    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    CHAPTER 8

    ENVIRONMENTAL MANAGEMENT PLAN

    8.0 Introduction

    An environmental management plan (EMP) consisting of proposed pollution

    abatement system to cope up undesirable impacts, are delineated below.

    Conceptual plan as Master Plan is shown below.

    8.1 Landuse Planning and Area Statement

    The area statement including land use of the proposed project is given in Table 8.1.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    2/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 1 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    Table 8.1

    Area Statement

    Sl.

    No.

    DescriptionArea (sqm) %

    1 LAND AREA AS PER DEED 102809.360

    AREA OF ALIGNMENT LINE

    NET LAND AREA 102809.360 100.0

    2 GROUND COVERAGE AREA 24945.95 24.26

    SERVICE AREA 891.47 0.87

    TREE PLANTATION AREA 26802.38 26.07

    ROAD/ PAVED AREA 15193.35 14.78

    SEMI PAVED AREA 7165.68 6.97

    OPEN PARKING AREA 0.56 0.10

    FUTURE EXPANSION AREA 393.88 0.38

    GIFTED LAND AREA 308.52 0.30

    BASEMENT 27007.57 26.27

    TOTAL 102809.360 100.00

    3 TOTAL GREEN AREA 30435.50 29.6

    EXCLUSIVE TREE PLANTATION AREA 26802.38 26.07

    50% OF SEMI PAVED AREA 50.28 0.05

    50% OF OPEN PARKING AREA 3582.84 3.48

    4 TOTAL PAVED AREA 18826.47 18.31

    ROAD/ PAVED AREA (BEYOND BASEMENT 15193.35 14.78

    50% OF SEMI PAVED AREA 50.28 0.05

    50% OF OPEN PARKING AREA 3582.84 3.48

    5 TOTAL NOS. OF FLATS 3100 NOS.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    3/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 1 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    8.2 BUILDING ARCHITECTURAL DESIGN CHARACTERISTICS WITH

    EMPHASIS ON BUILDING ENERGY PERFORMANCE

    Proposed ground coverage is just 25% leaves adequate open space in the

    site. Paved area in the site is very less than 25% and open space at the

    ground level is about 50% with a green area of about 30%.

    This has got a two-fold benefit. Firstly, substantial green cover that is lower

    albedo (reflectivity) compared to that of paved surface results in reduction of

    glare and temperature stratification leading to heat island effect as commonly

    witnessed in urban areas. Secondly, absorption of rainwater through the

    green cover recharges the ground water level and also reduces the load on

    the storm water channels due to lesser surface run-off. Additionally, green

    cover reduces heat carried into adjoining building due to its lower reflectivity,

    and maintains lower air temperature adjacent to the building by promoting

    evaporative cooling.

    There is a clear hierarchy of open spaces in between the tower blocks and

    the central open spaces, which are aligned along the N-S axis. Predominant

    wind flow along the N-S axis will be channelised into the smaller pockets in

    between the blocks.

    Most of these small pockets of open spaces within the clusters of G+6 (for

    existing buildings) and G+20 (proposed) blocks will remain under shade from

    the afternoon sun during the summer. The breeze drawn into these pockets

    will lose some of its heat before entering the living spaces of the apartment

    units.

    Layout of the tower blocks on both sides in a staggered manner provides

    mutual shade, resulting in substantial reduction of solar heat gain. The central

    open space remains well protected from the afternoon sun on the west.

    Vertical fenestrations on the recessed external facades with mutual shading

    of the building blocks would receive lesser solar radiation, and also the

    external surface conductance (fo) for the opaque wall surface would become

    almost half (about 8 to 13 W/m2K) in case of sheltered exposure, compared to

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    4/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 2 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    normal exposure, resulting in substantial reduction in heat gain through the

    wall and fenestration.

    Openings on the recessed building facades with staggered alignment of the

    tower blocks provide protection to the west facades in particular. Apart from

    that, projection of 500 mm. has been considered for solar shading of the

    vertical fenestrations, particularly on the West and South. Roof would be

    provided with insulation of about 30 mm. thickness of PU Foam to meet the

    U-value standards as prescribed in the National Building Code, 2005.

