CIVL4171 Offshore Structure

download CIVL4171 Offshore Structure

of 18

Transcript of CIVL4171 Offshore Structure

  • 7/29/2019 CIVL4171 Offshore Structure

    1/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Offshore Structures 8551

    Lecture Plan & Assessment

    Dr Andrew GrimeArup

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Gravity base offshore structures

    Characteristics & Types of GBSs

    Key Issues in GBS Selection

    Steel & Concrete GBSs

    GBS Development

    Design

    Construction

    Oils Storage Systems

    Installation

    Summary

    The Future

  • 7/29/2019 CIVL4171 Offshore Structure

    2/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Characteristics of GBSs

    Use the mass of the topsides, substructure andtrapped soilin skirts

    (or solid ballast) to resist uplift.

    Can be concrete or steel:

    Traditionally concrete.

    Steel examples becoming more common, particularly for self-installing

    platforms

    Well-suited to one or more of the following:

    Storage (oil, condensate, LNG, LPG) / no pipelines.

    Large topsides particularly concrete GBSs.

    Remote locations for mobilisation of installation equipment.

    Relatively weak soils.

    Removable / relocatable (must be designed in).

    Ice load resistance.

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Types of GBSs

    Concrete:

    1st GenerationCondeeptype

    Mid 70s to mid90s

    2nd Generation dry-built CGSs (Concrete Gravity Substructures)

    Late 80s onwards

    Steel:

    Suited to self-installing platforms - becoming more common

    ArupACE

    TalismanMOAB

    Technip TPG500

  • 7/29/2019 CIVL4171 Offshore Structure

    3/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Key Drivers for Selecting a Substructure Type

    CAPEX: Total installed substructure cost:

    Onshore fabrication

    Transport to site

    Substructure installation

    Follow-on works piles for jackets solid ballast & / or scourprotection for GBSs (if required)

    Total installed topsides cost:

    Onshore fabrication

    Transport to site

    Topsides installation

    HUC

    OPEX:

    Seldom a key driver for fixed substructures.

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Key Drivers for Selecting a Substructure Type

    Function of offshore facility

    Is infield storage needed ? or

    New (or existing) pipelines instead ?

    Physical drivers:

    Water depth

    Soils

    Metocean (both operational and for installation)

    Size of topsides

    Offshore industry capacity: Currently becoming an issue

    Fabricators

    Marine contractors

    Schedule drivers usually, but not always, its neededASAP

  • 7/29/2019 CIVL4171 Offshore Structure

    4/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Steel GBSs - Self-installing / Relocatable Platforms

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Typical ACE Installation

    Entire facility installed

    as one unit

    Removal is a reverse

    of the installation

    sequence

  • 7/29/2019 CIVL4171 Offshore Structure

    5/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Steel GBSs Other Examples

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Concrete GBS Key Elements

  • 7/29/2019 CIVL4171 Offshore Structure

    6/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    GBS Development Phase 1 70s & 80s

    GBSs answered the development needs of the Northern North Sea in the1970s.

    Gulf of Mexico technology OK for Southern North Sea (started in 60s):

    Piled jackets

    Subsea pipelines

    GoM technology insufficient in northern North Sea:

    Piles

    No subsea hammers

    Large fields = heavy topsides

    High loads = long piles = long time

    Limited offshore floating crane capacity

    Adverse seastates

    Cost of subsea pipelines Deep waters

    Adverse installation seastates

    CIVL 4171 Platform,Pipeline & Subsea Technology

    GBS Development Phase 1 70s & 80s

    Phase 1GBSs solved these issues:

    Very large concrete substructures

    Innovativewet dockconstruction (Norwegian fjords or Scottish sea lochs)

    Most successful example, the NorwegianCondeep

    Last Condeep,Troll, installed in 96

    ~20 such GBSs built, ~75% Condeeps

    Condeeps provided:

    Fast offshore installation (gravity base = no piles)

    Well suited to harsh metocean (installation & operation)

    Good topsides solution:Ability to carry large topsides

    Deck-mating in inshore sheltered waters

    Limited offshore HUC

    On-board oil storage in base caisson:

    Limiting need for subsea pipelines

  • 7/29/2019 CIVL4171 Offshore Structure

    7/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Condeep Type GBSs

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Condeep Construction and Installation

  • 7/29/2019 CIVL4171 Offshore Structure

    8/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Became progressively more complex

    to design & build:

    Bigger, deeper

    Based on shells structures

    Very efficient for high hydrostatic

    loads on elements

    Particularly for base caisson

    But this is hardest part to design &

    build

    Marrying shell elements increased

    design & construction complexity Needed progressivelyhigher tech

    concrete up to 85MPa cube

    Condeep Construction and Installation

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Meanwhile Other Technologies Improve

    Piled jackets (in the 80s)

    Improved installation barges

    Pile hammers larger, & subsea

    Heavy lift crane vessels for topsides installation

    Floating platforms - particularly FPSOs (in the 90s)

    FPSOs seen as the ideal solution

    Cheap ship hulls

    Apparently simple topsides

    Good answer for deep waters

    Simple infield storage Reusable

    Many FPSOs did not achieve initial promise (substantial cost& schedule overruns)

    but

  • 7/29/2019 CIVL4171 Offshore Structure

    9/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Meanwhile Other Technologies Improve

    but Majority of these problems now solved

    Subsea pipelines (on-going)

    Improved installation technologies

    More extensive (& virtually permanent) networks

    So infield storage requirement diminished

    CIVL 4171 Platform,Pipeline & Subsea Technology

    GBS Development Phase 2 89 & onwards

    Condeeps

    Constrained by places to build

    Wet dock construction expensive

    No Condeep type substructures currently

    planned worldwide

    Phase 2 the dry-built CGS:

    Built entirely in the dry

    Ravenspurn North - the 1st

    Made concrete competitive again

    10 built so far

    Advantages of concrete GBSs retained Storage

    Large topsides

    Good for remote locations

    Good for relatively weak soils

    Removable / relocatable

    Ice load resistanceRavenspurn North, 1989

  • 7/29/2019 CIVL4171 Offshore Structure

    10/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Gravity base offshore structures

    Built entirely in the dry Most skilled civil contractors can build them.

