Circular. C26 SUMMARY OF DRILLING LOG AND PUMPING …
Transcript of Circular. C26 SUMMARY OF DRILLING LOG AND PUMPING …
SUMMARY OF DRILLING LOG AND PUMPING TEST
State' of HawaiiDEPA~TMENT OF lAND AND NAT"J RAL RESOURCES
DIVISION OF WATER AND LAND DEVEI,oPMENT
J
For
Circular. C26
PULAMA WELL 9- 10Pulama, Puna, Eawai i
JOB NO. l7-K··9Exploratory Drilling
May 1964
J
II
I :
H'!
•j i
HI ~
_._- ----- -
ILLUSTRATIONS
CONTENTS
! .
Page
iii,
SYNOPSIS ' I
SUMMARY OF DRILLING 1: !
LOG i
;' !SUMMARY OF PUMPING TEST 3 i. f::,
; f
THE DRILLING LOG 4 Iii'
PUMPING TEST RECORD 8 l:!
~CHEMICAL ANALYSIS OF THE WATER 12: .f
LOCATION MAP
SECTION OF THE WELL
GRAPH OF THE PUMPING TEST RECORD
. ':.
~------
SYNOPSIS
wcation and Description
Pulama Well 9-10, drilled under the State's exploratory welldrilling program, is situated four miles west of KalapanaBlack Sand Beach in the Puna District of the "Big Island".The well lies 1.8 miles inland from the coast at an elevationof 230 feet and its total depth of 250 feet extends 20 feetbelow sea level. Eight-inch casing is set to the total depthwith the bottom 21.7 feet perforated.
Geology and Hydrology
Pulama Well, the first to be drilled in the southern portionof the Puna District, encountered highly permeable basaltflows of the Puna vo19anic series which erupted from thePuna rift zone about 4 miles mauka.
Based on the driller's log, the formations penetrated arepredominantly "hard" to "medium hard gray rock" intercalatedwith "soft" to "very hard" zones. The aquifer rocks consistof "cinders" and "clinkers" reported between the 233-foot and250-foot depths.
Several faults roughly parallel to the east-west trendingPuna rift zone have been mapped in the Pulama a~ea. Theabrupt change in slope immediately mauka of the well canbe followed for several miles and is believed to be a faultscarp buried by sUbsequent lava flows. Other parallel faultshave been mapped near the coast. It is not known what effect.if any, the structural geology of the area has on the aquifersystem. However, no hydrologic boundary conditions areindicated by the pumping test data.
Annual rainfall averages about 75 inches at the well site andincreases with elevation to over 100 inches along the riftzone;- four mile distant. Although a rainfall belt of thismagnitude could be expected to provide sufficient recharge tomaintain a fresh water lens, Pulama Well has a chloridecontent of about 300 ppm and is sensitive to changes inchlorides under pumping conditions. An extremely permeableaquifer and structural geology may be influencing factorsof the anomalous situation.
Temperature of the well water is slightly above normal at78.5 degrees Fahrenheit.
~ping Test Results
Pulama Well 9-10 was pump tested for 73~ hours with a turbinepump driven by a 165 HP diesel engine from 11:25 a.m. onDecember 3 to 1:00 p.m. on December 6, 1963. The well was
iii
i -r
; .-
Results of the pumping test indicate these salient points:
pumped at rates of 50 and 100 gpm during the first 24 hoursand at 50 gpm for the next 42 hours. Five additional hoursof pumping were at step-up rates~of 100, 200, 300, and 450gpm with a maximum drawdown of 0.14 feet.
Chlorides of the pumped water increased from an initial278 ppm to 307 ppm while pumping at a rate of 100 gpm. Onreducing the pumping rate to 50 gpm, the chlorides stabilized'in a range of 293 to 298 ppm. Pumping the well at a maximumrate of 450 gpm with only 0.1 foot drawdown,the chloridesrose to 346 ppm, an increase of 150 ppm in 5 hours.
the aquifer is extremely permeable,the well is capable of yielding 50 gpm of water withchlorides stabilized at about 300 ppm,the water level in the well under pumping conditionsfluctuate with a periodicity closely resembling theocean tides, andwhile pump ing at a rate of 50 gpm, the chlorides of thepumped water fluctuates about 5 ppm.
