CITY OF NEW ORLEANS
Reporting Period: June 1 – June 30th
Office of Performance & Accountability
ReqtoCheckSTAT
www.nola.gov/opa
Context In order to deliver critical services for its citizens—such as constructing roads, rehabilitating homes, or picking up trash—the City often engages with private companies with specialized expertise. Because these and other services are so critical, Mayor Landrieu has made it a priority for vendors to be selected fairly, for contracts to be negotiated expeditiously and in the best interests of New Orleanians, and for vendors to be paid in a timely manner. What is ReqtoCheckStat? In order to improve the performance, accountability, and transparency of the City’s contracting system, Mayor Landrieu asked the Office of Performance and Accountability to design a performance management program for the entire process of contracting out services—from the requisition of budgeted funds to the issuance of check for services rendered. The result is ReqtoCheckStat, a performance management system where key City officials review data to assess how the City is meetings its goals and to hold departments accountable for their results. ReqtoCheckStat, which takes place monthly, are working meetings, intended to provoke constructive dialogue on what is working, what is not, and what the City needs to do to improve. Can I participate? This meetings are open to the public. Members of the public are invited to submit questions, which will be addressed by City officials.
Procurement Process Overview*
Requisition
•Department identifies need, and creates a requisition
•Requisition to use budgeted funds is approved by different offices
Procurement / DBE
•Approved requisition is reviewed by the Bureau of Purchasing
•Requisition is converted to Purchase Order (PO), Bid or Request for Proposal (RFP), depending upon scope of work and dollar amount
Contract Creation and
Routing
• Department routes contract materials through the system in order to obtain a contract
Contract Processing
and Approval
•Contract is reviewed for form, legality by Law Department
•CAO, City Attorney, Executive Counsel, Mayor/ Council review and approve contract
Payment
•Department reviews invoice and submits payment voucher to Accounts Payable (AP) to process payment
•Accounts Payable processes requests and makes payment
*See a more detailed process map on slide 30
Note : The reporting period covering the period 12.15.2011 to 1.31.2012 includes 1 ½ months of activity .
Requisition Approval
• Requisition Approved and Processed per Period
• Requisition Approval Queue by Approval Level
• Approval Time of Requisitions
Requisition Procurement
/ DBE
Contract Creation and
Routing
Contract Processing
and Approval Payment
Source : City of New Orleans Procurement System 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Approval Queue at 57 Requisitions as of 6.30.2012
66 63 57
976 979 933 939
Ending Approval Q4.30.2012
New RequisitionsCreated
RequisitionsApproved
Ending Approval Q5.31.2012
New RequisitionsApproved
RequisitionsProcessed
Ending Approval Q6.30.2012
Requisition Approval Queue General Fund for Period Ending 6.30.2012
130
48 51 47 29 34
214
132
40 19 34 17
33
42
6
344
213
133
66 63 57
0
50
100
150
200
250
300
350
400
1.31.2012 2.29.2012 3.31.2012 4.30.2013 5.31.2012 6.30.2012
Finance
Budget
Department
Requisitions in Q to be Approved
8
1
3
5
0 2 4 6 8 10
2 Days or Less
3- 5 Days
6-10 Days
Over 10 Days
Age of Requisitions in Q Budget Office
1
5
0 10 20 30 40
2 Days or Less
3- 5 Days
6-10 Days
Over 10 DaysAge of Requisitions in Q Finance
Source : City of New Orleans Procurement System 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Number of Days to Approve Requisitions
2.1 2.45 1.88
0.6 0.6 0.45
