1 Managing Catastrophe Observations Of A Canadian Peacekeeper In Haiti On 12 January 2010 And Potential Application Towards Project Management Chris Haché, MSM, CD, PMP Lieutenant Commander Canadian Forces Maritime Warfare Centre

description

Project Management and Peacekeeping by Chris Hache'

Transcript of Chris hache -_managing_catastrophe_observations_final

Page 1: Chris hache -_managing_catastrophe_observations_final

1

Managing Catastrophe

Observations Of

A Canadian Peacekeeper In Haiti On 12 January 2010

And Potential Application Towards Project Management

Chris Haché, MSM, CD, PMPLieutenant Commander

Canadian Forces Maritime Warfare Centre

Page 2: Chris hache -_managing_catastrophe_observations_final

2

Learning Objectives

• Creating a risk matrix that is truly reflective of your risk environment

• Adapting to immediate changes in the triple constraints

• Managing increases to project complexity

Page 3: Chris hache -_managing_catastrophe_observations_final

3

Disclaimer

• The views and opinions expressed herein are my own based on my personal observations and perspectives

• My views are not necessarily reflective of or are endorsed by the Royal Canadian Navy, the Canadian Forces, the Government of Canada, the United Nations or my spouse

Page 4: Chris hache -_managing_catastrophe_observations_final

4

Online Resources

• Public Safety Canada

• A guide to business continuity planning

• Nova Scotia Emergency Management Office

• Business Continuity Management

Page 5: Chris hache -_managing_catastrophe_observations_final

5555

Creating A Risk Matrix That Is Truly Reflective

Of Your Risk Environment

Creating A Risk Matrix That Is Truly Reflective

Of Your Risk Environment

Page 6: Chris hache -_managing_catastrophe_observations_final

6

Risk Environment

• Understanding your physical environment

• Team impacts

• Security / emergency services

• Infrastructure

Page 7: Chris hache -_managing_catastrophe_observations_final

7

Understand Your Environment

• Emergency services

• Much applicable across industry

• How it can affect you

• Personally

• Entering an affected area

Page 8: Chris hache -_managing_catastrophe_observations_final

8

Team Impact• Loss of critical members

• Loss of critical mass

• Effect on team efficiency• Family loss, disabilities,

injuries, trauma, etc.

• Environmental effects• Breathing, drinking, eating,

sanitation

• Acclimatization for new members

Page 9: Chris hache -_managing_catastrophe_observations_final

9

Security / Emergency Services

• Requirements

• Police, fire, medical, military

• Damage to prisons & jails

• Impact on security levels

• Civil disobedience

• Civil unrest

• Internal conflict

• External conflict

Page 10: Chris hache -_managing_catastrophe_observations_final

10

Infrastructure

• Requirements

• Power, water, fuel, heat, etc.

• New products, repairs, spares, etc.

• Effects to transportation

• Vehicles, roads, rail, air, seaports, etc.

• Debris

Page 11: Chris hache -_managing_catastrophe_observations_final

11

Risk Matrix• UN knew of risk

• Hotel (HQ) was a known risk entity

• Executives concentrated in one location

• Earthquake caused by undiscovered fault

• How detailed is your matrix?

• Interrelationships of risk matrices

Page 12: Chris hache -_managing_catastrophe_observations_final

11221122

Adapting To Immediate Changes In The Triple

Constraints

Adapting To Immediate Changes In The Triple

Constraints

Page 13: Chris hache -_managing_catastrophe_observations_final

13

Adapting The Triple Constraints

• (Integration / Communications)

• Scope

• Time

• Cost

Page 14: Chris hache -_managing_catastrophe_observations_final

14

Project Charter• Originally UNSC Resolution 1529

(2004)

• Originally 8,322 military and police

• UNSC Resolution 1908 (2010)

• Military – from 6,940 to 8,940 (+2,000)

• UNPOL – from 2,211 to 3,711 (+1,500)

• Ensure safe and secure environment

• Implied task – provide relief

Page 15: Chris hache -_managing_catastrophe_observations_final

15

Stakeholder Analysis• Citizens!

• UN Organizations

• OCHA, UNICEF, WFP, UNHCR, etc.

• International Military

• Over 20

• Integrated / arms length

• International NGOs / Charities

• Dozens / Hundreds

Page 16: Chris hache -_managing_catastrophe_observations_final

16

Requirements• Maintain secure environment

• Integration with foreign security partners

• Integration with NGOs - security and distribution

• Responding to debris concerns

• Responding to sanitation concerns - IDP camps, mass burials

• Responding to stakeholder concerns (e.g., UNESCO)

Page 17: Chris hache -_managing_catastrophe_observations_final

17

Time

• ASAP!

