CIL rate setting
description
Transcript of CIL rate setting
Community Infrastructure Levy
Rate Setting
July 2014
Context
The Funding Pie
The levy cannot be expected to pay for all of the infrastructure required:
• 5-10%
• Consider CIL as just one small part of a more complex blend of funding.
Local Gov-ernment Grants
CILs106
Business Rate Retention
Capital reciepts
Borrowing
Regional Growth Fund
Value
The proportional impact of CIL on development viability
£10/ sq m variance in CIL rate 10% variance in build costs 10% variance in sales values1
6
11
16
21
26
31
36
Preparatory work
Getting started
Developing a Working Hypothesis
What might the schedule of rates
look like in your area?
Charging Authority:_________________________
Development Type/ scale
Area 1_______________
Area 2_______________
Area 3_______________
Area 4_______________
Type 1 £ £ £ £
Type 2£ £ £ £
Type 3£ £ £ £
Type 1, Scale A £ £ £ £
£ £ £ £
£ £ £ £
Simplicity v Complexity
Simplicity
• single rate (?)
• requires minimal evidence
• need to set near the lowest value use / area (an opportunity cost?)
Complexity
• differential rate (probably) optimises income for infrastructure
• “Progressive”: the most profitable developments pay more
• too complex may be off-putting and awkward to operate
• too complex likely to require greater justification through evidence.
Differential vs Single Rate
Use / Area A Use / Area B Use / Area C
CIL Viability levels
Differential Rate 2income (£/time)
Single Rate income (£/time)
Differential Rate 1 income (£/time)
Workshop
Format and considerations
• Hosted by project sponsor
• With or without members depending on level of knowledge
• Viability advisor in attendance
• CIL income projection model linked to charging schedule
• A buffer of around 25% below maximum CIL rates
• How do changes in CIL rates effect income
CIL Income Projections
Maximum CIL Rates
Summary
Summary
• Direct the viability work using your own local knowledge.
• You are required to involve developers prior to the publication of draft rates
• Use a rate setting workshop that brings together viability and projected income to reach an optimal solution
Questions