    Natural ventilation through large openings on the windward and leeward sides

    of the living spaces of the units has been considered in this design for

    maintaining the indoor thermal comfort during summer.

    Due to natural ventilation in the living areas of the units, minimum 4 to 6 air

    changes per hour (ACH) has been considered. Heat gain due to natural

    convection would be minimized as the open spaces would remain under

    reasonable shading during the overheated hours, resulting in lowering the

    temperature of the wind flow and most of the openings are located on

    recessed building facades designed in a staggered manner with mutual

    shading of tall building blocks.

    Natural ventilation has been considered as the means of cooling during the

    overheated hours in summer, and adequate openings on the windward and

    leeward facades have been provided to facilitate natural ventilation in the

    living zones of the apartments. Though provision of Air-Conditioning has been

    considered in one or two of the bedrooms for 2-bedroom and 3-bedroom

    units, respectively; electrical load due to AC units as already considered in

    the load calculation, may be saved with the use of natural ventilation. Thus,

    out of a total demand load calculated more than 13% energy may be saved

    by means of proper utilization of natural ventilation.

    8.3 ENERGY CONSERVATION MEASURES AND USE OF RENEWABLE

    ENERGY ESPECIALLY SOLAR LIGHTING AND WATER HEATING

    In a standard building around 8820925 kWh energy is required and for the proposed building

    7602900 kWh energy is required thus a net saving of 13.84% energy is observed. Detailed

    energy simulation study report is enclosed in separate volume.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    5/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 3 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    8.4 Water & Wastewater Management with Detailed Water Balance Statement

    Daily water demand of the proposed project during operation phase will be 2445 kLD, out

    of the total water demand 1577 kLD will be the fresh water demand and rest 868 kLD

    (Landscaping: 79 kLD, Car Washing: 92 kLD, Dual flushing : 697 kLD) will be recycled

    from treated wastewater. The fresh water will be provided by Kamarhati Municipality.

    FlatsOccu.Rate

    Totalpop.

    LpcdTotallitre/day

    kLD

    Residential 3100 5 15500 135 2092500 2093

    Club (1850.591sqm)

    185 70 12950 13

    CommercialArea (4615.864sqm)

    140 45 6300 63

    Servicepersons

    790 70 55300 55

    FloatingPopulation

    1200 15 18000 18

    Sub Total 1 2242Landscaping 79

    Car washing 92Losses 22

    Swimming Pool 10

    Sub Total 2 203TOTAL WATER REQUIREMENT 2445

    Total Wastewater Generation 1886

    Total Wastewater Recycled 868Flushing 697Landscaping 79Car washing 92Total Wastewater discharge 1018

    Fresh Water Requirement 1577OCCUPANCY RATE NBC 2005, PAGE 21, BUILDING SERVICES-SECTION 3

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    6/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 4 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    WATER BALANCE DIAGRAM

    8.5 Water Use Reduction and Water Conservation Measures

    Water usage for applications such as f lushing, bathing and washing is as high as 90% of

    water demand in any building. However, measures can be adopted to reduce this

    demand through use of water efficient practices and devices (efficient plumbing fixtures).

    The conventional fixtures used in toilets use water at the rate of 12-15 litres per flush.

    Use of more efficient water saving toilets having low rate flushing system can save of

    atleast 50% of water. Dual plumbing system will be provided for this project to reuse the

    treated wastewater in flushing system. In the landscape areas treated wastewater will be

    used to reduce the fresh water consumption. Apart from that treated wastewater will alsobe used for car washing. As the car washing in a house is not similar that of in servicing

    centre, so much oil or grease may not be discharged from the car washing.

    8.6 Rainwater Harvesting

    The total roof area is about 24919.61 sqm. The SEAC guideline regarding rain water

    harvesting is as follows

    FRESH INPUT1577 kLD

    Residential1396+697 =2093 kld

    Commercial

    63 kld

    Club

    13 kldService55 kld

    Floating18 kld

    SwimmingPool

    10 kld

    Losses

    22 kld

    WASTEWATERGENERATION

    1886 kld

    TREATEDWASTEWATER

    GENERATED 1886 kld

    Landscaping79 kld

    CarWashing

    92kldRECYCLED 26 kld

    RECYCLED DUAL FLUSHING 697 kld

    1396 kld

    TREATEDWASTEWATER

    DISCHARGE 1018 kld

    697 kld

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    7/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 5 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    Sl.