1.0 0.55 0.57
0.6 0.4 0.87
3.10 3.00 2.45
1.21 1.02 1.32
0
1
2
3
4
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Number of Days to Approve Requisitions by Reporting Period (Budget Office and Department of Finance)
Finance(1 Working Day Target)
Budget(2 Working Day Target)
3 Working Day Target
Days to Approve 1.31.2013 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
2 or less 71% 53% 74% 96% 96% 99%
3 Days 9% 15% 8% 3% 2% 1%
4-5 Days 9% 25% 11% 1% 1% 0%
6-10 Days 10% 7% 6% 0% 1% 0%
11-15 Days 1% 0% 1% 0% 0% 0%
Over 15 Days 0% 0% 0% 0% 0% 0%
Budget 2012
Days to Approve 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
1 or less 85% 99% 97% 96% 100% 93%
2 Days 7% 1% 2% 2% 0% 5%
3-5 Days 8% 0% 1% 2% 0% 2%
6-10 Days 0% 0% 0% 0% 0% 0%
11-15 Days 0% 0% 0% 0% 0% 0%
Over 15 Days 0% 0% 0% 0% 0% 0%
Finance2012
Requisition to Procurement
• Processing of Requisition by Bureau of Purchasing
• Status of Requisitions Awaiting Buyer Response
• Time to Convert Requisition to PO
• Status of Requests for Proposals
• Status of Bids
• DBE Compliance (Preliminary Data)
Requisition Procurement
/ DBE
Contract Creation and
Routing
Contract Processing
and Approval Payment
Source : Obtained from the Bureau of Purchasing 6.1.2012 and 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Number of Requisitions in Queue Waiting to be Processed by the Bureau of Purchasing Increased to 171
141 148 171
979 972 939 916
Ending Approval Q4.30.2012
New RequisitionsApproved
Requisitions Processed Ending Approval Q5.31.2012
New RequisitionsApproved
Requisitions Processed Ending Approval Q6.30.2012
Bureau of Purchasing Requisition Processing General Fund for Period Ending 6.30.2012
Status Count
Completed as of 7.9.2012 63
Need Contract 83
Processing Procurement 15
Waiting for Support 10
Grand Total 171
Status of Reqs Awaiting Buyer Processing
Status Count
Economic Development 2
Property mgmt. 2
Public Works 2
Aviation Board 1
NORD 1
Parks & Parkways 1
Police 1
Grand Total 10
Waiting for Support
92% 93% 93% 89% 85% 86% 92%
7% 3% 4% 5% 7% 9% 3%
1% 5% 3% 6% 8% 5%
5%
0%10%20%30%40%50%60%70%80%90%
100%
11.16.201112.15.2011
12.16.20111.31.2012
2.1.20122.29.2012
3.1.20123.31.2012
4.1.20124.30.2012
5.1.20125.31.2012
6.1.20126.30.2012
9 Days and Over 5 - 8 Days 0 -4 Days
The Bureau of Purchasing Processed Requisitions in Four Days or Less 86% of the Time (Average 920 POs per month)
* 6.1.2012 -6.30.2012 Includes time Req. to PO & RFPs and Bids time Req. received to time send to OIG
Source : Bureau of Purchasing 6.1.2012 and 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
6
4 4
9
2 3
4
7 4
7
2 2 3
Ending RFP Q4.30.2012
RFP Requests RFP Completed/ Cancelled
Ending RFP Q5.31.2012
RFP Requests RFP Completed/ Cancelled
Ending RFP Q6.30.2012
The Number of RFPS in Process Stands at 14 as of 6.30.2012
Waiting Committee Meeting
Waiting Opening Date
Total 15
Total 15 Waiting Information From Department / Other
Total 14
33% 33% 30% 36% 33% 43%
33% 50% 60% 50% 56%
48%
33% 17% 10% 14% 11% 10%
0%10%20%30%40%50%60%70%80%90%
100%
1.31.20123
YTD(2.29.2012)
6
YTD(3.31.2012)
10
YTD(4.30.2012)
14
YTD(5.31.2012)
18
YTD(6.30.2012)
21
10 andAbove
4 to 9
3 andbelow
Number of Proposals Received for RFPs Completed YTD 2012 (as of 6.30.2012) Department Brief Description
Police Survey
Finance Municipal Revenue Collection System
Law Insurance Producer of Record
Finance Investment Consultants Retirement
Economic Development Alternative/Temporary Staffing Svcs
Aviation Board Land Use
French Market Corp Multi-Use Parking Facility
Awaiting Committee Meeting
Department Brief Description Comment
CAO Group Term Life Plan Awaiting Decision
OCD Online Auction Services N.O. East Awaiting Decision
Public Works Curbside Management & Enforcement Awaiting Decision
Waiting on Support / Response from Departments
Source : Bureau of Purchasing 6.1.2012 and 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
* Includes cancelled Bids for which proposals were not received
8 3 1
6
5
12
5
4 7*
6
4
3 1
Ending Bid Q4.30.2012
Bid Requests Bids Completed/ Cancelled
Ending Bid Q5.31.2012
BID Requests BID Completed/ Cancelled
Ending BID Q6.30.2012
The Number of Bids in Process Decreased to 8 as of 6.30.2012
Waiting Opening Date
Waiting on Department
Total 18
Total 11
Total 8 In Process Bureau of Purchasing/DBE
9% 13% 24% 25%
34%
82% 75% 67% 69%
61%
100%
9% 13% 10% 6% 5%
0%10%20%30%40%50%60%70%80%90%
100%
1.31.20121
YTD(2.29.2012)
11
YTD (3.31.2012)
16
YTD(4.30.2012)
21
YTD(5.31.2012)
32
YTD (6.30.2012)
38
10 andAbove
4 to 9
3 andbelow
Number of Proposals Received for Bids completed YTD 2012 (as of 6.30.2012) YTD 38 Completed
Department Brief Description Comment
Capital NOFD Engine 31 Waiting Bid Recommendation
Awaiting on Department
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : Office of Supplier Diversity 6.30.2012
Cumulative YTD Percentage of DBE Committed Award Value as of 6.30.2012
1,190,946
4,756,283
7,905,779
$15,245,959
25,856,902 29,134,437
-
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
35,000,000
January February March April May June
DBE Commitment for Bids/RFPS Opened and that Have Been Reviewed by the Office of Supplier Diversity
Cumulative Estimated Contract Value 35% Goal DBE Award Value Committed
35% Goal
38% YTD Actual
5 9
3 4 3 2
3
3
4 3 1 1
3
1 3
1
8 3.2 Days
15 5.6 Days
8 5.1 days
7 4 Days
7 8.5 Days 4
6 Days
0
5
10
15
20
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 10 Days
4-10 Days
0-3 Days "Target"
Time to Process DBE Validation by the Office of Supplier Diversity 2012 Requests Completed (Working Days)
units
Contract Package Routing
• Average Contract Routing Time
Requisition Procurement /
DBE Contract Creation
and Routing
Contract Processing and
Approval Payment
Source : ECMS 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Average Time to Approve Contracts Meeting Target
2.3
1.1 0.6
1.3 1.4
0.4
0.4
0.5
1.8
0.3
0.6
0.4 0.9
1.6
0.9
0.8
0.5 0.5
1.0
1.2
4.1
2.4 2.5
5.7
3.8
0.0
1.0
2.0
3.0
4.0
5.0
6.0
2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Approval Time of Contracts by Approval Level in Days (by period)
CAO (1 daytarget)
Civil Service (1day target)
Finance (1 daytarget)
Bureau ofPurchasing (1 daytarget)
4 day aggregate target
Routing Aggregate Time 4.9 Days 5.15.2011
3 2 Days Purchasing
Finance
Civil Service
CAO
0 1 2 3 4 5
7 Contract Request are in Q as of 6.30.2012
4 5 Days
Days to Approve 4.30.2012 5.31.2012 6.30.2012 Days to Approve 4.30.2012 5.31.2012 6.30.2012
0-1 Days 91% 91% 83% 0-1 Days 93% 61% 90%
2- 3 Days 9% 7% 8% 2- 3 Days 7% 31% 0%
4-7 Days 0% 1% 9% 4-7 Days 0% 8% 10%
Over 8 Days 0% 1% 0% Over 8 Days 0% 0% 0%
Days to Approve 4.30.2012 5.31.2012 6.30.2012 Days to Approve 4.30.2012 5.31.2012 6.30.2012
0-1 Days 93% 74% 100% 0-1 Days 88% 76% 65%
2- 3 Days 2% 3% 2- 3 Days 9% 19% 28%
4-7 Days 5% 23% 4-7 Days 3% 3% 6%
Over 8 Days 0% 0% Over 8 Days 0% 2% 1%
Finance Distribution Approval
CAO Distribution Approval
Bureau of Purchasing Distribution Approval
Civil Service Distribution Approval
Contract Approval Process
• Contract Processing and Approval
Requisition Procurement /
DBE Contract Creation
and Routing
Contract Processing and
Approval Payment
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Contracts: All Contracts Processed, Received and in Queue 7.15.2011 – 6.30.2012 (Legal Review, CAO, Vendor Signature, City Attorney, Executive Council, Mayor/City Council)
Source : Law Department and ECMS System 7.1.2012
157 161 154 151 133 133 109
170 188 183 212
186 206
112 108
