CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour...
Transcript of CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour...
![Page 1: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/1.jpg)
CHATHAM BRIDGE PROJECT
Robert G. Ridgell, P.E., DBIA
VDOT Fredericksburg District, Assistant District Construction Engineer
May 14, 2020
City of Fredericksburg – Main Street Community Meeting
![Page 2: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/2.jpg)
“Pardon Our Dust” Meeting Agenda
2
• Project need
• Benefits and features of improved bridge
• How travelers will be affected
• Recreation on the Rappahannock River
• Construction highlights
• Your questions!
![Page 3: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/3.jpg)
Chatham Bridge Today
3
• Built in 1941 (79 Years Old)
• 16,000 vehicles a day
• Travel lanes – 4 lanes, each 10 feet wide
• Narrow sidewalks (4 feet wide)
• Structurally deficient
• Asphalt in poor condition due to age
• Impacts to travelers
• High maintenance costs
• Weight Posting
![Page 4: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/4.jpg)
Chatham Bridge Rehabilitation: Project Design
4
![Page 5: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/5.jpg)
5
Example of future shared use path on bridge: Photo from Dr. Martin Luther King, Jr., Memorial Bridge in Danville, Virginia
Chatham Bridge outer railing will be concrete-only
![Page 6: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/6.jpg)
6
Rendering of future Chatham Bridge
![Page 7: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/7.jpg)
7
Rendering of future Chatham Bridge
![Page 8: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/8.jpg)
8
Rendering of future Chatham Bridge
![Page 9: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/9.jpg)
9
Project Schedule
Phase Date
Dixon Street ramp improvements
Install detour signs (covered until needed)Complete!
Utility relocation Completion by June 15
Construction activity begins May 28, 2020
Bridge closes to all traffic
Demolition work begins
June 2020*
(*exact date to be announced two weeks ahead)
Bridge reopens to traffic 16.5 months after closure
(incentivized completion schedule)
![Page 10: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/10.jpg)
Detour Route
10
• Route 3 Business
• Blue & Gray Parkway
• Dixon Street
• Charles Street
Remember:
No change for traffic
approaching downtown from
Route 1 at Falmouth Bridge, or
Route 3 from Interstate 95
![Page 11: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/11.jpg)
Detour: Vehicles taller than 13 feet, 6 inches
Virginia Department of Transportation 11
• Route 3 Business
• Blue & Gray Parkway
• William Street
Remember:
No change for traffic
approaching downtown from
Route 1 at Falmouth Bridge, or
Route 3 from Interstate 95
![Page 12: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/12.jpg)
Dixon Street Ramp Improvements: Complete
Virginia Department of Transportation 12
![Page 13: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/13.jpg)
Hanson Avenue and Route 1 Traffic Pattern Changes
13
![Page 14: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/14.jpg)
Impacts to River Users
Virginia Department of Transportation
June 2020 through December 2020
14
![Page 15: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/15.jpg)
Impacts to River Users
Virginia Department of Transportation
December 2020
15
![Page 16: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/16.jpg)
River User Rules of Road
Virginia Department of Transportation
• Follow warning buoys
• Do not approach pipes
• Do not enter the workzone
• Use caution during high flows
• Intermittent short term closures (<24 hours) will be required
for beam demolition and setting and deck forming.
• Communication will be made to:
• Virginia Outdoors Center
• River Rock Outfitters
• Friends of the Rappahannock
• Fredericksburg Trails Alliance
16
![Page 17: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/17.jpg)
17
Construction Sequence Highlights
Construction Activity Approximate Timeframe
Access road and causeway construction
Traffic signal modifications at Route 1, Hanson Avenue
Detour sign
Late May and Early June 2020
Causeway construction continuing into July
Bridge Deck Demolition June – July 2020 (estimated 3 weeks)
Steel Beam Demolition Early August 2020
Top of river pier demolition and widening
Shore foundations and supports
Foundation protection in river
Late August 2020
![Page 18: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/18.jpg)
18
Construction Sequence Highlights
Construction Activity Approximate Timeframe
Placement of new structural steel December 2020
Bridge deck forming and placement Spring 2021
Bridge rail forming and placement Summer 2021
Bridge deck finishing, traffic elements and new signs
BRIDGE OPENS! Early October 2021
![Page 19: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/19.jpg)
Coordination with private online mapping:
• Waze
• Apple
• TomTom
• Here.com
• Others … list is always growing!
Online Mapping Providers
Virginia Department of Transportation 19
![Page 20: CHATHAM BRIDGE PROJECT · Project Schedule Phase Date Dixon Street ramp improvements Install detour signs (covered until needed) Complete! Utility relocation Completion by June 15](https://reader033.fdocuments.us/reader033/viewer/2022053016/5f172bd84105b057b63bf8a7/html5/thumbnails/20.jpg)
www.VirginiaDOT.org/chathambridge
Live construction camera to be added once work begins!
Follow us on …
Facebook: VDOT Fredericksburg District Group
Twitter: @VaDOTFRED
Nextdoor
Need a Chatham Bridge project speaker, or have a question?
Contact us!
Kelly Hannon, VDOT Fredericksburg District
Communications Manager
(540) 374-3344 office
(540) 656-0321 cell
(540) 899-4288 VDOT Fredericksburg District Office
Stay informed!