(4)
( 1)(2)
(3)
_ ; 0'.- ; .1
iv
-- - - - _._- _ ...._-----_.---~_.~-~...._- -
-1-
~ - . ~'.::.'.:' .'
predominantly "hard" to"medium hard gray lava rock"with occasional "very hard"or "soft" zones.
"Cinders and clinkers" withsome "medium hard rock".
o ft. to 233 ft.
233 ft. to 250 ft.
Ground Elevation
230 feet above mean sea levelElevation of (+) mark N. Cor. Cone. Block = 230.04 1
Depth and Size of Drilled Hole
Total Depth: 250 feet (-20 feet, msl)Size: 12" hole to total depth.
Static Water Level
3.29 feet above mean sea level on Nov.26, 1963: 3:05 pm
Location of Well
Pulama Well 9-10 is located on a Hawaii County-ownedparcel of land in the Puna area. The well site lies1.8 miles inland from the coast and 4.0 miles due westof Kalapana beach.
Tax Map Key: 1-1-01
SUMMARY OF DRILLING LOG
Rock Formation
Depth:
Casing Installed
Size: 8 5/8" O.D. x 0.25" wall thicknessLength: 251.40 feet, total. Bottom 21.7 feet perforated
with 40 rectangular slots (1 1/2" x 1/4") perlineal foot.
Bottom elevation: -20 feet, msl
Contractor:
Samson and ZerbeDivision of Pell Co., Inc.P. O. Box 1441Honolulu, Hawaii
Drilling EqUipment
Bucyrus Erie 60-L cable-tool drilling rig
.' ~ .
- -------- - ___.. '_... 'm~
42 days
9 days23 days
18 days
4 days96 l-lorking
days
Drilling .•..•...•.•••.••••••.••.••••••••.•.••Regular work shifts 23Second work shifts ~
Total No. of shifts 29
-2-
Reaming •••••••••••••••••••••••••••••••••••••Regul ar work shifts 42Second work shifts 12
Total No. of shifts 57Other (Installing casing, rock ••••••••••••••••••
r~~king, grouting, etc.)~ping test ••••••••••••••••••••••••••••••••• __~~~~__
TOTAL TIME
Nobi l i za tion and demobilization •••••••••••••••••
Sam LeslieHarold PerrellsHerman MeyersHenry Heanu
~111ers
&pstruction Time
Mobilization began: August 14, 1963
Dnlling completed: November 22, 1963
~1ng test completed: December 6, 1963
Demobilization completed: December 18, 1963
. f"
i. .',:i ..
..•.. - . .I_-~
.... ,
~ :".:: _,.2
.,,
SUMMARY OF PUMPING TEST
Test Pump
Deep-well vertical turbine3:4 ratio (increasing) Johnson Gear Co. right-angle drive23-stage, Fairbanks-Morse Bowl Assembly (7 Me)6 11 pump co1wnn165 H.P. G.M. diesel engine, at 1800 rpm
Total Depth of Well
250 feet (-20 feet, IDS 1)
Test Results
Static Water Level: 3.41 feet, ms1, on 12/3/63Yield: 50 gpm with no drawdown.Chloride Content: 293 to 298 ppm, at 50 gpmWater Temperature: 78.50F
Total Pumpage: 329,000 gallons
Date of Test
December 3-6, 1963
Present at Test
Sam Wong and Bob Siaro~ - Division of water and LandDevelopment
Steve Bowles - U. S. Geological Survey
Chloride Analyses By
Sam Wong - Division of Water and Land Development
-3-
'. ~t
~ ,~ :::f:' : .i
DRILLING LOG
,, ~
;
1 1
I
~ '1.. ; . ~. ,, .
