NO. 6 4 - 19 -11 CITY COUNCIL AGENDA MEETING DATE: APRIL 19, 2011 TO: CITY COUNCIL / CITY MANAGER FROM: ENGINEERING DEPARTMENT 1200 SUBJECT: FULLERTON GOLF COURSE IRRIGATION REPLACEMENT CONTRACT AWARD Approved for Agenda: Office SUMMARY Award a construction contract for the Fullerton Golf Course Irrigation Replacement project to O & J Landscape Construction, Inc. of Moreno Valley, California. RECOMMENDATION 1. Approve the plans and specifications for the Fullerton Golf Course Irrigation Replacement project. 2. Award a construction contract to O & J Landscape Construction, Inc. for the Fullerton Golf Course Irrigation Replacement project in the amount of 1, 731, 715. 99. PROPOSED COSTS Funding for this project is from the Recovery Zone Economic Development Bond RZED Bond) approved at the November 2nd, 2010 City Council meeting. A Budget Data Sheet/ Summary of Bids is attached for Council' s reference (Attachment 1). DISCUSSION On December 21, 2010 City Council approved the Golf Course Irrigation Replacement Project No. 54002 for the Fullerton Golf Course located at 2700 N. Harbor Blvd. The

Transcript of CITY COUNCIL AGENDA - Breadam.org – Fullerton,...

NO. 6

4 -19 -11

CITY COUNCIL AGENDA

MEETING DATE: APRIL 19, 2011

TO: CITY COUNCIL /CITY MANAGER

FROM: ENGINEERING DEPARTMENT

1200

SUBJECT: FULLERTON GOLF COURSE IRRIGATION REPLACEMENTCONTRACT AWARD

Approved for Agenda:

Office

SUMMARY

Award a construction contract for the Fullerton Golf Course Irrigation Replacementproject to O & J Landscape Construction, Inc. of Moreno Valley, California.

RECOMMENDATION

1. Approve the plans and specifications for the Fullerton Golf Course IrrigationReplacement project.

2. Award a construction contract to O & J Landscape Construction, Inc. for theFullerton Golf Course Irrigation Replacement project in the amount of

1, 731, 715. 99.

PROPOSED COSTS

Funding for this project is from the Recovery Zone Economic Development BondRZED Bond) approved at the November 2nd, 2010 City Council meeting. A Budget

Data Sheet/ Summary of Bids is attached for Council' s reference (Attachment 1).

DISCUSSION

On December 21, 2010 City Council approved the Golf Course Irrigation ReplacementProject No. 54002 for the Fullerton Golf Course located at 2700 N. Harbor Blvd. The

Fullerton Golf Course Irrigation Replacement

Page 2 of 2

work includes construction of a water efficient irrigation system and geographical

positioning system ( GPS) control to replace the existing system installed in 1963.

Five bids were received on March 31, 2011, for the Fullerton Golf Course Irrigation

Replacement project. American Landscape, Inc. of Canoga Park submitted the low bid

in the amount of $ 1, 499,367. However, American Landscape subsequently submitted arequest to withdraw their bid due to a mathematical error in the calculation of the bid

that staff finds acceptable ( Attachment 2). O & J Landscape Construction, Inc.

submitted the next lowest bid in the amount of $ 1, 731, 715. 99. This bid as submitted is

approximately 10% under the engineer's estimate of $ 1, 930, 000. The bid documents

have been reviewed by staff and are considered acceptable.

Staff received an e- mail protesting the award of the contract to O & J Landscape

Construction. The e -mail claimed that O & J Landscape Construction was not qualified

based on the minimum experience requirements of the contract. Staff verified O & J

Landscape past work experience and confirmed that they are qualified to perform thework. In addition, the City attorney was consulted and concurred with staff'sdetermination.

A requirement of the RZED Bond is for the project to be completed December 31, 2011.

Construction is scheduled to begin in late May, 2011 and be completed by November30. 2011.

An environmental assessment has been prepared in accordance with the California

Environmental Quality Act ( CEQA) Guidelines, and it has been determined that theproject is categorically exempt.

Wonald K. HoppeDirector of Engineering

DKH /KK/ bas

Attachment

Attachment 1 — Budget Data Sheet

Attachment 2 — Contractor' s withdraw letter

David
Highlight

FULLERTON GOLF COURSE IRRIGATION REPLACEMENT

Budget Data Sheet

Source of Funds

Fullerton Golf Course Irrigation Replacement

Project No. 54002:

RZED Bond $ 2, 300, 000

TOTAL

Estimated Expenditures

Contract amount $ 1, 731, 716

Design ( Consultant & Staff time) 85,000

Inspection, testing andcontract administration, estimated 230,000

Contingencies 253, 284

TOTAL

Summary of Bids

Bid Opening: March 31, 2011

Engineer's Estimate: $ 1, 930,000

Contractor Location

1. American Landscape, Inc. Canoga Park, CA

2. O & J Landscape Construction, Inc. Moreno Valley, CA3. Formost Construction Temecula, CA

4. Wadsworth Golf Buckeye, AZ

5. Christensen Irrigation Co., Inc. Costa Mesa, CA

Bid withdrawn — Mathematical Error

2, 300, 000

2, 300, 000

Amount

1, 499,367

1, 731, 716

1, 841, 038

1, 859,310

1, 929,000

Attachment

David
Highlight
David
Highlight
David
Highlight
David
Callout
Why so much?
David
Highlight
David
Highlight
David
Callout
Was this money actually needed?

s y • ° •

t

wr. eon t tt

AMERICAN LANDSCAPE, INC. A Green Industry Contractor

April 1, 2011

City of Fullerton

Engineering Department303 West Commonwealth Ave.

Fullerton, Ca 92832 -1775

Attention: Mr. Kevin Kwack, Project Engineer

Re: Fullerton Golf Course Irrigation Replacement

Dear Kevin,

With great disappointment, I must inform you that we have found a mathematical error in

our bid to you for Fullerton Golf Course. We just completed the conversion of our electronic

estimating program from Lotus to an Excel base, the proper wage rates did not carry over to thisgolf estimate (our first estimate we created using this program).

Due to that error, we must respectively request to withdrawal our bid for this project.

Sincerely,

Mallory ChaidesAssistant to Gary Peterson, President

7013 Owensmw1h Ave • Canoga Park, CA 91303 • 818. 999.2041 Tel • 818.999.2056 Fax

License CA #288229 • www.americantandvcape. com