Clare Hospital Case Study

download Clare Hospital Case Study

of 2

Transcript of Clare Hospital Case Study

  • 7/29/2019 Clare Hospital Case Study

    1/2

    SITE

    First built in between 1970 and 1971, Clare

    Hospital (CH) is a 25-acute-bed sub-regional

    hospital situated in the hills and outskirts of

    Clare. CH is located at 41-45 North Road,

    Clare, South Australia.

    BACKGROUND

    In year 2000, Clare hospital underwent an

    extension and refurbishment of the Theatre,

    Delivery, Recovery CSSD and Support Areas.

    Since that time the air conditioning systems in

    these areas have proved to be problematic

    and a number of alterations and additions

    have been made in an effort to overcome

    the deficiencies.

    System Solutions Engineering (SSE) was

    commissioned to investigate the mechanical

    system and provide engineering options.SSE was briefed by Mr Rick Jarvis who has

    been involved with the operation of the plant

    since inception and taken complaints from

    staff and he has also been involved with the

    rectification of defects and the additions to

    the systems since commissioning.

    There were many complaints regarding the

    system;

    Temperature fluctuations in the Theatre

    (mainly cold air falling from the diffusers to

    work area).

    Temperature fluctuations have been

    ongoing in the areas other than theTheatre.

    The heater bank installed during the period

    2001 2003 has been problematic and

    the safety controls had failed, resulting in

    a dangerous overheating issue. (New flow

    switch fitted)

    Complaints about the energy consumption

    in this area due to the use of the heater

    bank.

    The HEPA filters require constant

    adjustment and the indication is located

    in the ceiling space.

    Concerns have been raised about the

    pressure exerted on the flexible ductworkto the HEPA filter modules.

    Type of pre-filter used upstream of the

    HEPA filters.

    The doors between the Theatre Area and

    the main Hospital need to remain open

    to allow return air to get back to ACU-5

    and this area is a transfer area from the

    change rooms to the Theatre area and

    the Hospital would rather have the doors

    closed.

    The supply air fan is continually breaking

    causing the unit to fail.

    The wiring within the air conditioning unit

    and the heater bank is poorly installed

    and difficult to fault find. The wiring has

    not been numbered, tidied up and

    proper wiring diagrams provided for the

    manuals.

    CASE STUDY:

    Clare Hospital - Riverland Regional Services

    SSE INVESTIGATIONS

    The Subject Area (Theatre, Delivery,

    Recovery CSSD and Support Areas) was

    designed as one functional/thermal

    zone. The air conditioner is an AirChange manufacture 100% outside air

    unit incorporating a heat exchanger with

    evaporative assistance, and two stages of

    heating and cooling.

    The operation of the system as designed,

    was for the control of the environment

    within all zones at 220C with the location

    of the controlling sensor from the 1st

    Stage Recovery (Predominantly) and from

    Theatre (On Demand) when in use.

    During the first months of operation the

    use of the Theatre at (180C) below the

    designed set point of 220C and this resulted

    in complaints of too cold in all other areas.The reality was found that the Theatre

    should infact be a separate thermal zone

    to ensure that its operation at a differing

    setpoint so that it does not affect the other

    adjacent spaces.

    In order to provide a separate thermal

    zone within the original design, a heater

    bank of approximately 12 kW (4 stages)

    was installed with the conditioner being

    controlled by the Theatre sensor at 180C

    and the heater controlled by the sensor in

    the 1st stage recovery. This theoretically

    allows the Theatre to control the air

    conditioning for cooling and heating tosatisfy the thermal zone of the Theatre and

    the remaining areas to be zoned by the 4-

    stage re-heater.

    Whilst this approach does provide zoning

    with the Theatre as the driver of the air

    conditioning demand and the heater

    bank, will in most cases be fully utilised to

    offset the lower supply air to achieve a 40C

    rise to satisfy the remaining air conditioned

    space. If the load within the remaining

    area is lower than design and the theatre

    is at designed temperature, the 12 kW

    heater may not be large enough and

    this may be the reason why there are stillcondition complaints from the Delivery,

    Recovery CSSD and Support Areas.