• Three main period identified

• Emergency/Rescue

• Recovery

• Improvement

• Determining activity resources/durations

Page 18: Chris hache -_managing_catastrophe_observations_final

18

Cost

• Initially not a significant concern

• Opportunity

• Land owners

• Trades industries

• Employment Programs

• Cash For Work

• Cash For Food And Work

Page 19: Chris hache -_managing_catastrophe_observations_final

11991199

Managing Increases To Project

Complexity

Managing Increases To Project

Complexity

Page 20: Chris hache -_managing_catastrophe_observations_final

20

Managing Increased Complexity

• Quality

• HR

• Communications

• Risk

• Procurement

• DATA!!!

Page 21: Chris hache -_managing_catastrophe_observations_final

21

Quality

• Measuring effects

• Rioting levels

• Security incidents

• Personnel migration

Page 22: Chris hache -_managing_catastrophe_observations_final

22

Human Resources

• 2000 troops / 1500 police

• Composition / requirements matrix

• Security? Engineering? Specialists? Optimal ratio?

• Rapid indoctrination

• Modifications to other documents

Page 23: Chris hache -_managing_catastrophe_observations_final

23

Communications

• Communications matrix is key

• Appropriate method for each stakeholder

• Radio

• Cell phone (SMS)

• Television

• Web

• Manage expectations

Page 24: Chris hache -_managing_catastrophe_observations_final

24

Risk• Re-evaluate risk matrix

• New items may be present

• Severity / impact may have changed

• Not all risk events are bad

• Extra attention / assistance

• More health projects (water, medical)

• Economic development

• Innovative business opportunities

Page 25: Chris hache -_managing_catastrophe_observations_final

25

Procurement• Land

• Extra footprint of incoming troops

• IDP

• Debris

• Logistical Issues

• Ready-use stores

• Ramp-up of suppliers

• Landing areas

Page 26: Chris hache -_managing_catastrophe_observations_final

26

Data!!!• Significant Impact

• Loss of computer servers on same site

• Infrequent backups

• Even offsite susceptible

• Could be equally affected)

Page 27: Chris hache -_managing_catastrophe_observations_final

22772277

Criteria For SuccessCriteria For Success

Page 28: Chris hache -_managing_catastrophe_observations_final

28

Criteria for Success (1)• Robust risk analysis /

detailed planning

• Identification of reliance & interdependency

• Potential partnerships

• Haiti had the world

• Measures to assess catastrophe impact

• Adequate response

• Exercise the plan

Page 29: Chris hache -_managing_catastrophe_observations_final

29

Criteria for Success (2)• Empowerment

• Provide strategic direction & let teams work

• Lessens personal impact (keeping people busy)

• Capture identified lessons

• Generate lessons learned

Page 30: Chris hache -_managing_catastrophe_observations_final

33003300

SummarySummary

Page 31: Chris hache -_managing_catastrophe_observations_final

31

Learning Objectives• Creating a risk

matrix that is truly reflective of your risk environment

• Adapting to immediate changes in the triple constraints

• Managing increases to project complexity

Page 32: Chris hache -_managing_catastrophe_observations_final

32

Take-Away Tool

Page 33: Chris hache -_managing_catastrophe_observations_final

33

Contact Information

Chris Haché, MSM, CD, PMP

Lieutenant CommanderCanadian Forces

Maritime Warfare Centre

(902) 721-8482 (w)[email protected]@hotmail.co

m

Page 34: Chris hache -_managing_catastrophe_observations_final

33443344

Take-Away ToolBonus MaterialTake-Away ToolBonus Material

Page 35: Chris hache -_managing_catastrophe_observations_final

35

Calculating Risk

• Risk is the estimate of injury or gain/loss, defined as a measure of the probability and severity of an event

