01 Dec 2016 to 31 Dec. 2017.

21 CMA-17-HQ 2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor

2 EOD ,1EOD Supervisor. , 1NTS

BAC#01 and BAV#03 of former HQ-CMA-17 moved to work at DDU-NR5-3 since 01 February 2017.

22 CBP-ERW-TIMA 3ERWI 3ERWI 3ERWI 3ERWI 3ERWI 3ERWI

1)-This project is started from 1 March 2016 until 28 February 2017.

Page 13: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 13 of 32

S/N Project's

name July-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Remarks

23

CMA-17-MDD program in TC

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

MDD Instructors

This project is starts from 01 January 2017 until new notice.

24 CMA17-TIMA

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

1IED-dog, EOD supervisor

25 TC- Golden West foundation

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons)

1 Dive team (11persons) and 1Explosive Harvesting team (8persons), 1NTS

1 Dive team (11persons) and 1Explosive Harvesting team (8persons), 1NTS

1 Dive team (11persons) and 1Explosive Harvesting team (8persons),

Reference to Decision:057/ DG/CMAC/15 dated:26-Apr-2015, Those teams are under command, control and support by CMAC-TC.

26 Community Development Center (CDC)

4BC 4BC 4BC 4BC 4BC 4BC

Note:

The renew period of IMV3 (DU2) is from 01 November 2016 to 31 October 2019.

The renew period of USA20 (DU5) is from 01 November 2016 to 31 October 2017 and this project extended for 2 months from 01 January to 31 December 2017.

The Chroay Chongvar Bridge project (DDU) is from 01 December 2016 until new notice.

The renew period of the demiming on National Road N0. 5- Phase-3 at DDU was from 01 January to 31 December

2017.

APOPO project of DU4 is from 01 January to 31 December 2017.

MAG is ongoing hiring 2 SLD (SLD#03 and SLD#12) to work at DU2 (for Pailin and Battambang provinces) from 1 February 2017 until 30 April 2018.

DU1-CFR13 and DU2-CFR14 have started from 01 March 2017 until 28 February 2018, these project were topped up and extended for 2 times ( in August and November 2017).

The renew period of JMAS (CBD-ERW) at TIMA is 01 March 2017 to 28 February 2018.

The Alex-02 project (DDU) started from 15 March to 31 July 2017. The renew period of the Safety Village Construction (SVC) project in Battambang (DU2) is from 01 April 2017 up

to 31 March 2018. The Project of NTS of DU1-CFR and DU2-CFR started on 01 April to November 2017.

The EDC2 to 5 project (DDU) was from 24 June 2017 until new notice.

The renew period of JMAS-PCD (DU1) is from 08 October 2017 to 07 October 2018.

DDU-Alex-02 project was extended for a month from 01-31 July 2017.

DDU-NR5-3 project was extended for 6 months from 01 July to 31 December 2017.

Page 14: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 14 of 32

2BC (BC#03&13) of former DDU-Alex-02 were moved to work at DDU-EDC-2 on 14 July 2017.

2TSC (TSC#12&19) and MPL#102 of former DDU-Alex-02 were moved to work DDU-EDC-2 on 17 July 2017.

3 SLD (SLD#01, 04&05) and BAC#18 were recreated and SLD#01 is under DU1-FCR13 project and SLD#04&05 and BAC#18 are under DU2-CFR14 project since 01 August 2017.

3MP(MP#101,103&103), 2BC(BC#15&23) and TSC#30 of former DDU-Alex-02 project transferred to DDU-RN5-3

project on 01 August 2017.

All demining tools of DU5-USA20 project were extended for 2-month ( November to December 2017).

MPL#142, 2BC (BC#10&20) and TSC#12 were deployed to have operational clearance mine/UXO under DU1-FCR13 project (Top Up) since 01 November 2017.

2MPL(MPL#102&147) and BC#06 were deployed to have operational clearance mine/UXO under DU2-FCR14 project (Top Up) since 01 November 2017.

BC#10 of former DDU_NR5-3 moved to work at DU1_CFR13 (Top Up) 0n 01 December 2017. NTS#03 of former TIMA_Golden West moved to work at CMAC HQ_CMA17 0n 01 December 2017.

a. Teams deployed Vs Staff Variation in 2017: As mentioned on the table 1 and table 2 above, we can identify the teams deployed and staff per mobile platoons and mobile teams that were lost at least 0.17 during the working period due to the various reasons such as resignation, leave without pay, absent without permission…etc as the following table 4:

Table 4:

Demining Tool/Asset

No. of Teams

Jan-Dec 2017

No of Staff Per

Team

Total Staff (Jan-Dec 2017) Different Remarks

Total Male Female

MPL (27staff) 109 27 2,943 2,699 175 69

9 mobile platoons have deployed from Jan to Oct 2017. There were 10 MPL from Nov to Dec 2017.

MPL (17staff) 38 17 646 646 - -

4 mobile platoons were recreated and deployed to have operational clearance mine/UXO in DDU_Alex-02 project along national road no.4 from 15 Mar to Jul 2017.

BC (9 staff) 44 9 369 382 14 13

1)- Three BC teams were deployed at DU1 and DU2 from Jan to Sep 2017. 2)- The project of PCD-JMAS (DU1) reformed BC#09 consists of 2 persons into 9 persons. 3)- Three BC teams consists of 2 persons were reformed into 9 persons. So there are 7 BC teams now.

Page 15: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 15 of 32

Demining Tool/Asset

No. of Teams

No of Staff

Total Staff (Jan-Dec 2017) Different Remarks

BC(2 staff) 234 2 468 468 - -

DM (21 staff) 60 21 1,260 1,166 74 20

DM(12 staff) 36 12 432 426 - 6

DM(2 staff) 24 2 48 46 0 2

1)- DM#04 consists of 2 operators but DM#10 has only one operator . 2)- DM#10 has been trial and supported fund by JMAS.

SLD 51 10 510 432 63 15

1)- Three SLD teams have deployed to have operational clearance mine/UXO from Jan to July 2017. 2)- Three SLD teams were recreated for project of DU1-CFR13 and DU2-CFR14 on 01 August 2017.