i I
No drillingReaming holeReaming holeReaming holeReaming hole
Remarks
MobilizationMobilizationMobilization
Hauling water
Hole going off
No drilling
Tools stuckReaming holeNo drillingReaming holeReaming holeReaming holeReaming holeLost mud
Reaming hole
Reaming holeReaming holeReaming holeReaming holeReaming holeReaming hole w/12"
bitReaming hole
Reaming holeReaming holeReamed hole to 47'
-4-
Driller'sDescription
Cinder pocketVery hard rock
Backfill hole to 36'w/rocks
Backfill hole to 38'\v/rocks
444545
4647
4446
4142
41
4332
0 6 Lava rock6 18 lava rock
18 26 Hard gray rock26 32 Hard lava rock32 35 Very hard gray rock35 39 Very hard gray rock
39 45 Very hard gray rock
DepthBelowGroundSurface
In FeatFrom to
43434345454647474747
4229
414447
o
ooo
30*
Oct. 11*2
Foot-Date age
PerShift
~
Aug.14-l517
I. 2729 630 12
Sep. 34 85 66 37 49
10 61112 01314 016 017 018 019 120 12324 024* 025 025* 0
26 0
26* 027 027* 028 028* 030 0
DRILLING LOG(Cont.t d )
DepthFoot- Below
:ate age Ground Driller'sPer Surface Description RemarksShift In Feet
Fr om To
l22l:tt . 2* 3 47 48 Very hard rock 711 pilot hole
48 50 Soft rock:3 8 50 52 Med. har d rock 711 pilot hole
52 58 Ha.rd gra.y rock:3* 6 58 64 Hard gray rock4 1 64 65 Reaming 4£:;' - 48'4* 0 46 55 Reaming to lot" hole5 0 47 56 Reaming t o 1211
5* 0 56 60 Reaming hole7 0 60 62 Reaming hole
.1 7* 0 62 Reaming hole ... ... ....8 0 62 63 Reaming hole
, - ,,~\....~:~~ :
8* 0 63 , Reaming hole >::'..<~ :~
9 0 63 64 Reaming hole ·~1ti~; :i~':, , ~,~%':!f9* 0 64 65 Reaming hole ~ . ~j~,~.::.::.'~]10 0 65 Reaming hole10* 0 Equipt. repair
"' , 11 0 Reaming hole..~"
11* 2 65 67 Very hard gray rock Reaming and drilling12 6 67 73 Hard gray rock 7" pilot hole14 7 73 80 Hard gray rock
.' 14* 0 65 Rea.ming hole", 15 0 65 66 Reaming hole' .-. 15* 0 66 Reaming hole
16 3 80 83 Hard gray r ock Reaming and drilling ..16* 4 83 87 Har d gray rock 711 pilot hole17 13 87 100 Mod. } ' c~ rd rock with '
!_~'"' f eY soft spots17* 7 100 102 Med. hard rock
~ .:" 102 . 107 Har d rock18 4 107 I II Med. hard gray rock Prepare reamer18* 9 I II 117 Med. hard rock
117 118 Soft rock118 120 Hard rock
, " 19 0 63 67 Reaming hole21 0 67 68 Reaming hole
. ," 22 0 68 70 Reaming hole,;.23 0 70 72 Reaming hole
.. .... 24 0 72 73 Reaming hole26 0 73 74 Reaming hole28 0 74 75 Reaming hole
r ..~. , .
DRILLING LOG(Cont t d)
~te
FootagePerShift
DepthBelowGroundSurf ace
In FeetFrom To
Driller' sDescription Remarks
Cinders falling in
Bit wedging inCinders falling 1n
Reaming holeReaming holeReaming hole, tools
stickingReaming hole
Reaming hole with12" bit
Reaming holeReaming holeReaming hole7" pilot hole
Encountered waterWater level = 227.15'Cinders falling in
Cinders a problemReamed 7" hole,
163' to 185'Reamed hole to 12nReamed holeReamed holeReamed holeReamed hole to 247'Begin installing
8" casing
-6-
Med. hard gray rockCavityHard rockMed. hard ro ck
Mad . hard rockHard rockMad. hard rockHard cracked rockMed. hard rockHard rockMoo. hard rockHed. hard rockHard rock with soft ,
thin layerMed. hard rock .Har d rockHard rockHed. hard rockCinders and clinkersCindersMed. hard rockCindersCinders
CindersMed. hard rock
75 7675 7777 80
80 105120 130130 132132 136136 140110 130
130 148148 160160 163170 174174 176176 181181 185185 192192 195195 206206 210210 217
217 222222 225225 228228 233233 235235 237237 243243 · 246246 247
185 210210 231231 2L.O240 245247 248248 250
~
:et.29 a30 031 0
Iov. 1 01* 20
5' 0...:t.
