CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation...

13
CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010

Transcript of CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation...

Page 1: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

US 41 Utility Corridor Study Presentation

April 27, 2010

Page 2: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

US 41 Corridor Study Participants

North Port Utilities Staff Jody Kirkman, Sarasota County Mark Flint, Watermark Engineering

Sub-consultants and staff Rob Ori, Public Resources Management Group Shaun Cullinan, North Port PZ&E WVID Stakeholders

Page 3: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Purpose and Overview of Corridor Study Identified Capital Projects Cost Recovery and Customer Impacts Recommendations and Commission Discussion

Agenda

Page 4: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Purpose and Overview of Study

The utility US41 plan supports:A shared vision for the gateway to the City

Architectural/ Land use Protection of Myakka River BasinEconomic development of corridorAnnexation of corridor propertiesWVID commitments Efficient use of existing transmission

Page 5: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

US41 Corridor Boundaries

Page 6: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Lines Constructed and Dedicated by WVID

Page 7: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Corridor Utility Service Needs

990 ERCs needed City commitment to WVID for transmission

capacity 3,600 ERCs of temporary wastewater transmission capacity 5,600 ERCs of permanent water transmission capacity

City has ample treatment capacity

Page 8: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Water Projects to Serve Corridor

New water transmission lines Myakkahatchee Creek WTP to US 41 North Port Blvd and US 41 to Ortiz Blvd.

Design trigger 2,800 ERCs paid within WVID/Corridor

Page 9: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Wastewater Projects

4” Force main collection system Construction trigger - 8 commercial service

connections and/or 28 ERCs per segment

Neighborhood lift stations Construction trigger - 43 ERCs commercial per

segment (Includes 28 ERC’s from force main project)

Page 10: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Capital Project Funding Summary

Project cost estimates : Water = $1,377,300 Wastewater = $1,484,400 Total Cost = $2,861,700

Wastewater project costs: Projects already constructed not included

Page 11: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Funding and Cost Recovery Corridor Capital Recovery Fee Per ERC:

Water = $400 / Wastewater = $1,620 Paid at capacity reservation Paid at time of reservation in addition to Capacity

Fees Allows growth & satisfies commitment to WVID Available Wastewater Transmission Capacity is 476

ERCs WVID WWTP must be built to add more ERCs

Page 12: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Recommendations

City and County will coordinate: City of North Port service of corridor Annexation issues Architectural / land use requirements

City will: Begin wastewater project for MMHP Proceed with triggered water and wastewater projects Establish reasonable capital recovery fees

Page 13: CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN US 41 Utility Corridor Study Presentation April 27, 2010.

CITY OF NORTH PORT US41 CORRIDOR UTILITIES MASTER PLAN

Discussion and Commission Discussion