40 47 90 93 81 99
39 63
141
80 114 96 111 116 123
94 100 126 120 100
0
50
100
150
200
250
300
350
7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
All Contracts Processed, Received and in Q at the End of the Reporting Period as of 6.30.2012 (in units)
216 Contracts as 3.15.2011 2011 2012
In Queue Received
Closed
2 4
-7 -3 -18 -24
61
18
-5
29
-26
20
-40
-20
0
20
40
60
80
7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Net Change in Contracts Queue
2012 2011
Increase Q
Decrease Q
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Contracts : All Contracts in Process by Period (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)
Source : Contract Management System ECMS 7.1.2012
43 74
109 94 118
86 104 25
42 26 45
52
47 39
13
24 24 11
13
21 29
6
10 13 13
7 11
10
22
20 16 20
22 21
24
0
50
100
150
200
250
300
12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 120 Days
91 - 120 Days
61 - 90 Days
31- 60 Days
0 - 30 Days
The Average Age of Contracts Awaiting Processing Decreased to 50 Days
Total 188 Average Days 46
Total 183 Average Days 48
216 Contracts 64 Average Days
3.15.2011
Total 206 Average Days 50
Total 109 Average Days 64
Total 170 Average Days 53
Total 212 Average Days 43 Total 186
Average Days 51
102
19 4 3 39
89
4
165
11 Contracts
69 Contracts 64 Contracts
020406080
100120140160180
Manually RoutedEmergency
(Location NotSpecified)
Attorney Dp. City Att CAO To Send Vendor From Vendor Ordinance Executive Counsel Returned
Location and Average Age of Contracts in Process as of 6.30.2012 (Age from being received from the previous stage)
10 Contracts 15 Contracts
6 Contracts
5 Contracts
ECMS
28 Contracts
Age
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : : Contract Management System ECMS 7.1.2012
Contracts : All Contracts Executed by Period (Legal Review, CAO, City Attorney, Executive Counsel, Mayor/Council Approval)
30% 41% 33% 42% 34% 48% 54%
70% 59% 67%
58% 66% 52% 46%
60
39
56 62 58
51 40 41
-
10
20
30
40
50
60
70
80
90
100
11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 30 Days
0-30 Days
The Average Time to Close Contracts During the Period Increased to 41 Days from 40 Days. 36% of Contracts Were Closed in 30 Days or Less (80% Target)
66 Days 3.15.2011
28%
72%
24
14
2 1 4
15
2
0
5
10
15
20
25
Manually RoutedEmergency
(Location Not Specified)
Legal Review D. City Att CAO To Send Vendor From Vendor Executive Con.
Average Days to Process Contracts Completed During the Period 6.1.2012 - 6.30.2012 (by Stage)
ECMS
Contracts Awaiting Vendor Signature
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source : : Contract Management System ECMS 7.1.2012
Note: Per policy memorandum 122R, each department/agency is responsible for reaching out to the vendor to obtain their signature after the law department sends the initial notification.
Department Number Contracts Average Days Waiting For Signature
AVIATION (Waiting on Law Department to Approve) 2 2
NEIGHBORHOOD STABLIZATION 2 2
NEW ORLEANS BUILDING CORPORATION 1 8
CAO 2 9
LAW 6 17
PUBLIC WORKS 5 17
CAPITAL PROJECT 5 17
ECONOMIC DEVELOPMENT 1 17
MOSQUITO CONTROL BOARD 1 19
SANITATION DEPARTMENT 2 25
HOMELAND SECURITY 9 26
FINANCE 1 30
FIRE DEPARTMENT 1 39
HEALTH DEPARTMENT 3 40
OFFICE OF TECHNOLOGY & INNOVATION 2 41
CIVIL SERVICE 2 41
NORD RECREATION DEPARTMENT 3 44
MAYOR 2 46
DISASTER CDBG UNIT 1 47
BLIGHT & REVITALIZATION 1 47
PROPERTY MANAGEMENT 12 102
The Check: Accounts Payable
• General Fund Payments
• Processing by Accounts Payable
• Payment from Invoice Date
• Capital and Grants Expenditure Payments
• Processing by Accounts Payable
• Payment from Invoice Date
• Detail Review (invoices in the pipeline)
• CDBG Invoice Payments
• DPW Payments
• DPW Revolver Payments
• Capital Projects Payments