    No.

    Category of Building Minimum percentage of rain water which

    should harvested by

    Surface

    Storage

    Sub-surface Recharge

    1 10 to 15 storied Building &

    Above

    40% 60%

    2 6 to 10 storied Building 35% 45%

    3 3 to 5 storied Building 25% 15% (recharge or additional

    storage)

    4 Less than three storied Building 10% 10%

    Note

    While suggesting the guidelines, RWH potential in 1000 sqm Roof Area was considered

    to be 7, 68,000 liters annually based on the rainfall characteristics. Uniform utilization of

    harvested rainwater throughout the year from created storage tank was also considered.

    Based on the above consideration, the storage facility to be created from 1000 sqm roof

    area for Sl. No. 1,2, 3 were thought to be 3 lakh litre, 2.5 lakh litre and 1.5 lakh liters

    respectively.

    As per SEAC proposed guidelines the rain water harvesting potential is calculated in the

    following Table:

    Details

    No.

    Of

    Story

    Roof

    Area,

    Sqm

    Total

    Rain

    Water

    Potential,

    Lakh

    Litre

    Minimum % Of Rain

    Water Which Shouldbe Harvested by

    Rain Water

    Harvesting Potential

    As Per SEAC

    Guidelines

    Surface

    Storage

    (%)

    Sub-

    Surface

    Recharge

    (%)

    Surface

    Storage,

    Lakh

    Litre

    Sub -

    Surface

    Recharge,

    Lakh Litre

    GroundCoverage /roof Area

    G+14,G+17

    24919.61191.38 40 60 76.55 114.83

    TOTAL 191.38

    As per SEAC proposed guidelines of storage facilities and sub-surface recharging

    facilities required will be 76.55 lakh liters and 114.83 lakh liters respectively. Total

    volume of roof top rain water to be harvested as per SEAC guidelines is 191.38 lakh

    litres i.e. 19138 cum/year.

    All roof top rain water will be diverted to the rainwater storage tank of 26 nos. @ 60 cum

    capacity each and overflow of the tank will be diverted to recharge structure and

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    8/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 6 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    overflow of the recharge structure will be diverted to the pond and further overflow if any

    will be diverted to storm water drain within the campus.

    From the local survey/the agencies working for doing borewells, it is observed that there

    are prominent sand layers (confined aquifer) in the 110.0 to 150.0 meter zone. We are

    proposing to install our strainer in between 112 to 148 meter zone.

    The quantity of Recharge, Q can be calculated through the following formula for

    confined Aquifer:

    Q = [2(22/7) * T *(H-h)] /[2.3 log 10(R/r)]

    Where,

    K= Permeability Coefficient is 10 cum/day/sqm, considering fine sandb = Average height of Confined Aquifer = 36 meter,

    T= Tansmissibility of the aquifer = K b

    H=Initial artesian pressure at the bottom of the aquifer

    h=Artesian pressure in the well,

    (H-h) = Draw down =1.0 meter,

    R = 200 meter

    r =Radius of well = 150mm = 0.15 M

    Therefore, Total recharging capacity from 1 no. 150 mm diameter tubewell is given

    below

    Q= [2X (22/7) 10 36] / [{2.3 Log 10 (200/0.15)}]= (2262.88 / 7.19) Cum/Day

    = 314.73 cum /Day

    Average Capacity of recharging through 1 no. tubewell is = 314.73 cum/day. Total rain

    water available is 19138 cum/year, proposing 26 nos. @ 150 mm diameter recharge

    tubewell along with 26 nos. @ 60 cum storage tank. Total rain water harvested is

    9742.98 cum/year

    50% of the rain water would be harvested

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    9/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 7 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    RECHARGE STRUCTURE

    300

    2000

    300

    300

    300

    G R O U N D L E V E L

    R . C . C . S L A B5 0 0 C O V E R

    G R O U N D L E V E L

    M E S H

    M E S H

    R E C H A R G E S T R U C T U R E

    300

    S T E P

    L E G E N D

    I N P U T

    A : 1 8 M t .

