Closeout Report on the DOE/SC CD-4 Review of the · 2018. 8. 23. · – Project reporting supports...

28
OFFICE OF SCIENCE 1 Closeout Report on the DOE/SC CD-4 Review of the Utilities Upgrade Project (UUP) Fermi National Accelerator Laboratory August 22-23, 2018 Raymond Won Committee Chair Office of Science, U.S. Department of Energy http://www.science.doe.gov/opa/

Transcript of Closeout Report on the DOE/SC CD-4 Review of the · 2018. 8. 23. · – Project reporting supports...

  • OFFICE OF

    SCIENCE

    1

    Closeout Report on the

    DOE/SC CD-4 Review of the

    Utilities Upgrade Project (UUP)

    Fermi National Accelerator LaboratoryAugust 22-23, 2018

    Raymond Won

    Committee Chair

    Office of Science, U.S. Department of Energy

    http://www.science.doe.gov/opa/

    http://www.science.doe.gov/opa/

  • OFFICE OF

    SCIENCEReview Committee

    Participants

    2

    Raymond Won, DOE/SC, Chairperson

    Observers

    Marc Jones, DOE/SC

    David Michlewicz, DOE/SC

    Steve Neus, DOE/FSO

    Review Committee

    Subcommittee 1—Technical

    *Pat Hogan, ANL

    Dan Nassar, ANL

    Subcommittee 2—ES&H

    *Michelle Solaroli, TJNAF

    Subcommittee 3—Cost and Schedule

    *Kelly Krug, TJNAF

    Carrie Sauter, BNL

    Subcommittee 4—Project Management

    *Michelle Solaroli, TJNAF

    *Lead

  • OFFICE OF

    SCIENCE

    3

    Charge Questions

    1. Technical: Are all Key Performance Parameters that pertain to the project sufficiently

    achieved and documented? Are the modernized utilities ready for operations?

    2. Cost, Schedule, Risk and Contingency: Has the project been completed within the

    cost and schedule baseline? Was the use of contingency appropriately executed?

    3. Management: Is the project properly organized, staffed and managed for successful

    completion? Is the Transition to Operations plan updated and approved?

    4. Environment, Safety and Health: Are ES&H aspects of the project adequately

    addressed? Are prerequisite documents such as the final Hazard Analysis and the

    draft Project Closeout Report approved or prepared?

    5. Prior Reviews: Has the project responded appropriately to recommendations from

    prior reviews?

    6. Lessons Learned: Has the project adequately documented lessons learned and best

    management practices?

  • OFFICE OF

    SCIENCE

    4

    2. Technical DRAFT

    P. Hogan, ANL, D. Nassar ANL

    1. Technical: Are all Key Performance Parameters that pertain to the

    project sufficiently achieved and documented? Yes.

    Are the modernized utilities ready for operations? Yes.

  • OFFICE OF

    SCIENCE

    5

    5. Prior Reviews: Has the project responded appropriately to

    recommendations from prior reviews? Yes.

    6. Lessons Learned: Has the project adequately documented lessons

    learned and best management practices? Yes.

    2. Technical

    P. Hogan, ANL, D. Nassar ANL

  • OFFICE OF

    SCIENCE

    6

    Findings

    • Significant effort was placed on customer interfaces with the impacted utilities.

    • Management used regular project meetings including daily interfaces with critical

    facilities to coordinate construction activities.

    • FESS Facilities Management personnel participated in the Commissioning and

    Start-up of systems.

    • The project executed seven Beneficial Occupancies on the High Voltage (HV)

    portion.

    • The project executed 18 sectionalized Beneficial Occupancies on the Industrial

    Cooling Water (ICW) portion.

    • Commissioning and Transition to Operations is complete for both the HV and ICW

    portions.

    • All training is complete.

    • Operations stakeholders signed-off on Final Acceptance

    • The project achieved all Level 1 Milestones.