LLD 12 10 120 108 12 -

EDD 48 6 288 276 12 -

TSC 279 7 1,953 1,894 12 47

TSC 25 5 125 89 36 -

BAV 7 7 49 49 0 - All staff resigned. BAC-S 212 5 1,060 1,025 34 1

BAC-L 53 16 848 836 12 -

1 BAC-L was created and deployed at DU4 to have operational clearance mine/UXO on 01 August 2017.

BAC-MTT 72 6 360 360 - - Former ERWI of DU5-USA19.

EOD 24 3 72 72 0 -

ERWI 84 5 420 420 0 -

NTS 37 5 179 179 - -

1)- 5 NTS had deployed operational resurvey at DU1 &DU2 from 01 Apr- 30 Sep 2017. 2)- 2 NTS had deployed operational resurvey at DU1 &DU2 from 01 Sep- 30 Nov 2017.

MDR 12 10 120 84 36 -

CBMRR 255 21 255 185 70 -

IED-Dog 12 5 60 36 24 -

EOD Dive 12 11 132 132 0 -

Total 1,740 12,744 11,997 574 173

Note: 1. Restructure/reform:

Page 16: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 16 of 32

BC#09 consists of 2 operators of former DU2_CBPD (JMAS) reformed into 9 persons moved to work at DU1_PCD(JMAS) on 08 October 2017 until 07 October 2018.

3 BC teams consists of 2 operators of former DDU_NR5-3 reformed into 9 persons moved to work at DU1_CFR13(2teams) and DU2_CFR14 (1team) on 01 November 2017 until 28 February 2018.

One Mobile Plation consists of 17 deminers of former DDU_NR5-3 reformed into 27 persons moved to work at DU2_

CFR14 on 01 November 2017 until 28 February 2018.

BAV#03 of BAC#18 of DDU_Alex-02 were demobilized on 01 August 2016.

b. Planned and actual operational team .day in 2017 There were 237 working-day in 2017, the mobile platoon and mobile team lost at least 0.10 working days because of the movement of teams to the new minefields, attended the meeting, technical working group, receptions of delegations and/or guests who visited the minefields and public holiday as mentioned in page 1, that are the cases of losing working days and progress during the reporting period as below Table 5.

Table 5:

Tools/Assets No. of Tools

Operational Days Jan-Dec 2017

Different Remarks Jan-Dec

2107 Planned Actual

MPL 148 2,881 2,825 56

BC 278 5,494 5,456 38

DM 120 2,410 2,363 47

SLD 51 967 927 40

LLD 12 237 234 3

EDD 48 948 938 10

TSC 304 6,007 5,959 48

BAV 7 141 141 0

BAC-S 212 4,184 4,164 20

BAC-L 53 1,044 1,044 0

BAC-MTT 72 1,422 1,422 0

EOD 24 474 474 0

ERWI 84 1,642 1,613 29

NTS 36 689 684 5

MDR 12 235 235 0

CBMRR 255 4,871 4,858 13

IED-Dog 12 237 237 0

EOD-Dive 12 237 24 213

Total 1,740 34,120 33,598 522

Note:

6. Activities Output

a) Completion Minefield in 2017:

Page 17: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 17 of 32

During the reporting period, all Demining Units completed at least 873 mine/ERW fields. All completed mine/ERW fields have been handed over to the local authorities and communities for productive purposes in accordance with their requests. Among those minefields cleared, it shows the number of beneficiaries as shown in table 6:

b) Number of Minefield and Socio Beneficiaries in

2017 CMAC mine action activities contribute significantly to the country in terms of mine/UXO casualty reduction. They also contribute to the enhancement of livelihood, settlement, socio-economic and infrastructure activities for individual and also for the affected community development so as to meet the National Strategy in poverty reduction. Without demining, most development activities cannot be taken place caused by landmine and UXO contamination. Therefore, the CMAC’s mine action activity is still at the top important issue and requirement of the Royal Government of Cambodia

to

assist Cambodians’ people and develop its country as well without the threats of mine/ERW.

Similar to previous years, socio-economic benefits gained in 2017. In total, land and ERW clearance in 2017 benefited in total amount of 77,627 families, which included 4,442 families directly and 72,436 families indirectly as well as approximately 749 students.

A large portion of the cleared land is used to support development, resettlement and agriculture activities, and a small portion goes to humanitarian and emergency purpose. There were 7 categories of land use, after land clearance in 2017 and cleared land allocation in square meters and

percentage is shown in table 6.

Page 18: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 18 of 32

Table 6:

DEVELOPMENT CATEGORY All Demining Tools Agriculture 60,404,630 m²

Resettlement plus Agriculture 5,754,687 m² Resettlement 51,220 m² Road portion (infrastructure development) 2,081,963 m² Road/canal 89,804 m²School 100,944 m² * Others Uses (Pond, health center……), See below 17,054,471 m²

Total 85,537,719 m²

* Other Uses: Pagoda, temples, tourist site, administrative office, well, pond, health center, historical sites, construction sites, risk reduction.

Chart 3: Analysis Chart of Land Use Beneficiary

Agriculture, 60,404,630, 

71%

Resettlement & Agriculture, 5,754,687, 7%

Resettlement , 51,220, 0%

Road, 2,081,963, 2% School, 

100,944, 0%

Road/canal, 89,804, 0%

Other Used, 17,054,471, 

20%

Page 19: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 19 of 32

c) Land Released Productivities from January up to December 2017

The overall progress achievement from January to December 2017 was 104,052,429m², which 14,273,881m² was released as C1 and 17,719,409m² was released as C2 and 56,699.988m² was released as C3 and 15,359,151m² was released by of areas cleared as called Survey and Spot Check for Safety without sketches respectively. In addition to this, at least 16,766 items of Mine/ERW, (3,696 APM including 25 Improvised Mines), 54 Anti Tank mines and 13,016 ERW) were found in the affected landmine and UXO contamination areas to destroy safely. And it should be noted that these figures (mine/UXO found) as mentioned above are not included with the number of devices found and destroyed by EOD teams during the reporting period.