    " A "

    " B "

    " C "

    C O A R S ES A N D

    G R A V E L

    G R A V E L

    S T R A I N E R

    P I P E D I A M E T E R

    " D "

    B : 1 3 3 M t .

    C : 1 M t .

    D : 0 . 1 5 M t .

    L E N G T H - E

    W I D T H - F

    E : 6 M t .

    F : 5 M t .

    3 - 5 m m S L O T T E D P I PE

    P L U G

    5 0 0 C O V E R

    P L U G

    1 . 5 - 2 . 0 m m

    5 - 1 0 m m

    1 0 - 2 0 m m

    P I T

    O V E R F L O W

    E F F E C T I V E D E P T H : 2 M t .

    E F F E C T I V E V O L U M E

    = 6 * 5 * 2 = 6 0 C U M

    8.7 Solid/Hazardous Waste Management Plan

    Garbage will be segregated at source for biodegradable, in-organic recyclables and in-

    organic inert material during construction (200 kg/day) (1000 persons @ 0.2 kg/day) and

    operational phase (8550 kg/day). Mechanical composter will be used for organic part to

    convert it in to manure, inorganic-recyclables will be sold to vendor and in-organic inert

    material will be disposed off by Kamarhati Municipality (BM) as per MSW (M&H) Rules

    2000.

    The breakup of solid waste generation is given in Table 8.2.

    Table 8.2Solid Waste Generation

    Person Rate Total

    kg/day kg/day

    Residential 15500 0.50 7750.0

    Club (1850.591 sqm) 185 0.60 111.0

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    10/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 8 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    Commercial Area(4615.864 sqm)

    1400.15 21.0

    Service persons 790 0.10 79.0

    Floating Population 1200 0.10 120.0Street Sweeping 17815 0.025 445.4

    GRAND TOTAL 8526.4

    SAY 8550

    The construction materials to be handled, stored and used are mostly of non hazardous.

    The hazardous waste are mainly of centering oil, grease, water proofing compounds,

    paints, wood dust from treated wood, discarded lube oil etc.. Special care will be taken

    to prevent spillage so that the hazardous waste will not be mixed with non-hazardous

    waste. Proper ventilation arrangement for painting work will be done to minimise

    exposure of workers. Discarded lube oil will be stored in HDPE container as per

    Hazardous Waste (M&H) Rules 1989 and its subsequent amendments and finally sold to

    the authorized vendor of MoEF.

    8.8 Control of Stack Emission & Noise Pollution from DG Sets, Vehicular

    Emission Etc.

    The project will consist of a residential housing complex with commercial facilities. During

    power failure DG will be source for air pollution. Use of low sulphur content ultra pure diesel

    reduces SO2, NOx and PM emissions from the DG sets. DG sets - 10 nos. 500 KVA each is

    proposed and 2 nos. 250 KVA. The emission from DG sets will be discharged through a 4.5meter stack for each 500 kVA and 3.2 meter stack for each 250 KVA above the roof of the

    building. Fuel required for DG sets will be about 660 litre/hr. The emission from DG sets will

    be maintained as per the norms of CPCB given below :

    PM < 0.3 G/kw-hr

    CO < 3.5 G/kw-hr

    HC < 1.3 G/kw-hr

    NO2 < 9.2 G/kw-hr

    The vehicle to be used during construction and operational phases must have a valid

    Pollution Under Control (PUC) certificate during construction phase.

    8.9 Traffic Management and Road Design Features

    There would be adequate provision for parking and as per construction Manual (similar

    to NBC 2005) required car parking was calculated and greater of these two was

    provided during designing the project. Visitors parking should not disturb the traffic of

    surrounding area. Total no. of car parking (open and covered) provided will be 2292.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    11/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 9 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    In order to reduce vehicular speed and reducing the noise and air pollution traffic

    calming is a good measure to make the system pedestrian and avoid accident. Traffic

    calming improves the transportation system in terms of visual comfort too. This should

    be done by the use of physical fixtures such as speed humps and traffic circles to control

    the speed and movement of vehicles.

