Holy Trinity Catholic Church 216 2 nd Street North Royalton, MN Insulation Retro-fit Project Review Chris Froelke, BPI Analyst MN Contractor Lic #BC 631810
-
Upload
clean-energy-resource-teams -
Category
Documents
-
view
353 -
download
0
Transcript of Chris froelke royalton
Holy Trinity Catholic Church216 2nd Street North
Royalton, MN
Insulation Retro-fit Project Review
Chris Froelke, BPI Analyst
MN Contractor Lic #BC 631810
Dome
Sanctuary
Old Fiberglass Insulation
Removal is Necessary
Before…
Insulation Removal…Issues Revealed
Attic…2. Spray Foam 3. Blown Cellulose
1. Removal
Thermographics!Before “Half-Done”
Dark colors indicate
massive heat loss!
Dome…2. Spray Foam
3. Blown Cellulose(Not Pictured)
1. Removal
Hi!
Accessing this area was a challenge... And a great accomplishment!
Thermographics!Before After
Dark colors indicate
massive heat loss!
Blower Door Testing
39%Reduction
In
Leakage