The below table 7 is providing a summary of productivity achieved during the reporting period and implemented by all Demining from January to December 2017.

Table 7: Summary of productivity achieved

Land Released

Categories Area (m²)

AP Mine destroyed

AT Mine destroyed

ERW destroyed

IP Mine destroyed

Fragment Small

Arm(kg)

C1 area released

14,273,881

C2 area released

17,675,584 488 3 1,115

191,419

C3 area released

56,766,806 3,173 51 11,784 25 1,438,108 129

Other Clearance

15,336,158 10

117

156,628

Total 104,052,429 3,671 54 13,016 25 1,786,155 129

Page 20: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 20 of 32

d) EOD Team Operational Achievement

During the report period, CMAC deployed 2 EOD teams at CMAC Technical Institute of Mine Action

(TIMA) and CMAC HQ Phnom Penh but there are other demining tools to EOD jobs so-called BAC, TSC, ERWI, BAC-MTT …etc they were deployed at DU1, DU2, DU4, DU5, DDU and CMAC Headquarter to collect and destroy mine/ERW reported by local authorities, local people, policemen and NGOs. They did this to provide a safe environment free from the threat and fear of mines and ERW in the country. Regarding this activity, those teams achieved the following results:

By the way, in results to compare the number of requests (EOD calls) from January to December 2017, it is 44.16% lower than yearly target plan 2017 (as of 9,000 requests). They did this to

provide a safe environment from the threat and fear of mines and ERW in the country. Regarding this activity, those teams achieved the following results:

Table 8: Description Jan-Dec 2017 Jan-Dec 2016 Variance

Areas Cleared (Spot check) in m² 171,594 129,974 ±1.32

# EOD tasks conducted (Responded) 3,974 2,623 ±1.52

# APM destroyed 1,606 1,788 ±0.90

# ATM destroyed 54 81 ±0.67

# ERW destroyed 26,743 19,408 ±1.38

#Improvised mines destroyed 84 23 ±3.65

# Small Arms Ammunition (kg) 1,723 517 ±3.33

# Fragment (pieces) 28,623 37,854 ±0.76

As the table 8 mentioned above, at least 3,748

requests with 1,690 AP mines(including 84 IMP), 54 AT and 25,964 ERW were collected and destroyed by were collected and destroyed by 2BAC, 7ERWI, 6BAC-MTT and DU5 OPS section, ERWI#16, BAC#16 (DU1), BAC#17, ERWI#13,18 (DU2),ERWI#01 ,06,08 (TIMA), ERWI#22(DU4), BAC-MTT#05,10,14, 25,28, OPS-section (DU5) and also BAC-MTT#23 at CMAC HQ in Phnom Penh from January to December 2017.

e) Mine Risk Education and Reduction (MRE) In addition to the landmine and UXO clearance as

called land release, CMAC also deployed 21 CBMRR District Focal Point (DFP) throughout the country to

Page 21: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 21 of 32

conduct mine risk education and reduction (MRE) activities directly to local and vulnerable people who are living in mine/UXO affected areas to understand as well the mine and UXO incident, threatening and stay away for individual and family safety, especially to avoid from any tampering on unknown items. 5 District Focal Point (DFP) networks in DU1 and 16 District Focal Point (DFP) networks in DU2. However, the remaining CBMRR, demining teams and platoons are still doing their tasks as well to conduct MRE to local communities, authorities and NGOs staff. Regarding this, at least 9,330 MRE sessions to 159,132 audiences, and visited 6,071 households and collected 1,794 community's requests, were carried out by all CBMRR and demining platoons and mobile teams during the reporting period from January to December 2017. The below Table 9 provides an overview of details MRE outputs.

Table 9: Overview of outputs

Types of Progresses Demining teams

CBMRR (DFP)

Total

Village visited 2,988 2,134 5,122 Course of MRE session 4,217 5,113 9,330 Household and field visited 995 5,076 6,071 Total audience group attended in MRE Course 60,133 98,999 159,132 Men 21,140 34,359 55,499 Women 15,805 31,908 47,713 Children in school 11,504 24,472 35,976 Out of school children 11,684 8,260 19,944 Total number of requests(M/UXO) and report to EOD 1,078 716 1,794 AP & Improvised mines 351 680 1,031 AT mines 5 34 39 UXO 3,739 2,236 5,975 MRE materials have been used for their activities large T-shirt - 68 68 Small T-shirt - 164 164 Note book 1,230 793 2,023 Poster 458 1,462 1,920 Flyer 391 922 1,313 Leaflet 4 410 414 Other 220 - 220

7. Productivity Analysis

1) Planned VS actual team deployed in 2017 At the start of the 2017, the certain planned-deployment teams were more than actual deployment ones and some teams deployed after IWP Plan set up.

Page 22: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 22 of 32

Table10: Yearly Planned VS Yearly Actual Deployed

Team/ month

Demining tools

MP

(17-

27st

aff)

BA

C-L

BA

C-S

/B

AC

BA

C-M

TT

SLD

LL

D

ED

D

BC

(2-9

staf

f)

DM

(3-2

2sta

ff)

TSC

(5-7

staf

f)

NT

S

EO

D(3

-5 s

taff

)

ER

WI

IED

-MD

D

D-E

OD

EH

T

CB

MR

R&

PC

Planned 144 48 216 72 12 48 288 120 396 156 72 12 12 24 372Actual 147 53 216 72 51 12 48 278 120 304 37 24 84 12 12 24 255 Variance 3 5 0 72 -21 0 0 -10 0 -92 37 -132 12 0 0 0 -117

2) Progress Comparison to the Set IWP 2017 by Demining Tools: The table 10 below is demonstrated the Set of Demining Tools and Monthly Clearance Target in IWP 2017 by comparing with the Actual Monthly Clearance Target and actual progress achievement accomplished in 2017. Table 11: Yearly Clearance Target and Actual 1-Year Achievement in 2017

Tools/Assets

Integrated Work Plan 2017 Achievement in Jan-Dec 2017

Different of Progress (m²)

