Hamburg Metropolitan Region Partners, organisation and projects Welcome.
Checklist for Partners Working on High Risk D&B Projects
Click here to load reader
description
Transcript of Checklist for Partners Working on High Risk D&B Projects
Page 1© 500 Word Contracts, 2014
Checklist for a Design & Build Project
The 2011-2012 court decisions in Trebor Bassett v ADT Fire and Security1 analysed in detail how two
partners carried out pre-contract processes for the design and installation of equipment. The
judgments are full of tips for those involved in high risk or D&B projects. It should also act as a
warning as the claim for £110m arose out of a contract for the design and supply of equipment
costing a mere £9,000.
The tips, quotes and lessons have been collated into a series of recommendations for partners
entering into contracts for construction projects, particularly those involving hazardous processes.
Risk Analysis
You Should:
Assess and appreciate the risk of each project separately: in this case, the buyer “never fully
appreciated the increased risk” that the project would bring. [55]2
Assess “the risks before the project workscope was defined.” [77]
Avoid preparing “a specification based on a 'minimum spend'” which decision could be
exacerbated by “a refusal to consider any recommendation which might add to the workscope,
even if they provided the only way of truly controlling the risk.” [77]
Never assume that a similar system is appropriate for a similar project. {21}
Ascertain or communicate any history of risk events occurring on similar projects, especially to
the designer of a system intended to protect or minimise the consequences of those risk events.
Your designer should appreciate all significant risks. [140] {21}
Carry out a proper technical appraisal of the risks, ideally in conjunction with the supplier of
relevant risk protection equipment. [75]
Identify precisely the risks and hazards on each project “and/or how those risks could be best
dealt with.”3 This should be done in detail. [61, 367]
Make sure one person within your organisation ‘owns the risk.’ Often this is the project manager
who is responsible for “recognising and then minimising all the risks created by that project.”62]
Check all assumptions made for significant risk factors (i.e. those with potentially catastrophic
consequences). “This erroneous assumption gave rise to the conclusion that there was no health
and safety issue; it follows that, if the [buyers] had bothered to check the as-built drawings, they
would have seen that the assumption was wrong, and that therefore there was a major health
and safety issue.”[88]4
Take advice from risk professionals, but make sure their advice is based on evidence and not
assumptions. [68-69]
Ensure all recommendations from risk managers are properly followed through: “one significant
recommendation made by the [buyer’s own risk managers]…was not followed” and that none
are ignored. [7, 36]
Where the best option to protect against a risk event is not adopted, ensure that the alternative
means of protecting against risk events are adopted. [72]
Keep records of meetings with Fire Officers. [121]
Not “decide what to do and then assess the risk” but the other way round. [77-78]
Page 2© 500 Word Contracts, 2014
Not determine the significance of risks on the “value of the proposed works”5 but on “the value
of the building and equipment at risk if those works were not properly specified and designed.”
[85]
Not assume that Certification by the Fire Brigade is sufficient to establish risks have been
managed and the process is not hazardous, such as “an industrial process involving naked
flames.” [44]
Specifying the Works
You Should:
Decide your objective – you cannot have both high quality, low price and tight timescales: “The
timing was very tight… it was imperative that the new lines were up and running by Christmas
2003, in order to meet the surge in demand for popcorn, particularly for the cinema trade, over
the Christmas period. This timetable could not be changed.” But the same project was costed “on
a requirement of minimum spend to introduce a safe system of work.” [54, 58]
Agree what design responsibility each partner will have: “the most important element of the
workscope was that done by the [sellers’] designers: the decision to use a particular piece of
equipment in a particular place, with the intention of achieving a particular effect.” [215]
Specify the works based on the needs of the project, not on existing experience. [92-96]
Ensure the partners work together on producing the design and specification: “the [buyers’]
haphazard approach at the outset was not picked by the [sellers], and was compounded by the
[sellers’] rather cavalier attitude to what they were being asked to do.” [113]
Avoid using standard form specifications for bespoke projects with significant risks. [107]
Specifying Standards of Quality
You should:
Understand the general standards of quality. A contractor providing design services “will not
generally owe a higher obligation than the duty to use reasonable skill and care.” If you want a
higher standard, you will have to say so, clearly. [217] Be specific if you want quality guaranteed: “one would need to identify with much more
specificity precisely what it is that [the sellers were] alleged to have been impliedly asked to do
and, in consequence, what result it is that it is said to have undertaken to bring about.” {56} State the standards you require. If your contract states ‘good quality’, the court will not imply a
term what the goods will be of satisfactory quality.6 [218-220] Ensure, in a contract for the sale of goods, where you want to rely on an implied obligation as to
fitness for purpose, that you:
o State your particular purpose “must have been made clear… At no stage did the [buyers]
ever indicate any particular purpose” for which the system was being acquired; [223-
224]7
o rely on the sellers’ advice or expertise; in the case, the buyers “did not rely on the
defendant's skill or judgment at all.” [226]
Page 3© 500 Word Contracts, 2014
Set out the standards on quality in the specification: “The specification, with its reference to
British Standard 5306 and other assumptions and requirements, formed the benchmark against
which the [sellers’] obligations were to be performed.” [264]
Understand what any relevant British Standard requires – often it is more a set of
recommendations, which is not sufficient for a guarantee or warranty. [243]
Set out any promise or guarantee in clear words: “[T]he fact that the system had been designed
‘to suit the specific requirements of the risks to be protected’ (to use the words of the
specification) does not mean that the system was guaranteed to eliminate those risks every time.
It was designed, manufactured and installed with those risks in mind, but the obligation as to
design was to take reasonable skill and care and there was nothing in these words to impose
upon the defendant a more onerous obligation. A design intended 'to suit the specific
requirements of the risks' may or may not be done with reasonable skill and care, but it was not a
promise that the design would eliminate all risks. A promise that a particular risk will be
eliminated must say so in clear terms. The specification did not do so.” [242]
Designing and Commissioning the Works
As a designer/D&B contractor, you should:
Use correct and detailed drawings in order to prepare your design. In this case, “the working
documents should have identified the relevant hazards.” [105,111]
Seek “as much information” as you can. Do not design “on assumptions [but]… find out the facts
for itself.” [509]
As your first step, “identify the risks which were to be protected and to design a system that
suited the specific requirements of the risks to be protected.” [510]
Ensure, as “a specialist was providing a design, and then manufacturing and installing the
product so designed…that there was proper communication between the designer and the
installer.” [511]
Ensure any checks of design assumptions by the installer or buyers are followed up: “if the
design engineer worked from drawings, he would need the installing engineer to check that his
design assumptions were well-founded.” [112-113, 138]
Ensure your design is based on detailed accurate information, reviewed and checked. [113]
Obtain good information and corroborate with your partners, to avoid: “the patently inadequate
information which the [sellers] had, and the difference of approach between its two designers
which was its probable result, demonstrates a fundamental flaw at the heart of the [sellers’]
work on this contract.” [140]
Do more than just check “the system had been installed in accordance with the drawings” where
the drawings are inadequate. [145]
Agreeing the Terms and Conditions
You Should:
Keep records to show that previous contracts have been agreed on the same basis, if you want
to establish a course of dealing, and that your T&C are incorporated as a result. [161]
Page 4© 500 Word Contracts, 2014
Ask for a copy of any T&C referred to on any contract document, especially where it states
“already supplied… Additional copies available on request”. You must also respond to any terms
with which you disagree. {27}
Understand the rules relating to incorporation of terms and conditions.8 [172-173]
Ensure your terms and conditions are sensible and certain: a clause limiting liability to a multiple
of an annual service charge is not effective in a contract for the provision of goods and services.
Such a limit “was meaningless, because the limitation was calculable only by reference to the
value of a non-existent contract. That was too uncertain to be enforceable.” [197-198]
Training Staff
You Should:
Use risk identification processes to establish standard operating procedures. [367]
Create clear safety procedures and train operatives accordingly. [367]
Ensure all relevant staff are given a detailed demonstration of all relevant systems as part of the
commissioning or post-commissioning follow-up. Do not leave it to one person. [270-286]
Ensure all operatives are aware of any safety features or procedures on newly installed or
altered equipment: “very few of the operatives in the 'oil pop' popcorn production area were
aware that the CO2 suppression system protecting the elevator and the hopper could be
manually activated, and even fewer knew how that manual activation was to be triggered.”[8]
Ensure the procedures approved by managers are appropriate. [10]
Ensure there is a satisfactory and safe working environment for operatives, and a satisfactory
system to detect and respond to risk events such as fires. [264-266]
Follow up when risks events occur. [269]
Ensure checks required by a manual or users’ handbook are completed as required. [311]
Check whether training is reflected in changed behaviours. [333-335]
Write down all approved procedures for dealing with risk events. [338]
Act on knowledge that operatives are not aware of safety procedures. [346]
Undertake structured and systematic evaluations of processes to identify risk to personnel and
equipment, in a HAZOP format. [349]
The Author
Sarah Fox of Enjoy Legal Learning wrote this note. She is a speaker and trainer who cuts through the
complexities of construction law. She provides confidence to construction companies to read, use
and understand their contracts. She is also author of the 500 Word Contract™.
To find out how Sarah can help you love your terms and conditions, contact her on: 07767 342747 or
by email: [email protected]
Footnotes
1 The first was by Mr Justice Coulson in Trebor Bassett Holdings Ltd & Anor v ADT Fire and Security Plc
[2011] EWHC 1936 (TCC) and the second by the Court of Appeal [2012] EWCA Civ 1158. 2 References in square brackets are to the TCC judgment and in curly brackets are to the Court of
Appeal judgment. 3 TCC, 56.
Page 5© 500 Word Contracts, 2014
4 See also paragraphs 7 “A critical assumption about the existence of fire segregation turned out to be
entirely misplaced”, and 45-49. 5 See e.g. the comments at paragraph 91: the suggestion from the claimant that they “might be over-
spending, by installing a system costing a few thousand pounds, in order to protect building and equipment now said to be worth £110 million, is unfathomable. It betrays an absence of understanding of what the fire risks really were, and restates the false cost=significance proposition.”
6 This term is implied under s4 of the Supply of Goods and Services Act 1982. 7 In the Court of Appeal judgment, Tomlinson LJ said, at paragraph 57: “[The buyers] cannot, for the
purposes of s.4(4) of the 1982 Act, show that it made known to [the sellers] a particular purpose for which the system was being acquired. {The buyers] did not sufficiently explain the process or its hazardous nature…no such absolute but undefined obligation could be undertaken or guarantee given.”
8 A quotation is an offer, and a purchase order with a different set of terms and conditions is a counter-
offer. If this is the ‘last-shot’, then the buyers’ terms and conditions apply. The fact that the buyers’ terms and conditions were not enclosed with their purchase order does not prevent their incorporation if (1) they were incorporated by notice (2) there was no requirement for specific or particular notice as none of the terms and conditions were unduly onerous. [191-192]