    The tools of traffic calming are

    1. Installation of speed humps by raising the surface of the street in certain spots.

    2. Narrowing the street to give drivers the feeling they are in a crowded place, which will

    make them slow down and totally or partially blocking half the entrance to a side

    street so drivers cannot turn in but still can come out.3. Speed tables, build outs, etc.

    8.10 Power Supply and Back Up Power

    Electricity will be supplied by CESC. During power failure DG will be source for air

    pollution. The connected load will be about 17 MVA. The emission from DG sets (10

    nos. 500 KVA each and 2 nos. 250 KVA each) will be discharged through a 4.5 meter

    stack for each 500 kVA and 3.2 meter stack for each 250 KVA above the roof of the

    building. Fuel required for DG sets will be about 660 litre/hr diesel, which will be low

    sulphur disel. It reduces SO2, NOx and PM emissions from the DG sets. In the common

    area solar energy will be used in some places for lighting to minimize the energyconsumption. The emission from DG sets will be maintained as per the norms of CPCB

    given below

    PM < 0.3 G/kw-hr

    CO < 3.5 G/kw-hr

    HC < 1.3 G/kw-hr

    NO2 < 9.2 G/kw-hr

    8.11 Landscape Planning and Green Belt Development

    Planting trees, bushes and properly planned landscape will reduce the heat island effect

    by reducing ambient temperature through evapotranspiration. Trees will be planted

    around the building, which intercept solar radiation and shade the walls and windows of

    building (with S, SW and SE exposure) to prevent heat gain to a certain height. Apart

    from that northward orientation has a very brief period of exposure to solar radiation:

    early morning and late afternoons on clear summer days, the building is designed

    northward orientation to reduce heat gain. Broken china mosaic, light coloured tiles as

    roof finish, which reflects the heat off the surface because of high solar reflectivity, and

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    12/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 10 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    infrared emittance, which prevents heat gain. In the parking areas hollow concrete

    pavers will be used.

    Since, there is no tree in the project area, the operation stage of the proposed project

    will not pose any significant impact to the biodiversity of the area and the activities both

    during construction and operation phase would not cause any adverse impact on the

    local ecology. Moreover plantation program will give shelter to the avifauna.

    The proposed complex will have landscape garden and plantation along the boundary,

    roadside and inside the hard surface area. This plantation programme will create a

    better landscape quality as well as a barrier for dust and noise.

    Total no. of proposed trees is 1880. Details of Plantation program are given in Table 9.3.

    It has been already established that fast growing evergreen leaves of hairy type withhigher leave surface area are the efficient dust collector.

    Table 8.3

    Trees Plantation Details

    SL.NO.

    BOTANICAL NAME COMMON NAME QUANTITY

    1 Terminalia catappa Badam 140

    2 Peltophorum pterocarpum Radhachura 140

    3 Spathodea campanulata African Tulip Tree 140

    4 Tabebuia rosea Rosy Trumpet tree 145

    5 Acacia auriculiformis Akashmoni 145

    6 Azadirachta indica Neem Tree 145

    7 Cassia fistula Amaltash 145

    8 Delonix regia Gulmohur 145

    9 Lagerstroemia speciosa Jarul 130

    10 Artocarpus heterophyllus Kanthal 150

    11 Schleichera oleosa Kusum 145

    12 Mangifera indica var. 'MULLICA' Mango 150

    13 Ficus benjamina Banyan 10

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    13/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 11 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    14 Syzygium cumini Jamun 150

    TOTAL 1880

    8.12 Risk & Disaster Manament System

    The whole construction of the project will be Type-I category fire resisting

    standard. Materials of Rapid flame category will not be used and interior

    finish will be made with the materials of low flame spread, low smoke and

    low toxic generating categories conforming to IS specification.

    For fire fighting sufficient quantity of water will be kept reserved in

    underground reservoir as per West Bengal Fire Services, Govt. of West

    Bengal norms. Fire extinguisher will be provided in suitable locations as

    per West Bengal Fire Services, Govt. of West Bengal norms. In case of

    emergency, the reserved water shall be used for fire fighting.

    In addition to that the following measures will be taken.

    Fire fighting system will be designed in accordance with the AFS

    and NBC norms.