No. of Tools

in Plan for 1-year

No. of Actual Tools

deployed for 1-year

monthly Clearance Target (m²)

Total Yearly Clearance Target in IWP (m²)

Total Actual Yearly Target (m²)

Actual Progress from Jan- Dec 2017

(m²)

MPL (27 staff) 144 100 80,000 11,520,000 8,000,000 7,959,316 3,560,684

BC (9 staff) 96 44 75,000 7,200,000 3,300,000 3,954,119 3,245,881

DM (21 staff) 60 60 120,000 7,200,000 7,200,000 6,555,836 644,164

DM (12staff) 36 36 75,000 2,700,000 2,700,000 3,378,159 678,159

DM (2 staff) 24 24 75,000 1,800,000 1,800,000 906,359 893,641

SLD 96 36 50,000 4,800,000 1,800,000 3,256,973 1,543,027

LLD 12 12 60,000 720,000 720,000 858,637 138,637

EDD 48 48 65,000 3,120,000 3,120,000 4,103,026 983,026

MPL BAC‐L BAC‐SBAC‐MTT

SLD LLD EDD BC DM TSC NTS EOD ERWIIED‐MDD

D‐EOD

EHTCBM‐PC

Planned 144 48 216 72 12 48 288 120 396 156 72 12 12 24 372

Actual 147 53 216 72 51 12 48 278 120 304 37 24 84 12 12 24 255

0

50

100

150

200

250

300

350

400

450

Chart2:  Planned  VS Actual team deployed

Page 23: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 23 of 32

TSC (7 staff) 324 194 60,000 19,440,000 11,640,000 9,019,214 10,420,786

TSC (5 staff) 84 24 45,000 3,780,000 1,080,000 477,051 3,302,949

BAV (7staff) 1 1 45,000 45,000 45,000 23,714 21,286

BAC-S (BSL)

48

634,850

BAC-S (TS) 60 48 150,000 9,000,000 7,200,000 7,864,013 1,135,987

BAC-S (FC) 132 110 50,000 6,600,000 5,500,000 12,419,347 449,696

BAC-L (16 staff)

48 52 120,000 5,760,000 6,240,000 12,384,637 6,624,637

BAC-MTT

72 5,000 0 360,000 2,728,397 2,728,397

EOD (5 staff) 132

50,000 6,600,000

6,600,000

EOD (3 staff) 24 24 5,000 120,000 120,000

120,000

ERWI 72 81 50,000 3,600,000 4,050,000 109,835 3,490,165

NTS

33 11,973,800

MDR 12 12 362,530

DDU 162 162 10,100,000 10,100,000 15,082,616

Total 1,963 1,497 1,180,000 104,105,000 74,975,000 104,052,429 16,395,688

Regarding the Table 10 above, the actual progress from January to December 2017 is 104,052,429m². If this is compared to the overall CMAC yearly clearance target (as of 100,500,000m2) in IWP 2017, it presents 103.53% and or it is 3.53% higher than yearly target IWP. But if this progress of 104,052,429m² is compared to the CMAC Yearly Actual clearance target (as of 74,975,000m²) for the same period in 2017, it presents at least 138.78% and/or it is 38.78% higher than the Actual CMAC yearly clearance target 2017.

3) Progress Achievement by Demining Units The purpose of setting out the planned target to all Demining Units is for CMAC Internal Monitoring activity at CMAC Senior Level and also to reflect progress achievement against the annual work plan based on existing projects, project target, demining resources, clearances techniques and methodologies of CMAC. However, DU4

104,052,429 100,500,000 104,052,429

74,975,000

0

20,000,000

40,000,000

60,000,000

80,000,000

100,000,000

120,000,000

ActualAchievementJan‐Dec 2017

IWP Target2017

ActualAchievementJan‐Dec 2017

ClearanceTarget based onActual Team(One‐Year)

Chart3: Comparison between  1‐year actual progress VsIWP  target  2017

Page 24: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 24 of 32

had planned resources more than actual resources the beginning of 2017 and TIMA activities focused on training. Otherwise, each Demining Unit was not set out the same standardized figures (Planned Target), this due each Demining Unit consists of different projects, resources, timeframe and budgeting to perform at different terrain and locations. Regarding this, the table 11 below shows us each Demining Unit progress achieved against the planned target of each DU, starting from January to December 2017. Table 12:

Note: HQ’s productivities included with DDU’s was 15,082,666m2 from January to December 2017.

Chart1: Comparison of each DU target set in IWP 2017 VS Actual yearly Achievement (Jan-Dec 2017)

Even achievement reached the IWP target 2017 but some reasons are encountered during the performing period for some DUs that made them unachievable the clearance achievement against IWP target 2017 as the following points:

1. DU4 has planned deployment tools more than actual ones the beginning in 2017.

2. TIMA has 3 ERWI teams the same as planned deployment tools but these teams focused on training the beginning in 2017.

4) Progress Achievement by Project:

6,360,000

37,860,000

7,860,000

34,080,000

1,800,000 12,540,000

10,290,461

39,424,418

1,504,016

37,618,604

45,606

15,169,324

0

5,000,000

10,000,000

15,000,000

20,000,000

25,000,000

30,000,000

35,000,000

40,000,000

45,000,000

DU1 DU2 DU4 DU5 TIMA DDU/HQ

yearly target plan to be cleared by DU(m2) Actual cleared Areas  by DU Jan‐Dec 2017

S/N Demining Unit

Annual Work Plan Set, 2017 Actual Achievement, 2017 Areas to be cleared by DU in (m²)

Annual (%) by DU

Accumulated progress by DU from Jan-Dec 2017 in (m²)

% in comparing to Annual Work Plan by DU

1 DU1 6,360,000 6.33 % 10,290,461 161.80%2 DU2 37,860,000 37.67 % 39,424,418 104.13%3 DU4 7,860,000 7.82 % 1,504,016 19.14%4 DU5 34,080,000 33.91% 37,618,604 110.38%5 TIMA 1,800,000 1.79% 45,606 2.53%6 DDU/ HQ 12,540,000 12.48% 15,169,324 120.97% Total 100,500,000 100% 104,052,429 103.53%