    2. Technical

    P. Hogan, ANL, D. Nassar ANL

  • OFFICE OF

    SCIENCE

    7

    Findings (cont)

    • The project implemented a successful work-around in response to a delay caused by

    the Master Substation (MSS) vendor: The vendor was late in completing its factory-

    based work, including factory assembly and testing. Late delivery of the MSS

    would have impacted the work of on-site subcontractors whose work was dependent

    on arrival of the MSS. Fermi decided to allow MSS shipment and on-site testing by

    the vendor in order to mitigate delays to the on-site subcontractors.

    • There were no Technical scope Recommendations in the prior review (July 2016).

    • The project has documented a number of lessons learned and best practices.

    • The threshold scope was completed, and objective scope was completed as indicated

    in the table below:

    2. Technical

    P. Hogan, ANL, D. Nassar ANL

    Description of Scope KPP Threshold Achieved Objective KPP Achieved

    High Voltage Electrical (H/V) Upgrade

    Replace Master Substation Control Building

    Replaced: Building, Switchgear/Equipment,

    Protection System, Cable Vault, Yard Wiring and

    Portions of Feeder System

    Constructed: Blast Wall, Generator and Duct

    Bank

    Master substation 345kv circuit

    breaker replacement

    Industrial Cooling Water (ICW) Upgrade

    Install new ICW backbone piping network from

    Casey's Pond to the Main Injector ICW system

    Installed: four miles of new and replacement

    ICW pipe and two new pump stations.

    Casey’s Pumphouse Electrical Room Addition

    Makeup Water Improvements

  • OFFICE OF

    SCIENCE

    8

    Comments

    • The project has achieved all threshold elements of the key performance parameters.

    The project has also achieved completion of three objective elements. A list of

    elements is included in the Findings Section.

    • All of the constructed facilities have been accepted and transitioned to operations as

    documented in the Transition to Operations Plan.

    • The lessons learned from the project are well documented.

    • The project team successfully overcame a significant challenge regarding the vendor-

    delayed MSS.

    • The project team maintained critical systems operation during construction to ensure

    Lab requirements continued to be met.

    • The project team included subject matter experts for each discipline that significantly

    impacted the success of the project.

    • The electrical commissioning reports are well thought out and the testing plans

    followed ANSI/NETA test practices

    2. Technical P. Hogan, ANL, D. Nassar ANL

  • OFFICE OF

    SCIENCE

    • Recommendations

    • The project is ready to proceed to CD-4.

    9

    2. Technical

    P. Hogan, ANL, D. Nassar ANL

  • OFFICE OF

    SCIENCE

    10

    3. Environment, Safety and HealthM. Solaroli, TJNAF / Subcommittee 2

    4. Environment, Safety and Health: Are ES&H aspects of the project adequately

    addressed? Yes Are prerequisite documents, such as the final Hazard Analysis and the

    draft Project Closeout Report, approved or prepared? Yes

    5. Prior Reviews: Has the project responded appropriately to recommendations from

    prior reviews? Yes

    6. Lessons Learned: Has the project adequately documented lessons learned and best

    management practices? Yes

  • OFFICE OF

    SCIENCE

    11

    3. Environment, Safety and HealthM. Solaroli, TJNAF / Subcommittee 2

    Findings

    • UUP was acknowledged in Lab’s Site Sustainability plan with achieving success

    in meeting the Lab’s sustainability goals and improving operational resilience in

    FY 2017.

    • Project utilized Predictive Solutions, an occupational safety software, for analytics

    on workplace injury prevention, which has been integrated into Lab’s ES&H

    program.

    • Subcontractors have worked at the Lab in the past; therefore, they were aware of

    the safety culture and expectations of the Lab.

    • Best value selection included ES&H performance as a critical parameter to ensure

    subcontractors can meet FNL ISM requirements.

    • Subcontractor total hours worked = 64,986 hrs

    • Project had a TRC case involving wrist injury and a DART case involving knee

    injury. Both the Project incident and DART rates were 3.1.