    Fire Consultant will be appointed for drawing up an appropriate

    plan for control / management of any fire in the complex.

    Fire alarm system will be provided at appropriate locations.

    Security Manager will be stationed to inform Fire Brigade / Police

    Station / Hospitals / Local Administrations in case of an emergency

    / disaster.

    All preventive measures will be adopted for disaster management as per the

    National Building Code (NBC).Detail disaster management and emergency

    preparedness planning is furnished in Annexure 7.

    8.13 Corporate Social Responsibility Programme

    On completion of the project some changes in the surrounding ambience will take

    place. Substantial no. of people will reside in this complex. To meet up daily

    requirement of the residents different types of commercial establishments will come

    up in the surrounding areas. Different types of activities inside and outside the

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    14/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 12 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    premises may cause deterioration of environmental quality. The project authority will

    take initiative to introduce some programmes to upgrade the standard of living

    welfare of the local residents and improvement of overall environment. Price wise

    break-up is given hereunder.

    1. Donation of garments to BPL people Rs. 0.525 Crore

    2. Tree plantation in the surrounding area of project site in consultation with

    Municipality and Forest Dept. Rs. 0.525 Crore

    3. Donation of an Ambulance to the local NGO Rs. 0.525 Crore

    4. Donation to the Dhrubashram (Govt. Run Home) Rs. 0.525 Crore

    8.14 Operation and Maintenance of the Facilities Craeted

    The project constitution is a mixed variety of G+19 residential units,commercial unit and club.

    FACILITY MANAGEMENT

    To have proper Facility Management Team on board the first and foremost

    important area to be looked into is an office space in the Club Complex so that

    the Club and the complex can be controlled. The operations where the Facility

    Management Team will present his valuable inputs and that they will emphasize

    more to control every aspect is as mentioned below -

    SECURITY SYSTEM HOUSE KEEPING FIRE CONTROL PANEL LANDSCAPE MAINTENANCE DOS AND DONTS WASTE MANAGEMENT PEDESTRAIN MOVEMENT VEHICULAR MOVEMENT LOGISTICS PLAN CAR CLEANING

    BASEMENT CONTROL SEWAGE & STORM FIRE & ELECTRICAL PANELS SAFETY LIFTS DG

    SECURITY SYSTEM

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    15/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 13 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    Round the clock security system will be there for the complex as per the followingdistribution

    Entry and Exit will have minimum 4 Securities in day time which will be 2

    nos. in night.

    Every reception will have a security with CCTV and will have the fire

    panel.

    Every basement entry and exit will have security.

    A security head will be on patrol for 24 hrs around the periphery.

    Video door phone will be installed at every flat and networking will be

    done with CCTV.

    If we divide the HIG with MIG & LIG then there should be clear and

    separate security zone. Considering the above the no. of Securities required are

    Under these circumstances on Security Rs 0.11/sft will be the cost.

    The number of Security personnel considered is around 100 min.

    Club, sports area will be taken separately.

    HOUSEKEEPING WASTE MGMT

    A proper plan for this has been drawn as it is an area where cost has to be under

    control.For the same reason the program decided to be executed are as follows :

    The road and the deck levels will be cleaned at the early hours of the

    day 6-8 people dividing in 4 zones, 2 of them in each zone.

    4 people will be used to clean up the common lobby and the stair case

    area of every block once they complete the road & deck lvl.

    Washing of the Car to be done by the extra people who will join the

    common lobby & staircase area once they complete washing. It will not

    only save money but will allow paying a little more.

    Waste Management of flat will be done common lobby cleaning boys

    while doing their regular cleaning. Time will be fixed by FM.

    Any Interior or renovation work to be carried out later it will be done only

    after handover of the flat. Debris that will generated has to be taken out

    by staircase by the Client himself by his/her vendor as otherwise if the

    FMG does it will be more expensive. This is termed as the logistics plan

    for the future construction.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    16/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 14 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    A better plan can be adopted if we have a waste disposal zone in one

    corner of the premises which will be tied up with Corporation for regular

    cleaning. Housekeeping cost will be Rs 0.05/sft of around 35 40 people.

