CHERRY GARDEN PROGRESS PHOTOS W/E 16TH Junefluencycontent2-schoolwebsite.netdna-ssl.com/File... ·...

3
CHERRY GARDEN PROGRESS PHOTOS W/E 16 TH June Image 01, 16-06-2017; concrete blinding to oversite in preparation for concrete floor slab; grids 7-13/A-C Image 02, 16-06-2017; striking formwork from side walls to concrete walls to hydrotherapy pool

Transcript of CHERRY GARDEN PROGRESS PHOTOS W/E 16TH Junefluencycontent2-schoolwebsite.netdna-ssl.com/File... ·...

Page 1: CHERRY GARDEN PROGRESS PHOTOS W/E 16TH Junefluencycontent2-schoolwebsite.netdna-ssl.com/File... · CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June Image 03, 13-06-2017; preparation

CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June

Image 01, 16-06-2017; concrete blinding to oversite in preparation for concrete floor slab; grids 7-13/A-C

Image 02, 16-06-2017; striking formwork from side walls to concrete walls to hydrotherapy pool

Page 2: CHERRY GARDEN PROGRESS PHOTOS W/E 16TH Junefluencycontent2-schoolwebsite.netdna-ssl.com/File... · CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June Image 03, 13-06-2017; preparation

CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June

Image 03, 13-06-2017; preparation to lift pit, blinding concrete to base, cutting away concrete top of piles

Image 04, 16-06-2017; tanking detail, concrete base and reinforcement to lift walls in progress

Page 3: CHERRY GARDEN PROGRESS PHOTOS W/E 16TH Junefluencycontent2-schoolwebsite.netdna-ssl.com/File... · CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June Image 03, 13-06-2017; preparation

CHERRY GARDEN PROGRESS PHOTOS – W/E 16TH June

Image 05, 16-06-2017; installing underground drainage within the building footprint in progress

Image 06, 16-06-2017; excavated trench as part of the Japanese Knot Weed treatment works in progress