Page 25: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 25 of 32

In addition to the progress by each DU and by demining tools, CMAC is still implementing and recording the progress by each project including the bilateral and earmark projects. Regarding this, the two different projects hereinafter called (the Clearing for Results “CFR11”) at DU1 and (the Clearing for Results “CFR12”) at DU2 and other projects are presenting as below table 12: Table 13: Some Current Projects Executing the early of 2016 up to December 2017

Project Name 

Project Duration  Achievement 

Project Target 

Percentage 

Starting date  End date 

Project progress   

Project progress  

Project accumulated  % 

up to last month 

in D 2017 (m2) 

progress up to Dec    

in 2016 (m2)      2017 (m2)    

CAC (IMCCD)  16‐Aug‐17  15‐Aug‐18  89,290  25,820  115,110  200,000  57.56% 

USA‐NPA (USA20) 

1‐Nov‐16  31‐Dec‐17  39,178,810  3,579,349  42,758,159  42,815,943  99.87% 

IMV3 for 2nd year 

1‐Nov‐17  31‐Oct‐18  1,899,904  2,099,410  3,999,314  26,721,410  14.97%

CFR‐BMC‐13  1‐Mar‐17  28‐Feb‐18  3,140,699  726,797  3,867,496  5,219,724  74.09% 

CFR‐BTB‐14  1‐Mar‐17  28‐Feb‐18  4,011,450  897,010  4,908,460  7,170,661  68.45% 

5) Operational Factor Analysis: Regarding the above progress mentioned, there have some more relevant reasons that made the productivity did not achieve the clearance target for 12-month period as the following:

1. Fragment Contamination (FC), in total 1,786,155 pieces found over a cleared area of 104,052,429 m². This is 0.02 pieces per square meter. In percentage of technical terms, it is: 93.28% of land cleared had only light fragment contamination, in the operational areas of all DUs, 06.72% of land cleared had medium fragment contamination, in the operational areas at all DUs,

2. The presence of personnel at work, in total (216,389 person-days): 89.23% of total field personnel were present at work 2.78% of total field personnel were assigned to attend CMAC training courses, 0.54% were on mission, 3.32% were on taken annual leave, 0.91% were on sick leave, 0.27% were on compensation leave 0.13% were on maternity leave 0.28% were on leave without pay 0.06% were on leave without permission, 1.58% were shortfall field personnel, 0.06% were absent , 0.21% were on obligation leave (to work out of the project temporarily…etc), 0.62% were absent for other reasons

3. Working Hours, in total (180,296 hours-days): 78.30% of total times were working hours 1.06% of total times were the raining period, 12.61% of total times were the travelling hours, 1.49% of total times were the maintenance periods of all BC and DM teams, 0.39% of total times were the repairing hours of all BC and DM teams, 0.15% of total times were waiting periods to get spare part for repairing some BC and DM teams,

Page 26: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 26 of 32

0.16% of total times were the movement or replacing accommodation and transportation of goods; and BC or DM to the new location,

5.83% of total times were other reasons and or moved BC to assist other development.

4. The Mine Detectors, in total (144,197 mine detector-days): 59.59% of all mine detectors (MD) were actually used for the operations. 40.41% of mine detectors were not used due to deminers being absent or on leave, or detectors

broken and being sent for repairs at the CMAC Central Workshop in Battambang province,

5. The mine detection dogs (MDD), in total (8,489 mine detection dog-days): 66.50% of all mine detection dogs (MDD/EDD) were actually used for operations. 19.90% of mine detection dogs were assigned to attend refresher training at the CMAC TC and 5.17% of mine detection dogs were sick and had to be treated at the CMAC Training Center. 8.43% of lack mine detection dogs.

6) Other Reasons Affecting Operational Progress:

a) Adherence to work plan

During the reporting period from January to December 2017, DU4 and DU5 are still improving the Land Release Techniques, Process and methodology to eliminate the mistakes to their demining teams in terms of correction and prevention of any misunderstanding and technical aspects so that to urge them work well, speed up operations and progress to meet the planned target of CMAC Annual Work Plan as set out of the year 2017.

DU1 and DU2 are continuing to perform their operations smoothly on the Land Release Techniques, Process and methodology with a good result for all projects without any critical issues occurred during this reporting period.

b) Collaboration with others

At least 873 mine/UXOfields have been fully completed and handed over to the land owners and

local communities for productive purposes at Banteay Meanchey, Battambang, Pailin, Pursat, Siem Reap, Oddar Meanchey, Kampong Cham, Kratie and various provinces in collaboration with the local authorities, MAPU and CMAA in doing the QA/QC activities before releasing land safely. In addition to this, during the reporting period all DUs have also cooperated with MAPU, local authorities, NGOs, stakeholders and other development partners in Banteay Meanchey, Battambang, Pailin, Pursat, Siem Reap, Oddar Meanchey, Preah Vihear, Kampong Thom, Kampong Cham, Kratie, Prey Veng, Svay Rieng and southeastern provinces of Cambodia to collect the mine/UXO clearance requests for their next clearance planning.

c) Challenges and actions taken

Demining Unit 1:

It rains heavily and it was flood on some minefields this month. So some deminers walk on foot to the minefileds.

A year by year, minefields are far away and it is very difficult to access during raining and season. Some operational material/equipment is broken and older. Deep search detectors are old and loose its camlocks.

Demining Unit 2:

It rains frequently. There was dense vegetation in some areas.

Page 27: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 27 of 32

Some areas were mineralized soils. There was a lot of fragmentation. Some operational material/equipment such as grass cutters and hand cutting tools are broken.

Demining Unit 4

It rains frequently. There were dense vegetations. Some areas were mineralized soils. Some fields are the plateaus.

Demining Unit 5:

It rains heavily to interrupt operational clearance for field operators. Mobile teams moved often because access road to UXO fields was flood this month. There were dense vegetation, soil as solid as rock and mineralized soils in some areas. It was hard for mobile teams to access the UXO fields because of raining in earlier this year. There were insects in some UXO fields to disturb operational clearance. The ERW requests from local authorities were not taken place on time due because of remote

places.

