CITY OF SEATTLETOPOFF-2

INTEGRATED PLANNINGPresented by

SergeantDebra Jelcick

Jim PapineauAMTI

Battalion ChiefRandy Hansen

D’Arcy MorganDHS / ODP

Page 3: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

3

Everyone’s Input is Necessary

Private Public Local Regional State Contractor Federal

Page 4: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

4

Proportionate Preparation Time

TableTop – TTX

CommandPost – CPX

FullScale – FSE

Page 5: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

5

Determine the Exercise Type

No – Notice– Focus on a few simple objectives

Limited – Knowledge – Simple objectives with some specific

complexities

Open Book– Complexity enhanced yet manageable

Page 6: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

6

Experience Dictates Outcome

Exercise Planners MUST have:– Subject matter knowledge– Exercise design experience– Exercise production experience

If not – outside Contractor must be:– Experienced– Trustworthy– Reliable

Page 7: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

7

Establish Responsibilities Early

“Planning Team” aka Production– Everything necessary to “produce” the play– “Trusted Agents” and Lead Planners– Core Planning Team– Before ~ During ~ After the event– Continuity is critical for key positions

Page 8: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

8

Establish Responsibilities Early

“Participants” aka Responders– All the response elements to the event– Drives the Logistics side of Planning– Must be involved early on to be proactive

for specific logistics needs– Should use this process to identify current

SOP gaps and do real-world plan revisions

Page 9: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

9

Remember...

Page 10: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

10

To Maximize Your Outcome

Maximize venue input and collaboration Determine objectives that drive strategies Identify key players / planners early Ensure continuity with planning partners Establish cornerstone items early Don’t be afraid to be Lee Iococca If necessary, remember “NFW”

Page 11: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

11

To Maximize Your Outcome

Establish the exercise timeline Adhere to deliverable dates Collective engagement and agreement

by numerous agencies ~ herding cats Set ground rules at the beginning Solicit buy-in from participating

agencies

Page 12: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

12

Site Layout Issues – The Basics

Physical size requirements Complexity / scope of the FSE Objectives of the FSE Realism versus real-world safety and

security constraints On-site / Off-site integration & logistics

Page 13: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

13

Site Layout Issues – The Basics

Traffic considerations Neighboring business impacts Public anxiety Crowd control VIP’s and Observers Media considerations

Page 14: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

14

Site Overview

8th Ave

Hanford

HortonHinds

Airport Way

Media

Production

Page 15: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

15

Page 16: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

16

Page 17: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

17

Page 18: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

18

Page 19: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

19

Page 20: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

20

Page 21: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

21

Security Issues – On / Off Site

Participant security inside the site (absolutely no weapons)

Roving internal security teams (armed) Perimeter security (armed) Visual identification

– Personal (photo ID with Security Decal)– Weapons-free indication (wrist bands)– Vehicular clearance (grill bands)

Page 22: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

22

Security Issues – On / Off Site

Pre-Credentialing wherever possible Security Enhancement Decal Criminal background checks (for non-

government employees) Responder “pre-staging” off-site “Bubble-to-bubble” security process Mobile credentialing process

Page 23: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

23

Safety Plans

Responder Safety Officer(s) – in play Exercise Safety Officers – Production Role Player Safety Officers – Production Integrated with real-world 9-11 system

Page 24: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

24

Media Site

Page 25: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

25

Ensure PIO / PAO’s are Involved

Proportionate to the profile of the event Provide adequate time to address

issues Ensure that Subject Matter Experts

(SME’s) and First Responders are involved in their planning meetings

Page 26: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

26

Communications Plans

Responder’s internal plans Production crews (on/off site) Multiple venues

– Responder Staging areas– Master Control Center– Traffic units

Cannot overload real-world systems Combination of radio, cell, Nextels, video

Page 27: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

27

Executive or Command Level

Ensure real-world political perspective Early involvement Confirm objectives match the Planning

Team’s Provide SME’s / First Responders at

their planning meetings

Page 28: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

28

VIP / Observer Stands

Page 29: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

29

VIP’s, Observers

Get control from the beginning Establish written ground rules Distribute the rules far and wide Stick to your rules, but determine

exceptions ahead of time

Page 30: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

30

Blast area aerial view

Page 31: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

31

Blast props

Page 32: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

32

Blast props

Page 33: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

33

Blast props

Page 34: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

34

Vehicle blast pattern

Page 35: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

35

Vehicle tire

Page 36: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

36

HazMat and too many others

Page 37: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

37

Grey helmets & Safety

Page 38: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

38

Treatment areas

Page 39: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

39

Logistics Plans

Feeding and hydration Port-a-lets Shelters for weather issues Power Night operations considerations Personnel parking / transportation Responder requests – anticipated gaps

Page 40: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

40

Evaluation and Controller Process

They must have experience in their respective disciplines

Exercise complexity and Evaluator experience should be commensurate

Start this process early to meet needs No 20-something poli-sci grads

(remember the warehouse inventory)

Page 41: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

41

Evaluation and Controller Process

Must have exercise experience “Exercise Command” structure should

be as tight as your IC structure Requires integrated “Trusted Agents”

from key host agencies Continuity is essential

Page 42: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

42

Data Collection and Documentation

Establish the Process Central collection POC and oversight

is critical On-field hotwash process is difficult,

but worthwhile Too much info isn’t possible Collection delays cause data loss

Page 43: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

43

Methods of Data Collection

Handwritten notebooks, pre-formatted Consider pocket tape recorders

(date/time stamp is helpful) Disposable cameras with CD

processing Documentary crew for video and stills

(including ‘The Creation of XXX”)

Page 44: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

44

TOPOFF-2 “Data Collector Log”M

SG

in

MS

G o

ut

disc

ussi

on

Dec

isio

n

Dir

ectiv

e

Mov

emen

t

Act

ivity

Oth

er

INJE

CT

Observed Event Type

Observation Description Time

Page 45: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

45

Lessons Learned and the AAR

Applies to everyone involved Planners Production personnel Controllers & Evaluators Responders Victims (role players)

Page 46: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

46

The After-Action-Report/Review

Timely Accurate Complete Minimally sanitized Widely distributed Readily available on-line

(unless sensitive ~ FOUO)

Page 47: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

47

KEY ISSUES FOR PLANNING

Exercise Planners MUST have:–Subject matter knowledge

–Exercise design experience

–Exercise production experience

Page 48: City of Seattle TOPOFF-2 Central Planning Staff1.

City of Seattle TOPOFF-2 Central Planning Staff

48