6 07 08 09 15
-- 11 21
12 19
...
13 10
14 8
15 316 1
18 019 0
. ( 20 0e . 21 0
22 3
DRILLIEG LCG(Corrt t d)
:...~' .
DateFootagePerShift
DepthBelowGroundSurface
In FeetFrom To
Driller'sDescription Remarks
* Second Shift
Installed 13 Lgt.hs, of 8" casing = 251. 40'Equipment maintenanceRan bailing testRan plumbness and alignment testInstalling test pumpInstalling test 'pumpInstalling test pumpCompleted installing test pumpBegan pumping testPmnping testPumping testPumping testPtnnping testPumping test
Ended pumping testDemobilizationDemobilizationDemobilization and placed 5' cement plugDemobilization and rock-packed annular space with
7t yd. crushed rock to 53' depthRan plumbness and alignment test. Cleaned holeDemobilizationConstructing concrete blockGrout annular space and pour concrete blockC~mpleted demobilization
1213141617-18
1963Nov. 23
2526272930
Dec. 1233*44tl
55*66*79
10II
>.-
"'I', ...
- .
} : ..J -,
, .
~'.
-7-
ttJ
i-:?
Test Pump:Deep-well turbine3:4 ratio gear drive23-stage bowl assembly165 H.P. diesel engine
Pressure Gage: Ashcroft0-30 psi
Hater Meter: 4" HerseySparling flowmeter
PUt·j!"'Il.G 1::.;8T RECORD
PULAEA HELL 9-10Pu'lama , Puna, Hawaii
Airline Readings
-12.41 ft., H.S.L.
0 6.85 15.82 (Static)Start Pump
50 6.85 15.82 0.0 278 7949 6.83 15.78 .04 278 7949 6.80 15.71 .11 278 7948 6.78 15.66 .16 283 7948 6.76 15.62 .20 283 7948 6.74 15.57 .25 283 7949 6.70 15.48 .34 288 7948 6.70 15.48 .34 288 7949 6.66 15.38 .44 288 7948 6.70 15.48 .34 283 7949 6.66 15.38 .44 288 7949 6.65 15.36 .46 288 7946 6.65 15.36 .46 288 79
Open discharge valve wider to pump 100 gpm98 6. 70 15.48 .34 288 7994 6.65 15.36 .46 293 7894 6.65 15.36 .46 293 78
102 6.95 15.36 .46 298 78102 6.60 15.25 .57 298 79101 6.52 15.06 .76 298 7896 6.48 14.97 .85 298 78
1963
tic Hater Level: 3 •41 ft., Ivl. S. L.on 12/3/63 (airline)
250 ft. (-20 ft., N.S.L. )
243 ft.
HaterTemperature
~_~_""""=,""--__",,,-=::"='__....lo.::.=::.L-__--..lo.:~~ --.l.=~ ~oF)
5: L;() pm6:J.iJ pm7.LIJ pm8:LIJ pm9:.40 pm
. 1.0:.40 pm
. . 11:40 pm
:F..d "r~· .15 aml:w,..~-..25 am
:35 am11:50 am12:20 pm12:50 pm1:20 pm
. 1:50 pm2:20 pm2:50 pm3:20 pm3:50 pm4:20 pm4:50 pm5:20 pm
,.
I ·
PUl1PIEG TEST RECORD(Cont.t d)
Hater:ate Pumping Ai r l i ne Readings Draw- Temper-md Rate down Chlorides aturelime (gpm) (psi) (feet) (feet) (ppm) (OF)
;tee. 4. 1963
3:40 am 101 6.54 15. 11 .71 303 794:40 am 98 6.60 15.25 .57 298 795:40 am 100 6.70 15.48 .34 303 796:40 am 100 6.80 15.71 .11 303 79
~'.' 7:40 am 97 6.90 15.94 303 79". 8:40 am 100 6.95 16.05 303 79i·~ ' . , ..' -
9:40 am 99 6.97 16.10 307 7910:40 am 100 6.97 16.10 307 79
r 12:00 noon 93 6.90 15.94 307 79...
