Cloquet Mill Air Permitting Summary June 12, 2013 Presented by: Rob Schilling and Justin Finke
description
Transcript of Cloquet Mill Air Permitting Summary June 12, 2013 Presented by: Rob Schilling and Justin Finke
1
Cloquet Mill Air Permitting SummaryJune 12, 2013
Presented by: Rob Schilling and Justin Finke
2 2
AGENDA
3 3
Sappi Cloquet Overview
Pulp Mill Overview:• 10 batch digesters• Capable of producing specialized cellulose or kraft paper
pulp• Capacity set by recovery boiler permit limit 904,200 tpy BLS
Paper Mill Overview: • 2 paper machines• 1 off-machine coater• Manufacture > 1,000 tpd of coated paper• Paper sold in rolls or sheets
Utilities Overview:• 3 industrial boilers (2 bark, 1 natural gas)• 1 recovery boiler• 3 steam turbines• 4 hydro electrical turbines• Generate ~90% of electrical use on-site• Fuel use is 85-90% renewable energy
4 4
Sappi Cloquet Overview
Environmental Overview:• EMS is certified by the ISO 14001:2004 standard• Onsite industrial landfill
• Waste to LF reduced by >85% over last 10 years • Onsite primary waste water treatment plant (no direct
discharges to St Louis River)• Final waste water treatment at WLSSD• Regulated by both individual and general storm water permits• Environmental department staffed by:
• Manager, 2 Environmental Engineers, co-op
5 5
Sappi Title V Permit Summary
Significant Emissions Units (control equipment):
• PB7, PB9 – bark fired power boilers (ESP)• PB8 – natural gas fired power boiler (None)• RB10 – black liquor recovery boiler (ESP)• Smelt Dissolving Tank (Scrubber)• Lime Kiln (ESP)• Bleach plant (OOZDED) (Scrubber,
COD)• IQS (Incinerator,
scrubber)
Source of emission limits:
• NESHAPs (Subparts S, MM, DDDDD, JJJJ)• BACT (PSD)• NSPSs• Modeling/NAAQS
6 6
Sappi Title V Permit Summary
Compliance Demonstration:• PB7, PB9 (COMS, CEMS, Stack Tests)• PB8 (CEMS)• RB10 (COMS, CEMS, Stack Tests)• Bleach plant (Stack Tests, scrubber flow and pH)• SDT (Stack Tests, scrubber flow, delta P, nozzle pressure)• Lime Kiln (COMs, CEMs, Stack Tests)• IQS (Stack tests, temperature, scrubber flow and pH)
7 7
Cloquet Project History
1. Pulp Mill Modernization2. Project Hercules3. Project Athena
8 8
Project History – Pulp Mill Modernization
Pulp Mill Modernization
• Increased pulp production from ~500 tpd to ~1500 tpd• Required full EIS• Air Permit issued in 1993• Construction complete in 1999• Newest pulp mill in North America• Cluster Rule MACT compliant on startup – first pulp mill to
comply• Criteria air emissions reduced from:
• 1999 = ~ 45 lb/ton • Today = < 15 lb/ton
• Resulted in ~1000 tpd of pulp being sold as “market” pulp
9 9
Project History – Project Hercules
Project Hercules
• Fix market pulp “problem” by building new paper machine and eliminate market pulp sales
• $6MM in engineering and environmental review• EAW and major Air Permit Amendment completed
• Started Dec 2007, Permit issued Oct 2009• Project never constructed – multiple factors
10 10
Project History – Project Athena
Project Athena
• Fix market pulp “problem” by converting pulp mill to produce specialized cellulose
• ~$5MM in preliminary engineering and environmental permitting• Major Air Permit Amendment required
• PSD for ozone emissions• Triggered Cloquet Area Modeling Project
• Project Approved / funded November 2011• Total investment ~$170MM• Construction started April 2012• Start-up May 2013
11 11
Project History – Project Athena
Cloquet Area Modeling Project
• Modeling analysis involving USG, SMI, Jarden Home Brands and Sappi
• Project coordinated by MPCA, modeling completed by Barr and Wenck
• Analysis included NAAQS and Increment for:• PM10• PM2.5• NOx• CO
• Historical modeling for each site predicted compliance w/ all NAAQS at PTE emission rates
• Initial combined impacts of plumes predicted impacts > NAAQS• Final predicted impacts < NAAQS for all pollutants after changes
made by USG, SMI, JHB and Sappi
12 12
Project History – Project Athena
13 13
Air Permitting – What’s Next?
NAAQS (ozone, PM2.5, SO2, NO2)Boiler MACTBiogenic CO2/GHG deferral, PSD IssuesNSPS/MACT residual risk technology reviewsRegional HazeCSAPR/transport rulesEnvironmental justice
14 14
15
Defining Sustainability
“A sustainable corporation is one that creates profit for its shareholders while protecting the environment and improving the lives of those with whom it interacts.”
— A. Savitz, author of The Triple Bottom Line
16 16
people planet prosperitysocial environmental economic
Labor practicesCommunity impactsHuman rightsProduct responsibility
Air qualityWater qualityEnergy usageWaste produced
Sales, profits, ROITaxes paidMonetary flowsJobs created
SUSTAINABILITY
17
Customers Employees Communities
Three pillars of sustainability
People Planet Prosperity
Three key environmental issues
ResponsibleForestry
Energy and Emissions
Recycling and Recycled Fiber
Three key stakeholder groups
18
Thank you