Civil Engineering
Michael C. ApplegateHQ AFSOC/CEV
WETLANDS CONSTRUCTION AS MITIGATION
![Page 2: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/2.jpg)
2
Wetland MitigationWetland Mitigation
PURPOSE DESCRIPTION OF THE PROJECT AFFECTED WETLANDS DESCRIPTION OF THE MITIGATION AREA MITIGATION DESIGN RESULTS OTHER RECENT MITIGATION
![Page 3: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/3.jpg)
3
Purpose:Purpose:
Provide information on mitigation procedures for construction in wetlands
Provide background on project Provide construction information Show results Discuss ongoing mitigation project
![Page 4: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/4.jpg)
4
Project DescriptionProject Description
Mitigation Location: Estuary on the Florida Gulf Coast
Projects to be mitigated Wetland filling in four different locations on base Filling 17 acres of freshwater hardwood wetlands
Some isolated wetlands Wetlands above the headwaters of a stream impacted prior to
seventies by roadway.
![Page 5: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/5.jpg)
5
Affected WetlandsAffected Wetlands
Fill Projects Affected two types of freshwater wetlands Isolated broad leaved deciduous shrub and pine Titi swamp
Vegetation Titi Cliftonia monophylla, Cyrilla racemiflora Slash Pine Pinus elliotti
Broad Leafed deciduous forested wetland and pine Vegetation
Magnolia Magnolia grandiflora Sweet bay magnolia Magnolia virginiana Red bay Persea berbona Titi Cliftonia monophylla, Cyrilla racemiflora Black gum Nyssa sylvatica Cypress Taxodium ascendens
![Page 6: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/6.jpg)
6
Mitigation Design Mitigation Design
Wetland functions to be replaced or restored Replace forested hardwood swamp and shrub deciduous swamp
Create similar swamp habitat Functions DESIRED
Energy export through detrital food web Food source for invertebrates Habitat for reptiles, amphibians, birds and small mammals
![Page 7: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/7.jpg)
7
Mitigation Design Mitigation Design
Site evaluations Searched for uplands on base to be converted into freshwater wetlands Existing uplands pristine pine flatwoods-FWS “not recommended” Land acquisition – not feasible due to policy at the time Estuarine marsh – site available on base
Pros Shoreline –un-vegetated sandy shore and 250 foot seawall No vegetation
Cons Barge traffic creating severe waves parallel to shoreline Erosion undermining trees, archeological sites Coordination and permits necessary
![Page 8: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/8.jpg)
8
Description of Mitigation Area Description of Mitigation Area
Mitigation Area approximately 4.7 acres on Santa Rosa Sound Estuarine ecosystem Eroding shoreline at two locations
70 feet of erosion along approx 1000 linear feet of beach in Santa Rosa Sound
Erosion causing destruction of archaeological sites Seawall installed in mid 80s which caused further erosion at ends of
wall Erosion result of prevailing south winds, ship and boat traffic
Intra-coastal waterway channel No endemic vegetation
![Page 9: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/9.jpg)
9
Eroded shoreline in areaEroded shoreline in area
![Page 10: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/10.jpg)
10
Mitigation Design Mitigation Design
Functions desired Tidal marsh ecosystem Protect uplands from erosion Provide habitat for estuarine species Provide nursery areas for estuarine species Provide high value vegetation for detrital food web Provide methods for export of detritus/interchange of tidal waters Provide feeding areas for fish, birds and invertebrates
![Page 11: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/11.jpg)
11
Mitigation Design Mitigation Design
Vegetation Mimic natural systems in the area Use combination of littoral species Optimize elevations for planting Vegetation in area
Smooth cordgrass Spartina alterniflora Black needlerush Juncus roemerianus Saltmeadow cordgrass Spartina patens
![Page 12: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/12.jpg)
12
Mitigation Design Mitigation Design
Elevations Mimic natural systems in the area
Elevations of the existing vegetation in the area were taken to optimize planting success Cross sectional design included a stone rip rap barrier of sufficient size to insure good water
flow but of sufficient height to act as a wave attenuator Elevations were varied to create shallow and deep intertidal areas
![Page 13: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/13.jpg)
13
Mitigation Construction Mitigation Construction
Breakwater constructed first Fill - clean sand fill installed to match the design elevations Planting
Plant sprigs from a local supplier were installed by contractor on 18 inch centers in the spring of the year
Hurricane Opal destroyed one of the two planted areas in November of 1995 Elevations had to be re-established and area had to be replanted
![Page 14: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/14.jpg)
14
Mitigation CostsMitigation Costs
Initial Costs 4.7 acres – $350k 2.3 acres refilled, graded and replanted - $150k Total Cost - $500k
![Page 15: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/15.jpg)
15
Results – Eastern marshResults – Eastern marsh
![Page 16: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/16.jpg)
16
Results - Western marshResults - Western marsh
![Page 17: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/17.jpg)
17
Western marsh ecotoneWestern marsh ecotone
![Page 18: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/18.jpg)
18
Western marsh ponded areaWestern marsh ponded area
![Page 19: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/19.jpg)
19
Ongoing Mitigation Project 4.3 acOngoing Mitigation Project 4.3 ac
![Page 20: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/20.jpg)
20
Ongoing mitigation high tideOngoing mitigation high tide
![Page 21: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/21.jpg)
21
Ongoing mitigation low tideOngoing mitigation low tide
![Page 22: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/22.jpg)
22
Ongoing mitigation tidal creekOngoing mitigation tidal creek
![Page 23: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/23.jpg)
23
Ongoing mitigation existing vegetation, shallow area, rip rap Ongoing mitigation existing vegetation, shallow area, rip rap
![Page 24: Civil Engineering Michael C. Applegate HQ AFSOC/CEV WETLANDS CONSTRUCTION AS MITIGATION.](https://reader037.fdocuments.us/reader037/viewer/2022103122/56649c9a5503460f9495761a/html5/thumbnails/24.jpg)
24
Last slide – Questions?Last slide – Questions?