12:05 pm Adjust discharge valve to pump 50 gpm12:15 .pm 51 6.88 15.89 307 79 t:-1:. "'~ :
1:00 pm 50 6.85 15.82 0 307 79:.:.~ 2:00 pm 50 6.80 15.71 .11 298 79~\ .~:! . .-- . .. 3:00 pm 50 6.72 15.52 .30 293 79~~ I..·· · , ; . 4:00 pm 50 6.67 15.41 .42- 298 79~.::. 5:00 pm 50 6.68 15.43 .39 293 70.:~ 6:00 pm 50 6.68 15.43 .39 298 79... '
7:00 pm 50 6.69 15. 45 .37 293 79."
;~~ 8:00 pm 50 6.69 15.45 .37 293 79::-t ., .. , ; [ - 9:00 pm 50 6.66 15.38 .44 293 79' .. "
;~ . , ~ :~ :r Jo:OO pm 50 6.64 15.34 .48 288 79:": ) - '. ("" 11:00 pm 50 6.60 15.25 .57 293 79~~ : ' ... .. , 11,
">(,., : :- ":. 12100 mid- 48 6.56 15.15 .67 293 79
...., night:...~"}
:.-.
·:1" . 1:00 am 49 6.50 15.02 .80 293 79' .' ,
2:00 am 48 6.4<) 14.99 .83 288 793:00 am 47 6.50 15.02 .80 288 79
n, ' 4:00 am 49 6'. 54 15.11 .71 293 79.a : 5:00 am 50 6.61 15.27 .55 293 79~l:- 6:00 am 48 6.70 15.48 .34 293 79:0:.••• 7:00 am 48 6.79 15.68 .14 298 79
8:00 am 49 6.85 15.82 .00 298 79<: ~ -. 9:00 am 49 6.95 16.05 298 79. ]0:00 am 48 6.97 16.10 298 79
11:00 am 48 6.98 16.12 298 79 "... 32:00 noon 49 6.97 16.10 298 79 } ~ ;
:'~ ,. 1:30 pm 49 6.88 15.89 298 79';;,i;:
.." 3:00 pm 59 6.80 15.71 .11 298 79..~.,, ' .
PUi'iPING T-C;ST RECORD(Cont'd)
PumpingRate(gpm)
Airline Readings
(psi) (feet)
Drawdown(feet)
Chlorides(ppm)
WaterTemperature(OF)
7979797979
797979797979
78.578.578.578.5
78.578.578.5
78.578.578.578.578.5
293293293298298
346346346342346
.00
.02
.00
.07
6.70 15.48 .34 293 796.66 15.38 .44 298 796.68 15.43 .39 293 796,69 15.45 .37 293 796.69 15.45 .37 298 796.66 15.38 .44 298 79
Dec. 6. 1963
&c. 5, 1963
4:30 pm 496:00 pm 497:30 pm 509:00 pm L,8
10:30 pm 5012:00 mid- 49
night
-10-
1:30 am3:00 am4:30 am6:00 am6:55 am7:00 am7:05 am7:30 am8:00 am8:30 am9:00 am9:30 am9:55 am
10:00 am10:05 am10:20 am10:35 am10:55 am
11:10 am11:30 am11:55 am
47 6.59 15.22 0.6049 6.55 15.13 .6949 6.60 15.25 .5748 6.69 15.45 .3749 6.74 15.57 .25Open discharge valve wider to pump 100 gpm
100 6.74 15.57 .25100 6.78 15.66 .16 298100 6.82 15.75 .07 298100 6.e8 15.89 298100 6.90 15.94 293100 6.94 16.03 303
98 6.95 16.05 307Increase engine speed and adjust discharge valve
200 6.95 16.05216 6.95 16.05 307200 6.96 16.08 312200 6.95 16.05 322
Increase engine speed and adjust discharge valve303 6.95 16.05 322316 . 6.95 16.05 332310 6.95 16.05 342
Increase engine speed12:10 pm 384 6.96 16.0812:20 pm 450 6.85 15.8212:30 pm 450 6.84 15.8012:45 pm 448 6.85 15.82
o 1:00 pm 443 6.82 15.751:02 pm Stop pump1:02:30 pm 0 6.951:03 pm 0 6.95
.r. • • ~J,
. ". ;
.' .... '.' -.