    • Project had three (3) Category 4 ORPS . Two were related to exposure to

    hazardous electrical energy and one involved excavation beyond permit limits.

  • OFFICE OF

    SCIENCE

    12

    3. Environment, Safety and HealthM. Solaroli, TJNAF / Subcommittee 2

    Findings (continued)

    • Project had (1) ORPS involving lack of proper signage, incorrect PPE and lack of

    volt meter verification. The CSO issued safety stand-down until assurance of

    subcontractor qualifications, hazard analysis and work controls were in place.

    • Project had (1) ORPS during HV Upgrade project involving excavation into

    Meson Beam line berm, which was outside approved excavation permit limits.

    Lab addressed incident by shutting down Meson beam and having Radiation

    group identify boundaries and posting for restricted digging area.

    • Project had (1) ORPS involving a LOTO violation. Lab addressed incident with

    stand down until an investigation was completed. A second occurrence with same

    sub-tier subcontractor resulted in removal from the project.

    • Hazard Analysis Report was reviewed from CD-3b and concluded that no updates

    were required.

    • Security Vulnerability Assessment Report has been updated to include

    Cybersecurity Analysis of Master Substation Building. Assessment is pending

    DOE approval.

    • UUP Quality Assurance Plan has been reviewed and updated.

    • Project closeout report is in draft form and contains information on ESH elements,

    such as incidents and ORPS.

  • OFFICE OF

    SCIENCE

    13

    3. Environment, Safety and HealthM. Solaroli, TJNAF / Subcommittee 2

    Comments

    • ES&H is well integrated into the project team and this directly contributed to the

    success of safety on the project.

    • Coordination between subcontractors and the Lab successfully mitigated

    operational risks.

    • The Lab’s proactive management of two ORPS involving electrical violations

    including LOTO, improper signage and PPE usage demonstrated the strength of

    their safety culture by issuing a stand down until an investigation was completed.

    A second occurrence with same sub-tier subcontractor resulted in removal from

    the project.

    • Project team adequately addressed all recommendations from previous reviews.

    • ESH Lessons Learned and Best Management Practices were documented in the

    Project Closeout Report.

    • The inclusion of the site specific construction safety plan as part of the

    subcontract documents for necessary flow down of safety requirements to sub-tier

    subcontractors was a notable lessons learned.

  • OFFICE OF

    SCIENCE

    14

    3. Environment, Safety and HealthM. Solaroli, TJNAF / Subcommittee 2

    Recommendations

    • The project is ready to proceed to CD-4

  • OFFICE OF

    SCIENCE

    15

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

    • Cost, Schedule, Risk and Contingency: Has the project been completed within the

    cost and schedule baseline? Yes. Was the use of contingency appropriately

    executed? Yes.

    • Prior Reviews: Has the project responded appropriately to recommendations from

    prior reviews? Yes.

    • Lessons Learned: Has the project adequately documented lessons learned and best

    management practices? Yes.

  • OFFICE OF

    SCIENCE

    ▪ Findings

    ▪ The project TPC is $36.0M with a TEC of $34.9M and OPC of $1.1M

    ▪ EVMS statistics as of July 31, 2018

    ▪ BCWS: $35,180k

    ▪ BCWP: $35,413k

    ▪ ACWP: $35,484k

    ▪ BAC: $35,478k

    ▪ EAC: $35,549k

    ▪ CPI/SPI: 1.00/1.01

    ▪ 99.8% complete

    ▪ Forty-seven (47) baseline changes have been processed/approved through July

    2018

    ▪ $4,750k drawn from TEC contingency since CD-2

    ▪ TEC Cost variance of $71k

    ▪ Remaining contingency of $451k

    ▪ TEC of $96k, OPC of $355k

    ▪ 4 months remaining schedule contingency to Jan-2019 CD-416

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

  • OFFICE OF

    SCIENCE

    ▪ Findings (continued)

    ▪ All project risks in Risk Registry have been retired. $96k remains in

    uncommitted contingency.