    FIRE CONTROL

    The Fire Protection & Fire Detection should be analyzed in a manner so that

    the floor no along with the sprinkler no and the detector is tracked down in the

    single panel of the reception lobby of every block. If the panel is designed

    accordingly then it can be easily handled or located by the security at the

    reception.

    All the panels must be interlinked through software and will be monitored

    from the Master PC at the Facility Management Office.

    The pumps are to placed under the same BMS so that it can controlled

    from the same PC and the FM will monitor

    The Dos & the Donts will be given during registration.

    Fire drills has been planned to be presented once a substantial no. of

    residents starts residing to make every individual aware.

    Contractor who will be involved in executing the work will have a periodic

    duty to do the performance analysis of the system implemented and

    corrections to be adopted or to be maintained.

    If we divide the HIG with MIG & LIG then there should be clear and

    separate fire system with separate tank to avoid future confusions and to

    have better cost control as it will be 2 different cost.

    Under this circumstances we will not consider any extra cost for the said

    system as it will be periodically handled by Contractor & FM

    LANDSCAPE

    Landscape as the integral part of softscape unless and until it is maintained thebeauty of the project will die and it is this environment today Customers pay an

    extra money and Developer put extra bit. And for its intelligent maintenance

    working a nursery will be formed to cut down cost of Developer as well to have

    full grown trees once its required during handover of Project.

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    17/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 15 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    The water required for this purpose will be collected from the treated

    wastewater and will recycled through simple sprinkler system to cut

    down cost as well as to maintain the main garden. For remaining area there at the initial stage will be around 10-12

    gardeners which over a period will reduce to 4-6 nos. maximum.

    An AMC will be in place with the Landscape Contractor so that in future

    he/she takes care of the plants till the time the Defect Liability period of

    the Developer is there as it becomes the discretion of the Society how

    they want to maintain in future.

    We will divide all blocks by a landscape barrier.

    Considering the above the no. of gardeners required are 16

    On landscape the maintenance cost will be hardly Rs 0.02/ sft

    This we can consider provided treated wastwater through sprinkler

    system in garden area reducing manpower.

    DOS N DONTS

    We say a goal to be achieved and to maintain that a mission and wish to be

    portrayed so that it can be sustained. Architects will present his/her requirement

    where as Developer along with his Team and with FMG will set out the rules of

    the Society. This subject is vast and it will be derived once the Cooperative is

    formed by the society members in presence of the Developer for the mutual

    benefit as well as the benefit of the Project.

    The Developer will set up his/her own set of Dos and Donts of the project which

    further will be evaluated the by the Cooperative society and if any changes to be

    implemented will be done so if it benefits project without affecting the aesthetic or

    the vision of it.

    This can be derived by professionals once they are appointed.

    It will not have any cost implication or any increase in project cost as to the

    Developer or the Valued Client who will maintain later in regard to themaintenance or in regard to construction cost what so ever.

    MOVEMENT

    Here we take up the aspect of pedestrian movement along with the movement of

    the vehicle and control of the basement. Here we will see a marginal cost

    implication in Construction but will also see how we save cost on security if we

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    18/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 16 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    spend on signage and stickers. This needs to be given during registration.

    Following will be adopted for better control of traffic as well as cost control

    Stickers with Flat and Block No to be placed in the cars so that only

    on entry point a security can check thus by reducing the exit zone

    security and the maintenance cost goes down every month.

    A secluded pedestrian pathway is been designated for safety.

    Vehicular movement in basement or in peripheral roadway will be a

    one way traffic so to reduce accident and to increase safety

    measures inside the premises of the project and it reduces cost.

    Visitors car parking has got a separate zone.

    Parking inside the basement will be done with exhaust away from

    the wall side to avoid the smoke stain in future in the walls.

    Considering the above it will be entirely handled by the Securities.

    It will be clearly mentioned in the agreement/ sale deed that operation andmaintenance cost for common facilities will be borne by the owner of the flat.

    8.15 FLY ASH

    Bricks or blocks or tiles manufactured from fly ash will also be used in the

    project as per the notification No. S.O.763 (E) dated 14.09.1999 and

    subsequent amendment under S.O.979 (E) dated 27.08.2003 of Ministry ofEnvironment and Forest, Government of India and subsequent Memorandum

    of Department of Environment, Government of West Bengal vide No.