• Risk has two components

• Probability – the probability or frequency of the event occurring

• Severity – the impact if the event occurs

Page 36: Chris hache -_managing_catastrophe_observations_final

36

Risk Can Be Good!Pro

babili

ty

Severity

Highest Risk

Lowest Risk

Exploitatio

n

Remainder of

presentation will

focus on negative

risk…

Page 37: Chris hache -_managing_catastrophe_observations_final

37

“Traditional” Risk MatrixPro

babili

ty

Severity

Highest Risk

Lowest Risk

Mitigatio

n

Page 38: Chris hache -_managing_catastrophe_observations_final

38

Risk Indices

• Probability

1. Improbable

2. Remote

3. Occasional

4. Probable

5. Frequent

• Consequences

1. Negligible

2. Marginal

3. Significant

4. Critical

5. Catastrophic

Page 39: Chris hache -_managing_catastrophe_observations_final

39

ProbabilityImprobabl

eSo unlikely it may not be experienced

Remote Unlikely, but could possibly occur in the life of the project

Occasional Unlikely, but can be reasonably expected to occur in the life of the project

Probable Will occur several times in the life of the project

Frequent Likely to occur regularly

Page 40: Chris hache -_managing_catastrophe_observations_final

40

Consequences - Negligible

• Personnel

• Minor impact / minor first aid, no appreciable change in productivity

• Infrastructure

• Minor damage, limited & temporary loss of some non-critical resources

• Project

• Minor degradation / project continues as scheduled

Page 41: Chris hache -_managing_catastrophe_observations_final

41

Consequences - Marginal

• Personnel

• Single minor injury or temporary disability, emergency medical treatment

• Infrastructure

• Moderate damage, moderate &/or longer loss of some non-critical resources, possible minor/temporary impact on critical resources

• Project

• Certain aspects of the project will be notably over on time/scope/cost, project continues

Page 42: Chris hache -_managing_catastrophe_observations_final

42

Consequences - Significant

• Personnel

• Single severe or permanent injury, multiple minor injuries or disabilities

• Infrastructure

• Major damage, temporary loss of critical resources, requires specialized repair teams

• Project

• Single significant project element failure but with workarounds - may be unsuitable to continue

Page 43: Chris hache -_managing_catastrophe_observations_final

43

Consequences - Critical• Personnel

• Single death / multiple severe injuries / multiple permanent disabilities

• Infrastructure

• Severe damage, extended loss of critical resources, requires specialized repair teams

• Project

• Multiple significant project element failures but with workarounds, likely unsuitable to continue

Page 44: Chris hache -_managing_catastrophe_observations_final

44

Consequences - Catastrophic

• Personnel

• Multiple deaths

• Infrastructure

• Damaged beyond repair

• Project

• Irrecoverable project failure and inability to continue

Page 45: Chris hache -_managing_catastrophe_observations_final

45

Risk Levels•Acceptable (without review)

•No further action required

A

•Acceptable With Review

•Tolerable but must be reviewed by the project team on a periodic basis

R

•Undesirable

•Should only be tolerated if risk reduction is impractical

U

•Intolerable

•Intolerable – risk is to be reduced / transferred or else the project should be cancelled

I

Page 46: Chris hache -_managing_catastrophe_observations_final

46

Risk Matrix

5

4

3

2

1

NegligibleMarginalSignificantCriticalCatastrophic

R U I I I

R R U I I

A R U U I

A A R U U

A A A R R

Pro

babili

ty

Consequences

1 2 4 5

Frequent

Probable

Occasional

Remote

Improbable

3

Page 47: Chris hache -_managing_catastrophe_observations_final

47

Risk Mitigation / Controls

• To reduce risk levels, you must:

• Reduce the frequency and/or

• Reduce the severity

• Eliminate, reduce, transfer, share, etc.

• If risk level has not dropped, then inappropriate / inadequate controls being used

Page 48: Chris hache -_managing_catastrophe_observations_final

48

Example

• Risk – Documentation on the plan no longer exists (server room collapsed)

• Probability: Remote

• Severity: Critical (Project)

• Risk Assessment Undesirable

Page 49: Chris hache -_managing_catastrophe_observations_final

49

Example (continued)

• Risk Mitigation/Controls:

• Off-site server backup, cloud computing, DVD backups

• Probability: Remote

• Severity: Negligible (Project)

• Residual Risk Assessment

• Acceptable

Page 50: Chris hache -_managing_catastrophe_observations_final

50

Risk Posture After Controls

FrequentProbable

OccasionalRemote

Improbable

Catastrophic

Critical

Marginal

Negligible

0

5

10

15

20

25

30

35

40

45

Before Controls

FrequentProbable

OccasionalRemote

Improbable

Catastrophic

Critical

Marginal

Negligible

0

10

20

30

40

50

60

70

After Controls

The number of risks have not changed,but the risk levels have!