MDD/EDD Program at TC:

No any female dog showed heating sign for breeding. Heavy rain affected dog training at training fields. Some dog materials at the fields are damaged and old and have to be replaced.

Safety and Occupational Health

- During the report period from January to December 2017, There were neither critical issues nor accidents at all DUs for this reporting period, especially the safety principle and staff healthy were strengthened and suffused to all mobile platoons and teams about SOP, sanitation, epidemic diseases and food prevention.

- All DUs, there were no critical issues concerning to a safety principle and staff healthy happened during the reporting period.

8. Training Activities

a)- Training by Demining Unit: Table 14:

S/N Training Course No. of Courses

No. of trainees

Location Remarks

1 Enhancing disciplinary daily task and operating mine detectors and precaution excavation 5 522

Site accommodation, Battambang

Jan-Sep 2017.

2

Briefing the following: - the method of land released. - one man one lane - the technique of destruction mine/UXOs. - Method of MRE education -the taking care of health and hygiene.

8

297

Site accommodation, Battambang

Jan-Sep 2017

3 DU2 OPS section briefing and refresher training to staff working for JMAS-CBPD project the following:

7 236 Site accommodation Battambang

Jan-Sep 2017

Page 28: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 28 of 32

S/N Training Course No. of Courses

No. of trainees

Location Remarks

- GPS operation - the method of mine clearance in all terrains. - first line management - Training the machine Vallon MVH3CS & VMX 10

4 DU2 Plan/OPS section briefing SOPs, discipline, HR policies, clearing operational equipment, JMAS-CBPD project.

9 576 Site accommodation Battambang

Jan- Sep 2017

Total: 13 819 Note: - DU1, DU4 and DU5 did not provide any refresher course on SOP and other topics to their demining teams during the reporting period up to December 2017.

b)- Training by CMAC Technical Institute of Mine Action (TIMA):

Table 15:

C)- MMD/EDD Training by CMAC Training Center:

S.N Course Title Course No.

Location Trainee Source

Number of Trainee

Duration Remarks

Inter. Train

Exter. Train

Started Date

Finished Date

1 EOD Level 1,2 and 3 20 TIMA DUs 27 - 01 –Sep-16 31- Jan- 17

2 Refresher training course for NTS

1 TIMA DUs 26 - 06-Mar-17 31-Mar-17

3 EOD Level 2 2 TIMA DUs 26 - 13-Mar-17 31-Mar-17 US instructors

4 Refresher training mine detectors 1 TIMA DDU 61 - 15-Mar-17 22-Mar-17

5 CBPD-ERWI(JMAS) Phase-I

4 TIMA TIMA 10 - 10-Apr-17 14-Jun-17

6 Intensive course (CBPD- JMAS)

Phase III DU2 DU2 26 - 17-May-17 26-May-17

7 Brush cutter training 1 TIMA DUs 31 - 22-May-17 13-Jun-17 Japanese instructors

8 Refresher training mine detectors (Vallon)

1 TIMA DDU 7 - 23-May-17 24-May-17

9 EOD level III Phase III TIMA DUs 20 - 29-May-17 16-Jun-17 US instructors

10 Marching rule training course 1 TIMA DUs 30 - 19-Jun-17 21-Jun-17

11 Mine detector Vallon VMH3CS training

1 DU2 DU2 25 - 20-Jun-17 22-Jun-17 CBDP JMAS

12 Baseline and landrelease training (ERWI-JMAS) 1 DU2 TIMA 10 - 20-Jun-17 30-Jun-17 CBDP JMAS

13 Marching rule training course 2 TIMA DUs 30 - 22-Jun-17 24-Jun-17

14 Intensive course (CBDP-JMAS)

IV TIMA TIMA 10 - 24-Jul-17 02-Oct-17

15 Refresher training course for SLD 202 MDD TC DU2 12 - 03-Jul-17 14-Jul-17

16 Training Machine Vallon MV3CS 2 DU4 DU4 14 - 02-Aug-17 04-Aug-17

17 Training Machine Vallon MV3CS

3 TIMA DUs 21 - 07-Aug-17 09-Aug-17

Total 17 Courses TOTAL : 386 - - - -

Page 29: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 29 of 32

Table 16:

9. Major Events:

1. On 10th January 2017, 4 delegates of French officials accompanied by Mr. Phat Phearak, Director of Public Relation department, visited the CMAC dog centre. The purpose of the visit was to learn about the MDD program and activities in training and mine action.   

2. On 11th January 2017, 4 delegates of French officials visited the minefield no. BS/CMAA/06991 at DU2, which is cleared by BC#14, located in Prey Totueng village, Chhnal Moan Commune, Koas Krala district, Banteay Meanchey province.  

  

3. On 20th February 2017, seven Japanese delegates visited the CMAC dog centre. The purpose of the visit was to learn about the MDD training program and activities in mine action.  

S.N Course Title

Course No.

No. of Trainees InstructorResponsibility by:

Duration

Location Staff Dog Internal External Started

Date Finished

Date

1 Advanced training course for EDD 38 3 3 1 15-Dec-16 03-Feb-17 MDP (TIMA)

2 Special course training 36 12 3 - 22-Dec-16 28-Feb-17 MDP (TIMA)

3 Refresher course training 196 20 8 1

-09-Jan-17 20-Jan-17 MDP (TIMA)

4 Refresher course training 198 10 4 1

-06-Mar-17 17-Mar-17 MDP (TIMA)

5 Refresher course training 199 7 2 1 - 20-Mar-17 31-Mar-17 MDP (TIMA)

6 New dog under training

1 - 6 4 - 01-Mar-17 Present MDP (TIMA)

7 Refresher training course 200 10 4 1 - 20-Apr-17 05-May-17 MDP (TIMA)

8 Refresher training course 201 9 4 2 - 22-May-17 02-June-17 MDP (TIMA)

9 Advanced training (1dog)

1 1 1 1 - 08-May-17 30-June-17 MDP (TIMA)