    EN/794/T-IV-1/002-i/2003, dated 10.06.2004.

    8.16 Other Pre-Construction and Post Construction Measures

    8.16.1 Recommended Mitigation measures during Construction Phase

    The impacts of the construction phase on the environment would basically be temporary

    in nature and are expected to finish on completion of the construction program. Thefollowing measures may be adopted by the project proponents:

    Implementations of proper drainage facilities to avoid wastewater/water

    stagnation from possible sources like catch pits or sedimentation basins to

    restrict the breeding of mosquitoes.

    Most of the work in construction phase is labor intensive. The labor would require

    fuel for their cooking. The Contractor in assistance with the project authority will

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    19/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 17 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACT ASSESSMENT

    assist to establish a system of distribution of fuel through local administration to

    restrict any illegal felling of trees.

    Proper Sanitary arrangement for the workers will be done within the project site.

    Initiation of plantation programme all around the complex. This plantation will

    reduce the fugitive dust as well as cause dampening of noise levels. In addition

    to that it will improve the aesthetic value of the area.

    Rubbish, debris, broken materials and others will be kept properly within project

    area at suitable place with proper water sprinkling facilities to prevent fugitive

    dust spreading.

    Introduction of screening wall all around the project area to such a height, that

    fugitive dust must not travel outside the project area.

    Water would be sprinkled on regular basis on road surface, material dumping

    and handling areas and other places to reduce dust from work place, during

    material handling and traffic movements. Limiting vehicle speed to such a limit that it could not generate dust.

    The construction materials will not be dumped in public roads around the

    property.

    Applying water and maintaining soil in a visible damp condition for temporary

    stabilization.

    Loading and unloading of construction materials will not be done at night at the

    store yard considering the huge noise likely to be generated from this activity.

    Concrete pouring and casting will not be done at night.

    Ambient and DG set noise levels will not exceed the permissible limit. Every care

    will be taken for noise control.

    Construction site will be disinfected at regular intervals. Ensuring that walking surfaces or boards at height are of sound construction and

    are provided with safety rails or belts.

    Providing protective equipment; helmets etc.

    Fire extinguishers and buckets of sand will be provided in the fire-prone area and

    elsewhere.

    Adequate emergency first aid system will be provided at project site.

    8.16.2 Recommended Mitigation Measures during Operation Phase

    It is advised to adopt the following mitigatory measures by the project authority in order

    to mitigate and control the environmental impacts that may arise due to operation of theproject.

    Wastewater generated from this project during operational phase is around

    1886 KLD. The wastewater will be collected through a well designed sewer

    network leading to STP. The STP will be based on FAB Technology followed by

    tertiary treatment and reused as much possible within the project. The treated

    wastewater will be reused for Landscaping, Car Washing, Dual Flushing and

  • 7/24/2019 Chapter8-Environmental Management Plan BT Road

    20/20

    Residential Cum Commercial Complex, at 117 B.T. Road, Kolkata 700 058

    Page 18 of 20

    Environmental Management Plan

    ENVIRONMENTAL IMPACTASSESSMENT

    HVAC System and the excess treated wastewater will be discharged into the

    Kamarhati Municipality drain.

    Solid waste, mainly garbage generated from the complex will be collected

    through containerized system and finally it will be transported, treated and

    disposed by Kamarhati Municipality drain as per MSW (M&H) Rules 2000. Spent

    oil from D.G. sets will be stored in HDPE container in isolated covered facility and

    disposed off as per Hazardous Waste (Management, Handling and

    Transboundary Movement) Rules 2008 & would be disposed off through

    registered recyclers only.

    Plantation development programme initiated during the construction period will

    be completed.

    Water will be sprinkled on regular intervals on road surface and other places to

    reduce dust from traffic movements.

    Suitable rainwater harvesting system will be installed to utilize the rain water inbest possible manner.

    Environmental awareness among all the peoples is very much needed for proper

    environment management. Overall improvement of the environment quality will

    be dependent on the environment awareness among all the sections of people

    associated with the proposed project.

    Guideline should be provided to the users to ensure conservation of energy and

    water.