    Civil Engineering Practice

    www.onlinecivil.tk

    RATE ANALYSISPCC (1:2:4) (Manual):-

    Wet PCC = 10

    Factor = 1.54

    Dry PCC = 15.4Material:-

    Cement = 1x15.4/(7x.035)= 62.857 bags

    Sand = 4.4

    Crush = 8.8

    Labour:-Mason = 0.1 day/

    = 1 day

    Waterman = 2.13 day/

    =21.3 daysLabour = 0.7day/

    = .7x(10+15.4)/2

    = 8.89 daysMachinery:-

    Viberator = 1 hour for 10

    = 0.125 days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 62.85714 Bags - 300 18857.14

    Sand 4.4 - 212 932.8

    Crush 8.8 - 1167 10269.6

    2

    Man Power

    Mason 1 - 1 600 600

    Water Man 1 - 21.3 150 3195

    Simple Labour 1 - 8.89 250 2222.5

    3

    Machinery

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 36277.04

    4

    Miscellaneous

    Water Charges 400

    36677.04

    Sundries @7.5% Of Sum Of Resources 2750.778Cost Without the Profit Of Contractor 39427.82

    5 Profit @10% 3942.782

    6

    Total Amount For 10 of PCC(1:2:4) 43370.6

    Total Amount For 1 of PCC(1:2:4) 4337.06

    Total Amount For 1 of PCC(1:2:4) 122.7933

  • 7/28/2019 civil engineering-Rate Analysis

    2/7

    Civil Engineering Practice

    www.onlinecivil.tk

    PCC (1:3:6) (Manual):-

    Wet PCC = 10Factor = 1.54

    Dry PCC = 15.4

    Material:-Cement = 1x15.4/ (10x.035)

    = 44 bags

    Sand = 4.62Crush = 9.24

    Labour:-

    Mason = 0.1 day/

    = 1 dayWaterman = 2.13 day/

    =21.3 days

    Labour = 0.7day/

    = .7x(10+15.4)/2= 8.89 days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 44 Bags - 300 13200

    Sand 4.62 - 212 979.44

    Crush 9.24 - 1167 10783.08

    2

    Man Power

    Mason 1 - 1 600 600

    Water Man 1 - 21.3 150 3195Simple Labour 1 - 8.89 250 2222.5

    3

    Machinery

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 31180.02

    4

    Miscellenous

    Water Charges 400

    31580.02

    Sundries @7.5% Of Sum Of Resources 2368.502

    Cost Without the Profit Of Contractor 33948.52

    5 Profit @10% 3394.852

    6

    Total Amount For 10 Of PCC(1:3:6) 37343.37

    Total Amount For 1 of PCC(1:3:6) 3734.337

    Total Amount For 1 of PCC(1:3:6) 105.7287

  • 7/28/2019 civil engineering-Rate Analysis

    3/7

    Civil Engineering Practice

    www.onlinecivil.tk

    PCC (1:4:8) (Manual):-

    Wet PCC = 10Factor = 1.54

    Dry PCC = 15.4

    Material:-Cement = 1x15.4/(13x.035)

    = 33.85 bags

    Sand = 4.74Crush = 9.48

    Labour:-

    Mason = 0.1 day/

    = 1 dayWaterman = 2.13 day/

    =21.3 days

    Labour = 0.7day/

    = .7x(10+15.4)/2= 8.89 days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 33.84615 Bags - 300 10153.85

    Sand 4.738462 - 212 1004.554

    Crush 9.476923 - 1167 11059.57

    2

    Man Power

    Mason 1 - 1 600 600

    Water Man 1 - 21.3 150 3195Simple Labour 1 - 8.89 250 2222.5

    3

    Machinery

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 28435.47

    4

    Miscellaneous

    Water Charges 400

    28835.47

    Sundries @7.5% Of Sum Of Resources 2162.66

    Cost Without the Profit Of Contractor 30998.13

    5 Profit @10% 3099.813

    6

    Total Amount For 10 of PCC(1:4:8) 34097.94

    Total Amount For 1 of PCC(1:4:8) 3409.794

    Total Amount For 1 of PCC(1:4:8) 96.54004

  • 7/28/2019 civil engineering-Rate Analysis

    4/7

    Civil Engineering Practice

    www.onlinecivil.tk

    PCC (1:2:4) (Mechanical):-

    Wet PCC = 10

    Factor = 1.54Dry PCC = 15.4

    Material:-

    Cement = 1x15.4/(7x.035)= 62.857 bags

    Sand = 4.4

    Crush = 8.8

    Labour:-Mason = 0.1 day/

    = 1 day

    Waterman = 2.13 day/=21.3 days

    Labour = 0.3day/

    = 3 days

    Machinery:-Viberator = 1 hour for 10

    = 0.125 days

    Concrete Mixer + Lift Arrangement = 0.45days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 62.85714 Bags - 300 18857.14