10 Refresher training course 202 12 6 1 03-Jul-17 14-Jul-17 MDP (TIMA)

11 Refresher training course 203 15 6 2 10-Jul-17 21-Jul-17 MDP (TIMA)

12 Refresher training course

204 6 4 1

07-Aug-17 18-Aug-17 MDP (TIMA)

13 Advanced training course 41 2 2 1 08-Aug-17 Present MDP (TIMA)

14 Semi Training 1 6 4 14-Aug-17 09-Mar-18 MDP (TIMA)

15 Refresher training course 205 16 5 1 04-Sep-17 15-Sep-17 MDP (TIMA)

16 Refresher training course 206 10 4 1 02-Oct-17 13-Oct-17 MDP (TIMA)

17 Semi Training 2 5 3 16-Oct-17 04-May-18 MDP (TIMA)

18 Refresher training course 207 21 9 1 20-Nov-17 30-Nov-17 MDP (TIMA)

Total 18 Courses 178 91 30 - - - -

Page 30: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 30 of 32

4. On 23rd February 2017, H.E Heng Ratana, delegate of the royal government in charge as Director General of CMAC which was accompanied by Madam Dr. Mar Phalay, Deputy Director of support/HR department visited TIMA in order to open special course and reminisce key staff and trainees. 

5. On 23rd February 2017, H.E Khem Sophorn, Chairman of CMAC governing council and his colleagues, who were accompanied by H.E Ek Bolin, Director of support/HR department, visited DU1 to reminisce the DUs key staff and deminers at Ou Beichoan pagoda, Ou Beichoan commune, Ou chrov district, Banteay Meanchey province and participated in Mine Awareness Day, Thma Puok district, Banteay Meanchey province on 24th February 2017.  

6. On 24th February 2017, the Mine Awareness Day (MAD) was held in the compound of Thmar Puok high school, Thma Puok district, Banteay Meachey province. This ceremony was chaired over by H.E. Serey Kosal, first deputy president of CMAA and there were 1,751 participants who are the Delegates of CMAA, CMAC, CMAC’s Governing Council, Demining NGO, Local Authorities, local people, teachers and students.  

7. On 24th February 2017, two Japanese visited the minefield no. BS/CMAA/06873 at DU2, located in Thvak village, Andaeuk Haeb Commune, Rotonak Mondol district, Battambang province.    

8. On 5th March 2017, H.E Heng Ratana, delegate of the royal government in charge as Director General of CMAC visited DU5 in order to reminisce the DU5 key staff and field staff. 

9. On 22nd March 2017, there were 21 German delegates visited the TIMA to see the mine/UXO display and training activities.   

10. On 31st March 2017, H.E. William A-Heidt, US ambassador to Cambodia accompanied by H.E. Serey Kosal, first vice president of CMAA, H.E. Heng Ratana, delegate of the royal government in charge as Director General of CMAC and H.E Oum Phumro, CMAC Deputy Director General Visited the TIMA.  Their purpose  of  visit  is  to  attend  the  closing  of  ceremony  on  EOD  Level  2  training  course  which  was instructed by US Marine  instructors  and  saw  TIMA/MDP  training  activites.  This  ceremony  chaired  by H.E. Serey Kosal.   

11. On 30th March 2017, one delegate of UNDP which were accompanied by CMAA officials visited the minefield no. BS/CMAA/22588 at DU1, located in Chouk chey village, Ou Beichoan Commune, Ou Chrov district, Banteay Meanchey province.  

 

12. On 30th March 2017, H.E. Sam Sovanny, Second deputy president of CMAA visited DU2 in order to reminisce the DU2 key and field staff at CMAC Community Development Center (CDC) in Chhnal Moan commune, Koas Krala district, Battambang province.  

 

13.  On 25th April 2017, H.E. Heng Ratana, delegate of the royal government in charge as Director General of CMAC visited DU2. His purpose of visit was to chaired the closing of ceremony on CBPD‐JMAS training course and visited fields operational activities.    

14. On 24th April 2017, 13 Japanese students visited the minefield no. BS/CMAA/22592 at DU1, , which was

cleared by MPL#130, located in Chouk Chey village, Ou Beichoan Commune, Ou Chrov district, Banteay Meanchey province.

15. On 2nd May 2017, Seven Laos trainees which accompanied by 7 CMAC officials visited the minefield no. BS/CMAA/06766 at DU5, located in Trea village, Trea Commune, Krouch Chhmar district, Tboung Kmum province. The purpose of visit is to see the Technical Survey method.

16. On 4th May 2017, Seven Laos trainees which accompanied by 7 CMAC officials visited the TIMA. The purpose of visit is to see the training activities.

Page 31: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 31 of 32

17. On 12th to 16th June 2017, Seven JMAS delegates visited the DU5. Their purpose of visit to observe 3 BAC-(MTT#05, 16 and BAC-MTT#25) of operational activities at fields.

18. On 21st to 23rd June 2017, Thirty CMAA-UNDP and NPA delegates visited the DU5. Their purpose of visit to observe 2 EDD (EDD#02&04), BAC-MTT#23 and BAC-S#11 of operation activities at UXOfields.

19. On 4th July 2017, four delegates of New Zealand visited the minefield no. BS/CMAA/21251 at DU1which was cleared by SLD#07, located in Kdeb Thma village, Kouk Romiet Commune, Thmar Puok district, Banteay Meanchey province. Their purpose of visit is to observe activities of mine action.  

20. On 7th July 2017, H.E. Khem Sophorn, president of CMAC governing council with his key staff visited the DU1 and DU2 to   reminisce with mobile Platoon commanders,  team  leaders, deminers and key office staff.        

21. On 7th July 2017, H.E. Oum Phumro, Deputy Director General of CMAC which was accompanied by JMAS resident representative and DU2 key staff to attend the ceremony of inauguration the primary school building which was supported fund by JMAS at Boeng Prei village, Snoeng commune, Banan district, Battambang province.    

22. On 11th July 2017, there were 26 Iraqi trainees visiting the TIMA. Their purpose of visit is to observe activities of mine action.

