Climate Change Vulnerability Assessment for...
Transcript of Climate Change Vulnerability Assessment for...
National Engineering Vulnerability Assessment of Public
Infrastructure to Climate Change
Climate Change Vulnerability
Assessment for Culverts
Agenda
• Introduction
• PIEVC Engineering Protocol
• Climate Analysis and Projections
• Project Definition
• Data Gathering and Sufficiency
• Risk Assessment
• Engineering Analysis
• Conclusions
• Recommendations
Introduction
• Who
– The study is co-funded by the City of Toronto and Engineers Canada
• What, Where, and When
– The study involves an engineering vulnerability assessment of three of the City of Toronto’s culverts; Ellesmere, Albion and Grandravine to existing and projected future climate conditions during the 2040’s time horizon
• How
– The assessment was conducted using the Public Infrastructure Engineering Vulnerability Committee (PIEVC) Protocol
• Why
– City’s objective is to proactively identify components of the culverts that have an increased risk of failure or damage due to potential climate change
Introduction
City of Toronto owns and operates over 150 large diameter culverts.
Three culverts were selected for this study:
PIEVC Engineering Protocol
• The study was conducted using Version 9 of the PIEVC Engineering
Protocol for Climate Change Infrastructure Vulnerability Assessment
(April, 2009)
• It consists of the following 5 steps:
– Step 1: Project Definition
– Step 2: Data Gathering and Sufficiency
– Step 3: Risk Assessment
– Step 4: Engineering Analysis
– Step 5: Recommendations
Project Definition – Ellesmere Culvert
• The culvert was constructed in1961
• Twin box reinforced concrete
Armour Stone
Storm Sewer Outlet
Outfall Headwall
Wingwall Concrete Twin
Box
Project Definition – Albion Culvert
• The culvert was constructed in 1964
• Corrugated steel pipe arch
Embankment
Inlet
Outlet
CSP
Buried Utility Infrastructure
Road Users/Vehicles
Pavement
Above-ground Infrastructure
Project Definition – Grandravine Culvert
• Year of construction is unknown
• Corrugated steel pipe arch
Floodplain
Channel
Pipe Arch Outlet Pipe Arch Inlet
Damaged CSP
Data Gathering and Sufficiency
• All the components were grouped into the following general categories:
• Administration/Operation
• Road
• Drainage
• Active Stream Corridor
• Natural Features
• Surrounding Area
• Utilities
Climate Analysis & Projections
• Selected a set of climate parameters describing climatic and meteorological phenomena relevant to the:
– Geographic areas of the Ellesmere, Albion and Grandravine culverts
– Potential risk and vulnerability of culverts
• Determined probability of occurrence of each climate event using available data sources (for existing/historical and future (2040’s))
High Temperature
Sustained High
Temperature in the Winter,
with snow on the ground
Heavy Winter Rain Ice Storm Tornado
Low Temperature Freeze/Thaw Freezing Rain Lightning Drought/Dry
Periods
Heat Wave Heavy Rain Heavy Snowfall Hailstorm Heavy Fog
Cold Wave Heavy 5-day Rain Blowing Snow Hurricane/Tropical
Storms
Extreme Diurnal
Temperature Variability
High Intensity Short
Duration Rainfall Snow Accumulation
High
Wind/Downburst
Climate Analysis and Projections
Climate Parameters for which the probability scores
increased from historical to future
High Temperature
Heat Wave
Heavy Rain
Heavy 5-Day Total Rainfall
High Intensity Short Duration Rainfall
Winter Rain
Freezing Rain
Ice Storm
Heavy Snow
Hurricane/Tropical Storm
Drought/Dry Period
Climate Parameters for which the probability scores
decreased from historical to future
Low Temperature
Cold Wave
Extreme Diurnal Temperature Variability
Freeze Thaw
Snow Accumulation
High Wind
• Comparison of probability scores between historical and future
Risk Assessment
• A risk assessment workshop was conducted on April 13th, 2011
• The workshop participants were from the GENIVAR team, City of Toronto staff, and the Project Advisory Committee
• In order to validate initial findings, the participants were asked to determine:
– Interactions between climate events and infrastructure components that they considered relevant to the study
– Severity of the climate event on the infrastructure component from a scale of 0 (negligible) to 7 (extreme)
Probability Scale Factors
• P = Probability of a negative event
• Our Study Team and the City of
Toronto selected Method A
Severity Scale Factors
• S = Severity of the event, given
that it happened
• Out Study Team and the City of
Toronto selected Method E
Risk Assessment
• Risk = P x S – P = Probability of Climate Event
– S = Severity of the climate event on the component
Risk Range Threshold Response
< 12 Low Risk No immediate action necessary
12 - 36 Medium Risk Action may be required
Engineering Analysis may be required
> 36 High Risk Immediate action required
In total there were 688 interactions – 53% were in the low risk category (under both existing and future conditions)
– 22% were in the medium risk category (under both existing and future conditions)
– 25% changed between low and medium risks from existing to future conditions
– None were in the high risk category
Engineering Analysis
• Engineering Analysis Results
Ellesmere Albion Grandravine
No. of interactions considered in
the engineering analysis 134 150 123
No. of interactions assessed to
be vulnerable 33 36 42
Generally, the vulnerabilities exist to the following climate events:
Heavy Rain, High Intensity Short Duration Rainfall, Heavy 5 Day
Rain, Hurricane/Tropical Storm, Freezing Rain, Ice Storm, Heat
Wave, High Temperature, Tornado, High Wind/Downburst
Conclusions
Generally, the results of the engineering analysis demonstrate that the culverts have relatively low vulnerability to potential future climate change.
Culverts studied are in relatively good condition
Many of the vulnerabilities identified relate to aspects which are not unique to culvert infrastructure systems. These have been assigned a low priority under recommendations.
Most critical vulnerabilities specifically related to these culverts:
1) Capacity
2) Embankment Stability
3) Potential Vegetation Impacts
Recommendations
• Review the flows being experienced at the culverts and compare with capacity of culverts
• Study potential for flooding upstream of the Grandravine culvert in further detail
• Review conditions of Grandravine embankment to determine capacity to withstand upstream flooding
• Review long term performance of the embankments under a range of overtop scenarios.
• Options to improve embankment stability to ensure performance during extreme floods should be considered.
Recommendations
• Review policies regarding floodplain maintenance and preventative measures (i.e. increased planting) to combat erosion. Conduct regular erosion monitoring of channel (annual or biannual)
• Utilize a “No regrets” strategy in determining prioritization of capital upgrades to culverts regardless of climate change
• Review the policies and procedures associated with the Operations personnel and how they get to the culvert and perform their duties, particularly under extreme conditions
• Continue to monitor the risks and vulnerabilities identified through the assessment, particularly as components continue to age
• Monitor the progress in climate science and revisit assessment as advances are made
Recommendations
• Preserve the high standard of maintenance and management that
the City has devoted to the culverts to this point. Implement
recommendations from Culvert Management System Review in the
following areas:
– Large Culvert Inspection
– Detailed and Minor Inspections of Large Culverts
– Maintenance/Repairs
– Reporting and Monitoring
– Control of Documents and Records
– Corrective Actions
– Management Review