    Sand 4.4 - 212 932.8

    Crush 8.8 - 1167 10269.6

    2

    Man Power

    Mason 1 - 1 600 600Water Man 1 - 21.3 150 3195

    Simple Labour 1 - 3 250 750

    3

    Machinery

    Concrete Mixer + Lift Arrangement 0.45 18000 8100

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 42904.54

    4

    Miscellaneous

    Water Charges 400

    43304.54

    Sundries @7.5% Of Sum Of Resources 3247.841

    Cost Without the Profit Of Contractor 46552.38

    5 Profit @10% 4655.238

    6

    Total Amount For 10 of PCC(1:2:4) 51207.62

    Total Amount For 1 of PCC(1:2:4) 5120.762

    Total Amount For 1 of PCC(1:2:4) 144.9819

  • 7/28/2019 civil engineering-Rate Analysis

    5/7

    Civil Engineering Practice

    www.onlinecivil.tk

    RCC (1:2:4) (Mechanical):-

    Wet RCC = 10

    Factor = 1.50

    Dry PCC = 15.0

    Material:-Cement = 62.857 bags

    Sand = 4.4Crush = 8.8

    Steel = 1% volume of concrete

    = 10/100x1x7850= 785 kg

    Labour:-

    Mason = 0.1 day/

    Waterman = 2.13 day/Labour = 0.3day/

    Steel Cutter = 250 kg/day

    Steel fixer = 1000kg/day

    Machinery:-Viberator = 1 hour for 10

    = 0.125 days

    Concrete Mixer + Lift Arrangement = 0.45days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 61.22449 Bags - 300 18367.35

    Sand 4.285714 - 212 908.5714

    Crush 8.571429 - 1167 10002.86

    Steel 785 Kg - 60 47100

    2

    Man PowerMason 1 - 1 600 600

    Water Man 1 - 21.3 150 3195

    Simple Labour 1 - 3 250 750

    Steel Cutter / Binder 1 - 3.14 600 1884

    Steel Fixer 1 - 0.785 600 471

    3

    Machinery

    Concrete Mixer + Lift Arrangement 0.45 18000 8100

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 91578.78

    4

    MiscellanousWater Charges 400

    91978.78

    Sundries @ 8% Of Sum Of Resources 7358.302

    Cost Without the Profit Of Contractor 99337.08

    5

    Profit @10% 9933.708

    Total Amount For 10 of RCC(1:2:4) 109270.8

    Total Amount For 1 of RCC(1:2:4) 10927.08

    Total Amount For 1 of RCC(1:2:4) 309.3737

  • 7/28/2019 civil engineering-Rate Analysis

    6/7

    Civil Engineering Practice

    www.onlinecivil.tk

    RCC (1:1.5:3) (Mechanical):-

    Wet RCC = 10

    Factor = 1.50Dry PCC = 15.0

    Material:-

    Cement = 77.92 bagsSand = 4.09

    Crush = 8.18

    Steel = 2% volume of concrete= 10/100x2x7850

    = 1570 kg

    Labour:-

    Mason = 0.1 day/Waterman = 2.13 day/

    Labour = 0.3day/

    Steel Cutter = 250 kg/day

    Steel fixer = 1000kg/dayMachinery:-Viberator = 1 hour for 10

    Concrete Mixer + Lift Arrangement = 0.45days

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Material

    Cement 77.92208 Bags - 300 23376.62

    Sand 4.090909 - 212 867.2727

    Crush 8.181818 - 1167 9548.182

    Steel 1570 Kg - 60 94200

    2

    Man PowerMason 1 - 1 600 600

    Water Man 1 - 21.3 150 3195

    Simple Labour 1 - 3 250 750

    Steel Cutter / Binder 1 - 6.28 600 3768

    Steel Fixer 1 - 1.57 600 942

    3

    Machinery

    Concrete Mixer + Lift Arrangement 0.45 18000 8100

    Viberator 1 - 0.125 1600 200

    Expanses On Material, Labour & Machinery 145547.1

    4

    MiscellanousWater Charges 400

    145947.1

    Sundries @ 8% Of Sum Of Resources 11675.77

    Cost Without the Profit Of Contractor 157622.8

    5

    Profit @10% 15762.28

    Total Amount For 10 of RCC(1:1.5:3) 173385.1

    Total Amount For 1 of RCC(1:1.5:3) 17338.51

    Total Amount For 1 of RCC(1:1.5:3) 490.8979

  • 7/28/2019 civil engineering-Rate Analysis

    7/7

    Civil Engineering Practice

    www.onlinecivil.tk

    SHUTTERING (Steel):-

    The Quantity of Shuttering = 10

    Rate of Shuttering & Supports per day = 45 Rs/= 485 Rs/

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Man Power

    Carpenter 1 - 0.3 600 180

    Labour 1 - 0.45 250 112.5

    2

    Miscellaneous

    Shuttering Plates 10 9 484.5 43605

    43897.5

    Sundries @7.5% of Sum Of Resources 3292.313

    Cost Without the Profit Of Contractor 47189.81

    3 Profit @10% 4718.981

    4

    Total Amount For 10 of Steel Shuttering 51908.79

    Total Amount For 1 of Steel Shuttering 5190.879

    Total Amount For 1 of Steel Shuttering 482.2014

    SHUTTERING (Wood):-

    The Quantity of Shuttering = 10

    Rate of Shuttering & Supports per day = 25 Rs/

    = 269.124 Rs/

    Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)

    1

    Man Power

    Carpenter 1 - 0.3 600 180

    Labour 1 - 0.45 250 112.5

    2

    Miscellanous

    Shuttering Plates 10 9 269.124 24221.16

    24513.66

    Sundries @7.5% of Sum Of Resources 1838.525

    Cost Without the Profit Of Contractor 26352.193 Profit @10% 2635.219

    4

    Total Amount For 10 of Steel Shuttering 28987.41

    Total Amount For 1 of Steel Shuttering 2898.741

    Total Amount For 1 of Steel Shuttering 269.2755