CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
-
Upload
hijran-zainal -
Category
Engineering
-
view
554 -
download
2
Transcript of CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
GROUP MEMBERS:
1) SITI HIJRAN BINTI ZAINAL 2011832518
2) NUR SAKINAH BT ABD HAMID 2011821644
3) NURUL AIMI BT MALEK 2011240844
4) NUR SYAZWANI BT JASNI 2011845836
GROUP : EC1106 B2
LECTURER : MR. KHAIRUL AMMAR BIN MUHD ALI
INTRODUCTION
In this last semester from November 2013 until April
2014, we are given a project of double storey house. We
are decided to make a rough estimation about a unit of
double storey house and 100 unit of double storey house
construction. With this, we were choosing a plan of Semi-D
residential of Timbalan Pengarah at Kolej Matrikulasi
Banting, Selangor as our project.
PROJECT DETAILS
TAKING OFF
SAMPLE CALCULATION
BEAMCONCRETE WORK
FORMWORK
REINFORCEMENT
COLUMNCONCRETE WORK
FORMWORK
REINFORCEMENT
SLAB
PILE CAP
STAIRCASE
BILL OF QUANTITY
BILL OF QUANTITY
THE GANTT CHART
S-CURVE
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
0
10000
20000
30000
40000
50000
60000
70000
80000
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Cu
mu
lati
ve C
ost
Co
st
Cash Flow Report
Cost Cumulative Cost
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
0
1000
2000
3000
4000
5000
6000
7000
8000
Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26Week 28Week 30Week 32Week 34Week 36Week 38Week 40Week 42Week 44Week 46Week 48Week 50Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26Week 28Week 30Week 32Week 34Week 36Week 38Week 40Week 42Week 44Week 46Week 48Week 50Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Cu
mu
lati
ve C
ost
Co
stCash Flow Report
Cost Cumulative Cost
DISCUSSION
The grand total of the material cost that we gained from the calculated taking off and the bill of quantities is RM 148,664.08. After including 11% from JKR References PulauPinang the actual material cost is RM RM 164,997.13.
The Gantt chart and S-curve shows the duration and construction cost of 100 unit of double storey house which is shows the time started the project until it finished.
CONCLUSION
In conclusion, the knowledge that we gained from doing this project really expose us the important of knowing the real specific of work. Taking off and the bill of quantity together with the Gantt chart and s-curve also be considered in the taking off in order to get estimated value for the each project. Thus, the specific cost needed for a unit of house have been estimated.