Chemical & Process Technology_ Two-Third (2_3) Rule or Ten-Thirteen (10_13) Rule

download Chemical & Process Technology_ Two-Third (2_3) Rule or Ten-Thirteen (10_13) Rule

of 3

Transcript of Chemical & Process Technology_ Two-Third (2_3) Rule or Ten-Thirteen (10_13) Rule

  • 5/2/13 Chemical & Process Technology: Two-third (2/3) rule or Ten-thirteen (10/13) rule ?

    webwormcpt.blogspot.in/2008/01/two-third-23-rule-or-ten-thirteen-1013.html 1/3

    Chemical & Process TechnologyA place to share knowledge, lesson learnt...

    HOME ARCHIVE LINK FREE MAGAZINES

    FOLLOW ME

    Enter your email

    address:

    Subscribe

    SUPPORT This Site

    Hot Posts

    Search

    Web Chem & Proc Tech

    CHEM & PROC TECHOIL & GAS TECH

    HEAT & EXCH TECHGEN TECH

    Two-third (2/3) rule or Ten-thirteen (10/13) rule ?

    Wednesday, January 30, 2008

    Display problem ? Click HERE

    I have noticed there are many engineers still asking a simple question. In determining if a

    Pressure Relief Device is required for tube rupture, should we apply two-third (2/3) rule or

    ten-thirteen (10/13) rule ?

    For those who has read my earlier post Criteria for Requirement of Pressure Relief

    Device for Tube Rupture may have aware that two-third (2/3) rule or ten-thirteen (10/13)

    rule are basically derivation of above criteria. Both are correct BUT subject to design

    code and revision of vessel being designed to.

    WHY two-third (2/3) rule ?

    Earlier revision of ASME required that equipment and piping be tested at 150% of stated

    design pressure. If the equipment design pressure

    is 15 barg, then the test pressure must be 22.5

    barg, thus 15/22.5 = 2/3. API RP 521 (1997 edition)

    stated that if the design pressure of the low-

    pressure side (LPS) is at least 2/3 of the design

    pressure of the high pressure side (HPS), tube

    rupture is not considered a credible relieving

    scenario.

    WHY ten-thirteen (10/13) rule?

    In latest ASME, it stated that the test pressure of equipment to be 130% of the design

    pressure. If the equipment design pressure is 15 barg, then the test pressure shall be

    19.5 barg, thus 15/19.5 = 10/13. Similarly follow API RP 521 (1997 edition) statement, if

    the design pressure of the low-pressure side (LPS) is at least 10/13 of the design

    pressure of the high pressure side (HPS), tube rupture is not considered a credible

    relieving scenario.

    In latest API STD 521, a more reasonable statement is the corrected test pressure of

    ASME Vessel Pressure API Flange ASME Flange

    Corporate Safety Training

    electronicsecurityfiretraininginstitute.com

    Get expert training on fire safety Apply nowfor NSDC Certified course

    Useful Documents Related to Pressure Relief Valve

    (PRV) - Part 1

    Pressure Relief Valve (PRV) has been widely use in

    overpressure protection of pressure containment

    equipment. Regardless of vessel/column/drum/tank

    designed in accordance to any pressure vessel code

    e.g. ASME, JIS, BS, GB, etc,...

  • 5/2/13 Chemical & Process Technology: Two-third (2/3) rule or Ten-thirteen (10/13) rule ?

    webwormcpt.blogspot.in/2008/01/two-third-23-rule-or-ten-thirteen-1013.html 2/3

    Recommended Jobs

    Product Consultant

    Bangalore, Karnataka - UOP

    LLC

    Marketing Engineer

    Indore, Madhya Pradesh - Effort

    Consultancy Services

    Chemical Engineer - Process

    India - Customer is King

    Chemical Engineer - Process

    Chennai, Tamil Nadu -

    Customer is King

    Chemical Engineer - Process

    Bangalore, Karnataka -

    Customer is King

    Enter search terms... Go

    www.indeed.com

    low pressure side (LPS) is more than the design pressure of high pressure side (HPS),

    tube rupture may not be considered a credible relieving scenario. This statement is

    applicable to any test pressure requirement.

    WHY both are correct ?

    One shall remember, the equipment may be designed to latest ASME code which called

    for test pressure to be 130% of equipment design pressure. Then ten-thirteen (10/13) rule

    is applied. But if the vessel is designed to AS (Australia), GB (China), etc which both

    standards still call for equipment test pressure to be 150% of equipment design pressure

    with stress correction, then two-third (2/3) rule still applied. Thus, whenever consider a

    tube rupture scenario, the design code of the vessel shall always be taken into

    consideration. Nevertheless, latest API STD 521 statement still applicable in conjunction

    with equipment design to any code (ASME, AS, GB, JIS, etc).

    Updated :

    June 07, 2008 : "...within" changed to "...at least". Thanks to swakee.

    Sept 20, 2008 : "22.5/15" to "15/22.5"...

    Related Topic

    Tube Rupture : Pressure Relief Valve (PSV) or Rupture Disk (RD) ?

    Criteria for Requirement of Pressure Relief Device for Tube Rupture

    Requirement of Overpressure Protection Device on "Final Vessel"

    FREE & Reliable Pressure Relief Valve Sizing Software

    Extra Caution When Eliminating Overpressure by Fire Attacks

    Should maximum recommended wall temperature (Tw) for carbon steel vessel

    used as design temperature ?

    Should we install Butterfly valve for Pressure Relief Valve (PSV) isolation ?

    WebWorm

    Continue receive FREE stuff & Update.......Subscribe by Email OR RSS

    Any comments / advices ?..........Drop it in comment field (below) or send a private email

    to me...

    Labels: Overpressure Protection

    Process engineer jobs

    Application Engineer-IIExpedia, Inc - Gurgaon, HaryanaeCommerce Application Engineer works with the

    Product... and accurately communicate to program

    managers, engineers, and senior management.

    Work Experience and...

    Expedia

    more jobs

    jobs by

    posted by Webw orm, 2:19 PM

    -->

    4 Comments:

    swakee said...

    As per this article for 2/3rd rule, it says "if design pressure of low pressure

    side (LPS)is within 2/3 of the design pressure of the high presure side, tube

    rupture is not consideredHigh pressure is not considered a credible relieving

    scenario".

    But API 521 says, the low pressure side is designed for atleast 2/3 of the

    design pressure of the high pressure side. Please correct the rule

    accordingly, otherwise this will mislead the people who refers this article.

    June 6, 2008 at 4:05 AM

    Webworm said...

    Thanks swakee. Updated.

    June 6, 2008 at 1:51 PM

    Anonymous said...

    Relief Valve

    API Flange

    ASME Flanges

  • 5/2/13 Chemical & Process Technology: Two-third (2/3) rule or Ten-thirteen (10/13) rule ?

    webwormcpt.blogspot.in/2008/01/two-third-23-rule-or-ten-thirteen-1013.html 3/3

    In your "WHY two-third (2/3) rule?" paragraph, i think 22.5/15 is more than 1,

    so it should be 15/22.5.

    September 19, 2008 at 4:26 PM

    Webworm said...

    Sharp ! Thx

    September 19, 2008 at 5:26 PM

    Post a Comment

    Let us know your opinion !!! You can use some HTML tags, such as , ,

    Enter your comment...

    Comment as: Google Account

    Publish Preview

    Subscribe to Post Comments [Atom]

    Links to this post:

    Create a Link

    Home: