Checklist for Inspecting vessels loading propylene oxide PO

7
PROPYLENE OXIDE SURVEY QUESTIONAIRE (COMPLIANCE WITH DOW BULK HANDLING GUIDELINES) Vessel name: Vessel owner: Date of inspection: Inspection location: Inspector: CERTIFICATES: Ref A.1 .a Appl ica ble U.S. Coast Guar d Let ter of Compli anc e or te I!" Cert ific ate for te carria#e must be current prior to te loadin# and for te duration of te $o%a#e. Certificate of &itness includes '.". (es )o Date Issued: *+piration Date: Issued b%: Date of ne+t annual sur$e% USCG Letter of Compliance: Date issued: *+piration date: List of car#o tan,s appro$ed for '.". Conditions of carria#e of '.". per certifica tes -attac a cop%: Does $essel meet tese conditions/ (es )o )0A If not note reasons below: DOW GAS RULES: If th !""# $" % &%" !""#' " $t *+,#- .$th D./" G%" R0#"1 Vessel 2%pe: SR Gas &R Gas Cem "ter:333333333333333333333333333333333  Y" N N2A TANK TIGHTNESS CERTIFICATES (R30$4 %t "+ U5S5 "$t"' "0*h %" F4,4t2H 0"t6): D" th !""# h%! t%67 t$&ht6"" *4t$f$*%t" f4 %## t%67" %,,4! f4 PO1 Note: Vessel must provide a copy of these to the terminal prior to the transfer  Y" N N2A If 8YES9' $" !""# $6 *+,#$%6* .$th th %660%# t"t$6& 430$4+6t1 Date of last test:3333333333333333333  Y" N N2A If 8NO9' " !""# h%! ,4*04"2,%,4.472,#%6" t *+,#t th t"t ,4$4 t %44$!%# t t4%6"f4 *%4&1  Y" N N2A  4*' 0 5 September 6778 66977685.doc 'a#e 1 of 9

description

Checklist for Inspecting vessels loading propylene oxide PO

Transcript of Checklist for Inspecting vessels loading propylene oxide PO

PROPYLENE OXIDE SURVEY QUESTIONAIRE

PROPYLENE OXIDE SURVEY QUESTIONAIRE

(COMPLIANCE WITH DOW BULK HANDLING GUIDELINES)Vessel name:Vessel owner:

Date of inspection:Inspection location:

Inspector:

CERTIFICATES:Ref A.1.aApplicable U.S. Coast Guard Letter of Compliance or the IMO Certificate for the carriage must be current prior to the loading and for the duration of the voyage.

Certificate of Fitness includes P.O.YesNo

Date Issued:Expiration Date:

Issued by:Date of next annual survey

USCG Letter of Compliance:

Date issued:Expiration date:

List of cargo tanks approved for P.O.

Conditions of carriage of P.O. per certificates (attach a copy):

Does vessel meet these conditions?YesNoN/A

If not, note reasons below:

DOW GAS RULES:

If the vessel is a gas vessel, does it comply with Dows Gas Rules?

Vessel Type: SR Gas FR Gas Chem Other:_________________________________YesNoN/A

TANK TIGHTNESS CERTIFICATES (Required at some U.S. sites, such as Freeport/Houston):Does the vessel have tank tightness certificates for all tanks approved for PO?

Note: Vessel must provide a copy of these to the terminal prior to the transferYesNoN/A

If YES, is vessel in compliance with the annual testing requirement?

Date of last test:___________________YesNoN/A

If NO, does vessel have procedures/paperwork/plans to complete the test prior to arrival to transfer cargo?YesNoN/A

Previous cargoes - for tanks approved for carriage of PO:

TankLast Cargo2nd Last3rd LastPlan to use for Dow PO this tripAdjacent cargoes OK per USCG Meets PO

Guidelines

PREPARATION FOR LOADING:Cargo will be loaded using vapor return, discharged under nitrogen blanketYesNo

Cargo tanks and piping system must be purged with nitrogen to an oxygen content of less than 0.5 % (5,000 ppm) oxygen before loading is commenced. For some shipments (Dow Polyurethane business), the vapor space of cargo tanks are purged to less than 0.05% (500 ppm) oxygen before the ship departs. It is recommended to add nitrogen through the liquid line (nitrogen bubbling) to stabilize pressure during the voyage.YesNo

Void spaces around cargo tanks must be purged with nitrogen to