• Capital Projects Revolver Payments
Requisition Procurement Contract Creation
and Routing
Contract Processing and
Approval Payment
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable and Office of Performance and Accountability. Collected 7.1.2012 – 7.12.2012
The Percentage of General Fund (and Agency) Payments Processed in 7 Days or Less Increased to 99%
20%
45% 45% 28%
62%
99% 48%
53% 54% 70%
38%
1%
30%
1% 1% 2% 1% 1% 2%
0%10%20%30%40%50%60%70%80%90%
100%
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Working Days to Process General Funds and Agencies Check Payments by A/P Office for Periods Ending 1.31.2011 to 6.30.2012 (in %)
(793 Payments June)
Over 30 Days
16 - 30 Days
8-15 Days
7 Days or less
90% Target
12
8 8 9
6
3
0
2
4
6
8
10
12
14
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Number of Days to Process Invoices by A/P Department (GF Expenditures)
Target 7 Days
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Percentage of General Fund (and agency) Payments in 30 Days or Less Increased to 66% in the Current Period
Source :Accounts Payable and Office of Performance and Accountability. Collected 7.1.2012 – 7.12.2012
34% 40% 56% 50%
63% 66%
42% 45%
33% 32% 24% 21%
16% 8% 8% 14% 9% 8% 8% 7% 3% 5% 4% 5%
0%10%20%30%40%50%60%70%80%90%
100%
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Percentage of Payments in Days From Invoice Date to Payment for General Fund (or Agency) Expenditures for Periods Ending
1.31.2012 - 6.30.2012(in %) (793 Payments June)
Over 121 Days
61 - 120 Days
31 to 60 Days
30 Days or Less
52 48
40 44
37 38
0
10
20
30
40
50
60
70
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Number of Days to Pay Invoices From Invoice Date (GF Expenditures)
Target 30 Days
The Percentage of Capital and Grant Payments Processed in 7 Days or Less Remains Over the 90% Target
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable and Office of Performance and Accountability. Collected 7.1.2012 – 7.12.2012
95% 92% 99% 98% 99% 98%
4% 5% 1% 2% 1% 2% 1% 3%
0%10%20%30%40%50%60%70%80%90%
100%
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Working Days to Process Capital Expenditures and Grants Check Payments by A/P Office for Periods Ending 1.31.2012 - 6.30.2012(in %)
Sample 100 selections 90% confidence level +--10
Over 30 Days
16 - 30 Days
8-15 Days
7 Days or less
3 4
2 2 2 2
0123456789
10
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Number of Days to Process Invoices by A/P Department (Capital and Grant Expenditures)
Target 7 Days
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
The Percentage of Capital and Grant Payments Made in 45 days or Less from Invoice Date Stands at 69%
Source :Accounts Payable and Office of Performance and Accountability. Collected 7.1.2012 – 7.12.2012
68% 66% 69% 69% 71% 69%
10% 15% 16% 7% 10% 9% 15% 14% 10%
12% 10% 20% 7% 6% 5% 12% 9% 2%
0%
20%
40%
60%
80%
100%
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Percentage of Payments in Days From Invoice Date to Payment for Capital and Grant Expenditures for Periods Ending
1.31.2012 - 6.30.2012(in %) Sample 100 selections 90% confidence level +-10
Over 121 Days
61 - 120 Days
46 to 60 Days
45 Days or Less
51 47 47 44 43
40
-
10
20
30
40
50
60
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Average Number of Days to Pay Invoices From Invoice Date (Capital and Grant Expenditures)
Target 45 Days
Sample Results for Payments Vouched Between 6.1.2012 – 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable Records 6.1.2012 – 6.30.2012 (Information collected between 6.26.2012 -7.12.2012)
Sample 100 Selections 90% Confidence level +--10 Vendor Payment Population 793 6.1.2012 -6.30.2012
General Fund & Agencies
Department No Yes Grand Total
(**) %
Dep.
LateCITY PLANNING COMMISSION 5 5 0%
CLERK OF CRIMINAL DIST COURT 1 1 0%
COUNCIL 29 29 0%
CRIMINAL DISTRICT COURT 2 2 0%
CRIMINAL SHERIFF 2 2 0%
DISTRICT ATTORNEY 2 2 0%
HISTORIC DIST LANDMARKS COMM. 3 3 0%
RIVERGATE DEVELOPMENT CORP 3 3 0%
SAFETY & PERMITS 4 4 0%
PARKWAY & PARK COMMISSION 53 2 55 4%
PUBLIC WORKS 36 2 38 5%
CORONER'S OFFICE 17 1 18 6%
FINANCE 15 1 16 6%
GENERAL SERVICES 15 1 16 6%
HEALTH 29 2 31 6%
LAW 27 2 29 7%
FIRE 10 1 11 9%
NORD 68 7 75 9%
LIBRARY 44 6 50 12%
PROPERTY MANAGEMENT 30 5 35 14%
N O MOSQUITO CONTROL BRD. 41 7 48 15%
CHIEF ADMINISTRATIVE OFFICE 57 13 70 19%
NEW ORLEANS AVIATION BOARD 83 19 102 19%
HUMAN SERVICES 13 3 16 19%
MAYORS OFFICE 34 8 42 19%
ECONOMIC DEVELOPMENT 4 1 5 20%
REGISTRAR OF VOTERS 4 1 5 20%
OFFICE OF HOUSING & URBAN DEV. 3 1 4 25%
POLICE 27 11 38 29%
SANITATION 11 5 16 31%
CIVIL SERVICE 10 5 15 33%
NEIGHBORHOOD HOUSING APPR. 4 3 7 43%
Total 686 107 793 13%
Over 60 Days
(**)Represents the percentage of payments over 60 days, from invoice date, for the specific department.
Capital & Grants
Department No Yes Grand Total(**) %
Dep. Late
CRIMINAL JUSTICE 2 2 0%
FIRE 1 1 0%
HOMELAND SECURITY 8 8 0%
MAYOR 4 4 0%
MOSQUITO 1 1 0%
NORD 3 3 0%
PROPERTY MANAGEMENT 1 1 0%
OCD 21 3 24 13%
CAPITAL 15 3 18 17%
HEALTH 16 4 20 20%
DPW 6 12 18 67%
Total 72 22 100 22%
Over 60 Days
Progress Report 5.15.2012 – 6.30.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Source :Accounts Payable Records 5.15.2012 – 6.30.2012
80% 81% 83% 83% 83% 87% 79% 81% 76% 85% 88% 82% 86% 87%
20% 19% 17% 17% 17% 13% 21% 19% 24% 15% 12% 18% 14% 13%
0%
20%
40%
60%
80%
100%
5.15.2011 6.15.2011 7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Percentage of Payments in Days From Invoice Date to Payment for General Fund 5.15.2011 - 6.30.2012(in %)
95% confidence level +-5
Payments Over 60 DaysPayments Under 60 Days
66% 74% 86%
71% 83% 79% 78% 77% 78% 81% 85% 76% 81% 78%
34% 26% 14%
29% 17% 21% 22% 23% 22% 19% 15% 24% 19% 22%
0%
20%
40%
60%
80%
100%
5.15.2011 6.15.2011 7.15.2011 8.15.2011 9.15.2011 10.15.2011 11.15.2011 12.15.2011 1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Percentage of Payments in Days From Invoice Date to Payment for Capital and Grant Expenditures
5.15.2011 - 6.30.2012(in %) 90% confidence level +-10
Payments Over 60 Days
Payments Under 60 Days
CDBG Invoices: Only a Few Outliers Remain Over the 60 Days Goal
Information obtained from Quickbase ( OCD ) 6.30.2012 – 7.13.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Over 60
days
Over 30
days
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Send to Owning Department 4 3 1 8
Owning Department to Send to Accounting 2 2 4
Accounting to Approve 4 1 5
State DRU to Send to State Finance 4 7 1 12
State Finance to Pay City 4 40 2 3 49
Payment to Hit City's Bank 1 19 20
City to Cut Check 7 3 10
Total 19 79 4 0 6 108
Reasons for Delay
Dispute with the vendor
Misplaced / not processed timely
With the State (average 15 days) 26 2
Contract being processed 1 3
Other 21 1
Paid as of 7.13.2012 31 1 3
Age
45 20
47 74 68
19
29 62 43
58 23
79
41 53 47
5
1 4
22 14 5 4
1
9 9 9 4
5 6
146 158 151 145
98 108
0
50
100
150
200
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 120
91-120
61-90
31-60
<=30
OCD Aging of Invoices in the Pipeline by Period
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Information obtained from Quickbase (DPW Department) 6.30.2012 – 7.13.2012
Over 60 days
Over 30 days
DPW City Invoices: A Number of Invoices in the 120 days Category are Waiting For Contracts to be Processed
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Approve 1 6 1 1 6 15
Department to Create Receiver 8 3 3 2 3 19
Finance to Cut Check 2 2
Grand Total 11 9 4 3 9 36
Reasons for Delay
Dispute with the vendor 1
Goods received at a later date / Services
were not rendered
Invoice was missplaced / not processed
Contract being processed 4 1 1 8
Other* 3 3 2 1
Paid by 7.13.2012 1
Age
Other - 1 is pending a final plan change and overrun/underrun statement. The other 8 all had funding issues related to SWB - funding has been
identified for 6 of those invoices (all are pending PJ approvals or a RX approval/conversion).
