CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture...

21
CHAPTER6: PRODUCTION PLANNING & CONTROL Production planning is concerned with the determination of production, inventory, and work force levels to meet fluctuating demand 2 A typical manufacturing plant This plant must purchase materials, and perhaps parts, convert these materials into specific components, then assemble the components into several products offered to the customers

Transcript of CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture...

Page 1: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

CHAPTER6: PRODUCTION PLANNING & CONTROL

Production planning is concerned with the determination of production, inventory, and work force levels to meet fluctuating demand

2

A typical manufacturing plant

� This plant must purchase materials, and perhaps parts, convert these materials into specific components, then assemble the components into several products offered to the customers

Page 2: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

3

PRODUCTION PLANNING FUNCTIONS

Aggregate Planning

Master Production Schedule

Material Requirements Planning

Inventory Management

Production Scheduling

4

AGGREGATE PLANNING

� Aggregate planning begins with the forecast of demand

� Aggregate planning translates demand forecasts into strategic decisions

Page 3: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

5

Planning strategies

� Zero Inventory Plan - Changing workforce levels –(cost effective, but poor long-run business strategy)

� Fixed Workforce Plan - Keeping inventory – allowing backlogging(increases motivation, commitment and efficiency, but builds up inventory, and decreases profits)

6

Aggregate Planning Example

� A company is to plan workforce and production levels for the six-month period January to June.

Month Jan. Feb. March April May June

Demand 1280 640 900 1200 2000 1400

Working days 20 24 18 26 22 15

� Ending inventory in December (current month) is expected to be 500 units, and the firm would like to have 600 units on hand at the end of June

� Forecast demands over the next six months for a particular line of products are as follows:

Page 4: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

7

Example 1 Continued

� There are currently (end of December) 300 workers in the plant

� There are only three costs to be considered:� Cost of hiring workers = CH = $500 /worker

� Cost of firing workers = CF = $1000 /worker

� Cost of holding inventory = CI = $80/unit/month

� Cost of backordering = CB = $150/unit/month

� K = 0.15 (number of aggregate units produced by one worker in one day

8

Level (Fixed) Workforce Plan

Fixed # of Workers =

Total demand

Total # of days x units/worker-day

Fixed # of Workers = = ≅ workers

Page 5: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

Fixed Workforce Plan

9

10

Zero Inventory Plan

Workers needed =

demand/month

days/month x units/worker-day

Page 6: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

Zero Inventory Plan

11

12

Inventory Management

� Inventory is a “buffer” between supply and demand

InventoryS(t) D(t)

Supply process (+) Demand process (–)

� S(t) and D(t) have different rates and timings due to endogenous and exogenous factors.

Page 7: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

13

Factors for Inventory

� Internal factors: are a matter of policy

� Economies of scale

� Operation smoothing

� Customer service

� External factors: are uncontrollable

� Uncertainty

14

Inventory Types

� Types are classified according to the value added during the manufacturing process:

� Raw material inventories

� Work-in-process (WIP) inventories

� Finished goods inventories

Page 8: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

15

Costs in an Inventory System

Inventory

holding cost

Ordering /

setup cost

Purchasing /

production cost

Stockout

cost

Total Inventory Cost

16

Inventory Holding Cost

H = i .c

Cost to carry

one unit of

inventory for one unit of time

Cost of carrying

$1 of inventory for

one unit of time

Cost / unit

Page 9: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

17

Fixed reorder quantity system

time

Inve

nto

ry le

ve

l

0

Q (order quantity)

Lead timeLead time

Reorder

point

Lead time

18

Average inventory

=⋅

=

T

TQ 2/

time

Inve

nto

ry le

ve

l

0

Q (order quantity)

Average inventory

per time-unit

T (period length)

Total Inventory

2

TQ ⋅2

QQ

Page 10: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

19

Annual holding cost

Annual setup cost

Annual purchasing cost

Total Inventory Cost

Where,

c = unit cost ($/unit)

D = annual demand (units)

A = fixed ordering cost ($/order)

H = annual inventory holding cost ($/unit/year)

Q = lot size (quantity to be purchased per order)

2)(

QH

Q

DAcDQTC ++=

20

Setup cost = Holding cost

Minimum total cost

Economic Order Quantity (EOQ)

2)(

QH

Q

DAQTC +=

Q* (EOQ) Q

Cost ($)

2

QH

(Holding cost)

Q

DA

(Setup cost)

Page 11: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

21

Economic Order Quantity (EOQ)

02

0)(

2=+−⇒=

H

Q

AD

dQ

QdTC

H

ADQ

2*=

Q* = Economic Order Quantity, EOQ (optimal lot size)

ic

ADQ

ic

ADQ

Qic

Q

AD 2*

2

2

2=⇒=⇒=

22

Supplier

PlantEOQ-Example

� Lead time = 2 weeks

� Consumption rate = 4 parts /hr � Available time = 40 hours/wk

� A= $1000 (fixed cost per order)� c = $500 per unit� i = 20%

Q (order quantity)

Open order

Two weeks later

?