    ▪ The Draft Project Closeout Report identifies 5 Level 1 Milestones and 19 Level

    2 Milestones all of which have been completed with the exception of Level 2

    Milestones: CD-4 Readiness and CD-4 ESAAB and Level 1 Milestone: CD-4:

    Approve Project Completion.

    ▪ A resource loaded schedule has been used throughout the project which

    represents the project scope.

    ▪ $2.0M of Objective Scope was completed drawing from project contingency,

    which equates to 42% of the contingency usage.

    ▪ All control accounts are 100% complete and closed to charges with the

    exception of Project Management which has $65k of work remaining and an

    open obligation of $.9k as of July 31, 2018.

    ▪ When a control account work scope is complete, the CAM notifies Project

    Controls, Procurement and Finance. They then follow their procedures to ensure

    contracts are closed out, all costs are incurred and the project is closed to new

    charges, and activities are complete and closed in the EVMS system.

    17

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

  • OFFICE OF

    SCIENCE

    ▪ Comments

    – The project team has successfully executed the project completing on schedule

    and within cost.

    – Use of $4,750k in contingency was appropriately executed by the project:

    • Threshold Scope used $2.8M, 58%

    • Objective Scope used $2.0M, 42%

    – 3 of 12 Objective KPPs were accomplished:

    18

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

    Objective Value Spend Down Items Cost

    Replace the Master Substation 345kV circuit breaker $338,000

    Electrical Room Addition for Casey’s Pond Pump House $1,445,000

    ICW Makeup Water Improvements $237,000

    Total $2,020,000

  • OFFICE OF

    SCIENCE

    ▪ Comments (continued)

    – The project has responded appropriately to previous review recommendations.

    – The project has developed a fairly comprehensive list of Lessons Learned and

    Best Management Practices (Successes) recognizing areas for improvement

    on future projects.

    – Project reporting supports the achievement of CD-4 within the approved

    baseline cost, however control documentation did not appear to align and

    explanations were needed to understand differences. As a consequence,

    control data should be aligned prior to issuing the final project closeout report.

    • The contingency usage since CD-2 was untraceable in the Change

    Control Log.

    – The $30.727M PMB at CD-2 is not reflected on the log

    – Consider improvement to the Change Control Log documentation to

    ensure transparency by adding the running total of the contingency

    remaining.

    19

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

  • OFFICE OF

    SCIENCE

    ▪ Comments (continued)

    • The objective scope added to the baseline could not be verified via the

    BCRs.

    – BCR documentation did not clearly delineate the objective scope

    additions when implemented into the baseline. Consider including, in

    the BCR form, separate detailed explanations of each change taking

    place.

    • Discrepancies exist between the milestone dates on PEP and Project

    Baseline Schedule

    • The actual dates on the Closeout Report should tie with the Project

    Working Schedule

    20

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

  • OFFICE OF

    SCIENCE

    ▪ Recommendations

    – Proceed to CD-4

    21

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

  • OFFICE OF

    SCIENCE

    22

    4. Cost and ScheduleCarrie Sauter, BNL, K. Krug, TJNAF

    PROJECT STATUS as of July 2018

    Project Type Line Item

    CD-1 Planned: Actual: Nov 2010

    CD-2/3a Planned: May 2015 Actual: Feb 2015

    CD-3b Planned: Dec 2015 Actual: Sep 2015

    CD-4 Planned: Jan 2019 Actual:

    TPC Percent Complete Planned: 99.2% Actual: 99.8%

    TPC Cost to Date $35.5M

    TPC Committed to Date $35.6M

    TPC $36.0M

    TEC $34.9M

    Contingency Cost (w/Mgmt Reserve) $ 0.1M 149% to go

    Contingency Schedule on CD-4 4 months 67%

    CPI Cumulative 1.00

    SPI Cumulative 1.01

  • OFFICE OF

    SCIENCE

    23

    5. Project ManagementM. Solaroli, TJNAF/ Subcommittee 4

    3. Management: Is the project properly organized, staffed and managed for successful

    completion? Yes Is the Transition to Operations plan updated and approved? Yes

    5. Prior Reviews: Has the project responded appropriately to recommendations from

    prior reviews? Yes

    6. Lessons Learned: Has the project adequately documented lessons learned and best

    management practices? Yes

  • OFFICE OF

    SCIENCE

    Findings

    • All Level 1 milestones were met.