    Well suited to countries without large offshorefabricators:

    Eg Australia & some SE Asia

    Focus on simple construction & installation:

    Flat slabs & straight walls easier than cylinders &domes.

    Lower concrete strengths (50 60MPa cube).

    All outfitting also in the dry.

    Much simpler ballasting systems.

    Well suited to offshore deck floatovers.

    More applicable to shallower waters

    Flat elements become inefficient with

    high hydrostatic heads

    But efficient designs for 160m

    water depths have been developed.

    WandooB

    1996

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Gravity base offshore structures

    CGS and CONDEEP comparison

  • 7/29/2019 CIVL4171 Offshore Structure

    11/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Design requirements

    Stable under transportation and installation.

    Carries topsides weight.

    Resists hydrostatic pressure at installation & operation.

    Transmits environmental loading to the underlying soils.

    Accommodates oil temperature differences in operation.

    Abandonable or Removable.

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Codes of Practice & Guidance Notes

    Det norske Veritas -Rules for the Classification of Fixed

    Offshore Installations

    ISO 19903:2006 -Petroleum and natural gas industries -- Fixedconcrete offshore structures

    BS8110 -British Standard for the Structural Use of Concrete

    NS3473 -Norwegian Standard for Concrete Structures

  • 7/29/2019 CIVL4171 Offshore Structure

    12/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Foundation criteria

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Foundation design issues

    Surficial soils critical unlike piles different SI data & testingneeded.

    Generally governed by sliding, overturning or bearing capacityfailure.

    Skirts used to transfer loads to competent strata but they have to

    penetrate to it too.

    Sandy soils: weight x angle of shear resistance.

    Silt and clay soils: base area x the shear strength.

    Skirts also contribute.

    Soil strength degredation in storms - build up of porewater pressure. Scour protection needed if competent strata is shallow.

    Settlements generally higher than with piles

    Potential for liquefaction under extreme seismic

  • 7/29/2019 CIVL4171 Offshore Structure

    13/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Construction

    Dock or casting basin facilityrequired.

    Only one casting basin in

    Australia at Bunbury.

    Several European docks exist.

    Potential sites in SE Asia.

    Medium to large projects can

    economically cover the cost of

    casting basin construction.

    Designing for easy construction

    IS KEY!

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Construction

  • 7/29/2019 CIVL4171 Offshore Structure

    14/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Construction

    Suspended roof slab constructionneeds an economic methodof decking out to fixreinforcement:

    Steel beams on metal decking isone solution (sacrificial).

    No on-site welding is involved.

    Use relatively low averagereinforcement density (300 350kg / m3) for CGS as awhole.

    Higher densities uneconomic, &

    excessively slow to build.

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Construction

    Slipforming is the most commonconstruction method.

    Form rises continually onhardened concrete.

    Very successful method, ifcorrectly done.

    Elements must be detailedcorrectly.

    Must get concrete mix right too: Strength & durability. Workability. Varied setting times for

    slipforming.

  • 7/29/2019 CIVL4171 Offshore Structure

    15/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Outfitting

    Usually critical path & timeconsuming.

    Keep steel to concrete interfacesimple.

    Modularise when possible, maximisingoff-site fabrication.

    Minimise number of connection pointsto the concrete.

    Maximise work at low level.

    Provide good temporary man access,& weather protection.

    Minimise work in shafts.

    Dont do civil & mechanical work in

    the same area at the sametime.

    CIVL 4171 Platform,Pipeline & Subsea Technology

    CGS Outfitting

    Oil & condensate can be stored in

    CGSs.

    Three systems available:

    Closed wet

    Open wet

    Dry (for condensate)

    Simplicity is the key on modernsystems.

    Cast-in pipework ensures durability &

    robust, leak-tight pipeworksystems.

  • 7/29/2019 CIVL4171 Offshore Structure

    16/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Oil storage systems

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Floatover Deck Installation

    Malampaya shown 12,000tedeck

    Naturally suits CGS layout &foundations.

    Deck floatovers good solution tominimise HUC.

    Wandoo was first open oceanapplication.

    Economic where large heavy lift

    crane vessels notavailable.

    Only relatively small oceangoing crane vesselscurrently operate in theAsia Pacific (circa 2,000temax. offshore lift).

  • 7/29/2019 CIVL4171 Offshore Structure

    17/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Future uses for CGS

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Future uses for CGS

  • 7/29/2019 CIVL4171 Offshore Structure

    18/18

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Gravity base offshore structures - Advantages

    No crane vessel needed

    Fast offshore installation

    Good for weakish soils

    Good for heavy topsides

    Oil storage in base

    Ideal for deck floatover

    Durability / low maintenance

    Fatigue resistant

    Robust re ship impact

    Appurtenance protection

    Low skill labour to build

    Local content

    Fast HUC

    New generation CGSsstraightforward to remove

    Good option if fabricators arebusy

    CIVL 4171 Platform,Pipeline & Subsea Technology

    Gravity base offshore structures - Disadvantages

    Best suited to remote offshore sites

    Construction requires casting basin and deep channel for tow.

    Less suited to well developed oil province with large numbersof existing pipelines (storage not required)

    Likely to be less economic than than traditional piled jacketsif Advantages issues not key.