23. On 20th July 2017, H.E. Heng Ratana, delegate of the royal government in charge as Director General of CMAC which was accompanied by key staff visited DU2 at CMAC community development center, Chnal Moan commune, Koas Kralar district, Battambang province. His purpose of  the  visit was  to  strengthen discipline and reminisce with mobile Platoon commanders, team leaders and key office staff.

24. On 12th August 2017, JICA delegates led by H.E. Oum Phumro, Deputy Director General of CMAC visited the DU2, minefields at Chi Sang village, Traeng commune, Rotonak Mondol district, Battambang province.    

25. On 25th August 2017, thirty five Japanese delegates (Peace Boat) visited the DU1 office and Mine-field no. BS/CMAA/22722 which is cleared by BC#14 , located in Snal Bat village, Ou Beichoan Commune, Ou Chrov district, Banteay Meanchey province. The purpose of visit is to see the Mine/UXO clearance activities.

26. On 26th August 2017, there are 36 Japanese delegates of Peace Boat Project visited the DU4. Their purpose of visit is to observe the activities of mine clearance of APOPO project and then went on inspection in School compound had already be cleared, and assessed a minefield which would be supported by Peace Boat, where is at Sna’ek village, Srayang commune, Kuleaen district, Preah Vihear province.  

27. On 30th August 2017, thirty five Japanese students visited the DU1 office and Mine-field no. BS/CMAA/22722 which is cleared by BC#14 , located in Snal Bat village, Ou Beichoan Commune, Ou Chrov district, Banteay Meanchey province. The purpose of visit is to see the Mine/UXO clearance activities.

28. On September 11th, 2017, three delegates of JICA accompanied by Mr. Srey Rithisak, DDOP in charge of

R&D, visited the TIMA. Their purpose of visit was to observe the display mine/UXO and the activities of training and explosive Harvesting program of Golden West.

29. On September 13rd, General Prasopchai Kongbran, TMAC Director General leading his 4 delegations official visited the TIMA and Dog Centre accompanied by H.E Oum Phuro, CMAC Deputy Director General. This delegate continuously visited the DU2 on September 14th, 2017.

30. On September 14th, 2017, a group of Media Company with 4 persons from USA accompanied by Mr. Um

Socheat came to visit CMAC Dog Centre. Their purpose of visit was to take film and photos of TIMA/MDD activities of training.

Page 32: CMAC Annual Achievement Report 2017€¦ · TSC#16 of former DU2-CFR12 converted into BAC#16 of DU1-CFR13 from 01 Mar 2017 to 28 Feb 2018. BAC#19 is recreated and deployed at DU2-CFR14

DEPARTMENT OF PLANNING & OPERATIONS

 

Saving Lives and Supporting Development for Cambodia Page 32 of 32

31. On September 26th, 2017, Professor Yoshiaki Ohkami along with Ms. Naotake Kumakai (co-researcher of

Prof. Ohkami) and Mr. Kentaro Imai (Robotics development company executive person) came to visit the TIMA and Dog Center which accompanied by Mr. Phat Phearak. This delegate continuously visited the DU2 to observe DM#05 operated mine clearance at Ta krok villages, Traeng commune, Rotonak Mondol district, Battambang province on September 14th, 2017. Their purpose of visit was to observe the activities of training for deminers and MDD/EDD and activities mine/UXO clearance.

32. On October 11th October 2017, DU2 Deputy manager had a presentation for delegates from CFR14 project

and took them visited the minefield which was cleared by BC#12 at Kouk Roka village, Doun Ba commune, Kaos Krala district, Battambang province.

33. On October 25th October 2017, There were UXO-Laos delegates visited the minefield which was cleared by DM#08 at Thngoar village, Chaeng Meanchey commune, Banan district, Battambang province. Their purpose of visit was to exchange the training experiences of clearance mine/UXO in fields.

34. On November 23rd November 2017, H.E Heng Ratana, Delegate of Royal Government of Cambodia as in charge of Director General of CMAC accompanied by some directors of department visited the DU 5 to reminisce with DU5 key staff and mobile team leaders.

35. On November 24th November 2017, H.E Heng Ratana, Delegate of Royal Government of Cambodia as in charge of Director General of CMAC accompanied by some directors of department visited the DU 2 to reminisce with DU1 and DU2’s key staff, mobile Platoon commanders and team leaders.

36. On November 29th November 2017, H.E Serey Kosal, first vice president of CMAA, H.E. Ly Thuch, general secretary of CMAA, Deputy governor and authorities of Battambang and UNDP delegates led by H.E Heng Ratana, Delegate of Royal Government of Cambodia as in charge of Director General of CMAC visited the DU2 at minefield which was cleared by MP#137 at Peam Ta village, Ta Taok commune, Samlout district, Battambang province.

37. On December 12th to 20th December 2017, there were 26 Iraqi trainees who attended training course of Land Released topics at DU2 office ( for theories) and fields (for practice). This training was  instructed by CMAC Planning/OPS Department officials.        

38. On December 13th December 2017, six delegates of Malaysia visited the DU2 to observe the oprational activities of DM#05 at Svay Sa village, Traeng commune, Rotonak Mondol district, Battambang province.        

39. On December 14th December 2017, H.E. Khem Sophorn, president of CMAC governing council with his key  staff  visited  the  DU1,  JMAS  project  at  Banteay  Ti  Muoy  village,  Toul  Pongro  commune,  Malai district,  Banteay Meanchey  province  to    reminisce  with mobile  Platoon  commanders,  team  leaders, deminers and key office staff.       

10. Suggestion/Conclusion:

The Department of Support/HR should resupply and repair in time the mine detectors and Grass Cutting Machines (Grass Trimmers) to DU1 and DU2 for their smooth operations without any blocking on the ground. Without enough demining equipment, the demining operations will not be run smoothly.

At least one or two chain saw machines are required to store at DUs Headquarter for urgent use by the deminers at some minefields.

The Department of Support/HR should replace unserviceable the grass-cutting tools to all DUs. The Central Workshop at Battambang province shall fix vehicles and demining machines in time with the

best quality without negligent and be higher responsibility.