    • HV Electrical Upgrade project was completed August 2017 and the project

    executed $316K in objective scope.

    • ICW Upgrade project was completed July 2018 and the project executed $1,682K

    in objective scope.

    • Only the WBS Project Management control account remains open.

    • Project SPI & CPI stayed within 10% threshold.

    • All risks have been retired. $96K remains in contingency.

    • Final Commissioning Report for HV 345kV Master Substation had three open

    items that were closed at CD-4 review.

    • Both HV Electrical Upgrade and ICW Upgrade are complete, commissioned and

    operational.

    24

    5. Project ManagementM. Solaroli, TJNAF/ Subcommittee 4

  • OFFICE OF

    SCIENCE

    Findings (continued)

    • Multiple Beneficial Occupancies were issued as part of HV and ICW

    construction.

    • Final Acceptance certificates were issued for the purpose of contractually

    establishing subcontracted work has been completed in accordance with the

    subcontract documents and constitutes the start of the warranty period.

    • The transition to Operations plan is complete and defined FNL basis for

    obtaining operability for the systems. Documentation, training and Lab

    interfaces have been coordinated and obtained.

    • Lessons learned including successes and potential improvements have been

    captured.

    25

    5. Project ManagementM. Solaroli, TJNAF/ Subcommittee 4

  • OFFICE OF

    SCIENCE

    Comments

    • Threshold KPPs and 3 Objective KPPs were successfully completed within the

    project baseline cost and schedule.

    • The project team effectively managed cost of additional threshold scope

    associated with cost overruns, field conditions, design errors, operational issues

    and constraints in the amount of $2,804K which was 13.8% of initial construction

    cost ($20,340K).

    • The project successfully spent approximately 49% of contingency on objective

    scope and various scope enhancements. The cost of executed objective scope

    ($2.14M) was 10.6% of initial construction cost ($20,340K). Well done!

    • Project team successfully managed changes to project staff throughout the project

    and is adequately staffed to complete the project.

    • The Transition to Operations Plan clearly defined the basis for attaining project

    closeout and included requirements for documentation, training and interfaces.

    • Subcontract management of ICW with unit pricing is a Best Management

    Practice and was applied successfully on this project when field changes

    occurred.

    26

    5. Project ManagementM. Solaroli, TJNAF / Subcommittee 4

  • OFFICE OF

    SCIENCE

    Comments

    • The MSS Bypass project proactively used Lab funds to install an alternate power

    source as a bypass for maintaining Lab operations during UUP HV project. This

    interfacing project funded by the Lab was necessary for moving forward on the

    HV project is considered a best management practice.

    • Project team successfully responded to the late delivery of the substation on the

    HV project by implementing additional management tools including engaging

    subcontractor management, holding daily meetings, modifying payment

    milestones and allowing final testing of some systems onsite. This modification

    to the contract’s delivery schedule utilized contingency funds effectively to

    mitigate overall project schedule delays.

    • The Design Phase Utility Locates was a notable lessons learned using design

    funding to locate existing utilities via potholing and hydro excavating. This effort

    positively obtained utility location/elevation information and mitigated conflict

    risks during construction.

    • Project team adequately addressed all recommendations from previous reviews.

    • Project team adequately documented lessons learned and best management

    practices.

    27

    5. Project ManagementM. Solaroli, TJNAF / Subcommittee 4

  • OFFICE OF

    SCIENCE

    Recommendations

    • The project is ready to proceed to CD-4

    28

    5. Project ManagementM. Solaroli, TJNAF/ Subcommittee 4