,:' . '
~.;~ . :
II
[. .
.. .. '.
- ,
; t: 0 t o
..~.. '
PID1PING TEST RECORD(Cont1d)
DateandTime
PumpingRate(gpm)
Airline Readings
(psi) (feet)
Drawdown(feet)
Chlorides(ppm)
vlaterTemperature(OF)
16.0315.99
,15.9915.9915.9915.9915.9915.99
End of Pumping Test
6.956.956.956.956.946.926.926.926.926.926.926.92
oooooooooooo
-11-
~c. 6, 1963
1:03 :30 pm1:04 pm1:04:30 pm1:05 pm1:06 pm1:07 pm1:08 pm1:09 pm1:10 pm1:12 pm1:15 pm1:20 pm
Preser.t at Test:Sam Wong and Bob Siarot - Division of Water and Land DevelopmentSteve Bowles - U. S. Geological Survey
Chloride Analyses By:Sam Wong - Division of Water and Land Development
': :, !.'
... . ' .
I./..
,. .
, .
.'. ."l
:-; " , : : .' .
.":'!'
CHE}1ICA1 ANALYSIS OF THE WATER
,Pularna Wel l 9-10
Pul.ama , Puna, Hawaii
Wat er Sample Taken ·t : 12:40 pvm, , December 6, 1963
Analysis made by: Hawaii State Department of HealthDecember 16, 1963
pH @ 25°C 7.45Color 5Odor 0Turbidity 2H0
2less than 0.001 ppm
N03 0.32 ppm~. Carbonate Alkalinity 0.0 ppm as CaC03
Bicarbonate Alkalinity 44 ppm as CaCD)Total Alkal i nit y 44 ppra as CnCD)Total Hardness 14~ ppm as C1 ~03
Total solids 838 ppm10ss on ignition 148 ppmSi02 72.4 ppmFe 0.1 ppmAl less than 0.05 ppmCa 15.9 ppmMg 31.2 ppmS04 65.1 ppmNa 170 ppmK 8.5 ppmChlorides 345 ppmAs less than 0.01 ppmF 0.1 ppmMn less than 0.05 ' ppmPb II II 0.001 ppmCu " II 0.1 ppmZn 0.1 ppmSe less than 0.001 ppmPhenols It " 0.001 ppm
-12-
•.", .
-r~" ", ' ., .~ 1:r f
,i
E
,. /(AN.4 tH~
AootoY l
PUN A
A
, .108 NO. 17 j
~XPLORATORY
PULA
f)r:P,
\\ ,
~LU~ '
7I
~.~~.llo ~, ' ,/
. ' /,
. ........- ----- , -. .
IZ ....
1
,i+
I -t!i .-+-- .- -- _.---+.
, ,, i
!
10 0 1- - - 4
o
-- ---J---- - - -- -DISCHARGE VALVE
1
I-t
-r-"--
-+- _.-.
STOP PUMP r I 00 "'"iADJUST ENGI"I£_.- -.~ ._ .._ .--r-- -..
ADJUsT E~ iI
- ADJUr:'NL ;" VA:!" -
- I . .--i t- .ADJUST ENGl~E Ii vALvE 'I
,-----t-o I '-rOP£N lllSOiARGE VA1.llE
I !
,......--.,-----,-'-:---r----r----r----r----r---~--.....,._--_,__--_r--_"T--___r--__.,,..__--.__--.__-___, 3.0
....o.....
1.0 ~
6.. 12_
I
---1. ...._ 0
i12_,~ o", 12-. 6 ....
December 6. 1963
I·----£--~----:.----...+----+_--_1 2..0 .....
" i I ....II \.~TIDE of -..""" Boy ~~ - _..+--+- --~_ .-+----
. \ , /--- :. -- - .~-~~_..-1
ORAWDOWN
~ "''\UJUJ 0u.
I~ ':1 GI ''')0 .5 1"\0z
;t0c;t<l 1.0a::0
1.512 Noon 6 prn IZMN
December 3. 1963 I" ...,