    KEY INITIATIVESMechanical system upgrade

    New BMS

    Human Comfort

    Energy Efficiency

    KEY OUTCOMESElectrical Energy Savings:

    30,318kWh pa or 109,146 MJ pa

    (4% site reduction)

    9 kWh/m2 pa or 32 MJ/m2 pa

    Cost Savings:

    $4780.00 pa

    $1.40 per m2 pa

    Payback Period:

    Just above 10 years

    Greenhouse Gas Savings:30 Tonnes of CO

    2

    (4% site reduction)

    Equivalent to taking 7 average

    passenger vehicles off the road

    9.15 kg CO2

    per m2 pa

    Internal Rate of Return:

    7.3%

    KEY CONTACTSDepartment of Health

    Mr John Diplock

    Project Manager

    Tel: (08) 8226 6354

    Email: [email protected]

    System Solutions Engineering

    Mr Brad Maynard

    Managing Director

    Tel: (08) 8333 1855

    Email: [email protected]

  • 7/29/2019 Clare Hospital Case Study

    2/2

    PROJECT IMPLEMENTATION

    SSE designed two main projects; project 1

    addressing the complaints and problematic

    mechanical system; Project 2 aiming

    energy efficiency of the mechanical

    system through the Building Management

    System (BMS).

    PROJECT 1

    Mechanical system upgrade mainly at

    operating theatres and area serve by

    ACU-5, was scoped under the project.

    Installed new hard supply air duct

    between four (4) HEPA filters and existing

    supply air duct.

    Installed new portion of supply air duct,

    including the existing in-line supply air fan

    with upgraded motor and new variable

    speed drive, water cooling coil, air filters

    and balancing dampers.

    Extended the two return air ducts and

    connect to the new supply air duct at

    the fan suction side.

    Installed new air-cooled chiller, to serve

    the single cooling coil only, inclusive

    of circulating pump, valves, piping

    electrical and controls.

    Installed new D.D.C. control system

    to control the operation of the chiller-

    circulating pump-cooling coil and

    HEPA filters-supply air fan arrangements,

    suitable for connection to future BMS

    system and inclusive of one variable

    speed drive to the supply air fan.

    Associated electrical work.

    Removed the existing heater bank

    serving the non theatre areas served by

    ACU 7.

    Replaced the evaporative assistance

    pump with an AIRAH type for ACU 7.

    Replaced the dump valve with a

    motorised ball valve type for ACU-7.

    Replaced fan belts and pullies on the

    supply and exhaust air paths of ACU-7

    A filter plenum for ACU-7 to house new

    filters of either four peak or V Form type

    to replace the existing air filtration.

    Reconnected the outdoor air flexible

    connection to the wall of the filter

    plenum.

    Installed fire/smoke damper in the new

    return air duct and interlock with the

    existing fire/smoke damper, so the two

    operate simultaneously and in the same

    direction.

    PROJECT 2

    This project involves mainly the BMS aiming

    for energy efficiency. The entire system was

    designed to incorporate the latest software

    revisions inclusive of the Automated Logic

    Systems including the ultimate facility toWEB enable the system and connection to

    the intranet.

    For each of the air conditioners the

    following control elements were provided;

    New temperature sensors complete with

    after hours push buttons where the plant

    is scheduled to run rather than run 24

    hours per day.

    Logical and user friendly active

    graphics using CAD plans for setpoint

    manipulation via graphical hot spots.

    Expand the current systems as they arecurrently set up.

    WEB Enabled the existing dedicated BAS

    PC located in the Hospitals Computer

    Room and arrange for a PSTN line, an

    ADSL connection and router for the BAS

    System. Set up VPN access via the WEB

    and provide a notebook computer with

    all required software to allow remote

    access via either a dial up connection

    or alternative ADSL connection.

    STRATEGIES IMPLEMENTED

    Fire shutdown of all air conditioning in fire

    mode.

    Run status for all plant.

    Fault status for all plant based on

    scheduled to run and not running logic.

    An architectural graphic (active) for the

    entire site and further graphics for each

    specific area to assist with interrogation.

    Thermal controls to allow staging of

    capacity to meet demand.

    Time schedules independent to each

    unit to allow tailoring of operational

    parameters to meet specific usage

    patterns.

    After hours override and green LED runindication.

    BENEFITS

    Monthly cumulative electricity

    consumption graph compares electrical

    energy consumption between 2003-04

    against 2006-07 financial year. This is an

    annual electricity reduction of 30,319 kWh

    which is equivalent to annual reduction of

    30 Tonnes of CO2

    emissions.

    The Clare Hospital Mechanical Project is

    another environmentally responsible site

    that System Solutions Engineering is proud

    to showcase our clients.

    CONTACT USEmail: [email protected]

    Street Address

    Level 1, 75 Fullarton Road

    Kent Town

    South Australia 5067

    Telephone: +61 08 8333 1855

    Facsimile: +61 08 8333 1866

    CASE STUDY: Clare Hospital - Riverland Regional Services

    0

    100,000

    200,000

    300,000

    400,000

    500,000

    600,000

    700,000

    800,000

    Jul A ug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

    MonthlyElectricityConsumption

    (kWh)

    2003/04 2005/06