Page 12: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

23

EOQ-Example Continued

� Suppose plant should work in its full capacity for 52 weeks in one year.

� Annual consumption of raw material in plant = D = annual demand from supplier

parts/year832052160 =×=D

24

Economic Order Quantity (EOQ)

unitsEOQH

ADQ 408

100

)8320)(1000(22* ==⇒=

Each inventory period length = Q* / D = 408 / 8320 = 0.049 years

0.049 x 52 weeks = 2.55 weeks

2.55 x 40 hours = 102 hours

EOQ

T

- D

Page 13: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

25

EOQ, T, and Reorder point (r)

0

Q* = 408

2.55 weeks

2 weeks

320

2.55 weeks

2 weeks

2.55 weeks

� EOQ = 408

� T = Q*/D= 2.55 weeks

� r = L x D= 2 x 160= 320L = lead time

26

Structure of MRP System

Explosion of parent planned order into component gross requirement.

Netting to generate net requirements. Lot sizing and

offsetting

Master Production Schedule

Inventory Master

Parts File

Open Purchase Orders

Open Shop Orders

Bill of Material

(BOM)

Planned Orders Releases Purchasing/Manufacturing

Page 14: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

27

Netting procedure

Finding net requirementsGross requirement – (on hand inventory + scheduled receipts)

Computing lot sizesSimplest is “Lot-for-Lot”: Batch size = period’s net requirement

OffsettingSubtracting the Lead-time from the time at which orders are delivered

28

Steps of MRP

� Explosion of parent into component items using BOM

� MRP performs netting calculation for each requirement of an item

� Generation of appropriate messages

Page 15: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

29

MRP – Example

� You are producing skateboards, and each consists of one unit of board, and two units of subassembly of roller-set. Roller-sets are produced inside the plant, and consist of two componentsrollers and axles. Prepare the MRP tables of all items.

30

Skateboard assembly

MaterialInventory

Page 16: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

31

Product Structure /Bill-of-matreial (BOM)

MaterialInventory

Item A: Skateboard

Item B: Board Item C: Roller-set

Item D: Roller Item E: Axle

32

Bill of Material (BOM)

A

D [ 2 ] E [ 1 ]

B [ 1 ] C [ 2 ]

Level 0

Level 1

Level 2

Parent of B and C

Components of A

2 units of C, and 1 unit of B to make 1 unit of A

2 units of D, and 1 unit of E to make 1 unit of C

Page 17: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

33

Master Production Schedule

Item A B C D E

Lead time (weeks) 1 2 1 3 2

Week 1 2 3 4 5 6 7 8 9 10

A 50 80

D 40 60

34

Inventory Master Parts File

MaterialInventory

Work-in-processInventory

Finished goodInventory

Item A B C D E

Current inventory levels 10 20 50 30 20

Lot size L4L 100 L4L 200 150

Page 18: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

35

Open Orders Data

Scheduled Receipts (Due Dates)

ITEM / WEEKS 1 2 3 4 5 6 7 8 9

A

B 20

C 90

D 40

E

36

MRP table for item A

WEEKS 1 2 3 4 5 6 7 8 9 10

Gross Requirements 50 80

Scheduled Receipts

Inventory on hand 10 10 10 10 10 0 0 0 0 0

Net Requirements 40 80

Planned Orders 40 80

Page 19: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

37

MRP table for item B

WEEKS 1 2 3 4 5 6 7 8 9

Gross Requirements 40 80

Scheduled Receipts 20

Inventory on hand 20 20 40 40 0 0 0 0 20

Net Requirements 80

Planned Orders 100

38

MRP table for item C

WEEKS 1 2 3 4 5 6 7 8 9

Gross Requirements 80 160

Scheduled Receipts 90

Inventory on hand 50 140 140 140 60 60 60 60 0

Net Requirements 100

Planned Orders 100

Page 20: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

39

MRP table for item D

WEEKS 1 2 3 4 5 6 7 8 9

Gross Requirements 40 260

Scheduled Receipts 40

Inventory on hand 30 30 70 30 30 30 30 170 170

Net Requirements 230

Planned Orders 400

40

MRP table for item E

WEEKS 1 2 3 4 5 6 7 8 9

Gross Requirements 100

Scheduled Receipts

Inventory on hand 20 20 20 20 20 20 20 70 70

Net Requirements 80

Planned Orders 150

Page 21: CHAPTER6: PRODUCTION PLANNING & CONTROLweb.iku.edu.tr/~rgozdemir/IE250/lecture notes/2010-2011/IE250_CHP6... · CHAPTER6: PRODUCTION PLANNING & CONTROL ... (optimal lot size) ic AD

41

MRP Outputs

Planned Orders (Release Dates)

ITEM / WEEKS 1 2 3 4 5 6 7 8 9

A 40 80

B 100

C 100

D 400

E 150