20 11 18 19 12 11
12
9 3 3 7 9
7
4 5
2 3 4
1
2 1 3 3
24
25 26 9
10 9
64
51 53
36 32 36
010203040506070
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 120
91-120
61-90
31-60
30
DPW City: Aging of Invoices in the Pipeline by Period
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Over 60 days
DPW Revolver Invoices : No Outstanding Invoices
Over 30 days
Information obtained from Quickbase (DPW Department) 6.30.2012 – 7.13.2012
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
Grand Total 0 0 0 0 0 0
Reasons for Delay
Dispute with the vendor
Goods received at a later date / Services
were not rendered
Invoice was missplaced / not processed
Amendment/Contract being processed
Other
Paid by 7.13.2012
Age
5 10 1 4
4 4 6 4
3 7
3 2
3
0
34 33 23
9
46 41 38
19 11
0
0
10
20
30
40
50
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 120
91-120
61-90
31-60
30
DPW Revolver: Aging of Invoices in the Pipeline by Period
Capital Projects City Invoices: Only a Few Outliers Over 60 Days
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Information obtained from Quickbase (DPW Department) 6.30.2012 – 7.13.2012
Over 60
days
Over 30
days
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
PM to Approve 1 1
Department to Create Receiver 1 1
Finance to Receive from Department 1 2 3
Finance to Cut Check 4 2 6
Finance to Release Check 1 1 2 4
Total 7 2 3 1 2 15
Reasons for Delay
Dispute with the vendor
Goods received at a later date / Services
were not rendered
Invoice was missplaced / not processed
timely 1
Contract being processed
Other 2 1 2
Paid by 7.13.2012 2
Age
24 21 13
7 16
7
7 9
7
3
4
2
1 4
3
3
1
3
1
2
1
1
1
4
1 1
2
36 35
25
15
23
15
0
10
20
30
40
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over 120
91-120
61-90
31-60
30
Capital City: Aging of Invoices in the Pipeline by Period
Capital Projects Revolver Invoices: Only a Few Outliers Over 60 Days
Information obtained from Quickbase (Capital Projects Department ) 6.30.2012 – 7.13.2012
Requisition Procurement / DBE Contract Creation and Routing Contract Processing and Approval Payment
Processing Stage <=30 31-60 61-90 91-120 Over 120 Total
Department to Create Receiver 1 1
Finance to Receive from Department 2 2
Finance to Send to State 3 3
State to Send to Hancock 8 5 2 2 17
Grand Total 13 5 2 1 2 23
Reasons for Delay
Dispute with the vendor 1Goods received at a later date / Services
were not renderedInvoice was missplaced / not processed
timely
Contract being processed
Other
Paid 7.13.2012 5 2 2
Age
Over 60
days
Over 30
days
16 15 17 8
16 13
8 2
5
1
4 5
2
2 2
2
4
1 1 1
3
2 1
2
1 2
33
21 24
11
24 23
0
10
20
30
40
1.31.2012 2.29.2012 3.31.2012 4.30.2012 5.31.2012 6.30.2012
Over12091-120
61-90
31-60
Capital Revolver: Aging of Invoices in the Pipeline by Period
Procurement Requisition
Contract Creation
and Routing
Contract
Processing
and Approval
Payment
Supplemental
Procurement
Evaluation Form Are you a city employee or a member of the public? On a scale 1-5, how useful was this meeting to you (1= least useful and 5= most useful)? What’s working? What’s not working?