CLIC RF structure development meeting Structure cost study (introduction)

17
CLIC RF structure development meeting Structure cost study (introduction) G. Riddone, 18.08.2010

description

CLIC RF structure development meeting Structure cost study (introduction). G. Riddone, 18.08.2010 . Content. Introduction and method Learning curves Manufacturing flow Parameters affecting the cost Some comparative numbers Cost study in industries. Introduction. Accelerating structures - PowerPoint PPT Presentation

Transcript of CLIC RF structure development meeting Structure cost study (introduction)

Page 2: CLIC RF structure development meeting Structure cost study (introduction)

2

Content

G. Riddone, 18/08/2010

Introduction and method Learning curves Manufacturing flow Parameters affecting the cost Some comparative numbers Cost study in industries

Page 3: CLIC RF structure development meeting Structure cost study (introduction)

3

Introduction

G. Riddone, 18/08/2010

Accelerating structures Two cases are considered:

Accelerating superstructures in quadrants Accelerating superstructures in disks

For both cases: Sealed structures Diffusion bonding at ~1000 ˚C under hydrogen 3 production lines

PETS Octants and mini tank concept 3 production lines

Page 4: CLIC RF structure development meeting Structure cost study (introduction)

4

Method

G. Riddone, 18/08/2010

Definition of the manufacturing

flow

Prototype cost based on current

design

Application of learning curves

Calculation of cumulative cost

Calculation of average unit cost

Identification of the main steps

Usually cost of the first third/fourfh

unit

Page 5: CLIC RF structure development meeting Structure cost study (introduction)

Learning curve - Theory

T.P. Wright, Factors affecting the cost of airplanes, Journ. Aero. Sci. (1936)

Unit cost c(n) of nth unit produced

with a = « learning percentage », i.e. remaining cost fraction when production is doubledCumulative cost of first nth units

with C(n)/n = average unit cost of first nth units producedn = number per production line ≠ total number in project

ancnc 2log)1()(

ancnC

a

2

log1

log1)1()(

2

We have to define c(1) and a

5 G. Riddone, 18/08/2010

Page 6: CLIC RF structure development meeting Structure cost study (introduction)

6

Learning percentage

G. Riddone, 18/08/2010

Typi

cal l

earn

ing

perc

enta

ge v

alue

s(N

ASA

Lear

ning

Cur

ve C

alcu

lato

r)

Page 8: CLIC RF structure development meeting Structure cost study (introduction)

Accelerating structures DISKS (142812)

G. Riddone, 18/08/20108

3. Assembly and brazing 285624 couplers

6. Baking 71406 ss

5. Final bonding and assembly (HOM, manifolds), incl. RF check

- 71406 ss

Sequ

ence

2. Machining4284360 disks (including HOM,

manifolds), QC and cleaning

4. Alignment and bonding 71406

disk stacks

8 couplers /cycle[35703 cycles]

4 ss/cycle[17852 cycles]

4 ss/cycle[17852 cycles]

Assumptions:1 as = 30 disksBonding of superstructures (2 as)

4 ss/cycle[17852 cycles]

a: 0.93

a: 0.85

a: 0.9

1. Raw material a:1

a: 0.85

a: 0.85

Page 9: CLIC RF structure development meeting Structure cost study (introduction)

Accelerating structures QUADRANTS (142812)

G. Riddone, 18/08/20109

6. Baking 71406 ss

5. Final bonding and assembly (HOM, manifolds), incl. RF check

- 71406 ss

Sequ

ence

2. Machining285624 quadrants (including

HOM, manifolds), QC and cleaning

4. Alignment and bonding 71406 structures 4 ss/cycle

[17852 cycles]

4 ss/cycle[17852 cycles]

Assumptions:1 as = 4 quadrantsBonding of superstructures (2 as)

4 ss/cycle[17852 cycles]

a: 0.93

a: 0.9

1. Raw material a:1

a: 0.85

a: 0.85

Page 10: CLIC RF structure development meeting Structure cost study (introduction)

PETS (71406)

G. Riddone, 18/08/201010

7. Baking 71406

6. Final bonding and assembly(HOM, minitanks), incl. RF check

- 71406

Sequ

ence

2. Machining571248 bars (including HOM),

QC and cleaning

5. Brazing 71406 couplers 8 couplers/cycle[8926 cycles]

8 ss/cycle[8926 cycles]

a: 0.92

a: 0.9

1. Raw material a:1

a: 0.85

a: 0.85

4. Machining71406 couplers, QC and

cleaning

3. Machining71406 minitanks, QC and

cleaning a: 0.92

a: 0.92

Assumptions:1 PETS: 8 bars, 1 couplerMini-tank concept

Page 11: CLIC RF structure development meeting Structure cost study (introduction)

11

Some parameters affecting the total cost

G. Riddone, 18/08/2010

Choice of learning factor (+++) Saturation value: value above which

learning stops, no average cost reduction (negligible)

Number of production lines (+)

Page 13: CLIC RF structure development meeting Structure cost study (introduction)

13

Saturation

G. Riddone, 18/08/2010

Examples [a= 0.9]:Sat 0.8 learning process stops after 80 % of the productionCumulative cost increase 0.31 %

Sat 0.5 learning process stops after 50 % of the productionCumulative cost increase 2.7 %

For CLIC RF structure quantities

Page 14: CLIC RF structure development meeting Structure cost study (introduction)

Influence of production lines

14 G. Riddone, 18/08/2010

(no saturation)

Examples [a = 0.9]:Cost increase of 18% from 1to 3 production lines

Page 15: CLIC RF structure development meeting Structure cost study (introduction)

15

RF structure cost

G. Riddone, 18/08/2010

Accelerating structures

Cost of test structure disk (ref . VDL)

Cost of 300-mm quadrant (ref. VDL) linearly scaled to 500-mm quadrant (maybe optimistic)

Cost of machining = 90 % of total

Total cost of machining of AS in quadrants = 75 %Total cost of machining of AS in disks

PETS

Cost of PETS octant @ 11.4 GHz (ref . VDL, Unitek)

Cost of machining: 75 % of total

Page 16: CLIC RF structure development meeting Structure cost study (introduction)

16

Two beam module cost

G. Riddone, 18/08/2010

BREAKDOWN RF system: 65 % Alignment system: 10 % Supporting system: 6 % Magnet system: 5 % Beam instrumentation: 5% Magnet powering system: 3% Vacuum system: 2.5 % Other systems: 3.5 %

The highest contribution!

Page 17: CLIC RF structure development meeting Structure cost study (introduction)

17

Industrialization and mass production study

G. Riddone, 18/08/2010

Launched industrialization and mass production studies in 3 industries/institutes: VDL KERN VTT/HIP

CLIC structures, with HOM damping material, vacuum material,….

Cost study will include both capital and running cost (CERN cost study only running cost)

Study currently under way. Analysis of the preliminary results confirm tendency of CERN

cost study